23
eni S.p.A. PAGE 1 of 23 1 Well Testing for Reservoir Management: A Case Study 2014-2015 Master in Petroleum Engineering and Operations eni Stage Thesis AUTHOR Pratik Nityanand Rao RESM / IPET Date: 15/10/2015 eni Stage Department eni Supervisors University Tutor RESM / IPET Mr. E. Beretta RESM / IPET Mr. G. Tripaldi Prof. F. Verga

Pratik Rao - Thesis Report FINAL

Embed Size (px)

Citation preview

Page 1: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

1 of 23

1

Well Testing for Reservoir Management: A Case Study

2014-2015 Master in Petroleum Engineering and Operations

eni Stage Thesis

AUTHOR

Pratik Nityanand Rao RESM / IPET

Date: 15/10/2015

eni Stage Department eni Supervisors University Tutor

RESM / IPET Mr. E. Beretta

RESM / IPET Mr. G. Tripaldi

Prof. F. Verga

Page 2: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

2 of 23

2

Management Summary

The scope of this project was to verify when well testing interpretation of permanent

gauges was feasible and helpful for reservoir monitoring and to provide a preliminary

reservoir characterization for the case study.

For the project, bottom-hole pressures from downhole gauges and field rates (April 2012 –

December 2013) were obtained from the well archives and inputted into Interpret in order

to achieve an interpretation of a selected build-up period.

The bottom-hole pressures and field rates were used from the aforementioned time period

because after December 2013, interference from other wells were occurring, therefore the

data post December 2013 could not be interpreted an was rejected.

From the interpretation of a single build-up period, the wellbore & bulk reservoir properties

along with the reservoir boundary distances were identified, which were subsequently

used to calculate a preliminary estimate of the gas originally in place (GOIP) using the

material balance and geologist’ method.

Page 3: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

3 of 23

3

Conclusions

The standard approach for build-up and drawdown interpretation could not be

applied to this case study due to inadequate build-up and drawdown durations,

hence an alternative workflow was implemented.

The average reservoir pressure at gauge depth (2752 m TVDss) after 0.6 GSm3 of

cumulative production resulted to be 348 bar, with a corresponding depletion of

about 25 bar (initial reservoir pressure = 372.9 bar from WFT / RFT).

The average effective gas permeability for Well A was 40 mD.

The skin was about -4, which indicates that the well is not damaged.

The skin could not be sub-divided into its components (mechanical, geometric and

turbulence) because at the horizontal well, early time cannot be recognised on the

derivative plot.

The preliminary estimate of GOIP was 14.40 GSm3 (from material balance) after

cumulative production of 0.6 GSm3.

Page 4: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

4 of 23

4

List of Contents

1. PROJECT BACKGROUND ...................................................................................................... 6

1.1. PROJECT SCOPE ......................................................................................................................................... 6

1.2. INTERFERENCE FROM NEARBY WELLS .............................................................................................. 6

1.3. STANDARD APPROACH TO WELL TESTING INTERPRETATION ...................................................... 7

1.4. ALTERNATIVE APPROACH TO WELL TESTING INTERPRETATION ............................................... 8

2. DISCUSSION OF THE CASE STUDY .................................................................................. 10

2.1. GENERAL INFORMATION OF THE FIELD .......................................................................................... 10

2.2. PRODUCTION HISTORY .......................................................................................................................... 12

2.3. COMPARISON OF BUILD-UPS FOR WELL A ....................................................................................... 13

2.4. SUB-MODEL 1 – RADIAL COMPOSITE MATCH FOR WELL A .......................................................... 14

2.5. SUB-MODEL 2 – CLOSED SYSTEM MATCH FOR WELL A ................................................................. 16

2.6. CLOSED SYSTEM VALIDATION ............................................................................................................. 18

2.7. PRELIMINARY ESTIMATE OF GOIP (P/Z METHOD) .......................................................................... 19

2.8. PRELIMINARY ESTIMATE OF GOIP (GEOLOGISTS’ METHOD) ..................................................... 20

3. CONCLUSIONS ........................................................................................................................ 22

4. BIBLIOGRAPHY ..................................................................................................................... 23

Page 5: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

5 of 23

5

List of the Figures

FIGURE 1: DRAWDOWN SCENARIO ...................................................................................................................................... 6

FIGURE 2: BUILD-UP SCENARIO .......................................................................................................................................... 7

FIGURE 3: CLOSED RECTANGULAR RESERVOIR ................................................................................................................... 7

FIGURE 4: ALTERNATIVE APPROACH................................................................................................................................... 9

FIGURE 5: DOWN-HOLE CONFIGURATION OF WELL A ...................................................................................................... 11

FIGURE 6: DOWN-HOLE CONFIGURATION OF WELL B ....................................................................................................... 12

