Piping Group & Equipment Space

Embed Size (px)

Citation preview

  • 8/3/2019 Piping Group & Equipment Space

    1/41

    PREPARED

    BY PTT PUBLIC COMPANY LIMITEDCHECKED

    BY ONSHORE COMPRESSOR STATION 4

    PROJECT

    APPROVED

    BY

    CERTIFIED

    (PTT)

    REV.

    NO.

    DATE REVISED

    BY

    APPROVED

    BY

    DESCRIPTION

    D118-Feb-

    08ISSUED FOR ITB

    D2 1-Jul-08 REVISION ISSUED FOR ITB

    SPECIFICATION FOR

    PIPING GROUP EQUIPMENT SPACING

    SPC-0804.02-50.03 REV.D2

    TOTAL 41 PAGES

    AREA CODE OF SITE LOCATION

    GENERAL AREA: 010

    .

    PTT PLC. CONTRACT NO. PTT PLC. PROJECT NO.

    0804.02

  • 8/3/2019 Piping Group & Equipment Space

    2/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 2 OF 41

    REV: D2

    CONTENT

    SECTION

    1.0 SCOPE ..................................................................................................... 3

    2.0 GENERAL CONSIDERATIONS ...................................................................... 3

    3.0 DEFINITIONS ............................................................................................ 4

    4.0 STANDARDS AND GUIDES......................................................................... 5

    5.0 SPACING OF UNITS AND AREAS ................................................................ 6

    6.0 ON SITE SPACING....................................................................................12

    7.0 OFFSITE SPACING....................................................................................22

    8.0 TANKAGE................................................................................................27

  • 8/3/2019 Piping Group & Equipment Space

    3/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 3 OF 41

    REV: D2

    1.0 SCOPE

    The scope of this standard is to define the basic design, equipment spacingcriteria and standards to be used in the layout of plant and equipment.

    The recommendations are based on current practice within the industry and are

    intended, as a minimum, to satisfy the requirements of all relevant Government

    safety recommendations.

    Where applicable this standard is to be read and utilised in conjunction with

    relevant National mandatory standards, listed codes and regulations which also

    apply to the location of the project.

    In the event of any conflict, Contractor shall seek clarification from the Clientbefore proceeding. Generally, the most stringent requirements shall apply.

    This standard is not applicable for the following: -

    Toxic Materials Handling Plant

    Explosives Plant

    Nuclear Plant

    Pharmaceutical Plant

    Equipment within Enclosed Buildings

    Offshore Facilities

    Well Drilling Sites for Oil or Gas

    2.0 GENERAL CONSIDERATIONS

    The objective of the spacing recommendations is to ensure that maximum

    economical use is made of available plot areas, compatible with the safety ofpersonnel and vulnerability of plant.

    In achieving this end, consideration shall be given to:

    a) Accessibility for normal operation and maintenance

    b) Accessibility for fire fighting

    c) Accessibility for emergency shutdown

    d) Accessibility for evacuation of personnel

    e) Segregation of high-risk facilities and sources of ignition

    f) Protection of critical emergency facilities

    g) Protection of adjacent facilities in event of fireh) Security of installations from outside hazards

    i) Minimising danger and inconvenience to personnel and property

    beyond the boundary fence.

  • 8/3/2019 Piping Group & Equipment Space

    4/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 4 OF 41

    REV: D2

    j) Ergonomic Factors

    k) Escape access ways shall be as straight and obstruction free as

    possible.l) Hazardous area classification

    m) Ensuring that flammable vapour generated from one facility will

    diffuse to a concentration well below the lower explosive level (LEL)

    before it reaches any other facility or area where a source of ignition

    may exist.

    n) Providing a reasonable degree of protection (distance) against heat

    radiation

    2.2 Circumstances will arise where it will be difficult to adhere to the minimum

    spacing requirements; e.g. where there are severe limitations on plot

    availability. In such cases a reduction of minimum spacing (less than 10%) shall

    only be acceptable, after agreement with PTT/CONSULTANT. Any reductions in

    the proposed distances between equipment shall be subject to a Risk

    Assessment or Hazard Analysis. In this case extra safety features such as

    Firewalls, Sprinklers, Emergency Shutdown Facilities etc., shall be required to

    be incorporated into the design in order to compensate for the reduction in the

    distances between the equipment. Such reductions shall not be made without

    prior reference to PTT/CONSULTANT.

