POM Edited

Embed Size (px)

Citation preview

  • 7/31/2019 POM Edited

    1/35

    INTRODUCTION

    The concept of a metro for Delhi was first formalized in the Delhi Master Plan of 1960, and the

    legal framework for the metro was laid out in the Metro Railways (Construction of Works) Act

    of 1978. Actual work towards building the metro, however, only started in March 5, 1995,

    when the DMRC was established to provide a rail-based transport system that will alleviate

    Delhis ever growing transport congestion and vehicular pollution. The government of Japan

    has contributed more than half the cost of this project, through a soft loan disbursed by

    DMRCs major funding agency, the Japan Bank for International Cooperation (JBIC). Delhis

    metro rail system, to be constructed in four phases covering 245 kilometers, is scheduled to be

    finished in 2021. Today three functioning lines connect central Delhi to east, north, and

    southwest Delhi. DMRC is responsible not only for construction of the system but

    also for its operation and maintenance. It has 450 personnel in its construction department and

    3,000 staff for system operation and maintenance. Physical construction work started on

    October 1, 1998 Aside from one major disagreement in 2000, where the Ministry of Railways

    forced the system to use broad gauge despite the DMRC's preference for standard gauge,

    construction proceeded smoothly. The first line opened on December 24, 2002 and the entire

    Phase I of the project was completed in December 2005, on budget and almost three years

    ahead of schedule, an achievement described as "nothing short of a miracle".

    Operations management of DMRC Page 1

  • 7/31/2019 POM Edited

    2/35

    NEED FOR MRTS

    As cities grow in size, the number of vehicular trips on road system goes up. This necessitates a

    pragmatic policy shift to discourage private modes and encourage public transport once the

    level of traffic along any travel corridor in one direction exceeds 20,000 persons per hour.

    Introduction of a rail based (MRTS) Mass Rapid Transit System is called for. Mass Rapid

    Transit Systems are capital intensive and have long gestation period. It has been observed that

    in developed countries, planning for mass transit system starts when city population size

    exceeds 1 million; the system is in position by the time the city population is 2 to 3 million and

    once the population exceeds 4 million or so, planned extensions to the Mass Rapid Transit

    Systems is vigorously taken up. In developing countries including India, because of paucity of

    funds planning and implementation of rail based Mass Rapid Transit Systems has been lagging

    far behind the requirements. The city of Delhi with a population of round 12 (16.2) million

    should have had an MRTS network of at least 100 (300) KM by this time, whereas actually it is

    still (65.10 kms) at the take-off stage. Delhi has all the ideal dress-up for an excellent Mass

    Rapid Transit System to be brought in. It has wide roads (roads cover 23% of the city area)

    where road possession for construction is not difficult (except in the old city area).

    Implementation will also not involve demolition of large scale private properties. Most of the

    land required is under Government control and hence can be easily acquired. The citizens are

    enlightened and would eagerly welcome introduction of people friendly MRTS though they

    may initially face some difficulties during the implementation phase. Added to this Delhi has

    an unassailable advantage in its excellent railway network comprising two rings and six spurs

    totaling about 120 KM within the urban area. Unfortunately, these Rail assets are not presently

    fully being utilized as its share of commuter traffic is only a mere 2%.

    Operations management of DMRC Page 2

  • 7/31/2019 POM Edited

    3/35

  • 7/31/2019 POM Edited

    4/35

    Line1

    Shahdara Inderlok - Rithala 22.0 km 18 stations

    Line2

    Vishwa vidyalaya Central secretariat 11.0 km 10 stations

    Vishwa vidyalaya to Kashmere gate 4.0 km

    Kashmere gate to Central secretariat 7.0 km

    Line 3

    Barakhamba road -Dwarka 25.60 km 31 stations

    Barakhamba road - Indraprastha 2.81 km

    Dwarka Dwarka sub city 6.5 km

    PHASE 2

    Between stations Length (km) Date of Commencement

    of Operation

    Shahdara Dilshad 3.1 June 4, 2008

    Garden

    Operations management of DMRC Page 4

  • 7/31/2019 POM Edited

    5/35

    Vishwavidyalaya 6.3 February 4, 2009

    Jahangirpuri

    Indraprastha Yamuna 2.1 May 10,

    2009

    Bank.

