  • 8/3/2019 Prasarana Ima

    1/97

    Item Description Unit Quantity

    1 PRELIMINARIES

    All onligations, directions and instruction in these General Conditions

    and Preliminaries (hereinafter referred to as "Preliminaries") are

    directed at the Sub-Contractor, unless otherwise noted. The Sub-

    Contractor shall ensure that all suxh obligations, directions and

    instructions, directions and instructions are complied with whether by

    himself or by his servants, agents, workmen or sub-contractors.

    The Sub-Contractor is deemed to have included or allowed for

    compliance with all requirements in these Preliminaries in the Sub-

    Contract Sum, regardless of whether or not specific stipulations on

    such inclusion have been in the clauses herein.

    A Performance bond sum -

    B Compliance with the Contracts. sum -

    C Other (Please specify) : sum -

    (a) (b)

    (c )

    (d)

    (e)

    (f) .

    (g)

    CARRIED TO COLLECTIONBQ 1/1

    PRELIMINARIES (CONT'D)

    Specified Requirements

    Testing and Sampling

    A Testing of all materials and works at an approved laboratory to

    ensure compliance with the Specification including attendance for

    additional tests not stipulated in the Specified.

    sum -

  • 8/3/2019 Prasarana Ima

    2/97

    Setting Out

    B Establishment of all necessary benchmarks for setting out of the

    works

    sum -

    Pregress Re ort

    C Preparation of monthly progress report as per Specification. sum -

    D Provide monthly progress colour photographs as per Specification. sum -

    Establishment and Maintenance of Nominated Sub-Contractor's

    Officers etc.

    E Establishment and removal of Nominated Sub-Contractor's offices,

    workshops, stores and housing including utilities.

    sum -

    F Maintenance of Nominated Sub-Contractor's offices, workshops,

    stores and housing including utilities for the duration of the works

    sum -

    CARRIED TO COLLECTIONBQ 1/2

    PRELIMINARIES (CONT'D)

    Specified Requirements (Cont'd)

    Safety Measures

    A Nominated Sub-Contract to allow for the following safety measures

    :-

    sum -

    (a) Provide and install all necessary protective netting or other

    measures for the safety of workmen. To protect the public from all

    risks of injury, especially from flying or falling objects, at all stages of

    construction. Safety measures adopted shall satisfy the

    requirements of the relevant Authorities. To allow for additional

    measures reasonably that may be required by the E.R. or

    Contractor.

    (b) Allow here for providing protection to Nominated Sub-Contractor's plant and temporary works as may be necessary.

  • 8/3/2019 Prasarana Ima

    3/97

    (c ) Provide all necessary measures for the proper protection of

    materials, goods, completed work and partly completed work from

    any form of damage or deterioration and against all weather

    conditions, work activities or other potential causes of damage

    including providing tarpaulins, guardrails, plywood, polystyrene and

    any other types of coverings or protection (including a combination of

    coverings or proection where required).

    CARRIED TO COLLECTION

    BQ 1/5

    PRELIMINARIES (CONT'D)

    Specified Requirements (Cont'd)

    Drawings

    A The Tenderer shall check and examine the drawings and he

    accompanying tender documents to satisfy himself that allinformation necessary for preparing his tender has been provided.

    Report any missing drawings, documents, pages or other

    discrepancies to the E.R.. No claims for extra costs or time as a

    result of non-examination will be considered.

    Before commencing on any portion of the Sub-Contractor Works, the

    Nominated Sub-Contractor shall check and verify all details and

    dimensions shown in or on any of the drawings, specifications or

    other documents which have been provided to him in connection with

    the Sub-Contract Works and shall immediately notify the E.R. of any

    discrepancy.

    (a) Preparation, completion and submission of shop drawings for allSub-Contract Works in accordance with the requirement of the Sub-

    Contract. Shop drawings for M&E works are to be measured

    separately

    (b) Preparation, completion and submission of as-built drawings for

    the Sub-Contract Works in accordance with the requirement of the

    Sub-Contract. As-built drawings for M&E works are to be measured

    separately

    CARRIED TO COLLECTION

    BQ 1/6

    PRELIMINARIES (CONT'D)

    Specified Requirements (Cont'd)

    COLLECTION PAGE

    BQ 1/1

  • 8/3/2019 Prasarana Ima

    4/97

    BQ 1/2

    BQ 1/3

    BQ 1/4

    BQ 1/5

    BQ 1/6

    TOTAL FOR BILL NO. 1 CARRIED

    TO SUMMARY OF TENDER SUM

    BQ 1/7

    BILL NO. 2

    BILL

    NO.

    BILL DESCRIPTION PAGE NO. AMOUNT

    (RM)

    2.1.1 Piling B/Q2.1.1/6

    2.1.2 Work Below Lowest Floor Finish B/Q2.1.2/5

    2.1.3 Frame B/Q2.1.3/4

    2.1.4 Upper Floor B/Q2.1.4/2

    2.1.5 Roof B/Q2.1.5/5

    2.1.6 Staircase and Handrailing B/Q2.1.6/9

    2.1.7 External Wall B/Q2.1.7/3

    2.1.8 Window B/Q2.1.8/2

    2.1.9 Door B/Q2.1.9/4

    2.1.10 Internal Wall & Partition B/Q2.1.10/2

    2.1.11 Internal Wall Finishes B/Q2.1.11/2

    2.1.12 Internal Floor Finishes B/Q2.1.12/2

    2.1.13 Internal Ceiling Finishes B/Q2.1.13/2

    2.1.14 External Finishes B/Q2.1.14/3

  • 8/3/2019 Prasarana Ima

    5/97

    2.1.15 Mechanical and Electrical B/Q2.1.15/18

    TOTAL FOR OF PARK & RIDE FACILITIES AT STATION 4

    CARRIED TO SUMMARY OF TENDER SUMBQ 2.1/1

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES STATION 4

    2.1.1 Piling (All Provisional)

    Bored Cast In Place

    Notes :

    Notwithstanding the laid rules laid down in the Standard Method of

    Measurement for Building Works for use in Malaysia - 2nd EditionMetric, the rates for piles and piling shall be deemed to include the

    followings, namely:

    1) Boring will be measured from ground level to include for

    empty bore from ground level to the planned specified cut off level

    (i.e. up to 75mm from bottom of pile cap) at ground level

    2) Concrete and reinforcement are measured nett i.e. from the

    bottom level of the bore to the planned specified cut off level (i.e. up

    to 75mm from bottom of pile cap).

    3) The rates for piles and piling are to include for :

    a) All labour and materials for the complete pile inclusive of

    wastage.

    b) Any pre-boring required.

    c) Normal wet weather delays.

    d) Replacement of damaged piles and piles which failed under

    test.

    e) Standing time for equipment and labour due to all the foregoing

    circumstances.

    f) Backfilling and removal of surplus excavated material off the site

    and including all temporary casing or bentonite drilling fluid.

  • 8/3/2019 Prasarana Ima

    6/97

    g) All necessary materials and equipment for the alignment and

    positioning of the piling equipment over undulating surfaces of site.

    CARRIED TO COLLECTIONBQ 2.1.1/1

    2.1 PARK & RIDE FACILITIES STATION 4

    2.1.1 Piling (All Provisional) (Cont'd)

    Bored Cast In Place (Cont'd)

    Notes : (Cont'd)

    3) The rates for piles and piling are to include for : (Cont'd)

    h) All necessary materials and incidental works to piling including

    removal of all obstructions.

    j) Any first boring required etc. to determine length of piles.

    k) Empty bore (other than for test pile mentioned above)

    l) Before commencement, and after the completion of the piling

    work, the Contractor shall engaged Licensed Surveyor to set out

    the correct aligment and eccentricity of each pile strictly in

    accordance with the E.R's layout drawings or any other layout

    drawings deemed necessary and subsequently issued by the

    Engineer during the progress of the piling works and submits

    drawings for piles driven certified by the Licensed Survryor on

    completion of the works.