    2.3 Other factors may require spacing greater than minimum recommendation of

    this Standard. In this category consideration should be given to:

    Proximity of adjacent property and the consequential environmental and public

    relations effects.

    Special process hazards, which may necessitate increased spacing.

    Special plant maintenance or installation considerations

    Future development plans both inside and outside the boundary fence.

    Topographical features of site and direction of prevailing winds

    Political security factors.

    Special hazard zoning plans for existing plant areas.

    3.0 DEFINITIONS

    The following definitions are used throughout the standard.

    3.1 Flash Point

    The flash point is the lowest temperature at which a product gives off sufficient

    vapour to form a mixture with air that can be ignited by a flame or spark.

    3.2 Auto Ignition Temperature (AIT)

  • 8/3/2019 Piping Group & Equipment Space

    5/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 5 OF 41

    REV: D2

    The auto-ignition temperature is the temperature at which a product will burn

    without application of any other form of ignition.

    The AIT of most petroleum products is between 250C and 500C. In general

    the AIT of petroleum hydrocarbons decrease with higher boiling fractions

    whereas flash points increase.

    3.3 Sources of Ignition

    Possible sources of ignition include the following:

    3.3.1 Electrical

    Sparks or arcs may occur when current carrying contacts are separated or

    through static electricity discharge.

    3.3.2 Naked Lights

    E.g. fired heaters, fires, smoking, hot work, gas welding, etc.

    3.3.3 IC Engines

    Spark-ignition systems, exhaust hot spots.

    3.3.4 Spontaneous Combustion

    Pyrophoric materials, vapour leakage at temperatures above AIT.

    3.3.5 Frictional Ignition

    Grit blasting, power tool grinding, mechanical failure of rotating machinery.

    3.3.6 High Temperature Surfaces

    Transfer lines, HP steam lines, and other hot surfaces.

    4.0 STANDARDS AND GUIDES

    Philosophy on plant layout is contained within various standards and guides,

    including;

    SPC-0804.02-50.01 Design Instruction for Piping Arrangement.

    Noise Control Eng. Std.

    Institute of Petroleum Model Codes of Safety Practice, Part 3

    LP GAS Association Code of Practice 1

    Institute of Petroleum Model Codes of Safety Practice, Part 9, LPG

  • 8/3/2019 Piping Group & Equipment Space

    6/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 6 OF 41

    REV: D2

    Area Classification Code for Petroleum Installations,(IP15) Model Code of

    Safe Practise in the Petroleum Industry Part 15

    NFPA-30 (Flammable & Combustible Liquids Code)

    NFPA-58 (Storage and Handling of LPG)

    NFPA-59 (Storage and Handling of LPG)

    NFPA-59A (Storage and Handling of LNG)

    Fire Fighting Systems

    European Standard EN 1473, Installation and equipment for LNG Designof onshore installations.

    European Model Code of Safe Practices in the Storage and Handling of

    Petroleum Products. Part 1, Operations.

    API Standard 2510 Design and Construction of LPG Installations

    Thai Fuel Oil Storage Act 2474

    Announcement of the ministry of liquid petroleum gas containment

    Note: Reference should be made to these documents when producing the

    optimum layout of the relevant plant facilities.

    5.0 SPACING OF UNITS AND AREAS

    Fig.1 Show a typical overall PLOT PLAN

    5.1 Process Unit

    A process complex consists of a combination of plants, each carrying out a

    specific processing duty. These plants are defined as PROCESS UNITS.

