Zone :South Zone Circle :Civil Circle -18 Division : Southern Division-2 Name of work : In Situ Rehabilitation at A-14 Kalka Ji Extn. SH. : Construction of 3000 Multi Storeyed DU’S at . . Community centre Site ( Turnkey Project) Agency : Era Infra Engineering Limited. Agreement No : 01/EE/SD-2/DDA/12-13

Presentation1 dda

Embed Size (px)

Citation preview

PowerPoint Presentation

Zone :South ZoneCircle :Civil Circle -18Division : Southern Division-2 Name of work : In Situ Rehabilitation at A-14 Kalka Ji Extn.SH. : Construction of 3000 Multi Storeyed DUS at . . Community centre Site ( Turnkey Project)Agency : Era Infra Engineering Limited.Agreement No : 01/EE/SD-2/DDA/12-13

HISTORY OF THE PROJECT The total 8000 houses for in situ rehabilitation of slum dwellers comprising Jawahar camp, Navjeevan camp & Bhoomihin camp is to be constructed . The total area of the plot comprising these three camps is 10.59 Hac.Originally this work of in situ rehabilitation at A-14 Kalkaji Extn. including construction of 8000 flats was proposed to be executed under PPP Mode (Public Private Partnership Mode)Later on Honble L.G in the meeting dated 16-09-2011 decided that DDA should do this work with its own funds. The meetings were held and it was decided that initially 3000 flats may be constructed in the adjacent plots ( measuring 3.068 hectares) earmarked as community centre plot and the land use may be swapped with an equivalent area at A-14 Kalkaji Extn. (in NavjeevanCamp/Bhumiheen Camp/Jawahar camp). The scheme has been approved in 318th meeting of screening committee vide dated 23-01-2014 vide agenda item no 14-2014 for built-up area 127529.80sqm for construction of 3024 DUs, accordingly the work is being executed at site in four cluster ie cluster-1,2,3&4 comprising cluster-1 -6 towers, cluster-2 2 towers, cluster-3- 6 towers & cluster-4 6 towers.The building is of 14 storeys.

Each dwelling unit comprises of 25 sqm carpet area having one living room, one bed room, one kitchen, bath / WC and balcony finished with vitrified floor tiles , ceramics tiles , Udaipur green marble counter in Kitchen etc. The building is of RCC framed structure.There is provision of STP and treated water will be used for flushing in cistern in toilets and for horticulture purpose . However DJB is not ready to approve the dual water supply system ( treated water+ potable water).

WORK AWARDED VIDE F7(08)/A/SD-2/DDA/11-12/438 DT10-1- 13AGENCY M/S ERA INFRA ENGINEERING LTDDESIGN CONSULTANT ADLAKHA ASSOCIATES PVT .LTD CONSULTANT(QUALITY) IRCLASS SYSTEMS & SOLUTIONS TYPE OF CONTRACT TURNKEYESTIMATED COST Rs. 205,99,63,495/-TENDER AMOUNT Rs. 260,38,27,200/-NEGOTIATED / ACCEPTED RATE Rs. 22,232 /-per SqmNEGOTIATED ACCEPT AMOUNT Rs. 2,31,92,42,240/-PLINTH AREA 104320 SQMTIME ALLOWED 36(THIRTY SIX) MONTHS (12 MONTHS FOR PLANNING & 24 MONTHS FOR CONSTRUCTION)

PROJECT HIGHLIGHTS

TIME SCHEDULEDate of Award:10.01.2013St. Date of Start:25.01.2013St. Date of Completion:24.01.2016Present Status of Work:29%Target date of completion:31.12.2016

Major Items Flooring : Vitrified tiles in rooms ,Kota Stone in gallery . . and staircase , ceramic tiles in ToiletsFinishingExterior : Grit WashInterior : Cement plaster with oil bound . distemperWood work : Flush door shutterWalls : CLC BlocksBoundary wall : Random Rubble stone masonry with SFRC . railing

COST OF THE PROJECT1. Major Head: B.G.D.A.2. Minor Head: 10A, Construction of Houses3. A/A & E/S : EM6(10)2012/Est/Pt/5081 dated 23.10.2012 for Rs. 2180812953/-4. Estimated Cost: Rs. 2059963493/-5. Tendered Amount: Rs. 2319242240/-6 Tentative cost :Rs. 2679014470 /-7. Budget Code: 440030798. Budget Provision for 2015-16: Rs. 18000 Lacs