FIGURE 7: CLOSED RECTANGULAR RESERVOIR VALIDATION ............................................................................................ 19

FIGURE 8: P/Z METHOD ...................................................................................................................................................... 19

List of the Tables

TABLE 1: GENERAL INFORMATION OF THE FIELD (RESERVOIR & FLUID DATA, WELLS A & B DATA) ............................. 10

TABLE 2: OUTPUT RESULTS FOR SUB-MODEL 1 ................................................................................................................ 16

TABLE 3: OUTPUT RESULTS FOR SUB-MODEL 2 ................................................................................................................ 18

TABLE 4: RESULTS OF P/Z METHOD ................................................................................................................................... 20

List of the Graphs

GRAPH 1: PRESSURE AND DERIVATIVE CURVES OF DRAWDOWN & BUILD-UP FOR STANDARD APPROACH ....................... 8

GRAPH 2: PRESSURE & DERIVATIVE CURVES OF DRAWDOWN & BUILD-UP FOR ALTERNATIVE APPROACH ...................... 8

GRAPH 3: PRODUCTION HISTORY FOR WELLS A & B ........................................................................................................ 13

GRAPH 4: COMPARISON OF BUILD-UPS FOR WELL A ........................................................................................................ 14

GRAPH 5: LOG-LOG MATCH OF SUB-MODEL 1 ................................................................................................................. 15

GRAPH 6: PRESSURE HISTORY MATCH OF SUB-MODEL 1 ................................................................................................. 15

GRAPH 7: LOG-LOG MATCH OF SUB-MODEL 2 ................................................................................................................. 17

GRAPH 8: PRESSURE HISTORY MATCH OF SUB-MODEL 2 ................................................................................................. 17

GRAPH 9: GOIP ESTIMATION FROM P/Z METHOD .............................................................................................................. 20

Page 6: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

6 of 23

6

1. PROJECT BACKGROUND

1.1. Project Scope

The scope of this project was to verify when well testing interpretation of permanent

gauges was feasible and helpful for reservoir monitoring and to provide a preliminary

reservoir characterization for the case study. The following key points were addressed

during the project:

Interference from nearby wells

Inadequate build-up and drawdown periods

Complexity of the interpretation model

1.2. Interference from Nearby Wells

For the drawdown scenario (please see figure below), there are 5 wells that are open and

producing at a constant rate. Each well is only producing within its drainage area and is

able to defend it from being encroached upon by the other 4 wells, hence the interpretation

is usually more reliable.

Figure 1: Drawdown Scenario

For the build-up scenario (please see figure in next page), there are 4 wells that are open

and producing at a constant rate and 1 well which is shut-in and therefore not producing.

Page 7: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

7 of 23

7

In this case, the 4 open wells initially deplete their respective drainage areas and then

invade that of the shut-in well. This phenomenon is known as interference from nearby

wells and the build-up late time models are usually disturbed, hence they cannot be

interpreted.

Figure 2: Build-Up Scenario

1.3. Standard Approach for Well Testing Interpretation

The standard approach for well testing interpretation is performed for long build-up and

drawdown periods. If a closed rectangular reservoir is considered, the reservoir response

shows IARF (Infinite Acting Radial Flow) behaviour before all the barriers are reached.

The duration of the radial flow is a function of the well location inside the rectangular area.

Figure 3: Closed Rectangular Reservoir

Page 8: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

8 of 23

8

In the drawdown derivative, when all sealing boundaries are reached, both the pressure

and deritvative curve follow a slope of 1 (straight line). For the build-up derivative, when

all sealing boundaries are reached, the reservoir pressure tends to stabilise at the average

reservoir pressure and therefore the curve drops.

Graph 1: Pressure and Derivative Curves of Drawdown & Build-Up for Standard Approach

1.4. Alternative Approach for Well Testing Interpretation

The alternative approach for well testing interpretation is performed during short or

inadequate build-up and drawdown durations. The data for this case is very difficult to

interpret and the model is complicated, hence it is divided into 2 sub-models.

Graph 2: Pressure & Derivative Curves of Drawdown & Build-Up for Alternative Approach

Page 9: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

9 of 23

9

Figure 4: Alternative Approach

Prior to commencing on the interpretation of the separate sub-models, it is compulsory to

set the initial reservoir pressure, which can be obtained from the WFT/RFT. Then, using a

build-up derivative, an interpretation is run in order to get a log-log plot which is

subsequently used to match the early and middle times for estimation of wellbore and bulk

reservoir properties. The next step is to match the middle and late times for estimation of

the reservoir boundaries.

If the simulated bottom-hole pressures do not match the actual bottom-hole pressures, the

boundary distances are to be modified and the simulation is restarted. In the event of both

bottom-hole pressures being matched, the variable skin is applied to correct the non-Darcy

skin and therefore improve the drawdown matching.