    Equipment items within the process unit limits are referred to as on-site

    equipment. On-site Spacing Chart, Fig. 4, gives the recommended spacing

    between these items of equipment.

    Equipment limits are determined by an imaginary line drawn around the outer

    edge of equipment within the Process Unit.

    5.2 Process Area

    Several process units may be combined to form a PROCESS AREA. These unitsmay be integrated, i.e. by no spacing between units other than basic equipment

    spacing, or may be laid out as separate units with spacing between equipment

    limits (as defined above) based on fire fighting access, process hazard or

    separate shut-down requirements; depending on overall plant philosophy.

  • 8/3/2019 Piping Group & Equipment Space

    7/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 7 OF 41

    REV: D2

    5.3 Process Block

    A number of process areas may be combined to form a PROCESS BLOCK. Fig.2 indicates an example of a Process Block showing the arrangement of a

    Process Unit (integrated and separate) and Process Areas within the block. The

    basic minimum spacing between Units and Areas are given on Fig. 2.

    5.4 Tankage Block

    Fig. 3 shows the basic minimum spacing between bunded areas for a

    TANKAGE BLOCK.

  • 8/3/2019 Piping Group & Equipment Space

    8/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 8 OF 41

    REV: D2

    Fig. 1 Typical Overall Plot Plan.

    FIRE TRAINING

    EFFLUENT

    TREATMENT.UTILITY AREA

    STORM

    DRAIN

    PROCESS

    UNITS

    ADMIN

    BLDG.

    FUTURE PROCESS UNITSFUTURE EXPANSION

    CRUDE OIL

    TANKAGE

    GRADE

    PIPETRACK

    LPG

    SPHERES

    INTER-

    MEDIAT

    TANKS

    PROCESS

    BLOCK

    FUTURETANKAGE

    TANKAGE

    BLOCK-PRODUCT

    STORAGE

    ELEVATED

    PIPERACK

    FUTURE

    UTILITY

    AREA

    REFINERY

    BOUNDARY

    FENCE LINE

    GATE

    HOUSE

  • 8/3/2019 Piping Group & Equipment Space

    9/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 9 OF 41

    REV: D2

    Fig. 2 Example of a Process Block

    Shows the process block divided into areas: and an area divided into units. Also showthe dimensions of the clearances required.

    10m

    C

    10m

    B

    EQUIPT.

    LIMITS

    ALL

    EQUIPT

    WITHIN

    LINES

    ACCESS

    EQUIPMENT LIMIT

    SINGLE LARGE UNIT

    INTEGRATED UNITS

    (No Physical Separation)

    AB

    C

    ACCESS

    SEPARATE

    UNIT

    10m 50m 50m 50m15m 15m

    10m

    80m

    80m

    60m

    30m

    30m

    A

    RESTRICT

    TO 300m

    (approx)

    UNIT

    LIMIT

    SEPARATE

    UNIT

    UNIT

    LIMIT

    C

    EQUIPT.

    LIMITS

    PROCESS AREA

  • 8/3/2019 Piping Group & Equipment Space

    10/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 10 OF 41

    REV: D2

    Fig. 3 typical Tankage Block

    Dimensions are from the inside of the top bund wall. Bund should not be less than 15

    m. from the outer boundary of the installation or the protection belt. This is to allow

    for an access for firefighting and also to create a safe distance from the boundary.

    30m 30m

    ACCESS

    ROAD

    30m

  • 8/3/2019 Piping Group & Equipment Space

    11/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 11 OF 41

    REV: D2

    Fig. 4 On Site Spacing Chart

    This chart to be used with On-site spacing guide.

    Note: All distances in metres

    N.A. Not applicable.

    X Provide spacing based on access for operation and maintenance.

    Y As required see On-site spacing guide.

    Basic spacing is the recommended distance required between a given facility and

    other general processing equipment. This spacing is not required between items

    in similar service, (i.e. pumps and spare etc).

    See notes in section 7.1: On-site spacing guide.

