CONSORTIUM GROUPE H - INTERTECNOBUREAU INTERNATIONAL DU TRAVAIL
ILO Renovation
Presentation to the steering committee
Friday 19th October 2012
CONSORTIUM GROUPE H - INTERTECNOBUREAU INTERNATIONAL DU TRAVAIL
ILO RenovationPresentation to the steering committee
Friday 19th October 2012
Mixed layoutScenario
N
0 5 10 20
Area required for work stations
Area required for shared spaces
Area required for circulation
Area required for services (copy, archives, toilets...)
183 Work stations
CONSORTIUM GROUPE H - INTERTECNOBUREAU INTERNATIONAL DU TRAVAIL
ILO RenovationPresentation to the steering committee
Friday 19th October 2012
Mixed layoutScenario
N
0 5 10
Area required for work stations
Area required for shared spaces
Area required for circulation
Area required for services (copy, archives, toilets...)
56 Work stations
CONSORTIUM GROUPE H - INTERTECNOBUREAU INTERNATIONAL DU TRAVAIL
ILO RenovationPresentation to the steering committee
Friday 19th October 2012
Mixed layoutScenario
N
0 5 10
Area required for work stations
Area required for shared spaces
Area required for circulation
Area required for services (copy, archives, toilets...)
56 Work stations
CONSORTIUM GROUPE H - INTERTECNOBUREAU INTERNATIONAL DU TRAVAIL
ILO RenovationPresentation to the steering committee
Friday 19th October 2012
Mixed layoutScenario
N
0 5 10
Area required for work stations
Area required for shared spaces
Area required for circulation
Area required for services (copy, archives, toilets...)
71 Work stations
Area required for work stations ...................... 1979m2 45%
Area required for shared spaces ...................... 646m2 15%
Area required for circulation ............................ 726m2 16%
Area required for services (copy, archives, toilets...) ...... 1041m2 24%
183 Work stations
N
CONSORTIUM GROUPE H - INTERTECNOBUREAU INTERNATIONAL DU TRAVAIL
ILO RenovationPresentation to the steering committee
Friday 19th October 2012
Mixed layoutScenario