    CARRIED TO COLLECTIONBQ 2.1.1/2

    2.1 PARK & RIDE FACILITIES STATION 4

    2.1.1 Piling (All Provisional) (Cont'd)

    Bored Cast In Place (Cont'd)

    A Allow for the supply and transportation to site all necessary piling

    frames, plant, tools, equipment, staging, framing and platformsnecessary for supporting the piling plant in and around the site over

    the position as required including any excavation that may be

    associated with this item, for the complete execution of the piling

    works including all handling, mobilising, assembling, maintaining,

    dismantling and removing from site on completion and for any idling

    time

    Item

  • 8/3/2019 Prasarana Ima

    7/97

    B Allow for the submission of records of all pile in duplicate duly

    signed by the Contractor and the Engineer's representative and

    delivered to the Engineer as the work proceeds

    Item

    C Allow for setting out and preparation of As-Built drawings Item

    Bore only through whatever type of formation (except rock) whichmay be met and removed excavated materials off site including all

    necessary coring, casing, lining and drilling fluid for

    D 600mm diameter bored cast in places piles (In No. 37) m 1265

    E 750mm diameter bored cast in places piles (In No. 208) m 8656

    Supply and placing of reinforced concrete Grade 40 by tremie

    method in diameter boreholes

    F 600mm diameter boreholes m 1184

    G 750mm diameter boreholes m 8112

    CARRIED TO COLLECTION

    BQ 2.1.1/3

    2.1 PARK & RIDE FACILITIES STATION 4

    2.1.1 Piling (All Provisional) (Cont'd)

    Bored Cast In Place (Cont'd)

    High tensile bar reinforcement as described

    A 10mm diameter high tensile bar reinforcement as described in pile

    as spiral

    kg 58,444

    B 25mm diameter high tensile bar reinforcement as described in pile kg 30215

    C 32mm diameter high tensile bar reinforcement as described in pile kg 420,239

    Cut off pile head at required level including trimming, stripping,

    dressing for key and strengthening and bending bar reinforcement in

    positing for pile cap connections and remove all debris off the site

    D 600mm diameter no. 37

    E 750mm diameter no. 208

  • 8/3/2019 Prasarana Ima

    8/97

    Carry out high strain dynamic test including preparation of pile head

    and charges of specialist testing specialist sub-contractor.

    F 750mm diameter no. 4

    Carry out integrity shock test including charges of specialist testing

    specialist sub-contractor.

    G 750mm diameter no. 4

    Carry out sonic logging test including charges of specialist testing

    specialist sub-contractor.

    H 750mm diameter no. 1

    CARRIED TO COLLECTIONBQ 2.1.1/4

    2.1 PARK & RIDE FACILITIES STATION 4

    2.1.1 Piling (All Provisional) (Cont'd)

    Bored Cast in Place (Cont'd)

    A Provide all necessary equipment kentledge and labour, and test only

    finish 750mm diameter working pile of twice the working load of

    6000 kN as required by the E.R. including all other before the

    commencing of the building works or on completion of piling work

    no. 1

    CARRIED TO COLLECTION

    BQ 2.1.1/5

    COLLECTION PAGE

    BQ 2.1.1/1

    BQ 2.1.1/2

    BQ 2.1.1/3

    BQ 2.1.1/4

    BQ 2.1.1/5

    TOTAL FOR BILL NO. 2.1.1 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4BQ 2.1.1/6

    2.0 PARK & RIDE FACILITIES

  • 8/3/2019 Prasarana Ima

    9/97

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.2 Work Below Lowest Floor Finishes

    Excavate and get out commencing from earthworks formation levels

    A Pit for pile cap in depth exceeding 2.00 m but not exceeding 4.00m m3 1233

    B Trench for ground beam in depth exceeding 0.25m but not

    exceeding 1.00m

    m3 525

    C Reduce level for ground floor slab in depth not exceeding 0.25m m3 652

    -------------------------------------

    D Disposal on site and off site of excavated material arising fromexcavations, remainder load and car away within appropriate

    distance to E.R's approval

    m3 1601

    E Filling to excavation for material arising from excavations including

    the works up levels where direced within the site

    m3 810

    CARRIED TO COLLECTION

    BQ 2.1.2/1

    2.1 PARK & RIDE FACILITIES AT STATION 4 (CONTD'T)

    2.1.2 Work Below Lowest Floor Finishes (Cont'd)

    50mm thick lean concrete Grade 15 as described blinding screed,

    apread and levelled under

    A Pile cap m2 451

    B Ground beam m2 808

    C Concrete bed m2 3728

    Vibrated reinforced concrete Grade 15 (ready to be hacked in future)

    as described filled into formwork and well packed around

    reinforcement in (Provisional)

    D Ground beam m3 4

    E Concrete bed m3 6

    Vibrated reinforced concrete Grade 40 as described filled into

    formwork and well packed around reinforcement in

  • 8/3/2019 Prasarana Ima

    10/97

    F Pile cap m3 760

    G Ground beam m3 361

    H Column stump m3 49

    J Concrete bed m3 559

    CARRIED TO COLLECTION

    BQ 2.1.2/2

    2.1 PARK & RIDE FACILITIES AT STATION 4 (CONTD'T)

    2.1.2 Work Below Lowest Floor Finishes (Cont'd)

    High tensile bar reinforcement in straight and bends bars as

    described

    A 12mm diameter in pile cap kg 450

    B 16mm diameter in pile cap kg 19430

    C 20mm diameter in pile cap kg 18438

    D 25mm diameter in pile cap kg 45872

    E 32mm diameter in pile cap kg 55720

    F 10mm diameter in ground beam as stirrups kg 10890

    G 12mm diameter in ground beam as stirrups kg 81

    H 12mm diameter in ground beam kg 37

    J 16mm diameter in ground beam kg 8034

    K 20mm diameter in ground beam kg 4823

    L 25mm diameter in ground beam kg 14949

    M 32mm diameter in ground beam kg 21989

    CARRIED TO COLLECTIONBQ 2.1.2/3

    2.1 PARK & RIDE FACILITIES AT STATION 4 (CONTD'T)

    2.1.2 Work Below Lowest Floor Finishes (Cont'd)

  • 8/3/2019 Prasarana Ima

    11/97

    High tensile bar reinforcement in straight and bends bars as

    described

    A 10mm diameter in column stump as links kg 2713

    B 12mm diameter in column stump kg 18

    C 16mm diameter in column stump kg 221

    D 20mm diameter in column stump kg 444

    E 25mm diameter in column stump kg 462

    F 32mm diameter in column stump kg 28206

    G 10mm diameter in concrete bed kg 34273

    H 16mm diameter in concrete bed kg 312

    Sawn formwork as described to

    J Sides of pile cap m2 1159

    K Sides of ground beam m2 1816

    L Sides of column stump m2 331

    CARRIED TO COLLECTION

    BQ 2.1.2/4

    COLLECTION PAGE

    BQ 2.1.2/1

    BQ 2.1.2/2

    BQ 2.1.2/3

    BQ 2.1.2/4

    TOTAL FOR BILL NO. 2.1.2 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4BQ 2.1.2/5

    2.0 PARK AND RIDE

    2.1 PARK AND RIDE STATION 4

    2.1.3 Frame

  • 8/3/2019 Prasarana Ima

    12/97

    Vibrated reinforced concrete Grade 40 as described filled into

    formwork and well packed around reinforcement in

    A Column m3 887

    B beam m3 2359

    Vibrated reinforced concrete Grade 15 (ready to be hacked in future

    as described filled into formwork and well packed around

    reinforcement in (Provisional)

    C Beam m3 2

    High tensile bar reinforcement in straight and bends bars as

    described

    D 10mm diameter in column as links kg 15955

    E 10mm diameter in beam as stirrups kg 77786

    F 12mm diameter in beam as stirrups kg 356

    G 12mm diameter in column kg 421

    H 16mm diameter in column kg 11025

    J 20mm diameter in column kg 7,217

    K 25mm diameter in column kg 18,594

    L 32mm diameter in column kg 179,280

    CARRIED TO COLLECTION

    BQ 2.1.3/1

    2.1 PARK AND RIDE STATION 4 (CONT'D)

    2.1.3 Frame (Cont'd)

    High tensile bar reinforcement in straight and bends bars as

    described (cont'd)

    A 12mm diameter in beam kg 2835

    B 16mm diameter in beam kg 49310

    C 20mm diameter in beam kg 46181

    D 25mm diameter in beam kg 79055

    E 32mm diameter in beam kg 299492

  • 8/3/2019 Prasarana Ima

    13/97

    Sawn formwork as described to

    F Sides of column m2 5902

    G Sides and soffit of beam m2 17713

    -----------------------------------------------

    H 63mm x 63mm x 6mm Thick mild steel to B.S. 15 as described

    angle guard 800mm long ramset including painting to exposed

    surfaces to concrete column and all necessary works

    CARRIED TO COLLECTION

    BQ 2.1.3/2

    2.1 PARK AND RIDE STATION 4 (CONT'D)

    2.1.3 Frame (Cont'd)

    The Following in Lift Core Wall

    Vibrated reinforced concrete Grade 40 as described filled into

    formwork and well packed around reinforcement in

    A Wall exceeding 150mm but not exceeding 300mm thick m3 84

    High tensile bar reinforcement ins traight and bends bars as

    described

    B 12mm diameter in wall kg 3519

    C 16mm diameter in wall kg 1001

    D 25mm diameter in wall kg 1918

    sawn formwork as described to

    E Sides of wall m2 60

    F Extra Over for sides of wall to a height exceeding 3.50m high m2 280

    Wrought formwork as described to

    G Sides of wall m2 52

    H Extra Over for sides of wall to a height exceeding 3.50m high m2 242

    ------------------------------------------

  • 8/3/2019 Prasarana Ima

    14/97

    J Extra Over for forming door opening size 1300mm x 2250mm

    including all necessary formwork

    no. 12

    (End of The Following in Lift Core Wall)