    7.5 7.5 7.5 7.5

    3 4.5 4.5 1.5 4.5

    7.5 7.5 7.5 N.A. 15 N.A. 7.5 7.5 7.5 7.5 X X X N.A. 7.5 X X

    EMERGENCY VALVES FOR SHUT-OFF,

    ISOLATING, SNUFFING ETC

    X

    EMERGENCY VALVES ETC

    X

    7.5

    4.5

    4.5 4.5 1.5 3 6 4.5 3 1.5 4.5 4.5 X 7.5 4.5 4.5

    ON SITE PIPE RACKS

    MAIN EQUIPMENT STRUCTURES

    X

    15

    15

    30

    X

    10.5

    4.5 4.5 X

    15 15 15

    22.5 X 4.5 X X 15 15 4.5 3 7.5 X X 30

    22.5 15 15 15 15 15 15 15 15 15 X X X

    15 15 15 22.5 15 15 15 15 15

    30 30 30 30 30 30 30 30 30

    4.5 4.5 X X X 4.5 X X 4.5

    4.5 7.5 10.5 22.5 15 4.5 10.5 10.5 7.5

    15 15 15 15 15

    30 30 30 30 30

    X 4.5 X X X

    15 4.5 10.5 X X

    15

    X X

    15 X

    X X X

    X X

    X

    7.5 7.5 7.5 7.5 22.5 15

    3 4.5 7.5 3 22.5 7.5

    4.5 4.5 7.5 4.5 22.5 15

    7.5 7.5 7.5 22.5

    4.5 3 3 15

    4.5 4.5 4.5 7.5

    15 15 15 15 22.5 15 15 15 15 30

    15 4.5 7.5 15 22.5 15

    3 4.5 7.5 3 22.5 7.5

    1.5 4.5 7.5 1.5 22.5 7.5

    7.5 15 15 Y

    4.5 3 X

    4.5 1

    15 7.5 7.5

    15 4.5 1

    15 1.5

    X

    X

    4.5 4.5 7.5 4.5 22.5 15

    7.5 15 15 7.5 22.5 X

    22.5 22.5 22.5 22.5 10

    1

    1.5 4.5 7.5 1.5

    7.5 7.5 1.5

    4.5 1.5

    3

    ELECTRICAL SUBSTATION

    UNIT CONTROL HOUSE

    CENTRAL CONTROL HOUSE

    EQUIPMENT HANDLING NON-

    FLAMMABLES

    COMPRESSOR DRIVERS (OTHER THAN

    STEAM OR MOTOR)

    GAS COMPRESSORS AND EXPANDERS

    HANDLING FLAMMABLE MATERIALS

    PUMPS HANDLING FLAMMABLE

    MATERIALS

    PUMPS ABOVE AIT

    COOLING TOWERS

    FIRED HEATERS

    AIR FIN COOLERS

    EXCHANGERS OPERATING BELOW AIT

    EXCHANGERS OPERATING ABOVE AIT

    BLOWDOWN AND DISENGAGING DRUMS

    ON-SITE PRESSURE STORAGE VESSEL

    DRUMS

    REACTORS ABOVE AIT INTERNALLY

    INSULATED

    REACTORS ABOVE AIT EXTERNALLY

    INSULATED

    N.A.

    15

    15

    30

    X

    10.5

    7.5

    3

    4.5

    15/30

    15

    3

    1.5

    4.5

    7.5

    22.5

    1.5

    7.5

    4.5

    1.5

    RT1

    RR1

    RS1

    RQ1

    RP1

    RO1

    RN1

    RM1

    RL1

    RK1

    RJ1

    RI1

    RH1

    RG1

    RF1

    RE1

    RD1

    RC1

    RB1

    RA1

    RU1

    RV1

    22.5

    ITEM

    REF.

    BASIC SPACING

    TOWERS

  • 8/3/2019 Piping Group & Equipment Space

    12/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 12 OF 41

    REV: D2

    6.0 ON SITE SPACING

    The recommended spacing for on-site equipment is indicated in On-site

    Spacing Chart Fig. 4.