    Line Name BetweenStations Length (Kms.) No. of stations

    Yellow Line Central Secretariat- 27.45 19

    Qutub Minar -

    Sushant Lok

    (Gurgaon)

    Violet Line Central Secretariat- 20.04 15Nehru Place -

    Badarpur

    Blue Line Dwarka (Delhi) 6.26 3

    Sector 9 - Sector

    21 - IGI Airport

    Blue Line Yamuna Bank - 15.07 11

    Mayur Vihar -

    NOIDA City Centre

    Blue Line(Branch) Yamuna Bank - 6.17 5

    Anand Vihar

    Green Line Inderlok Kirti 18.46 15

    Nagar - Mundka

    Airport Express New Delhi 22.4 6

    Railway Station -

    Indira Gandhi

    International

    Airport - Dwarka

    (Delhi)

    Blue Line(Branch) Anand Vihar - 2.57 2

    Vaishali

    Operations management of DMRC Page 5

  • 7/31/2019 POM Edited

    6/35

    (Ghaziabad)

    Future Extensions

    Phase III

    This phase has a 2015 deadline. The following lines are tentatively planned:

    1. Jahangirpuri - Badli (northern exten sion of Yellow Line) = 3.42 km

    2. Mukundpur - Azadpur - Rajouri Garden - AIIMS - Sarai Kale Khan ISBT = 31 km

    3. Central Secretariat - Mandi House - Daryaganj - Welcome Gokulpuri - Nawada

    (Bahadurgarh) = 18 km

    4. Rithala - Kirari - Barwala (western extension of Line 1/Red Line) = 6 km

    5. Dilshad Garden - Ghaziabad ISBT (eastern extension of Line 1/Red Line) = 9.5 km

    6. Airport link - Sushant Lok (Gurgaon) = 16.5 km

    7. Mundka - Delhi border Bahadurgarh (western extension of Line 5) =11 km

    8. Badarpur - YMCA chowk, Faridabad (southern extension of Line 6) =14 km

    9. Sushant Lok (Gurgaon) - T-junction of Sectors 47 & 48, Gurgaon (southern extension of

    Line 2/Yellow Line) = 6.5 km Jahangirpuri - Badli line may be implemented in Phase II

    Total length = 112 km

    Phase IV

    This phase has a 2020 deadline. The following lines are tentatively planned:

    1. Sarai Kale Khan ISBT - Anand Vihar - Dilshad Garden Yamuna Vihar - Sonia Vihar = 22

    km

    2. Sarai Kale Khan ISBT - Nehru Place - Palam - Reola Khanpur = 28 km

    3. Mukundpur - GTK By-Pass - Pitampura - Piragarhi - Janakpuri -Palam = 20 km

    Operations management of DMRC Page 6

  • 7/31/2019 POM Edited

    7/35

    4. Barwala - Mundka - Najafgarh - Dwarka = 20 km

    5. Ghazipur Noida Sector 62 = 7 km

    6. Dwarka Sector 21 - Iffco Chowk = 15 km

    7. Ajronda (Faridabad) - Kheri (Faridabad) = 5.5 km

    Total length = 108.5 km

    Operations management of DMRC Page 7

  • 7/31/2019 POM Edited

    8/35

    ORGANIZATIONAL STRUCTURE

    Procedures followed in the decision-making process, including channels of supervision

    and accountability

    The decision-making process in DMRC involves the following Channel:

    BOARD OF DIRECTORS

    MANAGING DIRECTOR

    FUNCTIONAL DIRECTORS

    EXECUTIVES

    Overall management of DMRC rests with the Board of Directors, its highest decision making

    body.

    DMRC being a 50-50 joint venture of the Government of India and the Government of

    National Capital Territory of Delhi, the Board of Directors of DMRC is accountable to the

    Government of India and the Government of National Capital Territory of Delhi. As per the

    provisions of the Companies Act, 1956 certain matters require the approval of the shareholders

    of the Company in general meeting. The primary role of the Board is that of trusteeship to

    protect and enhance shareholders value.

