NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 1 of 14
Printed copies are uncontrolled
Prepare Concurrent Operations Script
This document may set requirements supplemental to applicable law. However, nothing herein is intended to replace, amend, supersede or otherwise depart from any applicable
law relating to the subject matter of this document. In the event of any conflict or contradiction between the provisions of this document and applicable law as to the
implementation and governance of this document, the provisions of applicable law shall
prevail.
CONTENTS
1 OBJECTIVES ........................................................................................................................... 3
2 TARGET GROUP ..................................................................................................................... 3
3 SCOPE ...................................................................................................................................... 3
4 RISK DOMAIN AND RISK...................................................................................................... 3
5 INSTRUCTION ....................................................................................................................... 3
6 RELATED CONTROLLING DOCUMENTS ......................................................................... 5
7 APPENDICES .......................................................................................................................... 6
DOCUMENT HISTORY
Date Revision Reason for change
25 Sept. 2013 2 Comments of CO optimization project included
1 March 2012 1 New format and job-titles
New Concurrent Operations Script attachment
New document number (old nr.: E.ASS.WI.30.03)
June 2003 0 First release
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 2 of 14
Printed copies are uncontrolled
CMS Document Control Box
Field Name Field Description
Name Prepare concurrent operations script
Organisation NAM
Content Owner
(Authority to Issue) de Haan, Johan NAM-UIE/P/G
Custodian Bogers, Harry NAM-UIE/P/G
Document Custodian Bogers, Harry NAM-UIE/P/G
Author(s) Pluijmers, Ad NAM-UIE/S/G; Bogers, Harry NAM-UIE/P/G
CMS Number NAM-ASS.WI.30.03
Doc Number NAM200210100891
Revision Number 2
Cross References NAM200212000274, NAM200211100487, NAM200211100063, EP201211234614,
First Issue Date 01.06.2003
Issue Date 23.09.2013
Review Date 23.09.2015
External No
Document Type Work Instruction
Valid For NAM
UPBM Process ASS
UPBM Sub-process N/A
Discipline N/A
Expertise N/A
Used In UP Process ASS, 14, 17, 62, 63, 64, 71, 72
Used In Discipline N/A
Used in Expertise N/A
Language English
Risk Domains Health, Safety, Environment, Commercial, Reputation
Safety Case (UK) No Applicable Roles N/A
HSE MS Process, Asset and Standards
ISO 14001 4.4.6 Operational control
Security Restricted
Export Control Not subject to EAR – no US content
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 3 of 14
Printed copies are uncontrolled
1 OBJECTIVES
To prepare a Concurrent Operations (CO) Script, explaining how CO interaction risks in a project are to be managed.
2 TARGET GROUP
Concurrent Operations review team.
3 SCOPE
This instruction relates to:
Organisation: Production Assets, Wells, Projects, Geophysics
Process: 14, 17, 62, 63, 64, 71, 72
Asset: NAM Assets
4 RISK DOMAIN AND RISK
Risk Domain(s) Risk(s)
Health, Safety,
Environment
Ensure that all activities related to Concurrent Operations
interaction risks are described in a uniform manner and
communicated to the relevant parties
5 INSTRUCTION
Table of contents:
The Concurrent Operation script contains de following subjects:
1. Distribution list
See Appendix 1.
The aim is to reduce the number of hard copies to a minimum number.
2. Revision list
See Appendix 2.
3. Management summary
The summary shall be limited to one A-4 page.
3.1 Justification for operating under Concurrent Operations (see initiative note)
• Short description of the planned activities
• Description of the reviewed alternatives to avoid Concurrent Operations
• Contractual obligations
• Financial justification
• Planned starting date for executing Concurrent Operations
• Estimated duration of executing Concurrent Operations
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 4 of 14
Printed copies are uncontrolled
3.2 Risk analysis
Summary of the identified risks and the control measurements.
3.3 Quantitative Risk Analysis (QRA)
Summary of the executed QRA, if executed.
4. Concurrent Operations Script
For example purpose see Appendix 3.
5. Concurrent Operations Review Action follow-up list
See Appendix 3 of work Instruction “Execute Concurrent Operations Review”.
6. Emergency Response Table
An overview of the control measures which need to be taken in case of a calamity.
Consult the location specific emergency response documents. Example: Appendix 4.
7. Concurrent Operation Matrix of Permitted Operations (CO -MOPO)
As given in Appendix 2 of work instruction “Execute Concurrent Operations Review”.
8. Communication
Telephone list of all parties/persons involved. See Appendix 5 for an example.
Overview of all parties involved by means of an organigram as given in Appendix 6, including reporting lines, especially during emergencies.
9. Appendix
Other documents produced during the preparation of the Concurrent Operations script such as:
Action Party Status
1. Concurrent Operations Initiative note as per NAM.ASS.WI.30.01
2. Concurrent Operations Review Report as per NAM.ASS.WI.30.02.
3. Quantitative Risk Analysis (QRA), including agreed conclusions and actions, as per “Handleiding Risicoberekeningen Bevi” and the “Interim handleidingen risicoberekeningen externe veiligheid” from SodM. 4. Move-in / mobilisatie plan: is equal to the “Logistics plan”, consisting of sign plan including traffic guides, “ verkeer in- en uitritten, traffic signs etc. To obtain safe access to the working areas, adequate communications facilities and adequate escape provisions during concurrent operations, the following documents are
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 5 of 14
Printed copies are uncontrolled
required:
5. Integrated Concurrent Operations drawing, presenting the location of the drilling rig and drilling equipment, lifting area, storage area, traffic routes, escape routes, living units, fences and blocks, Ameland kappen, utility connections, fire water supply etc., including combined hazardous area
6. System connections, presenting communication- and, alarm lines.
7. Activity work planning sheet to obtain insight in the hazardous activities.
8. Abbrevations list.
Document management
Store the Concurrent Operations script in Livelink in the specific project environment. Revision management shall take place according to Livelink regulations.