    The information on this chart is supplemented by explanatory notes which are

    contained in Section 7.1 On-Site Spacing Guide.

    It is essential that reference is made to Section 7.1 when using On-Site

    Spacing Chart Fig. 4.

    Against each type a basic spacing dimension is quoted. This basic spacing is

    the recommended distance in metres between the item and other general

    process equipment. The recommended spacing between different items is

    given at the intersection of the horizontal line for one item and the vertical linefrom another. In general, this shall be the greater of the basic spacing

    dimensions for the two items. Explanatory notes can be found in Section 7.1.

    The spacing between two similar items is given in the first box adjacent to the

    item. Note that basic spacing is not required between items in the same

    service.

    6.1 On-Site Spacing Guide(Use with on-site spacing chart Fig. 4)

    6.1.1 Ref.: RA1 Towers

    (Basic Spacing 1.5 metres)

    The basic spacing of 1.5 metres provides access for operation and

    maintenance. The distance between two towers is twice the basic dimension.

    This provides some additional access for fire fighting and clearance for non-

    coincidental platforms.

    6.1.2 Ref. RBI Reactors

    (Above AIT externally insulated) (Basic spacing 4.5 metres)

    The basic spacing of 4.5 metres provides access for fire fighting and minimises

    damage to other equipment. The external insulation protects the reactor shell

    from fires on other equipment.

    Reactors may be grouped together; in which case operational and maintenance

    access of 1.5 metres between shells is satisfactory.

    Reactors operating below AIT may be regarded as drums, i.e. drum spacing

    recommendations will apply (see Ref. RD1).

    Spacing from Ref. RF1 is in excess of the greater basic dimension as theReactor is regarded as high-risk equipment.

    Since the Reactor is operating above AIT, other sources of ignition are not a

    spacing consideration and basic reactor spacing of 4.5 metres will apply, e.g.

    items Ref. RJ1 and R01.

  • 8/3/2019 Piping Group & Equipment Space

    13/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 13 OF 41

    REV: D2

    6.1.3 Ref. RC1 Reactors

    (Above AIT internally insulated. Basic spacing 7.5 metres)

    The basic spacing of 7.5 metres provides access for fire fighting, minimises

    damage to other equipment in event of reactor fire, and protects exposed shell.

    N.B. Internally lined reactor shells are more susceptible to fire damage than

    unlined vessels. Reactors may be grouped together; in which case operational

    and maintenance access of 1.5 metres between shells is satisfactory.

    Reactors operating below AIT may be regarded as drums, i.e. drum spacing

    recommendations will apply (see Ref. RD1).

    Spacing from RF1 is in excess of the reactor after basic dimension as the

    reactor is regarded as high-risk equipment.

    Since the reactor is operating above AIT, other sources of ignition are not a

    spacing consideration, basic reactor spacing of 7.5 metres will apply, e.g. items

    RJ1/R01.

    Spacing from Refs. RP1, RT1, RU1 these items are not regarded as fire

    hazardous the spacing of 4.5 metres will give these items protection in the

    event of reactor fires.

    6.1.4 Ref. RD1 Drums

    (Basic Spacing 1.5 metres)

    The basic spacing of 1.5 metres access for operation and maintenance. Spacing

    from RU1 is the basic drum spacing as the pipe rack is not considered fire

    hazardous. Drums should not be located under pipe racks.

    6.1.5 Ref. RE1 On-site Pressure Storage Vessels

    (Basic Spacing 22.5 metres)

    The basic spacing of 22.5 metres minimises exposure of unit equipment to a

    potential source of severe fire, and blast damage in the event of an explosion.

    Pressure storage in on-site locations shall be avoided wherever possible.