    The Board oversees the Companys strategic direction, reviews corporate performance,

    authorizes and monitors strategic decision, ensures regulatory compliance and safeguards

    Operations management of DMRC Page 8

  • 7/31/2019 POM Edited

    9/35

    interests of shareholders. The Board ensures that the Company is managed in a manner that

    fulfils stakeholders aspirations and societal expectations.

    The day-to-day management of the Company is entrusted with Managing Director who is

    supported by Functional Directors and other Officers and staff of the Company.For effective

    discharge of his functions, the Board of Directors has delegated most of the powers to the

    Managing Director. The Managing Director, in turn, delegated specified power to Functional

    Directors/Officers subject to due control being retained by him and subject to such conditions

    which are consistent with the need of prompt, effective and efficient discharge of

    responsibilities entrusted to such a Director/Officer. The Managing Director is accountable to

    the Board of Directors. Functional Directors are accountable to Managing Director. The

    Officers are accountable to concerned Functional Directors.

    MISSION

    To cover the whole of Delhi with a Metro Network by the year 2021.

    Delhi Metro to be of world class standards in regard to safety, reliability, punctuality,

    comfort and customer satisfaction.

    Metro to operate on sound commercial lines obviating the need for

    Government support.

    CORPORATE CULTURE

    We should be totally dedicated and committed to the Corporate Mission

    Operations management of DMRC Page 9

  • 7/31/2019 POM Edited

    10/35

    Personal integrity should never be in doubt, we should maintain full transparency in all our

    decisions and transactions

    The Organization must be lean but effective

    The Corporation must project an image of efficiency, transparency, courtesy and we mean

    business attitude.

    Our construction activities should not inconvenience or endanger public life nor should lead

    to ecological or environmental degradation

    All our structures should be aesthetically planned and well maintained

    Safety of Metro users is our paramount responsibility

    Our stations and trains should be spotlessly clean.

    IMPORTANT FEATURES OF DMRC

    All metro stations and trains are monitored constantly by more than 1200 closed-circuit

    cameras, and specially trained Delhi Metro police are stationed at all stations and trains to deal

    with law and order issues in the system. The Delhi Metro is also one of the few metros in the

    world to have plain clothed metro marshals on trains. Intercoms are provided in each train car

    for emergency communication between the passengers and the driver.

    Special Features in New Metro Trains

    The new trains in view of the increased rush on the Metro system in Delhi, will provide

    passengers with power connections inside the coaches so that they can use their laptops and

    charge their mobiles while they are travelling in the Metro. Every new Metro coach of Phase

    Operations management of DMRC Page 10

  • 7/31/2019 POM Edited

    11/35

    II will have power supply points for this purpose. The Metro coaches in Phase - II will also

    have reduced noise levels inside the trains as the DMRC is making major design changes to

    reduce the noise levels by use of special sound absorbing cushions in the walls of the Metro

    coaches and more buffing on the Metro doors which will be better sealed by reducing the door

    gaps to ensure that less sound from outside enters the trains thus enabling the passengers to

    travel in a better ambience. The noise level in the underground coaches has been reduced by 8

    decibels(db) as in Phase-I the internal noise levels was around 92 db which will now be

    only 84 db in Phase-II. In addition, a new type of compressor called Scroll Compressor System

    will be used in the air conditioners of the Phase-II coaches which will be sealed and is more

    compact and this will reduce noise level in the coaches further.

    The Phase-II Metro coaches will also provide a much better level of passenger comfort as for

    the first time there will be Humidity control as Humidity Sensors will activate the newly

    planned heating system of the air conditioner which will eliminate humidity inside the coaches.

    The temperature will be maintained at 25 degree Celsius and relative humidity will be

    maintained at 60 % during the summer and monsoon months (in Phase - I trains, there was only

    temperature control).

    With the start of Phase-II the Delhi Metro will start travelling very far distances covering

    around 50 kms in some destinations such as Dwarka-Noida, Gugaon-Jahangirpuri, etc.

    To avoid confusion for the passengers who will travel on these lines, there will be new

    destination sign boards in LED on one window of the side wall of each coach so that

    passengers can view the terminal stations while standing on the platform as some Trains may

    be terminating at intermediate stations depending upon operational needs. This will be

    necessary as on the same line different trains may be terminating at different destinations.