    CARRIED TO COLLECTION

    BQ 2.1.3/3

    COLLECTION PAGE

    BQ 2.1.3/1

    BQ 2.1.3/2

    BQ 2.1.3/3

    TOTAL FOR BILL NO. 2.1.3 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4

    BQ 2.1.3/4

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.4 Upper Floor

    Vibrated reinforced concrete Grade 40 as described filled into

    formwork and well packed around reinforced in

    A 150mm thick suspended floor slab m3 4059

    B 175mm thick suspended floor slab m3 6

    ----------------------------------------------

    C Extra Over for forming scuper drain 200mm wide x 200mm deep

    including all necessary bar reinforcement and formwork

    m 96

    D Extra Over for forming 100mm diameter outlet including all

    necessary and formwork

    no 24

    Vibrated reinforced concrete Grade 15 (ready to be hacked in future)

    as descibed filled into formwork and well packed around

    reinforcement in (Provisional)

    E 150mm thick suspended floor slab m3 10

    F 175mm thick suspended floor slab m3 1

    High tensile bar reinforcement in straight and bends bars as

    described

  • 8/3/2019 Prasarana Ima

    15/97

    G 10mm diameter in suspended floor slab kg 209,214

    H 12mm diameter in suspended floor slab kg 10461

    Sawn formwork as described to

    J Soffit of suspended slab m2 27092

    K Edge of concrete not exceeding 250mm high m 39

    -------------------------------------

    L 300mm x 50mm heavy high tensile grating m 96

    CARRIED TO COLLECTIONBQ 2.1.4/1

    COLLECTION PAGE

    BQ 2.1.4/1

    TOTAL FOR BILL NO. 2.1.4 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4BQ 2.1.4/2

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.5 Roof

    Vibrated reinforced concrete Grade 40 as described filled into

    formwork and well packed around reinforcement in

    A 150mm thick suspended roof slab m3 40

    B 175mm thick suspended roof slab m3 1044

    -------------------------------------------

    C Extra Over for forming 230mm wide x 50mm deep scupper drain

    including all necessary bar reinforcements and formworks

    m 579

    D Extra Over forming opening 150mm diameter rainwater downpipe no 30

    High tensile bar reinforcement in straight and bends bars as

    described

    E 10mm diameter in suspended roof slab kg 79446

  • 8/3/2019 Prasarana Ima

    16/97

    F 12mm diameter in suspended roof slab kg 135

    Sawn formwork as described to

    G Soffit of suspended roof slab m2 6026

    H Edge of concrete not exceeding 250mm high m 579

    CARRIED TO COLLECTION

    BQ 2.1.5/1

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.5 Roof

    Supply and dose 'XYPEX Admix C-1000NF' or other equal and

    approved integral concrete waterproofing system by crystallization

    effect at the dosage rate of 0.8% of the total cementitious contentbased on the proposed design mix, all strictly in accordance to

    manufacturer's

    A To slab m3 1088

    Supply and apply three (3) coats of 'XYLASTIC-500' or other equal

    and approved liquid applied seamless polyurethane waterproofing

    membrane at the rate of 0.5kg/m2 per coat complete with a layer of

    heavy duty fiber mesh reinforcement in between coating onto proper

    prepared surface, all in accordance with manufacturer's instruction :

    B To slab m2 3367

    C Extra over for scupper drain m 579

    CARRIED TO COLLECTIONBQ 2.1.5/2

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.5 Roof

    Supply and lay 75mm thick cement and sand (1:3) protective screed

    reinforced with a layer of BRC A6 cast in 1.2m x 1.2m panelcomplete with 25mm x 13mm movement joint in filled with

    polyrethane sealant laid to fall, all in accodance with manufacturer's

    instruction:

    A To slab m2 3367

    B Extra over for scupper drain m 579

  • 8/3/2019 Prasarana Ima

    17/97

    C Allow for necessary ponding test to reinforced concrete flat roof item -

    The Following in Reinforced Concrete Lift Roof

    Vibrated reinforced concrete Grade 40 as described filled intoformwork and well packed around reinforcement in

    D 200mm hick suspended lift roof slab m3 3

    High tensile bar reinforcement in straight and bends bars as

    described

    E 12mm diameter in suspended lift roof slab kg 294

    Wrought formwork as described to

    F Soffit of suspended roof slab m2 16

    G Edge of concrete not exceeding 250mm high m 17

    (End of The Following in Reinforced Concrete Lift Roof

    CARRIED TO COLLECTIONBQ 2.1.5/3

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.5 Roof

    unPlasticised Polyvinyl Chloride rainwater goods ans accessories toB.S 4576 solvent welded with and including joiners, brackets and ties

    all in accordance with the manufacturer's instruction (Provisional)

    A 100mm diameter rainwater downpipe fixed to brickwall with

    approved brackets

    m 330

    B Extra over for bend no. 90

    C Extra over for swan neck no. 30

    D Extra over for dome grating no. 30

    E 100mm diameter rainwater downpipe embedded in bed m 30

    -----------------------------------------------

    F Labour and material for connecting end of rainwater downpipe to

    side drain including cement and sand (1:3) grounting (Provisional)

    no. 30

  • 8/3/2019 Prasarana Ima

    18/97

    G Prepare and apply two coats of approved first quality arcrylic weather

    resisitent paint acrylic as "Jotosheild' or other equal and approved on

    100mm diameter rainwater downpipe (Provisional)

    m 330

    CARRIED TO COLLECTION

    BQ 2.1.5/4

    COLLECTION PAGE

    BQ 2.1.5/1

    BQ 2.1.5/2

    BQ 2.1.5/3

    BQ 2.1.5/4

    TOTAL FOR BILL NO. 2.1.5 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4BQ 2.1.5/5

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.6 Staircase, ramp and handrailing

    The Following in Staircase

    Vibrated reinforced concrete Grade 40 as described filled into

    formwork and well packed around reinforcementin

    A Staircase m3 57

    B landing beam m3 6

    C Landing slab exceeding 100mm but not exceeding 150mm thick m3 25

    High tensile bar reinforcement in straight and bends bars as

    described

    D 10mm diameter in staircase kg 787

    E 12mm diameter in staircase kg 1542

    F 10mm diameter in landing beam as stirrups kg 131

    G 12mm diameter in landing beam kg 39

  • 8/3/2019 Prasarana Ima

    19/97

    H 20mm diameter in landing beam kg 107

    J 10mm diameter in landing slab kg 262

    K 12mm diameter in landing slab kg 522

    CARRIED TO COLLECTIONBQ 2.1.6/1

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.6 Staircase, ram and handrailing

    The Following in Staircase

    Sawn formwork as described to

    A Sloping soffit of staircase m2 259

    B Sides and soffit of landing beam m2 97

    C Soffit of landing slab m2 166

    D Undercut riser not exceeding 250mm deep m 832

    E String of staircase maximum width 350mm including cutting to profile

    of treads and risers

    m 119

    F Edge of landing slab not exceeding 250mm deep m 219

    ------------------------------------------------

    G Provide railing comprising of 32mm x 9mm thick ,ild steel flat

    balustrade to 900mm high, 50mm diameter x 3 mm thick mild steel

    hollow section handrail to 900mm high and 16mm diameter x 2mm

    thick mild steel hollow section intermediate rail at centres of 150mm,

    all done in accordance to manufacturer's detail and E.R's approval

    as shown on Drawing No. : T/AMG/F/STN04-P/AR/5254

    H Extra Over for bend no. 132

    J Extra Over for ramp no. 132

    K Extra Over for stop end no. 18

    25mm thick cement and sand (1:3) as described paving trowelled

    smooth to

    L Landing slab m2 166

  • 8/3/2019 Prasarana Ima

    20/97

    M Tread 280mm wide m 832

    N Extra Over for nosing tiles with 3 rows of grooving m 832

    CARRIED TO COLLECTION

    BQ 2.1.6/2

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.6 Staircase, ramp and handrailing

    The Following in Staircase

    25mm thick cement and sand (1:3) as described paving (cont'd)