    It is sometimes necessary, e.g. in solvent propane dewaxing and deasphalting

    units to provide pressure storage facilities on-site; in such instances the

    inventory shall be held to a minimum and the storage vessel located at the unit

    battery limit and as far as possible from fired heaters and other source of

    ignition.

    For pressure storage vessels, in the same service provide a minimum of onediameter between shells for operational and maintenance access.

    Spacing from RU1 pipe racks is not considered as fire hazardous- spacing of

    4.5 meters affords protection to these items in the event of storage vessel fire.

  • 8/3/2019 Piping Group & Equipment Space

    14/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 14 OF 41

    REV: D2

    6.1.6 Ref. RF1 Blow-down and Disengaging Drums

    (Basic spacing 7.5 metres)

    The basic spacing of 7.5 metres provides protection to the Drum in the event of

    fire within the unit.

    For high-risk equipment the spacing shall be increased to 15 metres. High risk

    equipment includes reactors, exchangers and pumps, operating above AIT, fired

    heaters, gas compressors and expanders, and their drivers, e.g. items Ref. RB1,

    RC1, RG1, RL1, RN1, R01.

    Spacing from Ref. RU1 pipe racks are not regarded as fire hazardous

    spacing of 4.5 metres affords protection to the pipe rack in the event of

    blowdown drum fire.

    6.1.7 Ref. RG1 Exchangers

    (Operating above AIT) (Basic spacing 4.5 metres)

    The basic spacing of 4.5 metres minimises damage to other equipment in event

    of fire. Exchangers operating above AIT are high-risk items with greater

    probability of fire than for exchangers operating below AIT.

    Exchangers above AIT in the same service, i.e. connected by a common

    process stream, may be spaced 1.0 metres apart; for other exchangers basic

    spacing of 4.5 metres shall apply.

    Spacing from Ref. RJ1 since the fluid in the exchanger is already above its

    AIT, the fired heater, in this case, does not represent a source of ignition.

    However, a heater fire is considered likely to be more severe than other plant

    fires, so spacing greater than basic is applied to minimise damage to the

    exchanger in the event of a heater fire.

    Spacing from Ref. R01 since the fluid in the exchangers is above its AIT, the

    compressor driver does not represent a source of ignition. Therefore,

    exchanger basic spacing of 4.5 metres applies.

    Spacing from RF1 is in excess of the greater basic dimension as the exchanger

    (above AIT) is regarded as a high-risk item.

    Spacing from ref. RP1 protects equipment from a high fire risk system.

    6.1.8 Ref. RH1 Exchangers

    (Operating below AIT) (Basic spacing 1.5 metres)

    The basic spacing of 1.5 metres provides access for maintenance and

    operation. There are no limitations on spacing exchangers from pipe racks exchanger spacing applies.

    6.1.9 Ref. RI1 Air Fin Coolers

  • 8/3/2019 Piping Group & Equipment Space

    15/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 15 OF 41

    REV: D2

    (Basic spacing 3 metres)

    Air fin coolers by virtue of their design and operations are particularly vulnerableto fire hazard.

    For this reason grade mounted units isolated from other equipment are

    preferred. However, because of restrictions on area availability, it is common

    practice to mount air fin coolers on top of the pipe rack. In such cases

    consideration shall be given to the following:

    Air fin coolers shall not be mounted over pumps, compressors, drums or heat

    exchangers, containing flammable materials.

    There shall be no flanges or valves in any hydrocarbon lines on the rack

    beneath an air fin cooler.

    Horizontal spacing requirements of on site spacing chart, Fig.4, shall be met.

    Support legs for the air fin cooler shall be fireproofed in accordance with the

    relevant Project Engineering Standard.

    Access shall be provided for tube bundle removal by mobile equipment.

    The basic spacing of 3.0 metres (horizontal) minimises exposure to fire hazard

    air fins are more vulnerable to fire damage than shell and tube exchangers.

    Ref. RU1 the basic spacing of 3.0 metres is applicable to grade mounted air

    fin coolers only.