Timely submission to Regulator
In principle a Concurrent Operations Script does not need to be submitted to the Regulator (State Supervision of Mines), unless it is combined with another document that
does require (timely!) submission, such as a Work Safety Plan (WVP) for Drilling.
For further details see Appendix 1 in Procedure Authorise and Submit HSE Cases (NL) [ref. 5].
6 RELATED CONTROLLING DOCUMENTS
Ref. Title Document No.
[1] Procedure: Identification, Planning and Execution of Concurrent
Operations
NAM-ASS.PR.30
[2] Work Instruction: Create Concurrent Operations Initiative-note NAM-ASS.WI.30.01
[3] Work Instruction: Execute Concurrent Operations Review NAM-ASS.WI.30.02
[4] Role Description: Head Concurrent Operations NAM-ASS.RD.30
[5] Procedure: Authorise and Submit HSE Cases (NL) EPE.HSE.PR.02
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 6 of 14
Printed copies are uncontrolled
7 APPENDICES
Ref. Title Page
[1] Distribution list 6
[2] Revision list 7
[3] Example CO Agreement 8
[4] Example Emergency Response Table 9
[5] Example telecom list 10
[6] Example organigram 11
[7] Example HCO checklist 12
[8] Abbreviations list 13
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 7 of 14
Printed copies are uncontrolled
Appendix 1: Example Distribution list
Distribution List
CO Script: “…………………………..……..”
NAM Doc.No: …………………… Issue: …………………….
nr Department Function/Location copies
1 CO Custodian – Operations Manager 1
2 Head Area Operations 1
3 HCO 1
4 - T/DL Development 1
5 Well Engineering Well Engineer Operations 1
6 Well Engineering Senior Well Engineer 1
7 Well Engineering Completions Engineer 1
8 Noble Rig Manager 1
9 Noble George Noble OIM 1
10 Noble George NAM Drilling Supervisor 1
11 HMI (OIM) Offshore Installation Manager 1
12 UIE/S/N HSE department 1
14 UIE/P/S.. Marine/Land Operations 1
15 UIE/T/.. Structural and Underwater Engineering 1
16 CCK Plant Supervisor 1
17 UIE/S/N Emergency room 1
18 Document Control 1
19 ISC Engineering 1
20 1
21
22
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 8 of 14
Printed copies are uncontrolled
Document Revisions
Title: CO Agreement: “Drilling of Well 102 STR”
……………………………………………….
Rapport: NAM Doc.No: …………….……. Issue: ………………….
Rev.No.
Date
Pages Revised, Description of Change
Appendix 2 : Revision list
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 9 of 14
Printed copies are uncontrolled
Appendix 3: Examples CO Script
Offshore:
NAMASSWI3003App3a.docx
Onshore:
CO script generic format june 2013 rev 3.docx
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 10 of 14
Printed copies are uncontrolled
Appendix 4: Example of Emergency Response Table
NAMASSWI3003App4.docx
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 11 of 14
Printed copies are uncontrolled
Appendix 5 Example of Telecom list
Telecom list for ………….. – ……………
Title: Concurrent Operations Script “………….”
………….. and ………………..
Rapport: NAM Doc.No: ………….. Issue: ……………………………
Onshore Focalpoints
Head Area Operations Office:
Mobile:
Head Operations Office:
Mobile:
Wells Project Manager Office:
Mobile:
Senior Well Engineer Office:
Mobile:
Rig Manager Office:
Mobile:
Pagers via NAM security
Offshore Focalpoints
Head Concurrent Operations (HCO) Location:
Hoofd Mijnbouw installatie (HMI)
NAM Drilling Supervisor
RIG Radio room
Locations
Offshore
Den Helder
RIG
Onshore
Assen
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 12 of 14
Printed copies are uncontrolled
Appendix 6 Example Organogram
~~~~~~~~~~~~~~~~
Head
Operations
RIG
OIM
Activity
Co-Ordinator
Senior
Well Engineer
Organogram …………..….. - ………………
Head Area Operations
NAM Drilling Supervisor
Head Concurrent Operations
HCO
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 13 of 14
Printed copies are uncontrolled
Appendix 7 Example HCO Checklist (optional)
NAMASSWI3003App7.docx
NAM
Work Instruction
Prepare Concurrent Operations Script Restricted
Doc. No.: NAM-ASS.WI.30.03 EP No. : NAM200210100891 Page 14 of 14
Printed copies are uncontrolled
Appendix 8 Abbreviation list
ACT Asset Crisis Team (onshore emergency response)
ERP Emergency Response Plan
ERT Emergency Response Team (offshore investigation and search & rescue)
FFLB Free Fall Lifeboat (Platform)
FRC Fast Rescue Craft (on SBV)
HMI Hoofd Mijnbouw Installatie
HCO Head Concurrent Operations
LNG Locale Nood Group [Local Emergency Group] (offshore emergency response management)
MOB Man OverBoard
OCP Offshore Contingency Plan
OIM Offshore Installation Manager
POB Persons Onboard
SBB RP Scenario Based Brandbestrijdings- en Reddingsplan
SBV Stand-by Vessel
SHD Safety & Health Document
TEMPSC Totally Enclosed & Motor Powered Survival Craft