The 2 sub-models had to be consistent with the reservoir outer permeability because this

value was present in the middle time model, which was used in both sub-models.

Page 10: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

10 of 23

10

2. DISCUSSION OF THE CASE STUDY

2.1. General Information of the Field

Table 1: General Information of the Field (Reservoir & Fluid Data, Wells A and B Data)

Well A is a single producer and has a horizontal gravel pack along with 7” – 5.5”

completion. The gauge depth is 2752 m TVDSS and top and bottom gravel are at 2769 m

TVDSS and 2779 m TVDSS respectively. The angle of well A is 85-89 degrees at the

target, with a horizontal net length (Lw) of 200 m.

The geological data for well A was obtained between the top and bottom gravel, between

3104 m MD and 3320 m MD respectively. The lithology of this region was predominantly

high quality sandstone (Φ > 24%) along with poor quality sandstone (Φ = 9% – 15%) near

the top gravel.

Page 11: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

11 of 23

11

Figure 5: Down-Hole Configuration of Well A

Well B is also a single producer and has a horizontal gravel pack along with 7” – 5.5”

completion. The gauge depth is 2753 m TVDSS and top and bottom gravel are at 2785 m

TVDSS and 2798 m TVDSS respectively. The angle of well B is 85 degrees at the target,

with a horizontal net length (Lw) of 130 m.

The geological data for well B was obtained between the top and bottom gravel, between

3404 m MD and 3557 m MD respectively. The lithology of this region was a mixture of

shale and sandstone that ranged from high to poor quality. Near the bottom gravel, the

lithology was all high quality sandstone with porosity being greater than 24%.

Page 12: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

12 of 23

12

Figure 6: Down-Hole Configuration of Well B

2.2. Production History

The production history for wells A and B was split into two sections: field production for

well A and alternating production for wells A and B. Due to an electrical failure in the

gauges during the first 6 months of production, the bottom-hole pressures of well A could

not be recorded, however the initial reservoir pressure at gauge depth was 372.9 bar.

There were 3 distinct build-up periods when well A was shut-in, where the reservoir

pressure equilibrated to 348 bar (average reservoir pressure) at the end of the 3rd build-up

period. Well B was shut-in for this entire time period, except being open for around 3-4

days during its clean-up phase.

Page 13: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

13 of 23

13

Graph 3: Production History for Wells A & B

In section 2, there is alternating production for wells A & B, whereby when well A is shut-in

(production = 0), well B is open and producing and vice versa. However, during the build-

up of well A (when well B is production), its bottom-hole pressure initially increases and

then instead of stabilizing, it starts to decrease. The same can be seen when well B is in

build-up and well A in production. This proves that interference from wells is occurring and

therefore, interpretation of data (build-up and drawdown) is not possible for either wells.

Hence, this information was not used for the project and only that in section 1 (field

production for well A) was considered.

2.3. Comparison of Build-Ups for Well A

The bottom-hole pressures and field rates for well A were tabulated on Microsoft Excel and

then inputted into Interpret, where the production and pressure histories were displayed in

a graphical form. Flow periods were defined and each build-up period was selected to be

interpreted on the log-log plot to determine their consistency. All the build-up periods

Page 14: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

14 of 23

14

followed more or less the same trend (horizontal well) hence, they were consistent with

one another.

Graph 4: Comparison of Build-Ups for Well A

2.4. Sub-Model 1: Radial Composite Match for Well A

Since the log-log plot for all 3 build-ups displayed a shape that was pertaining to a

horizontal well, this model was used for matching the real data. The effective horizontal

producing length (Lw), for which the simulated data would match the real data, was a lot

greater than the actual Lw for well A (200 m). This was unrealistic, hence the vertical well

model was used for the matching on the log-log plot.

The interpretation for the first sub-model was done using wellbore storage & skin, radial

composite and infinite lateral extent. Since only the early and middle time models were to

be matched, the late time selected was infinite lateral extent, whereby the boundaries were

not defined. From the log-log match, the early and middle times are well honoured.

Page 15: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

15 of 23

15

Graph 5: Log-Log Match of Sub-Model 1

The first build-up period was analysed for this interpretation, and from the pressure history

match, all 3 build-ups were well honoured.

Graph 6: Pressure History Match of Sub-Model 1

Page 16: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

16 of 23

16

The key output results are shown in the table below:

Table 2: Output Results for Sub-Model 1

The well skin could not be divided into its respective components (mechanical, geometric

and turbulence) because at the horizontal well, the early time could not be recognized on

the derivative plot. Another reason as to why the well skin could not be divided was

because there was no spherical flow.

2.5. Sub-Model 2: Closed System Match for Well A

The interpretation for sub-model 2 was done using wellbore storage & skin, homogenous

reservoir and closed rectangle. Since only the middle and late times were to be matched,

a closed rectangle was selected as the late time in order to determine the sealing

boundaries of the reservoir. The early time matching was ignored.