    6.1.10Ref. RJ1 Fired Heaters

    (Basic spacing 15 metres)

    A fired heater by its nature is a permanent source of ignition while operating. A

    heater fire is likely to be of maximum severity. The basic spacing of 15 metres

    separates equipment handling flammable vapours from a permanent source of

    ignition and affords protection in the event of a major heater fire. Heater

    location will sometimes be predetermined by the requirement of grouping to a

    common stack with heaters from other process units.

    Where such restrictions are not applied, the heater location shall be selected on

    the windward side of the unit with reference to the prevailing wind, close to the

    battery limit and as far as practicable from other equipment. Consideration

    shall also be given to the proximity of plant and equipment outside the unit

    battery limit.

    When the heater has an individual stack, the top of the stack shall be at least 3

    metres higher than equipment within a horizontal distance of 15 metres and atleast 3 metres higher than any operating platform within a horizontal distance

    of 65 metres.

  • 8/3/2019 Piping Group & Equipment Space

    16/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 16 OF 41

    REV: D2

    Ref. RJ1 - If all heaters in a group shutdown together at plant turnaround,

    spacing between shells can be for normal maintenance only. If heaters are

    required to shutdown individually, spacing of 7.5 metres between shells isrequired for LP operation (less than 7 kg/cm2g) and 15 metres between shells

    for HP operation (7 kg/cm2g and above).

    Refs. RB1, RC1, RG1, RL1 are items operating above their AIT and in these

    cases the fired heater is not considered to be the primary source of ignition,

    spacing is based on affording protection in the event of heater fire.

    For reformer heater/reactor installations, where vapour only is present in heater

    tubes and reactors, spacing may be further reduced to 3 metres in the case of

    Ref. RB1 and 5 metres in the case of Ref. RC1.

    Ref. RN1 the compressor area is regarded as a special risk area in view of the

    potential release of large vapour quantities. Spacing greater than the basic

    dimensions are required.

    Ref. R01 the compressor driver is not considered a source of ignition in this

    case. The spacing of 7.5 metres minimises damage to the compressor driver in

    the event of heater fire.

    Ref. RP1 a spacing of 4.5 metres minimises damage in the event of the

    heater fire. For equipment higher than 3 metres, spacing shall be increased to

    7.5 metres from heaters with liquid in their tubes. Reduced spacing is

    permitted because there is no flammable material release in the event of

    damage.

    Ref. RU1 because of severity of heater fire, spacing to pipe racks is greater

    than basic.

    N.B. This does not apply to heaters own pipe rack

    6.1.11 Ref. RK1 Cooling Towers

    (Basic spacing 15 and 30 metres)

    Basic spacing of 15 metres applies to equipment lower than the cooling tower;

    basic spacing of 30 metres to equipment higher than the cooling tower.

    The cooling tower becomes a source of hazard in the event of tube failure in a

    water cooler. Basic spacing provides for dispersion of hazardous vapours,

    minimises corrosive effects of spray impingement and visibility problems from

    exhaust plume.

    The cooling towers shall be located on the leeward side of a process unit with

    reference to the prevailing wind.

    Ref. RU1 the factors above are not consideration in the case of a pipe rack.Pipe rack basic spacing will apply.

  • 8/3/2019 Piping Group & Equipment Space

    17/41

  • 8/3/2019 Piping Group & Equipment Space

    18/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 18 OF 41

    REV: D2

    Ref. RU1 is not a hazard producing item. The basic spacing of 4.5 metres

    provides protection in the event of compressor fire.

    6.1.15Ref. R01 Compressor Drivers(Other than steam or motor)

    (Basic spacing 10.5 metres)

    Basic spacing is not applicable between Compressor and driver. Gas turbine,

    gas engine or internal combustion engine drivers are sources of ignition. Basic

    spacing of 10.5 metres affords safe spacing from a source of ignition.

    For items RB1, RC1, RG1, RL1, which are operating above AIT, the driver is not

    considered to be the primary source of ignition. The basic spacing for these

    items therefore applies.