    A Riser 156mm high m 924

    B 100mm high skirting m 255

    ---------------------------------------------

    13mm thick cement ans sand (1:6) mixed with an approved

    plasticiser as described plainface

    C Sloping soffit of staircase m2 259

    D Sides and soffit of landing beam m2 97

    E Soffit of landing slab m2 166

    F String of staircase m 185

    G Edge of concrete exceeding 100mm high but not exceeding 200mm

    high

    m 119

    Prepare and apply one coat alkali resisting primer as 'Jotosealer 03'

    or other equal and approved and two coats of firet quality emulsion

    paint as "Jotaplast Max' or other equal and approved as described

    on plastered SURFACES OF

    H Sloping soffit of staircase m2 259

    J sides and soffit of landing beam m2 97

    K Soffit of landing slab m2 166

    L String of staircase m 185

    M Edge of concrete exceeding 100mm high but not m 119

  • 8/3/2019 Prasarana Ima

    21/97

    (End of The Following in Staircase)

    CARRIED TO COLLECTIONBQ 2.1.6/3

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.6 Staircase, ram and handrailing

    The Following in Ramp

    Vibrated reinforced concrete Grade 40 as described filled into

    formwork and well packed around reinforcement in

    A 175MM THICK RAMP m3 380

    B Landing beam m3 2

    C Stringer beam m3 110

    D Ramp beam m3 61

    E Landing slab exceeding 100mm but not exceeding 150mm thick m3 6

    F 150mm thick parapet wall m3 234

    ---------------------------------

    G Extra over for forming 150mm wide x 50mm deep scupper drain laid

    to fall including all necessary formworks

    m 1918

    H Extra over for forming 25mm wide groove line with 175mm spacing m2 2431

    High tensile bar reinforcement in straight and bends bars as

    described

    J 10mm dia,eter in ramp kg 17151

    K 10mm diameter in landing beam as stirrups kg 58

    L 16mm diameter in landing beam kg 75

    M 32mm diameter in landing beam kg 166

    CARRIED TO COLLECTIONBQ 2.1.6/4

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.6 Staircase, ramp and handrailing

  • 8/3/2019 Prasarana Ima

    22/97

    The Following in Ramp

    High tensile bar reinforcement in straight and bends bars as

    described (Cont'd)

    A 10mm diameter in stringer beam as stirrups kg 642

    B 12mm diameter in stringer beam as stirrups kg 3411

    C 16mm diameter in stringer beam kg 3924

    D 20mm diameter in stringer beam kg 3203

    E 25mm diameter in stringer beam kg 6031

    F 32mm diameter in stringer beam kg 289

    G 10mm diameter in ramp beam as stirrups kg 125

    H 12mm diameter in ramp beam as stirrups kg 515

    J 16mm diameter in ramp beam kg 354

    K 25mm diameter in ramp beam kg 718

    L 32mm diameter in ramp beam kg 1549

    M 10mm diameter in landing slab kg 233

    N 10mm diameter in parapet wall kg 6361

    CARRIED TO COLLECTIONBQ 2.1.6/5

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.6 Staircase, ramp and handrailing

    The Following in Ram

    Sawn formwork as described to

    A Sloping soffit of curved ramp (Various radius) for sloping over 15degrees from horizontal

    m2 2111

    B Sloping soffit of straight ramp for sloping over 15 degrees from

    horizontal

    m2 319

    C Sides and soffit of landing beam m2 14

  • 8/3/2019 Prasarana Ima

    23/97

    D Sides and sloping soffit of curved stringer beam (various radius) for

    sloping over 15 degrees from horizontal

    m2 778

    E Sides and sloping soffit of straight stringer beam for sloping over 15

    degrees from horizontal

    m2 271

    F Sides and soffit of ramp beam m2 429

    G Soffit of landing slab m2 33

    H Sides of vertical parapet wall m2 3113

    CARRIED TO COLLECTION

    BQ 2.1.6/6

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.6 Staircase, ramp and handrailing

    The Following in Ramp

    A Provide railing comprising of 32mm x 9mm thick mild steel flat

    balustrade to 900mm high, 50mm diameter x 3mm thick mild steel

    hollow section handrail to 900mm high and 16mm diameter x 2mm

    thick mild steel hollow section intermediate rail at centres of 150mm,

    all done in accordance to manufacturer's detail and E.R.'s approval

    as shown on Drawing No.: T/AMG/F/STN 04-P/AR/5254.

    m 79

    B Extra Over for bend no. 5

    C Extra Over for ramp no. 5

    D Extra over for stop end no 2

    E 25mm thick cement and sand (1:3) as described paving trowelled

    smooth to landing slab

    m2 33

    13mm thick cement and sand (1:6) mixed with an approved

    plasticiser as described plainface

    F Sloping soffit of ramp slab m2 2431

    G Soffit of landing slab m2 33

    H Sides and soffit of stringer beam m2 1049

    J Sides and soffits of landing beam m2 14

    K Sides and soffits of ramp beam m2 429

  • 8/3/2019 Prasarana Ima

    24/97

    L Sides of wall m2 3113

    Prepare and apply one coat alkali resisting primer as 'Jotoshield

    Primer 07' or other equal and approved and two coats of weather

    resisting acylic equal and approved and two coats of weather

    resisting acylic paint as 'Jotosheild' or other equal and approved as

    described on plastered surfaces of

    M Sloping soffit of ramp slab m2 2431

    N Soffit of landing slab m2 33

    CARRIED TO COLLECTION

    BQ 2.1.6/7

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.6 Staircase, ramp and handrailing

    The Following in Ramp

    Prepare and apply one coat alkali resisting primer (Cont'd)

    A Sides and soffit of stringer beam m2 1049

    B Sides and soffits of landing beam m2 14

    C Sides and soffits of ramp beam m2 429

    D Sides of wall m2 3113

    (End of The Following in Ramp)

    CARRIED TO COLLECTIONBQ 2.1.6/8

    COLLECTION PAGE

    BQ 2.1.6/1

    BQ 2.1.6/2

    BQ 2.1.6/3

    BQ 2.1.6/4

    BQ 2.1.6/5

    BQ 2.1.6/6

    BQ 2.1.6/7

  • 8/3/2019 Prasarana Ima

    25/97

    BQ 2.1.6/8

    TOTAL FOR BILL NO. 2.1.6 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4

    BQ 2.1.6/9

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.7 External Wall

    A Reinforced concrete Grade 25 as described filled into formwork and

    well packed around reinforcement in vertical stiffener

    m3 5

    B 6mm diameter mild steel bar reinforcement as described in stiffeneras links kg 218

    C 12mm diameter high tensile bar reinforcement as described in

    stiffener

    kg 1065

    D Sawn formwork as described to sides of stiffener m2 143

    E Halfwall in common bricks in composition mortar as described

    reinforcement as described

    m2 1410

    F Half brickwall in common bricks in composition mortar as described

    as parapet wall

    m2 1367

    G Horizontal damp proof course as described laid on half brickwall

    (measured nett-no allowance made for laps

    m 310

    H 6mm diameter mild steel to B.S. 15 as described bonding tie 375mm

    long, one end hooked and cast in concrete ans the other end buil

    into joints of brickwork including perforation in formwork

    no. 912

    J Supply and install 'Luxalon Aluminium Sun Louvres Type 132S

    (Module 140mm c/c)' or other equal and approved louvres including

    supporting frames and all other necessary works, all done in

    accordance to the manufacturer's specification and instruction.(Provisional)

    m2 288

    CARRIED TO COLLECTIONBQ 2.1.7/1

    2.1 PARK & RIDE FACILITIES AT STATION 4

  • 8/3/2019 Prasarana Ima

    26/97

    2.1.7 External Wall

    The Following in Railing

    A Provide railing comprising of 32mm x 9mm thick mild steel flat

    balustrade to 900mm high, 50mm diameter x 3mm thick mild steel

    hollow section handrail to 900mm high and 16mm diameter x 2mmthick mild steel hollow section intermediate rail at centres of 150mm,

    all done in accordance to manufacturer's detail and E.R's approval

    as shown on Drawing No. : T/AMG/F/STN 04-P/AR/5254.

    m 1614

    B Extra Over for bend no. 20

    C Extra Over for one end to be fixed to brickwall or concrete wall no. 396

    (End of The Following in Railing

    CARRIED TO COLLECTIONBQ 2.1.7/2

    COLLECTION PAGE

    BQ 2.1.7/1

    BQ 2.1.7/2

    TOTAL FOR BILL NO. 2.1.7 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4BQ 2.1.7/3

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.8 Window

    A Reinforced concrete Grade 25 as described filled into formwork and

    well packed around reinforcement in lintol

    m3 0.2

    B 6mm diameter mild steel bar reinforcement as described in lintol as

    stirrups

    kg 5

    C 12mm diameter high tensile bar reinforcement as described in lintol kg 11

    D Sawn formwork as described to sides and soffit of lintol m2 6

  • 8/3/2019 Prasarana Ima

    27/97

    Note : The

    size given hereunder serve only as a guide to tendering and the

    Contractor shall supply all the units in accordance with the site

    measurement and no claims will be entertained for any discrepancy

    between the Drawings, Bills of Quantities and Site Measurement.