Salient features

Area of plot : 3.068 HactBuilding : 14 storeyed Structure : RCC Framed Structure Total Dus as per agreement : 3000As per 318th screening committee : 3024 (Vide agenda no 14:2014 dt23/1/14)Area of one Flat : 25 SqmNO. OF CLUSTERS : 4 ( Cluster-1,Cluster-2,Cluster-3 & Cluster-4)NO. OF TOWERS : 20 TOWERS (6 towers in cluster-1, 2 towers in cluster-2, . . . 6 towers in cluster-3 & 6 towers in Cluster-4NO. OF FLOORS : Stilt +14Water supply : Dual water supply system (drinking & treated water)Sewerage : Sewerage treatment plant is to be constructed by agency Payment : Stage wise paymentFinal payment : Slab area shall be measured

CAMPS TO BE SHIFTEDNavjeevan camp Bhoomi heen camp Jawahar camp Clearance from various departments : EIA ,DUAC,AVIATION, DFS,DPCC obtained Approval of services : SW drain sanction by MCD (MCD/DJB) Water supply & sewerage scheme yet to be sanction by DJB

Reason for delay of the projectCourt case : RWA Pkt.A-14 KalkaJi Extn. move to court as . the land of the project initially was earmarked . commercial. The land use from commercial to . residential was changed by the Ministry of . . Urban development on 03- 06-2013. Thereafter . the court dismissed the petition on 02-07-2013 . . since petition withdrawn by the RWA Pkt. A-14 . Kalka Ji Extn. Due to change of land use from : 25-1-13 to 3-6-13 commercial to residential Permission of Tree cutting : 25-1-13 to 21-3-15Hindrance Water supply : As per agreement dual water supply . system is to be provided by the agency . . But DJB is not ready to sanction the . scheme with dual water .They are ready to . sanction single water supply system . DJB . has been requested for sanction of dual . water system which is awaited .Sewerage scheme : This scheme has been submitted to DJB . . The sanction is awaited

9

KEY PLANIn-situ Rehabilitation of JJ clusters

PROPOSED HOUSINGKEY PLAN

Project Layout

Cluster-1 layoutTOWERNOS. OF FLATSLIFTSTOWER-11402TOWER-21122TOWER-31680TOWER-4982TOWER-51262TOWER-61680TOTAL8128

12

Cluster-2 layoutTOWERNOS. OF FLATSLIFTSTOWER-11402TOWER-21680TOTAL3082

13

Cluster-3 layoutTOWERNOS. OF FLATSLIFTSTOWER-11402TOWER-2982TOWER-31680TOWER-4982TOWER-51402TOWER-61680TOTAL8128

14

Cluster-4 layoutTOWERNOS. OF FLATSLIFTSTOWER-1154TOWER-21542TOWER-32382TOWER-42382TOWER-51542TOWER-6168TOTAL10928

15

Carpet Area of D.U.

CLUSTER-4ERA INFRA ENGINEERING LTDPROJECT :- DDA KALKA JI DELHICLUSTER-4, PICTORIAL CHART M/C @ MUMTY ROOM3-Feb-161-Feb-1615-Mar-1630-Mar-162-Apr-164-Mar-1614th FLOOR9-Jan-1624-Jan-167-Jan-1622-Jan-1619/Feb/165-Mar-165-Mar-1620-Mar-168-Mar-1623-Mar-168-Feb-1623-Feb-1613th FLOOR24-Dec-158-Jan-1622-Dec-156-Jan-163/Feb/1618-Feb-1618-Feb-164-Mar-1621-Feb-167-Mar-1623-Jan-167-Feb-1612th FLOOR8-Dec-1523-Dec-156-Dec-1521-Dec-1518/Jan/162-Feb-162-Feb-1617-Feb-165-Feb-1620-Feb-167-Jan-1622-Jan-1611th FLOOR22-Nov-157-Dec-1520-Nov-155-Dec-152/Jan/1617-Jan-1617-Jan-161-Feb-1620-Jan-164-Feb-1622-Dec-156-Jan-1610th FLOOR17/Dec/151-Jan-161-Jan-1616-Jan-164-Jan-1619-Jan-166-Dec-1521-Dec-159th FLOOR1/Dec/1516-Dec-1516-Dec-1531-Dec-1519-Dec-153-Jan-1620-Nov-155-Dec-158th FLOOR15/Nov/1530-Nov-1530-Nov-1515-Dec-153-Dec-1518-Dec-157th FLOOR13-Nov-1529-Nov-1517-Nov-152-Dec-156th FLOOR.5th FLOOR4rth FLOOR3rd FLOOR2nd FLOOR1st FLOORSTILT FLOOR16-Nov-14RAFTCOMPCOMPCOMPCOMPCOMPCOMPCOMPPCCCOMPCOMPCOMPCOMPCOMPCOMPEXCAVATIONCOMPCOMPCOMPCOMPCOMPCOMP CL-4 TOWER - 1 CL-4 TOWER - 2 CL-4 TOWER - 3 CL-4 TOWER - 4 CL-4 TOWER - 5 CL-4 TOWER - 6ColourIdentificationCompletedWork in progressBlock work completedInternal plastering completedInternal plastering WIPTile work in ProgressTile laying Completed (Bed,living room)