    Operations management of DMRC Page 11

  • 7/31/2019 POM Edited

    12/35

    Phase - II trains will also have Closed Circuit Television Cameras (CCTVs) inside the coaches

    apart from cameras outside the coaches so that the driver can see the entry and exit of

    passengers from the train. The driver of the Metro trains will now be able to observe passenger

    behavior in every part of the train at all times. The trains in Phase - II are also being designed to

    travel upto a maximum design speed of 95 kmph as against 90 kmph in Phase - I. The braking

    system is also better as DMRC will use Wheel Mounted Disc Brakes which will be micro

    processor controlled. In addition, the train will have energy absorbent couplers which can

    absorb shock and reduce damage to the car body structure in collisions.

    FACILITIES

    1) FEEDER BUSES

    They are environment friendly with CNG engine Bharat Stage III buses.

    Aesthetics and safety are important features.

    Feeder buses have Global Positioning System (GPS) equipment for real time

    tracking, online alerts etc

    Control centers are set up to monitor the movement of vehicles and will have

    traffic managers, traffic inspectors and Control Room Operators.

    A complaint book is there in every bus - Zero tolerance of complaints.

    A Public Address System is there in every bus.

    All buses are fan cooled.

    First Aid box and Fire extinguisher are there in every bus.

    2) Has a carrying capacity as high as 60,000 80,000 phpdt (peak hour peak direction traffic).

    3) Requires 1/5th energy per passenger km compared to road based system.Operations management of DMRC Page 12

  • 7/31/2019 POM Edited

    13/35

  • 7/31/2019 POM Edited

    14/35

    Organisation Structure:

    The GoI and GNCTD constituted the Delhi Metro Rail Corporation Ltd

    (DMRC) as a company incorporated under the Companies Act for construction of the

    project and Mr. Sreedharan was appointed MD.

    The DMRC had two departments project organization and operation &

    maintenance in what is known as a lean organisation structure.

    Selected group of professionals were trained at Hong Kongss Mass Rapid

    Transit Railway Corporation (MTRC)

    Complete freedom was provided to Mr. Sreedharan to recruit people of his

    choice and build a team.

    Each candidate was personally interviewedby him after a thorough review of

    their track records with emphasis on integrity.

    Most of the employees were in the age group of 18 to 30 years.

    The stress was on effective contract awarding and procurement processes in

    order to prevent corruption.

    The contract awarding process was made simple and transparent, the

    procurement

    processes fair and just by removing all traces of subjectivity from tender

    evaluation.

    The MD was given complete autonomy on all matters and was the last

    authority on tenders.

    Review and Supervision:

    Operations management of DMRC Page 14

  • 7/31/2019 POM Edited

    15/35

    Every individual would be accountable for his/her role in the project. Each

    employee had to prepare a Detailed Project Report (DPR) with particulars

    regarding the work assigned and work completed each day to be submitted to the

    respective supervisors. In case of any deviations, the employees had to give reasons

    for the same and steps for rectification.

    Every Monday, the heads of departments had to meet to review progress, set

    new targets or revise targets.

    The stress was on adherence to schedules with reverse clocks to indicate the

    number of days left before important deadlines.

    Due to delay in setting up of the organisation the first phase of the project

    commenced three years after the scheduled date, but the original deadline was not

    revised and the project duration was reduced from 10 years to 7 years to make up

    for the delayed start.

    The Delhi Metro Railway (Operation & Maintenance) Act, 2002 was enacted,

    superseding the local municipal laws of Delhi and the lower courts were barred

    from issuing stay orders.

    A group of lawyers was engaged to make sure that the courts did not grant

    such stay orders.

    Cost Control measures:

    Operations management of DMRC Page 15

  • 7/31/2019 POM Edited

    16/35

    The total expenditure was split into 3 heads manpower, energy and

    materials including maintenance, each accounting for onethird of the total project

    cost.

    The DMRC employed only 45 persons per kilometre of track to adhere to

    international norms. This was only a third of the number of persons employed in the

    Kolkata Metro Rail project which was the only other such project in India before

    Delhi.