    E Supply, deliver to site and fix powder coated aluminium framed

    louvres window overall size 1800mm x 600mm high in 3 Nos. of

    equal panel of aluminium louvres as 'Luxalon 132S Sun Louvres' or

    equivalent and approved with and including aluminium framing,

    louvres as described, aluminium glazing beads, neoprene glazing

    gasket, all requisite neoprene weather strips, silicone sealant fillet,

    fixing screws, apinting to louvres, anti vermin netting fixed inside and

    all necessary ironmongery and othe accessories, all in acordance to

    manufacturer's detail and E.R's approval as shown on Drawing No.:

    T/AMG/F/STN 04-P/AR/8011 (Type LW3)

    no. 2

    CARRIED TO COLLECTION

    BQ 2.1.8/1

    COLLECTION PAGE

    BQ 2.1.8/1

    TOTAL FOR BILL NO. 2.1.8 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4BQ 2.1.8/2

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.9 Door

    A Reinforced concrete Grade 25 as described filled into formwork and

    well packed around reinforcement in lintol

    m3 2

    B 6mm diameter mild steel bar reinforcement as described in lintol as

    stirrups

    kg 87

    C 10mm diameter high tensile bar reinforcement as described in lintol kg 220

    D Sawn formwork as described to sides and soffit of lintol m2 44

  • 8/3/2019 Prasarana Ima

    28/97

    Note : The

    size given hereunder serve only as a guide to tendering and the

    Contractor shall supply all the units in accordance with the site

    measurement and no claims will be entertained for any discrepancy

    between the Drawings, Bills of Quantities and Site Measurement.

    Factory spray painted polyurethane (PU) painted steel framed, steel

    door panel as 'TACAM' or other equal and approved complete with

    necessary door features, i.e vision panel, bottom louvres, comprising

    of 1.5mm thick electro-galvanised steel frame and 1.0mm thick

    electro-galvanised steel door with honeycomb paper infill, including

    associated fixing strap bars, ironmongery (measured separately) and

    cementatious grout to door frame, all to manufacturer's details and

    E.R's approval as shown on Drawing No.: T/AMG/F/STN 04-

    P/AR/8011

    E Overall size 900mm x 2100mm (Type D3) no. 32

    F Overall size 2000mm x 2100mm (Type D10) no. 3

    CARRIED TO COLLECTION

    BQ 2.1.9/1

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.9 Door

    A Factory spray painted polyurethane (PU) painted BOMBA approved

    Fire Rated steel framed, steel door panel as 'TACAM' or other equal

    and approved overall size 900mm x 2100mm high comprising of

    1.5mm thick electro-galvanised steel frame and 1.0mm thick electro-galvanised steel door with honeycomb paper infill, including

    associated fixing strap bars, ironmongery (measured separately) and

    cementatious grout to door frame, all to manufacturer's details and

    E.R's approval as shown on Drawing No.: T/AMG/F/STN 04-

    P/AR/8011 (Type FD3)

    no. 32

    Supply and fix the following or other equal and approved

    ironmongeries unless otherwise stated including all necessary

    matching screws, all done in accordance to the manufacturer's

    instructions

    B DOLD S/S SUS 304, 100 x 75 x 3mm Concealed Knuckle BearingButt Hinge

    no. 280

    C BRINTON 1120B (EN2 - 4) Adjustable Door Closer with Back Check no. 70

    D ABLOY LC204/LC6112 Lockset (Entrance) no. 32

  • 8/3/2019 Prasarana Ima

    29/97

    E ABLOY LC4193 Lockset (Nightlatch) no. 32

    F ABLOY LC200 Lockset (Entrance) with Turn Indicator no. 3

    G ABLOY FORUM 4/007/A9 Lever Handle (Both sides lever) no. 35

    H ABLOY FORUM 4/029/A9 Lever Handle (Lever inside only, Blankescutheon outside)

    no. 32

    J DOLD PH200 Stainless Steel 200mm Pull Handle (Grub screw

    fixing)

    no. 32

    K ABLOY CY028P Cylinder Thumbturn no. 32

    L ABLOY CY 060P Half Cylinder no. 32

    CARRIED TO COLLECTIONBQ 2.1.9/2

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.9 Door

    Supply and fix the following or other equal and approved

    ironmongeries. (cont'd)

    A ABLOY CY037P Half Cylinder no. 3

    B DOLD S/S DHO071SS Wall Mounted Door Stopper no. 64

    C SUEHIRO Manual 3001 Extension Flush Bolt (300mm length) no. 6

    D ABLOY EA 281 Lead Cover (Wire Transfer) no. 3

    E Construction & Master Key Surcgarge no. 67

    CARRIED TO COLLECTIONBQ 2.1.9/3

    COLLECTION PAGE

    BQ 2.1.9/1

    BQ 2.1.9/2

    BQ 2.1.9/3

    TOTAL FOR BILL NO. 2.1.9 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4BQ 2.1.9/4

  • 8/3/2019 Prasarana Ima

    30/97

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & FACILITIES AT STATION 4

    2.1.10 Internal Wall and Partition

    A Reinforced concrete Grade 25 as described filled into formwork andwell packed around reinforcement in stiffener (Provisional)

    no. 0.1

    B 6mm diameter mild steel bar reinforcement as described in stiffener

    as links (Provisional)

    no. 3

    C 12mm diameter high tensile bar reinforcement as described in

    stiffener (Provisional)

    no. 10

    D Sawn formwork as described to sides of stiffener (Provisional) no. 2

    E Half brickwall in common bricks in composition mortar as described

    reinforced with and including brick reinforcement

    no. 169

    F Horizontal damp proof course as described laid on half brickwall

    (measured nett-no. allowance made for laps)

    no. 60

    G 6mm diameter mild steel to B.S. 15 as described bonding tie 375mm

    long, one end hooked and cast in concrete and other end built into

    joints of brickwork including perforation in formwork

    no. 240

    CARRIED TO COLLECTION

    BQ 2.1.10/1

    COLLECTION PAGE

    BQ 2.1.10/1

    TOTAL FOR BILL NO. 2.1.10 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4BQ 2.1.10/2

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.11 Internal Wall Finishes

    A 20mm thick cement and sand (1:6) mixed with an approved

    plasticiser internally as described plainface to wall and column

    m2 2007

    B Prepare and apply one coat alkali resisting primer as 'Jotosealer 03'

    or other equal and approved and two coats of first quality emulsion

    paint as'Jotaplast Max' or other equal and approved on plastered

    surfaces of wall and column

    m2 2007

  • 8/3/2019 Prasarana Ima

    31/97

    CARRIED TO COLLECTION

    BQ 2.1.11/1

    COLLECTION PAGE

    BQ 2.1.11/1

    TOTAL FOR BILL NO. 2.1.11 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4BQ 2.1.11/2

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.12 Internal Floor Finishes

    A 25mm thick cement and sand (1:3) as described paving trowelledsmooth m2 129

    B To carry out surfaces preparation with 'Captive shot Blasting to dust

    free' or other equal and approved, apply one coat of 'Fosroc

    Notoprime 31 Epoxy Primer, Fosroc Notoflor FC 150(M) Solvent

    Free' or other equal and approved, High Build Chemical Resistance

    Epoxy Resin Floor Coating system' or other equal and approved of 2

    coats @ 200 micron thick per coat with first op coat dressed with

    "Notoflor Antislip Grain' or other equal and approved, all in

    accordance with the manufacturer's instruction.

    m2 129

    C Supply and lay approved non-metalic floor hardener applied at rae of

    4 kg per square metre monolithically to freshly float cement and sandscreed including mechanically floating as described to floor

    m2 129

    CARRIED TO COLLECTIONBQ 2.1.12/1

    COLLECTION PAGE

    BQ 2.1.12/1

    TOTAL FOR BILL NO. 2.1.12 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4

    BQ 2.1.12/2

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.13 Internal Ceiling Finishes