Cluster-3ERA INFRA ENGINEERING LTDCLUSTER 3, PICTORIAL CHART M/C @ MUMTY ROOM13-Feb-1620-Apr-1621-Apr-1622-Mar-1613-Apr-165-Mar-1614th FLOOR19-Jan-163-Feb-1626/Mar/1610/Apr/1627-Mar-1611-Apr-1626-Feb-1612-Mar-1619-Mar-163-Apr-169-Feb-1624-Feb-1613th FLOOR3-Jan-1618-Jan-1610/Mar/1625/Mar/1611-Mar-1626-Mar-1610-Feb-1625-Feb-163-Mar-1618-Mar-1624-Jan-168-Feb-1612th FLOOR18-Dec-152-Jan-1623/Feb/169/Mar/1624-Feb-1610-Mar-1625-Jan-169-Feb-1616-Feb-162-Mar-168-Jan-1623-Jan-1611th FLOOR2-Dec-1517-Dec-157/Feb/1622/Feb/168-Feb-1623-Feb-169-Jan-1624-Jan-1631-Jan-1615-Feb-1623-Dec-157-Jan-1610th FLOOR16-Nov-151-Dec-1522/Jan/166/Feb/1623-Jan-167-Feb-1624-Dec-158-Jan-1615-Jan-1630-Jan-167-Dec-1522-Dec-159th FLOOR6/Jan/1621/Jan/167-Jan-1622-Jan-168-Dec-1523-Dec-1530-Dec-1514-Jan-1621-Nov-156-Dec-158th FLOOR21/Dec/155/Jan/1622-Dec-156-Jan-1617-Nov-157-Dec-1514-Dec-1529-Dec-157th FLOOR5/Dec/1520/Dec/156-Dec-1521-Dec-1528-Nov-1513-Dec-15##6th FLOOR19/Nov/154/Dec/1520-Nov-155-Dec-1512-Nov-1527-Nov-155th FLOOR4rth FLOOR3rd FLOOR2nd FLOOR1st FLOORSTILT FLOORPLINTH BEAM RAFTPCCEXCAVATION CL-3 TOWER - 1 CL-3 TOWER - 2 CL-3 TOWER - 3 CL-3 TOWER - 4 CL-3 TOWER - 5 CL-3 TOWER - 6ColourIdentificationCompletedWork in progressBlock work completedInternal plastering completedInternal plastering WIPTile work in ProgressTile laying Completed (Bed,living room)

CLUSTER-2ERA INFRA ENGINEERING LTDPROJECT :- DDA KALKA JI DELJICLUSTER-2, PICTORIAL CHART M/C @ MUMTY ROOM20/Feb/165/Mar/1614th FLOOR26/Jan/1610/Feb/169/Feb/1624/Feb/1613th FLOOR10/Jan/1625/Jan/1624/Jan/168/Feb/1612th FLOOR25/Dec/159/Jan/168/Jan/1623/Jan/1611th FLOOR9/Dec/1524/Dec/1523/Dec/157/Jan/1610th FLOOR23/Nov/158/Dec/157/Dec/1522/Dec/159th FLOOR21/Nov/156/Dec/158th FLOOR7th FLOOR6th FLOOR5th FLOOR4rth FLOOR3rd FLOOR2nd FLOOR1st FLOORSTILT FLOORPLINTH BEAM RAFTPCCEXCAVATION CL-2 TOWER - 1 CL-2 TOWER - 2ColourIdentificationCompletedWork in progressBlock work completedInternal plastering completedInternal plastering WIPTile work in ProgressTile laying Completed (Bed,living room)