    To cut energy costs, a special agreement was entered into with the Delhi

    Transco Ltd to source power at low rates.

    Project duration was controlled by use of special construction technologies

    like trenchless digging, use of ballastless tracks,etc.

    Primavera Project Planner:

    A special software Primavera Project Planner, was used for project planning

    and

    monitoring. The resource planning module of the project alerted users in case of excess

    or shortage of resources while the cost planning module provided a complete cost

    breakup of the project.

    The software was also used to keep trackof project activities, quantum of work

    completed at different levels, the time lost or gained etc.

    Information regarding all critical and upcoming activities was also available

    to facilitate tracking and rescheduling of activities where necessary.

    All this was necessary as the loss incurred if one day of work is lost is about 5

    million rupees.

    Operations management of DMRC Page 16

  • 7/31/2019 POM Edited

    17/35

    Quality Assurance:

    A special quality assurance team independent of the field executives was

    appointed to ensure quality in construction.

    All personnel working at the construction site were required to wear helmets

    and otherappropriate safety gear.

    Consultancy and contracts was undertaken by a global bidding program which

    required at least one Indian partner, to ensure technology absorption by Indian firms

    and for localisation and reengineering of technology.

    The technology used was the best and the latest available . Multinational

    engineering corporations from across the globe worked on the project.

    A five member consortium led by the Pacific Consultants International (PCI)

    was constitute to provide overall consultancy for the project.

    Work on utility diversion was undertaken much before the commencement

    of work on a particular section. The concerned consortium surveyed the area for

    utilities (water pipes, sewer, water pipes, etc) to submit a written report to DMRC

    which completed the work within the prescribed period.

    Operations management of DMRC Page 17

  • 7/31/2019 POM Edited

    18/35

    Managing the stakeholders Government, contractors, funding

    agencies and general public:

    Autonomy of the DMRC was ensured in the recruitment process, promotions,

    contract awarding and land acquisition. It took a stand that any change in any decision

    would be made only if it was required from a technical or professional angle and not

    simply because somebody wants it.

    Cordial relationship was maintained with the contractors by making

    payment on time. The contractors were grateful for not having to give bribes to

    secure the contracts which ensured their full cooperation and completion of the

    project ahead of schedule in certain sections because of their suggestions.

    The officials ofJBIC which provided a major part of the funding for the project

    were involved in all major events concerned with the project to maintain cordial

    relations with them.

    All utilities were diverted well in advance so as to ensure minimum

    inconvenience to the general public. Community interaction programmes were

    organised to inform and seek solutions from the public.

    Alternate traffic arrangements were made for the roads affected by the

    construction with the assistance of the Indian Institute of Technology, Delhi. This was

    done by building new roads or by widening of existing roads.

    The ISO 14001 certification, which deals with standards for minimising the

    adverse effects of the operational processes on the environment, was obtained. New

    York Metro is the onlyother metro to have obtained this certification.

    It also obtained the OHSAS 18001 certification for its environment,

    occupational health and safety management system.

    Operations management of DMRC Page 18

  • 7/31/2019 POM Edited

    19/35

    POWERS AND DUTIES OF OFFICERS AND EMPLOYEES

    ELECTRICAL

    1.Rolling Stock

    2. Electrical Power supply, Traction ,Air conditioning ,Ventilation

    3. Signaling & Telecom, AFC

    4. Store Procurement

    5. Computerisation

    Rolling Stock:

    1) Review of design, tendering, Contract management for procurement of Rolling Stock.

    2) Monitoring the production schedule of trains to match the requirement of rolling

    stock required for opening of different Lines/sections of Delhi Metro.

    3) Testing & Commissioning of Rolling Stock.

    4) Planning, construction & commissioning of Depots for Rolling Stock Maintenance.

    5) Coordinate for manpower planning and training for rolling stock.

    6) Performance monitoring of Rolling Stock under revenue service.

    7) Planning and arranging spares for rolling stock maintenance.

    8) Planning & Monitoring the Indiginasation of different equipments of Rolling Stock.

    9) Monitoring the required modifications in the Rolling Stock to eliminate equipments

    failures observed so far.

    10) Coordination for sanctioning of Rolling Stock from CMRS.