  • 8/3/2019 Prasarana Ima

    32/97

    A 12mm thick cement sand (1:6) mixed with an approved plasticiser

    plainface of concrete soffit, sides and soffit of beam

    m2 187

    B Prepare and apply one coat alkali resisting primer as 'Jotosealer 03'

    or other equal and approved and two coats of first quality emulsion

    paint as 'Jotaplast Max' or other equal and approved on general

    surfaces of plastered surface of concrete soffit, sides and soffit ofbeam

    m2 187

    CARRIED TO COLLECTION

    BQ 2.1.13/1

    COLLECTION PAGE

    BQ 2.1.13/1

    TOTAL FOR BILL NO. 2.1.13 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4

    BQ 2.1.13/2

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.13 External Finishes

    A Mechanical power trowel finish with SR 2 flatness 5mm over 3m

    span to general surface of unset concrete

    m2 31,400

    To carry out surface preparation with 'Captive shot Blasting todust

    free' or oher equal and approved, apply one coat of 'Fosroc

    Notoprime 31 Epoxy Primer, Fosroc Nitoflor FC 150TX SolventBased, High Texture Anti Slip Epoxy Resin Floor Coating system' or

    other equal and approved of 1.0mm thick texture coat and 200

    micron thick top coat, all in accordance with manufacturer's

    instruction to

    B Intermediate Slab m2 27032

    C Ramp m2 2431

    D 100mm wide parking line in continuous line m 11586

    E 600mm wide pedestrian marking m 2986

    F Directional signals - single arrow head (Provisional) no. 58

    G Directional signals - double arrow head (Provisional) no. 7

    H Motorcycle bay numbering (digit) to approval no. 712

  • 8/3/2019 Prasarana Ima

    33/97

    J Carpark bay numbering (digit) to approval no. 2353

    K Handicap wheel chair sign to approval no. 9

    To carry out surface preparation with 'Captive Shot Blasting to dust

    free' or other equal and approved, apply one coat of fosroc Nitoprime

    31 Epoxy Primer, one layer 5.0 mm hick Fosroc Notoflor FC 150TXSolvent Based, high Texture Anti Slip Epoxy Resin Floor Coating

    system' or other equal and approved of 1.0mm thick texture coat and

    200 micron thick top coat, all in accordance with the manufacturer's

    instruction to

    L Ground floor slab m2 4368

    CARRIED TO COLLECTIONBQ 2.1.14/1

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.13 External Finishes

    20mm thick cement and sand (1:6) mixed with an approved

    plasticiser internally as described plainface to

    A Wall and column m2 4353

    B Isolated column m2 2041

    Prepare and apply one coat alkali resisting primer as 'Jotoshield

    Primer 07' or other equal and approved and two coats of weather

    resisting acylic paint as 'Jotoshield' or other equal and approved on

    plastered of

    C Wall and column m2 4353

    D Isolated column m2 2041

    ----------------------------------------------

    E 530mm long x 50mm wide mild steel column guard including fixing to

    column and necessary accessories to E.R's approval (Provisional)

    no. 2326

    F 12mm thick cement and sand (1:6) mixed with an approvedplasticiser internally as described plainface of concrete soffit, sides

    and soffit of beam

    m2 31659

  • 8/3/2019 Prasarana Ima

    34/97

    G Prepare and apply one coat alkali resisting primer as 'Jotoshield 07'

    or other equal and approved and two coats of weather acrylic paint

    as 'Jotoshield' or other equal and approved on general surfaces of

    plastered surface of concrete soffit sides and soffit of beam

    m2 34659

    CARRIED TO COLLECTIONBQ 2.1.14/2

    COLLECTION PAGE

    BQ 2.1.14/1

    BQ 2.1.14/2

    TOTAL FOR BILL NO. 2.1.14 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4BQ 2.1.14/1

    2.0 PARK & RIDE FACILITIES

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Electrical boards

    Sub Switchboards and Distribution Boards

    Supply, delivery and installation of Sub Switchboards and Distribution

    Boards c/w Breakers, Couplers, Sectioners, Meters, Indicating

    Lights, Relay, PFR, Anti-Condensation, SCADA Interface, EarthingSystem, SPDs, CTS, Isolators, Fuses, Switches, Time Switch,

    Termination, 13A SSO with built in ELCD, cable box or gland to suit

    the connection of electrical supply as per drawings and all other

    accessories as per drawings and specifications though not

    listed/described but deemed necessary and essential for proper and

    safe operation of equipment/installation.

    A MDB-CP lot 1

    B DB-CPG lot 1

    C DB-CP1 lot 1

    D DB-CP2 lot 1

    E DB-CP3 lot 1

    F DB-CP4 lot 1

  • 8/3/2019 Prasarana Ima

    35/97

    G DB-CP5 lot 1

    H DB-CP6 lot 1

    J DB-CPR lot 1

    CARRIED TO COLLECTIONBQ 2.1.15/1

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Electrical boards

    Earthing System

    A DB Complete solid earthing system using copper tape, earth bar,connection/termination, testing from DB to earth bar only lot 1

    Testing and Commissioning

    B Testing and commissioning of the whole Distribution Boards as

    described in drawings and specifications

    lot 1

    Factory Acceptance Test

    C Complete Factory Acceptance test at Manufacturer's Works for 7

    representative as described in the technical specifications

    lot 1

    Defects Liability Period

    D Service and maintenance during Defects Liability Period lot 1

    CARRIED TO COLLECTIONBQ 2.1.15/2

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Electical distribution system

    Submains and Final Cub-Circuit Cables

  • 8/3/2019 Prasarana Ima

    36/97

    Supply, delivery and installation of Submains and Final Sub-Circuit

    Cables inclusive of CPC Cables, Hot Dipped Galvanised

    Ladder/Tray/Trunking/Underfloor Trunking /GI Conduit/Buried PVC

    Conduit, Cable Glands, Labeling, Identifications, Markers,

    Terminations, Metal Clad Back Boxes, Connections of electrical

    supply and all other accessoreis as per drawing and specifications

    though not listed/desribed but deemed necessary and essential forproper and safe operation of equipment/installation

    Final Circuits

    A Lighting pint using 2 x 1.5 sq.mm PVC Cu. c/w 1 + 1.5 sq.mm PVC

    CPC Cable c/w/ terminations

    no. 1630

    B Power point using 2 x 2.5 sq.mm PVC Cu. + 1 x 2.5 sq.mm PVC

    CPC Cable c/w terminations

    no. 80

    C Air-conditioning point usingg 2 x 4.0 sq.mm PVC Cu. c/w 1x 4.0sq.mm PVC CPC Cable c/w terminations no. 8

    D Exhaust Fan C/P using 4 x 4.0 sq.mm PVC Cu. c/w 1 x 4.0 sq.mm

    PVC CPC Cable c/w terminations

    no. 4

    Testing and Commissioning

    E Testing and commissioning of the whole cabling system as

    described in drawing and specifications

    lot 1

    Defects Liability Period

    F Service and maintenance during Defects Liability Period lot 1

    CARRIED TO COLLECTIONBQ 2.1.15/2

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Electical distribution system

    Welding of lighting protection system column from ground to

    roof

  • 8/3/2019 Prasarana Ima

    37/97

    A To supply and install the welding for each column of rebar to rebar

    for existing earthing connection using exothermic process for the

    earth system, from existing earthing rebar at ground level, 95 sq.mm

    earth cable to the steel columns and 95sq.mm cable to the roof with

    20 Cadwelds minimum at each column inclusive of accessories,

    bonding points, etc as indicated in detail drawings and specification

    lot 17

    Air Teminal

    B Supply and install complete air terminals inclusive of all connections

    to earth cable loop, base, bonding points, spacers, saddles, copper

    tape and all other accessories as per drawings and specifications

    though not listed/described but deemed necessary and essential for

    proper and safe operation of equipment/installation

    no. 17

    Air Terminal Cooper Tape Looping

    C Supply, deliver and install 3mm x 25mm cooper tape to loop

    between air terminals inclusive of spacer, sdaales and all other

    accessories as per drawings and specification though not

    listed/described but deemed necessary and essential fot proper and

    safe operation of equipment/installation

    m 300

    Earth Cable from Earth Pit to Room Earthing Bar

    D Supply, deliver and install 150 sq.mm PVC copper cable from Earth

    pit to earth bar terminals inclusive of GI conduits, sleaves,

    connections and all other accessories as per drawings and

    specifications though not listed/described but deemeed necessary

    ans essential for proper and safe operation of equipment/installation

    m 150

    CARRIED TO COLLECTIONBQ 2.1.15/4

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Earthing & Lighting protection system (cont'd)