CLUSTER-1ERA INFRA ENGINEERING LTDPROJECT :- DDA KALKA JI DELHICLUSTER-1,PICTORIAL CHART M/C @ MUMTY ROOM30-Jun-1623-Jun-1630-May-167-May-1610-Jun-1611-Jul-1614th FLOOR10-Jun-1625-Jun-163-Jun-1618-Jun-1610-May-1625-May-1617-Apr-162-May-1621-May-165-Jun-1621-Jun-166-Jul-1613th FLOOR25-May-169-Jun-1618-May-162-Jun-1624-Apr-169-May-161-Apr-1616-Apr-165-May-1620-May-165-Jun-1620-Jun-1612th FLOOR9-May-1624-May-162-May-1617-May-168-Apr-1623-Apr-1616-Mar-1631-Mar-1619-Apr-164-May-1620-May-164-Jun-1611th FLOOR23-Apr-168-May-1616-Apr-161-May-1623-Mar-167-Apr-1629-Feb-1615-Mar-163-Apr-1618-Apr-164-May-1619-May-1610th FLOOR7-Apr-1622-Apr-1631-Mar-1615-Apr-167-Mar-1622-Mar-1613-Feb-1628-Feb-1618-Mar-162-Apr-1618-Apr-163-May-169th FLOOR22-Mar-166-Apr-1615-Mar-1630-Mar-1620-Feb-166-Mar-1628-Jan-1612-Feb-162-Mar-1617-Mar-162-Apr-1617-Apr-168th FLOOR6-Mar-1621-Mar-1628-Feb-1614-Mar-164-Feb-1619-Feb-1612-Jan-1627-Jan-1615-Feb-161-Mar-1617-Mar-161-Apr-167th FLOOR19-Feb-165-Mar-1612-Feb-1627-Feb-1619-Jan-163-Feb-1627-Dec-1511-Jan-1630-Jan-1614-Feb-161-Mar-1616-Mar-166th FLOOR3-Feb-1618-Feb-1627-Jan-1611-Feb-163-Jan-1618-Jan-1611-Dec-1526-Dec-1514-Jan-1629-Jan-1614-Feb-1629-Feb-165th FLOOR18-Jan-162-Feb-1611-Jan-1626-Jan-1618-Dec-152-Jan-1623-Nov-1510-Dec-1529-Dec-1513-Jan-1629-Jan-1613-Feb-164rth FLOOR2-Jan-1617-Jan-1626-Dec-1510-Jan-162-Dec-1517-Dec-1513-Dec-1528-Dec-1513-Jan-1628-Jan-163rd FLOOR17-Dec-151-Jan-1610-Dec-1525-Dec-1516-Nov-151-Dec-1525-Nov-1512-Dec-1528-Dec-1512-Jan-162nd FLOOR01-Dec-1516-Dec-1524-Nov-159-Dec-1512-Dec-1527-Dec-151st FLOOR15-Nov-1530-Nov-1524-Nov-1511-Dec-15PLINTH BEAMRAFTcompCOMPCOMPPCCCOMPCOMPCOMPCOMPEXCAVATIONCOMPCOMPCOMPCOMP CL-1 TOWER - 1 CL-1 TOWER - 2 CL-1 TOWER - 3 CL-1 TOWER - 4 CL-1 TOWER - 5 CL-1 TOWER - 6ColourIdentificationCompletedWork in progressBlock work completedInternal plastering completedInternal plastering WIPTile work in ProgressTile laying Completed (Bed,living room)

Current Photographs of ProjectCLUSTER-4 ,TOWER-1

Cluster 4 Tower-2

Cluster-4 Tower-3

Cluster-4 Tower-4

Cluster-4 Tower-5

Cluster-4 Tower-6

Cluster-3 Tower-1

Cluster-3 Tower-2

Cluster-3 Tower-3

Cluster-3 Tower-4

Cluster-3 Tower-5

Cluster-3 Tower-6

Cluster-2 Tower-1&2

Cluster-1 Tower-1

Cluster-1 Tower-2

Cluster-1 Tower-3

Cluster-1 Tower-4

Cluster-1 Tower-5

Cluster-1 Tower-6