    Operations management of DMRC Page 19

  • 7/31/2019 POM Edited

    20/35

    Air conditioning & ventilation system:

    Planning, Review of design, Tendering, Contract Management, Construction and

    commissioning of following :

    1)Station ventilation, air conditioning & Smoke extraction system.

    2)Tunnel ventilation system.

    3)Testing ,installation and commissioning of the system.

    4)Coordination for sanctioning of VAC System from CMRS.

    5)Performance monitoring of VAC System under revenue service.

    Lifts and Escalators:

    1)Planning, procurement, installation and commissioning of Lifts and Escalators at

    stations , specially designed for elderly and physically challenged passengers

    2)Performance monitoring of Lifts and Escalators under revenue service

    Electrical & Mechanical System and Environment Control System:

    Planning, Construction and commissioning of the following :

    Power Supply Arrangement at Stations, U.P.Ss, Lighting, Fans, Pumping

    System etc.

    Operations management of DMRC Page 20

  • 7/31/2019 POM Edited

    21/35

    Building Management System

    Fire Detection & Fighting System

    Emergency and rescue arrangement

    Coordination with other wings for design and site interfaces and utility diversion

    Planning & commissioning of Infrastructure Facilities for Preventive

    Maintenance

    Performance monitoring of E&M and ECS system under revenue service

    SIGNAL & TELECOM and AFC

    Signaling/Train Control, Telecommunication and Automatic Fare Collection Systems:

    Planning, tendering, contract management, installation and commissioning of the

    Operations management of DMRC Page 21

  • 7/31/2019 POM Edited

    22/35

    following:

    Signaling/Train Control Systems comprising of:

    Automatic Train Operation

    Automatic Train Protection

    Automatic Train Supervision

    Solid State Interlocking

    Point Machines / Signals /Track Circuits

    Telecommunication Systems comprising of:

    Fibre Optic system : SDH/Access

    Train Radio system on trains and Radio Base Stations

    Operations management of DMRC Page 22

  • 7/31/2019 POM Edited

    23/35

    FPABXs at all stations

    Close circuit television (CCTV)

    Public Address System

    Passenger Information Display System

    Power Supply System

    NP-SCADA system

    Automatic Fare Collection System comprising of:

    Automatic Fare Collection Gates

    Ticket Office Machines

    Station Computer/Central ComputerOperations management of DMRC Page 23

  • 7/31/2019 POM Edited

    24/35

    Design review and approval

    Coordination with other wings for design and site interfaces

    Pre and Post Installation, commissioning and integration tests

    Submission of CMRS application and compliance of observations and inspection

    Monitoring of performance of completed works during warrantee period

    Planning of manpower and training thereof

    Planning and execution of ERP system and office telecom network and office

    computers

    CIVIL ENGINEERING

    PLANNING

    Operations management of DMRC Page 24

  • 7/31/2019 POM Edited

    25/35

    1. Deal with consultancy work being undertaken by DMRC at Ahmedabad, Kolkata,

    Bangalore, etc

    2. Deal with Parliament questions and Assembly Questions

    3. Estimate, Budget control

    4. Transport planning and related correspondence

    5. Member of Technical Committee of DDA

    6. Handle all civil engineering tenders, compilation of tender drawings and tender

    documents, pre-qualification tender drawings and tender document, to deal with

    correspondence and queries of tenders/contractors, preparation of briefing note and

    comparative statement, preparation of agreement and signing of agreement. coordination

    and association wit GC regarding tender and contract matters.

    7. Updating of Civil Engineering Contracts

    Operations management of DMRC Page 25

  • 7/31/2019 POM Edited

    26/35

    8. Maintenance of all tenders and contractors documents in safe custody and

    maintenance of confidential reports and documents.

    9. Preparation of various progress reports regarding tender/contract matters, related

    correspondence and coordination with other departments

    10. Planning and integration of different activities/packages, updating and monitoring of

    project

    11. Revision /updating of project estimate and related activities

    12. Generation of management information report regarding the project schedule/ mile

    stone and (ii) cost control.

    13. Preparation and review of yearly budget, forecast of cash flow requirements.

    14. Preparation of periodical progress report of project like monthly progress report,

    flash report, etc to ministries and correspondence with various ministries in this regard.