    Room Earthing Bar

    A Supply, deliver and install copper room earthing bar inclusive of

    spacers, test link, nuts, bolts, connections and all other accessories

    as per drawing and specifications though not listed/desribed but

    deemed necessary and essential for proper and safe operation of

    equipment/installation

    lot 6

  • 8/3/2019 Prasarana Ima

    38/97

    Testing and Commissioning

    B Testing and commissioning of the whole Earthing ans Lighting

    Protection system as described in drawing and specifications

    lot 1

    Defects Liability Period

    C Service and maintenance during Defects Liability Period lot 1

    CARRIED TO COLLECTION

    BQ 2.1.15/5

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Electrical Fittings

    Light Fittings

    Supply, delivery and installation of light fittings inclusive of Cable

    Glands Labeling, Identifications, Markers, Treminations, Back

    Boxes, Connections of electrical supply and all other accessories as

    per drawings and specifications though not listed described but

    deemed necessary and essential for proper and safe operation of

    equipment/installation

    A Type L14 - Fluorelite 2 x 36W surface Mounted Bare Channel

    Flourescent fitting c/w tube

    no. 1200

    B Type L50 - Schreder 70W High Pressure Sodium Vapour Bollard no. 70

    C L89 - Fluorelite 2 x 18W Surface Type Staircase Light no. 50

    D L90 - Fluorite 2 x 18W Surface Type Staircase Light with backup

    battery

    no. 50

    E L86 - 2 x 13W Surface Slim Line 'Keluar' Sign no. 30

    F L88 - 1 x 13W Surface Emergency Exit Light no. 130

    Testing and Commissioning

    G Testing and commissioning of the whole Electrical Fittings asdescribed in drawing and specifications

    lot 1

    Defects Liability Period

    H Service and maintenance during Defects Liability Period lot 1

    CARRIED TO COLLECTION

  • 8/3/2019 Prasarana Ima

    39/97

    BQ 2.1.15/6

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Power & Miscellaneous Outlets

    Supply, delivery and installation of Power Outlets inclusive of Cable

    Glands, Labeling, Identifications, Markers, Terminations, Back

    Boxes, Connections of electrical supply and all other accessories as

    per drawings and specifications though not listed/desribed but

    deemed necessary and essential for proper and safe operation of

    equipment/installation

    A Type P19 13A Metalclad Switched Socket Outlet no. 60

    B Type P57 13A Weatherproof Switched Socket Outlet no. 20

    C Type P73 Switches lot 1

    Testing and Commissioning

    D Testing and commissioning of the whole Power Outlets as described

    in drawing and specifications

    lot 1

    Defects Liability Period

    E Service and maintenance during Defects Liability Period lot 1

    CARRIED TO COLLECTION

    BQ 2.1.15/7

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Power & Miscellaneous Outlets

    E & M System's cable Tray/Trunking

    A Supply, delivery and installation of E&M System's cable

    tray/trunking/Underfloor Trunking inclusive in accordance to

    drawings and E&M System's requirements and all other accessoriesas per drawings and specifications though not listed/described but

    deemed necessary and essential for proper and safe operation of

    equipment/installation

    Testing and Commissioning

  • 8/3/2019 Prasarana Ima

    40/97

    B Testing and commissioning of the whole E&M System Cable

    Tray/trunking as described in drawing and specifications

    lot 1

    Defects Liability Period

    C Service and maintenance during Defects Liability Period lot 1

    CARRIED TO COLLECTIONBQ 2.1.15/8

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Fire Alarm System

    Supply, installation, testing and commissioning of the complete Fire

    Detedtion and Alarm System in accordance with the specification

    and tender drawings comprising but not limited to the following :-

    Fire Detection Unit

    A Smoke Detectors no. 15

    B Heat Detector no. 15

    C Break Glass Call Points no. 35

    D Strobe Light no 15

    E Electric Sounder no. 15

    F Main Fire Alarm Control & MIMIC Panel c/w internal and external

    cabling, controls, interfaces, logic display, printer units, batteries,

    battery charger, lightning surge arrestor and/or tender drawings

    lot 1

    CARRIED TO COLLECTIONBQ 2.1.15/9

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Fire Alarm System

    Wiring - the complete looping cables connections all addresses,

    isolator, trip, interface unit and all other accessories including

    connection to total flooding control panel with Main Fire Alarm Panel

  • 8/3/2019 Prasarana Ima

    41/97

    A As Per Tender Drawing Indication m 400

    B CMS Connection to Bomba and provision for SCADA (Supervisory

    Control and Data Acquisition) connection system

    lot 1

    C Testing and commisioning as per specification lot 1

    D Items not included in the above shown on the drawings, described in

    the specification required by the legislation or obviously necessary

    for the successful completion and satisfactory operation of the entire

    installation. If none is required, please write 'NIL' otherwise full

    details of the items are to be given :- 1)

    2)

    CARRIED TO COLLECTIONBQ 2.1.15/10

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Hose Reel System (Cont'd)

    To supply and install hose reel pipework of Class 'C' galvanised steel

    pipe conforming to BS 1387 : 1987 :

    A 50mm diameter m 500

    B 75mm diameter m 100

    C To supply and install Hose Reel complete with hose reel cabinets,

    hoses, mounting brackets, nozzles, stop valves, automatic air

    valves, fittings and all other with other associated accessories as per

    specifications and/or tender drawings

    lot 1

    D To supply and install screwed connections on threaded joints to all

    the pipe joints 50mm diameter and below with other associated

    accessories as per specification and/or tender drawings

    lot 1

    E To supply and install Hose Reel complete with hose reel cabinets,

    hoses, mounting brackets, nozzles, stop valves, fitting and all otherassociated accessories as per specifications and/or tender drawings

    lot 1

    F Painting, directional sign indications and all warnings sign boards to

    Bomba's requirement

    lot 1

  • 8/3/2019 Prasarana Ima

    42/97

    G Testing and commissioning as per specification and Bomba

    Requirements

    lot 1

    H Hose Reel Water Tank as per tender Drawing (Hot Dipped

    Galvanised Press steel Tank) to Authority approval. Tank Size: 1.2

    m x 4.8 m x 2.4 m (H)

    J Items not included in the above shown on the drawings, described in

    the specification required by the legislation or obviously necessary

    for the successful completion and satisfactory operation of the entire

    installation. If none is required, please write 'NIL' otherwise full

    details of the items are to be given :- 1)

    2)

    CARRIED TO COLLECTIONBQ 2.1.15/12

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Portable Fire Extinguiher

    Supply, deliver and install the fire extinguishers in accordance with

    the specifications and/or tender drawings comprising with the

    followings :

    Fire Extinguishers Unit

    A 9 Kg dry powder fire extinguisher c/w brackets no. 30

    B 5 Kg carbon dioxide extinguisher c/w brackets no. 20

    C Heavy gauge steel cabinets for the above fire extinguisher c/w

    painting (one primer coat, one undercoat and two finishing coat, side

    ventilation louvres, wire mesh glasses at cabinet doors, master key

    system and instruction plates in Bahasa Malaysia and English)

    lot 1

    D Testing and commissioning as per specifications lot 1

    E Items not included in the above shown on the drawings, described in

    the specification required by the legislation or obviously necessaryfor the successful completion and satisfactory operation of the entire

    installation. If none is required, please write 'NIL' otherwise full

    details of the items are to be given :- 1)

    2)

    CARRIED TO COLLECTION

  • 8/3/2019 Prasarana Ima

    43/97

    BQ 2.1.15/13

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    AIR CONDITIONING AND MECHANICAL VENTILATION SYSTEM

    Air Coolled Split Unit Air Conditioning

    To supply, install, test and commission the following as per drawings

    and specifications complete with cable termination at both end and

    all necessary accessories:

    A Indoor and Outdoor units complete with all its accessories as per

    specification and tender drawings

    lot 1

    B Refrigerant copper piping inclusive of closed cell rubber insulation,fittings, brackets and all other necessary accessories as per

    Specification and Tender Drawings

    lot 1

    C Hot Dipped Galvanized Metal trunking for exposed refrigerant copper

    pipes

    lot 1

    D Adjustable temperature sensor for all the System room & TPSS

    room as per specification and /or drawings

    lot 1

    E 1 inch UPVC condensate drain pipe c/w closed cell rubber insulation,

    fittings, brackets and all other necessary as per specification and /or

    drawings

    lot 1

    F Hot dipped galvanized steel frame for mounting of outdoor

    condensing units c/w all other necessary accessories as per

    specifications and/or drawings

    lot 1

    G Air Grilles/ Diffusers as per Specifications and Drawings lot 1

    Electrical works :- lot 1

    H Switchboards for FCU inclusive of all control wirinf, relays, starter,

    single phasing/ under voltage protection and all the necessary

    accessories as per Specification and/ or Tender Drawing

    lot 1

    CARRIED TO COLLECTIONBQ 2.1.15/14

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

  • 8/3/2019 Prasarana Ima

    44/97

    AIR CONDITIONING AND MECHANICAL VENTILATION SYSTEM

    Air Coolled Split Unit Air Conditioning

    Electrical works :-

    A Cabling and wiring lot 1

    B single protection for 3-phase motors lot 1

    C Power factor correctionfor the motors lot 1

    D Supply and install wired controller with LCD display control c/w

    control box, wiring and other necessary accessories for each of the

    following split unit A/C system including with the condenser unit:

    lot 1

    E FC / 3 / STN04 - 01 & 02 no. 2

    -----------------------------------

    F Testing and commissioning for each AC system lot 1

    G Provision for fire alarm interfacing works to AC Unit. Please refer to

    detail Specification/ Drawing

    lot 1

    H Items not included in the above shown on the drawings, described in

    the specification required by the legislation or obviously necessary

    for the successful completion and satisfactory operation of the entire

    installation. If none is required, please write 'NIL' otherwise fulldetails of the items are to be given :- 1)