Page 17: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

17 of 23

17

Graph 7: Log-Log Match of Sub-Model 2

As with the first sub-model, the first build-up period was analysed for this interpretation,

and from the pressure history match, all 3 build-ups were well honoured.

Graph 8: Pressure History Match of Sub-Model 2

Page 18: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

18 of 23

18

The key output results are shown in the table below:

Table 3: Output Results for Sub-Model 2

The reservoir outer permeability of 40 mD was consistent with both sub-models as it was

present in the middle time model, which was matched in sub-models 1 and 2.

2.6. Closed System Validation

From the late time model, the reservoir boundary distances were 860 m, 1300 m, 2300 m

and 5750 m respectively, with a total area of 17.40 km2.

Area = (860 + 1300) x (2300 + 5750) = 17.40 km2

Page 19: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

19 of 23

19

Figure 7: Closed Rectangular Reservoir Validation

2.7. Preliminary Estimate of GOIP (p/z Method)

A preliminary estimate of the gas originally in place (GOIP) was done using the p/z

method, where the GOIP (G) was obtained by plotting a graph of p/z vs Gp, extrapolating

the line to the point where p/z = 0 and reading the value of G on the x axis.

Figure 8: p/z Method

Page 20: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

20 of 23

20

In the case of the project, at cumulative production of 0 GSm3, the p/z was initial pressure

(372.9 bar) divided by its corresponding z factor (1.028) and after cumulative production of

0.6 GSm3, the p/z was the average reservoir pressure at the end of the 3rd build-up period

(348 bar) divided by its corresponding z factor (1.001). The value of GOIP at p/z = 0 was

14.40 GSm3 (represented by the blue cross).

Flow Period Gp (GSm3) Pressure (bar) z Factor p/z 0 0.0 372.9 1.028 362.74

234 0.6 348.0 1.001 347.64

Table 4: Results of p/z Method

Graph 9: GOIP Estimation from p/z Method

2.8. Preliminary Estimate of GOIP (Geologists’ Method)

The geologists’ method was used as another approach to obtain a preliminary estimate of

the GOIP and to verify the consistency of that from the p/z method. The key information

used to calculate the GOIP is given below:

Page 21: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

21 of 23

21

Area = 17.40 km2 = 17,400,000 m

Net Pay = 14 m (Net-to-gross ratio already factored in)

Porosity () = 0.23

Irreducible Water Saturation (Swi) = 0.1

Gas Formation Volume Factor (FVF) = 0.0036 Rm3 / m3

Area * Net Pay * * (1- Swi) 17,400,000 * 14 * 0.23 * (1 – 0.1)

GOIP = ------------------------------------------- = ------------------------------------------- = 14.00 GSm3

FVF 0.0036

The GOIP from geologists’ method is around 97% of the GOIP from material balance

(14.00 / 14.40), hence both values are consistent with one another.

Page 22: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

22 of 23

22

3. CONCLUSIONS

Taking into account the 3 key points mentioned earlier in the report, each one had a

solution which was implemented in the case study.

The solution for interference from nearby wells was to obtain a long drawdown acquisition

at constant rate, therefore the well testing interpretation was performed on data that was

unaffected by interference i.e. field production of well A only. This was because the build-

up and drawdown data for alternating production of wells A and B could not be interpreted

on the software.

The solution for inadequate build-up and drawdown durations was to implement an

alternative approach for interpretation, which required a reliable value of initial reservoir

pressure from WFT / RFT and at least one build-up acquisition. The initial reservoir

pressure obtained was 372.9 bar and the 1st build-up period from field production of well A

was analyzed.

The solution for complexity of the model was to divide it into 2 sub-models and interpret

each separately. The wellbore and bulk reservoir properties were obtained from sub-

model 1, by matching the early and middle times and the boundary distances were

obtained from sub-model 2, by matching the middle and late times. From this information,

a preliminary estimate of the GOIP could be calculated using the material balance and

geologists’ method.

Another solution for the model complexity was to use numerical well testing software,

however this was not possible because the software is used for complex systems,

complex geological features and multiphase flow, therefore this was beyond the scope of

the project.

Page 23: Pratik Rao - Thesis Report FINAL

eni S.p.A.

PAGE

23 of 23

23

4. BIBLIOGRAPHY

[1] Gas Well Testing Handbook, Amanat U. Chaudhry

[2] Dynamic Data Analysis, Olivier Houze, Didier Viturat & Ole S. Fjaere

[3] Introductory Well Testing, Tom Aage Jelmert

[4] Politecnico di Torino 2nd Level Master 2014-15 Notes, Prof. Francesca Verga

[5] Well Testing Analysis in Practice, Prof. Alain C. Gringarten