    15. Checking of alignment plans, L-Sections, Land plans; getting approval from HODs

    and keeping record thereof.

    16. Checking of civil engineering construction drawings of stations of Rail corridor and

    keeping record thereof

    17. Planning and monitoring of all matters pertaining to track structures including

    planning, design, use of modern track structure/fittings, coordination with other

    departments, especially to ensure overall compatibility of the systems.

    Operations management of DMRC Page 26

  • 7/31/2019 POM Edited

    27/35

    18. Planning and development of infrastructure and maintenance of all civil engineering

    structures.

    19. Programming and monitoring of works, presentation of progress report to

    management, flash Report, Monthly progress report, JBIC Quarterly Report, Interaction

    with JBIC regarding funding

    20. CMRS inspection, schedule of dimensions and all correspondence related to these

    items.

    21. Enviornmental management plan and its monitoring.

    22. Safety amd quarterly assurance, Internal Audit of works of all contractors.

    CIVIL (WORKS)

    1. Direction and supervision of all civil and utility works including review of estimates

    submitted by different departments are agreed .

    2. Coordination with local authorities

    3. Planning and construction of Depots

    4. Geotechnical investigation -including depot and other structures

    5. Water supply system

    6. Design coordination

    7. Tree cutting and plantation

    Operations management of DMRC Page 27

  • 7/31/2019 POM Edited

    28/35

    8. Quality control and quality assurance at work sites.

    9. Implementation of site safety plans, environmental plans at site.

    10. Completion of all woks at site within a stipulated time, keeping records of all site

    related activities, contract bills, finalisation of all claims, preparation of completion

    plans etc.

    11. Contract and Project management

    12. Tunnelling work

    13. Track work

    14. Floating of tenders, coordination with respective HODs and monitoring of the work

    15. Road diversions required before taking up the construction work, piles, pile cap and

    pier/ramp/raft/potals.

    16. Launching girders, operation of segment, lifting, traffic diversion, alignment,

    exposing, stressing etc

    17. Steel work, casting yard work etc

    18. Construction of staff quarters

    19. Land requirement review.

    20. Coordination with MCD, NDMC, N.Rly, Traffic Police.

    21. Keeping records of all site related activities, contract bills, cleaning etc finalisation

    of all claims and preparation of completion plans etc.

    Operations management of DMRC Page 28

  • 7/31/2019 POM Edited

    29/35

    22. Execution of works related to property development and rehabilitation.

    CIVIL (DESIGN)

    1. All civil engineering structure work.

    2. Checking , co-ordination, monitoring scrutiny and timely availability of design

    and drawings and particularly to get functional and economic design

    3. Coordination with DDC, proof consultants, GC and other departments for the

    structural design and drawings.

    4. Preparations of design criteria and standard drawing of Civil Engineering

    structures t o be followed in DMRC.

    5. Project management of all records pertaining to structural drawing and designs

    including the details required for CRS sanction/inspection

    6. Structural design of station

    Operations management of DMRC Page 29

  • 7/31/2019 POM Edited

    30/35

    CIVIL (GENERAL)

    1. Acquisition of land (Govt. & Private)

    2. Land survey, joint inspection and joint verification

    3. Valuation of properties/structures

    4. 4. Relocation of Govt. Structures

    5. High power committee meetings and other meetings with Govt. Deptt.

    6. Rehabilitation of jhuggies,

    7. Tree cutting

    8. Court cases in connection with land acquisition

    9. Shifting of religious structures

    10. Compliance of progress report and other data as requiredOperations management of DMRC Page 30

  • 7/31/2019 POM Edited

    31/35

    11. NOC to building plans for structures coming in MRTS alignment.

    12. Fencing and security arrangement till the land is handed over to the

    Contractors

    13. Construction of Staff Quarters

    14. Correspondence with Transport Commissions, Task Force Meetings

    15. Resettlement schemes

    16. Calculation of reserve price, terms of allotment for all permanent rehabilitation

    ARCHITECT

    1. Architectural planning and design of all stations on Delhi Metro

    2. All architectural works of stations and other related structures

    3. Signage , Graphic and Art works on stations.

    4. Supervision of architectural works at stations.

    PUBLIC RELATIONS

    1. Handling press, reporters, and media

    2. Coordinating visits of VIPs and high and important official to various metro sites.

    3. Handling various conferences and updating the media of the latest developments.

    4. Organising road shows,giving wide publicity about Delhi metro, keep liaison with

    media, press, reporters etc.

