Upload
issam-m-faqir
View
168
Download
0
Tags:
Embed Size (px)
Citation preview
NATIONAL HOUSING AL-BARSHA SOUTH
1
CONSTRUCTION OF 1240 VILLAS
ARABTEC CONSTRUCTIONA.L.D.
PROJECT MANAGERISSAM M. AL FAQIR
2
1. LIAISING WITH DIFFERENT GOVERNMENT AUTHORITIES FOR VARIOUS MATTERS SUCH AS PROJECT INSURANCE POLICIES, BUILDING PERMITS, NOCS, DEMARCATIONS, FINAL SURVEY CERTIFICATES, APPROVALS ETC.
2. DEALING WITH ALL SECURITY MATTERS OF THE DIVISION, ARRANGING/DEALING/CONTROLLING ACCOMMODATION AND TRANSPORTATION ISSUES AND MATTERS
3. RECRUITING/HIRING STAFF/MANPOWER AS PER THE PROJECTS REQUIREMENT IN COORDINATION WITH HEAD OFFICE.
3
4. PROJECT-WISE DAILY/WEEKLY AND MONTHLY RECORDING/UPDATING OF TOTAL MANPOWER AND CALCULATION OF TOTAL MAN-HOURS/TOTAL WAGES/TOTAL OVERTIME AND KEEPING PERCENTAGEWISE RECORDS OF THE SAME FOR THE COST CONTROL PURPOSE.
5. OVERALL CONTROL OF ADMINISTRATION AND HR MATTERS OF THE ALD1 PROJECTS/DEPARTMENT AND OFFICES AND WELLBEING OF STAFF AND LABOURS
6. ARRANGING WORK PERMIT CARDS/EMIRATES ID CARDS/ INSURANCE CARDS/VISA RENEWALS/VISA MEDICALS FOR ALL THE EMPLOYEES IN COORDINATION WITH HEAD OFFICE.
QA/QC OFFICE
4. INSPECTION & TESTING OF MATERIALS AS PER ITP
2. PREPARATION OF METHOD STATEMENT & ITP SCHEDULE3. METHOD STATEMENT & ITP PREPARATION AS
PER SCHEDULE
PROJECT LEVEL QA/QC PROGRAMME1. PREPARATION OF PROJECT SPECIFIC QUALITY
PLAN
4
8. ISSUE SITE OBSERVATION REPORT/ NON- CONFORMANCE REPORT FOR NON-COMPLIANCE OF WORK DURING EXECUTION (IF ANY) 9. PERIODIC INTERNAL AUDIT AS PER INTERGATED MANAGEMENT SYSTEM
6. QA/QC VERIFICATION OF WORKS AS PER QUALITY CONTROL CHECKLIST 7. SITE INSPECTION REQUEST SUBMISSION TO CONSULTANT FOR INSPECTION & APPROVAL
PROJECT LEVEL QA/QC PROGRAMME 5. WORK START NOTIFICATION PRIOR TO COMMENCEMENT OF EACH ACTIVITY
5
13. HANDING OVER
12. PREPARE & SUBMIT THE CLOSE-OUT DOCUMENTS
11. CARRY OUT THE SNAGGING & DE-SNAGGING PROCESS
PROJECT LEVEL QA/QC PROGRAMME10. CARRY OUT THE TESTING & COMMISSIONING OF ALL INSTALLED ITEMS
6
VILLAS CONSTRUCTION SEQUENCE SUMMERY (TUNNEL FORM WORKS )
7
First Stage Second Stage Third Stage
Substructure Superstructure Finishing
1
Excavation & Earth WorksIncluding leveling and compaction
1
RCC Columns & Walls Kickers Kicker: like the column necks to facilitate tunnel form installation
1
First Fix for MEP WorksAll embedded conduits and pipes to be installed in block walls
2Anti-termite (chemical spray)
2Tunnels Forms Installation Using mobile cranes cranes
2Wooden Doors Subframes12mm plywood
3PCC & Blinding50mm plain concrete below foundation
3RCC Works for Columns, Walls & Slab (GF, FF, etc.)