    2)

    CARRIED TO COLLECTIONBQ 2.1.15/15

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    AIR CONDITIONING AND MECHANICAL VENTILATION SYSTEM

    Mechanical Ventilation Fan

    To supply, install, test and commission the following as per drawings

    and specifications complete with cable termination at both end and

    all necessary accessories:

  • 8/3/2019 Prasarana Ima

    45/97

    A Mechanical ventilation fan complete with TEFC motors, vibration

    isolators, hangers and support, flexible connection, accoustic

    silencer and all other accessories to complete as per Specification

    and ? Or Drawings

    lot 1

    B Bare G.I duct complete with turning/guide vanes splitter hangersreducers, Tee, elbows of the duct and all other necessary

    accessories for supply and return air ductwork as per Specification

    and / or Tender Drawings

    lot 1

    C Aluminium construction exhaust air grilles and diffuser as per

    Specification and Tender Drawings

    lot 1

    D All electrical work inclusive of all wirings, switchboard complete with

    starters, single phasing protection, under voltage protection, power

    factor correction, indication lights and all the necessary accessories

    as per Specification adnTender Drawings

    lot 1

    For each of the following Exhaust Fan system:

    E EF / G / STN04 - 09 no 1

    F Items not included in the above shown on the drawings, described in

    the specification required by the legislation or obviously necessary

    for the successful completion and satisfactory operation of the entire

    installation. If none is required, please write 'NIL' otherwise full

    details of the items are to be given :- 1)

    2)

    CARRIED TO COLLECTIONBQ 2.1.15/16

    2.1 PARK & RIDE FACILITIES AT STATION 4

    2.1.15 Mechanical and Electrical

    Miscellaneous

    A Preparation and submission of method statement, material, shop

    drawings and all other necessary submittals for approval before

    commencement of Work

    lot 1

    B Preparation and submission of As-built Drawings, Operation and

    Maintenance Manuals (O&M)

    lot 1

    C Service and maintenance of the complete system during the Defects

    Liability Period

    lot 1

    D Training of Employer's Personnel lot 1

  • 8/3/2019 Prasarana Ima

    46/97

    CARRIED TO COLLECTIONBQ 2.1.15/17

    COLLECTION PAGE

    BQ 2.1.15/1

    BQ 2.1.15/2

    BQ 2.1.15/3

    BQ 2.1.15/4

    BQ 2.1.15/5

    BQ 2.1.15/6

    BQ 2.1.15/7

    BQ 2.1.15/8

    BQ 2.1.15/9

    BQ 2.1.15/10

    BQ 2.1.15/11

    BQ 2.1.15/12

    BQ 2.1.15/13

    BQ 2.1.15/14

    BQ 2.1.15/15

    BQ 2.1.15/16

    BQ 2.1.15/17

    TOTAL FOR BILL NO. 2.1.15 CARRIED TO COLLECTION FOR

    PARK & RIDE FACILITIES AT STATION 4

    BQ 2.1.15/18

  • 8/3/2019 Prasarana Ima

    47/97

    Tender

    Rate Amount

    Cost

    Rate Amount

  • 8/3/2019 Prasarana Ima

    48/97

  • 8/3/2019 Prasarana Ima

    49/97

  • 8/3/2019 Prasarana Ima

    50/97

  • 8/3/2019 Prasarana Ima

    51/97

  • 8/3/2019 Prasarana Ima

    52/97

  • 8/3/2019 Prasarana Ima

    53/97

  • 8/3/2019 Prasarana Ima

    54/97

  • 8/3/2019 Prasarana Ima

    55/97

  • 8/3/2019 Prasarana Ima

    56/97

  • 8/3/2019 Prasarana Ima

    57/97

  • 8/3/2019 Prasarana Ima

    58/97

  • 8/3/2019 Prasarana Ima

    59/97

  • 8/3/2019 Prasarana Ima

    60/97

  • 8/3/2019 Prasarana Ima

    61/97

  • 8/3/2019 Prasarana Ima

    62/97

  • 8/3/2019 Prasarana Ima

    63/97

  • 8/3/2019 Prasarana Ima

    64/97

  • 8/3/2019 Prasarana Ima

    65/97

  • 8/3/2019 Prasarana Ima

    66/97

  • 8/3/2019 Prasarana Ima

    67/97

  • 8/3/2019 Prasarana Ima

    68/97

  • 8/3/2019 Prasarana Ima

    69/97

  • 8/3/2019 Prasarana Ima

    70/97

  • 8/3/2019 Prasarana Ima

    71/97

  • 8/3/2019 Prasarana Ima

    72/97

  • 8/3/2019 Prasarana Ima

    73/97

  • 8/3/2019 Prasarana Ima

    74/97

  • 8/3/2019 Prasarana Ima

    75/97

  • 8/3/2019 Prasarana Ima

    76/97

  • 8/3/2019 Prasarana Ima

    77/97

  • 8/3/2019 Prasarana Ima

    78/97

  • 8/3/2019 Prasarana Ima

    79/97

  • 8/3/2019 Prasarana Ima

    80/97

  • 8/3/2019 Prasarana Ima

    81/97

  • 8/3/2019 Prasarana Ima

    82/97

  • 8/3/2019 Prasarana Ima

    83/97

  • 8/3/2019 Prasarana Ima

    84/97

  • 8/3/2019 Prasarana Ima

    85/97

  • 8/3/2019 Prasarana Ima

    86/97

  • 8/3/2019 Prasarana Ima

    87/97

  • 8/3/2019 Prasarana Ima

    88/97

  • 8/3/2019 Prasarana Ima

    89/97

  • 8/3/2019 Prasarana Ima

    90/97

  • 8/3/2019 Prasarana Ima

    91/97

  • 8/3/2019 Prasarana Ima

    92/97

  • 8/3/2019 Prasarana Ima

    93/97

    Item Description Unit Quantity

    3 PROVISIONAL SUMS

    Signages

    3.1 Provide the Provisional Sum of Ringgit Malaysia : Twenty

    Thousand Only (RM20,000.00) for Signages to be used as directed

    by the E.R. and to be deducted in whole or in part if not required

    Prov. Sum

    Guard House

    3.2 Provide the Provisional Sum of Ringgit Malaysia : Fifteen

    Thousand Only (RM15,000.00) for Signages to be used as directed

    by the E.R. and to be deducted in whole or in part if not required

    Prov. Sum

    Boom Gate

    3.3 Provide the Provisional Sum of Ringgit Malaysia : Forty Thousand

    Only (RM40,000.00) for Signages to be used as directed by the E.R.

    and to be deducted in whole or in part if not required

    Prov. Sum

    Roof Garden

    3.4 Provide the Provisional Sum of Ringgit Malaysia : Eight Hundred

    Fifty Thousand Only (RM850,000.00) for Signages to be used as

    directed by the E.R. and to be deducted in whole or in part if not

    re uired

    Prov. Sum

    Refuse Bin

    3.5 Provide the Provisional Sum of Ringgit Malaysia : Fifteen

    Thousand Only (RM15,000.00) for Signages to be used as directedby the E.R. and to be deducted in whole or in part if not required

    Prov. Sum

    CARRIED TO COLLECTIONBQ 3/1

    COLLECTION PAGE

  • 8/3/2019 Prasarana Ima

    94/97

    BQ 3/1

    TOTAL FOR BILL NO.3 CARRIED TO SUMMARY OF TENDER

    SUM

    BQ 3/2

  • 8/3/2019 Prasarana Ima

    95/97

    Rate (RM) Amount (RM)

    20,000.00

    15,000.00

    40,000.00

    850,000.00

    15,000.00

    940,000.00

  • 8/3/2019 Prasarana Ima

    96/97

    940,000.00

    940,000.00

  • 8/3/2019 Prasarana Ima

    97/97

    Item Description Page No. Amount (RM)

    1 PRELIMINARIES BQ 1/7

    2 PARK & RIDE FACILITIES AT STATION 4 BQ2/1

    3 PROVISIONAL SUMS BQ3/2 940,000.00

    TOTAL RINGGIT MALAYSIA (Carried to the Form of Tender) RM

    STS 1/1