    Operations management of DMRC Page 31

  • 7/31/2019 POM Edited

    32/35

    LEGAL

    1. Attend different cases in various courts/quasi-judicial authorities.

    2. Deals with all legal matters of the company including vetting of tenders, legal

    agreements and render advice.

    3. Maintenance of various court case files

    ACCOUNTS

    1. General administration and establishment bills

    2. Finance Scrutiny of Establishment proposals

    3. Accounts & internal audit

    4. Fund Management

    5. Computerisation and development of MIS for Finance/Accounts

    6. Tenders of Electrical , S&T, Civil, Stores including estimates & tender documents

    7. Financial analysis, Expenditure, Cheques & Cash, Budget, cash and Bank

    investments

    8. Interaction with GNCTD , GOI, JBIC and all matters pertaining to JBIC loan, JBICF

    payments

    9. Taxation matters - corporate taxation, Tax returns

    10. Finance Vetting and concurrences

    Operations management of DMRC Page 32

  • 7/31/2019 POM Edited

    33/35

    11. Maintain all books and register for contracts, work registers and contractor's ledgers

    12. Audit -Internal Audit, Statutory Audit and CAG

    13. Project cost control, feasibility reports, revised cost estimates

    14. ERP, Fare Policy, Fare collection and accounting.

    PERSONNEL

    1. Manpower planning

    2. Recruitment , Selection and Induction of staff

    3. Handling interviews, medical examination, verification of character and antecedence,

    etc

    4. Providing training to employees. Sending employees for various on the job training

    relevant to their field.

    5. Formation of Policy, Procedures, Rules and Regulations

    6. Dealing with induction of staff on deputation from different organizations.

    7. Annual performance Record- initiation and maintenance of the same

    8. Dealing with various advances like Festival Advance, House Building Advance,

    Motor Car Advance, Motor Cycle Advance etc

    9. Promotion and transfer of employees

    10. Welfare facilities like Birthday cheques, marriage gift., ex-gratia, etc.

    OPERATIONS

    Operations management of DMRC Page 33

  • 7/31/2019 POM Edited

    34/35

    1. Planning and monitoring of day-to-day operation of revenues services.

    2. Co-ordination with other allied wings to ensure punctuality and reliability of trtain

    services.

    3. Management of Operation Control Centre & centralised monitoring of train

    operations.

    4. Crew management for efficient running of trains.

    5. Management of stations, including monitoring of cleanliness.

    6. Issue of smart cards / tokens to passengers.

    7. Dealing with passenger's complaints.

    8. Dealing with property development matters within the station premises.

    9. Dealing with contracts / outsourcing of manning of booking windows, parking spaces,

    shops, Kiosks etc.,

    10. Management of safety requirements.

    11. Management of emergency situations during train operations.

    12. Cadre planning, identification of training needs, monitoring of competence

    requirements of operating staff.

    13. Time tabling, monitoring over cash collection from stations.

    14. Dealing with lost and found items.

    15. Management of Customer Care Centres.

    16. Crowd Management during special occasions.

    17. To implement contingency plan during incident / accident.

    18. To conduct mock drills.

    19. To send QRT and operate rescue operation during Disaster.

    20. Insurance of assets, cash and passengers.

    Operations management of DMRC Page 34

  • 7/31/2019 POM Edited

    35/35

    21. Safety related documentation, framing of procedure orders.

    22. Security services and liaison with Delhi Metro Police & Ambulance services.

    23. Co-ordinating with Project wing for proper trials and taking over of section.

    24. Planning, Maintenance, Blocks & monitoring their execution.

    BIBLIOGRAPHY

    http://www.delhimetrorail.com/rightto_infoact/powers.aspx

    http://www.delhimetrorail.com/rightto_infoact/powers.aspxhttp://www.delhimetrorail.com/rightto_infoact/powers.aspx