3
Plaster Works Plaster preparation including rush coat, fiber mesh, angle beads ..etc. Then filling by cement sand plaster
4RCC FoundationReinforced Strip Foundation
4
Roof Parapet, Staircase & Miscellaneous RCC Works as per architectural shop drawings
4
Roof Waterproofing Works Getting the slope by foam concrete then using membrane system and polystyrene for heat insulation and finally protected by natural gravel and concrete tiles
8
First Stage Second Stage Third Stage
Substructure Superstructure Finishing
5
Stub WallsAll around the center line of the strip foundation to suit the tunnel design
5
Block Works (Insulation)50 mm polystyrene is used between two block walls (100mm & 200mm) Total wall thickness is 350 mm
5
Tile & Marble WorksIncluding floor and wet area walls and staircase step and vanities and kitchen tops
6Damp ProofingBitumen Paint
6
Second Fix MEP (A/C System, High level Drainage) especially above false ceiling survices
7
Backfilling (Compaction on Layers) Including underground drainage and MEP services
7
External Works: Precast, Boundary Walls, External Drainage, Paving & landscaping.
8 Anti-termite 8False Ceiling WorksSuspension & Gypsum board installation.
9
First Stage Second Stage Third Stage
Substructure Superstructure Finishing
9Slab on grade100mm reinforced concrete
9Painting WorksInternal & External
10
UPVC & Aluminum WorksIncluding doors, windows and railings and other decorative items
11
Doors & Joinery WorksIncluding wardrobes and kitchen cabinets, wooden handrail and pergolas
12
MEP Final Fix (Electrical Accessories, Light Fittings, Sanitary Wares …etc.
13
Testing & Commissioning
14
Snagging & Handing overSpecial team for clearance and preparing the villas for final handing over to the end user.
Click icon to add picture
EXCAVATION & LEVELING
1240 Villas Progress Photos
10
PCC 11
Click icon to add picture
CASTED STRIP FOOTING 12
Click icon to add picture
CASTED STRIP FOOTING 13
Click icon to add picture
CASTED GROUND SLAB 14
GROUND FLOOR TUNNEL 15
GROUND FLOOR TUNNEL 16
FIRST FLOOR TUNNEL REINFORCEMENT WORKS 17
FIRST FLOOR TUNNEL WORKS 18
Click icon to add picture
PARAPET WORKS 19
BLOCK WORKS 20
PLASTER WORKS 21
BOUNDARY WALL PCC 22
Click icon to add picture
BOUNDARY WALL INSTALLATION 23
CLAY ROOF TILES 24
Click icon to add picture
ROOF WATER PROOFING 25
Click icon to add picture
GRC WORKS 26
Click icon to add picture
TILING WORKS 27
Click icon to add picture
DRAINAGE WORKS 28
SWEET SOIL FILLING 29
ELECTRIC PANEL BOARD 30
INTERNAL PAINTING OF WALL FINAL COAT 31
Click icon to add picture
TILE GROUT WORKS 32
Click icon to add picture
GARAGE GRAVEL FILLING 33
MARBLE VANITY TOP 34
WARDROBE SHUTTER FIXING (JOINERY WORKS) 35
JOINERY WORKS 36
JOINERY WORKS 37
FALSE CEILING WORKS38
UPVC WORKS - AREA 0339
Click icon to add picture
CAST ALUMINIUM WORKS – AREA 03
40
Click icon to add picture
STAIRCASE RAILING WORKS – AREA 03
41
Click icon to add picture
GARAGE PAVING BLOCKS WORKS 42
Click icon to add picture
ROOF AC MACHINE INSTALLATION 43
Click icon to add picture
HEEL KERB FIXING 44
EXTERNAL WALL PRIMER PAINT 45
Click icon to add picture
EXTERNAL WALL FINAL PAINTING WORKS 46
MEP SERVICES ABOVE FALSE CEILING WORKS 47
MEP SERVICES ABOVE KITCHEN FALSE CEILING WORKS 48
FALSE CEILING WORKS 49
FALSE CEILING GYPSUM BOARD FIXING 50
PAINTING OF GARAGE WALL 51
Click icon to add picture
GARAGE PAVING BLOCKS 52
KITCHEN CABINET SHUTTER FIXING 53
KITCHEN COOKER HOOD FIXING 54
SANITARY FIXTURE INSTALLATION 55
MANHOLE COVER PAINTING 56
HEEL KERB FIXING 57
Click icon to add picture
SWEET SOIL FILLING 58
Click icon to add picture
GARAGE ROAD BASE FOR COMPACTION 59
EXTERNAL ELECTRICAL OUTLET INSTALLATION 60
Click icon to add picture
ALUMINUM MAIN ENTRANCE GATE FIXING 61
Click icon to add picture
ROOF A/C MACHINE INSTALLATION 62
Click icon to add picture
ROOF A/C MACHINE INSTALLATION 63
ROOF SLAB PAVING BLOCKS AND GRAVEL 64
Click icon to add picture
ROOF WATERPROOFING LEAKAGE TEST 65
ATTACHED VILLA GAS ENCLOSURE INSTALLATION 66