    Ref. RJ1 spacing of 7.5 metres protects driver in event of heater fire.

    Ref. RF1 spacing greater than basic provides additional protection to critical

    item.

    Ref. RU1 the pipe rack is not a hazard rack basic spacing applies.

    6.1.16Ref. RP1 Equipment Handling Non Flammables

    (Spacing provided for operational and maintenance access)

    Ref. RB1, RC1, RG1, RJ1, RL1 spacing of 4.5 metres provides protection to

    equipment in the event of fire at likely sources of ignition.

    6.1.17Ref. RQ1 Central Control House

    (Basic spacing 30 metres)

    Basic spacing of 30 metres affords protection to personnel and critical control

    equipment from plant fire or explosion hazard. Consideration shall be given in

    special circumstances to blast-resistant design of building.

    Ref. RU1 on site pipe racks shall not be nearer than 30 metres to the Control

    House. Provided lines are fully welded with no valves or flanges, a pipe rack

    may be brought to 7.5 metres from one side only of a central control house.

    6.1.18Ref. RR1 Unit Control House

    (Basic spacing 15 metres)

    The location of a unit control house is obviously less critical than a centralcontrol house. It should be located at the battery limit adjacent to a roadway.

    Basic spacing minimises risk to personnel and equipment in the event of a unit

    fire.

  • 8/3/2019 Piping Group & Equipment Space

    19/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 19 OF 41

    REV: D2

    Ref. RU1 pipe rack basic spacing applies provided lines are fully welded

    without valves or flanges.

    6.1.19Ref. RS1 Electrical Sub-station

    (Basic spacing 15 metres)

    Electrical sub-stations are located close to the battery limit and near to a

    roadway. The basic spacing is fixed by Area Classification considerations and

    provides protection to the electrical equipment in the event of unit fire.

    Ref. RU1 pipe racks do not present a major hazard. Basic rack spacing

    applies.

    6.1.20Ref. RT1 Main Equipment Structures

    (Basic spacing not applicable)

    Sufficient spacing shall be allowed from ignition sources of high-risk RC1 items

    to prevent damage to structure in event of fire or explosion. Items RB1, RC1,

    RE1, RG1, RJ1, RL1, RN1 are in this category. In most other cases the

    equipment in the structure will govern its location with respect to other

    equipment.

    6.1.21 Ref. RU1 On-site Pipe Racks

    (Basic spacing 4.5 metres)

    Pipe rack basic spacing gives protection to the pipe rack in the event of

    equipment fires within a process unit. Items Ref. RB1, RC1, RE1, RG1, RK1,

    RN1 and R01 are located on this basis.

    Item Ref. RJ1 fired heater is a possible source of a major fire. Spacing

    greater than basic is required in this case.

    N.B. This limitation does not apply to the pipe rack serving the heater area.

    The pipe rack in itself is not considered highly hazardous. In general equipment

    which is not hazardous may be located on access and operability considerations

    relative to the pipe rack. Items Ref. RA1, RD1, RH1, RI1 (grade mounted) are

    in this category.

    In special cases where the hazard from the pipe rack shall be minimised, fittings

    and flanges which could be sources of leakage shall be eliminated from the pipe

    rack in the vicinity, e.g. from pipe racks under air fin exchangers and from pipe

    racks in the vicinity of control houses, i.e. items RI1, RQ1 and RR1.

    Pumps are also considered as a special case as, for layout purposes, access and

    operability, it is usual to have pumps in close proximity to the pipe rack, e.g.items Ref. RL1 and RM1 spacing is horizontal distance from pump stuffing

    box to edge of pipe rack.

  • 8/3/2019 Piping Group & Equipment Space

    20/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 20 OF 41

    REV: D2

    6.1.22 Ref. RV1 Emergency Valves for Shut-off, Isolation, Snuffing, etc.

    (Basic spacing 7.5 metres)

    The basic spacing is the distance between the emergency valve and the

    equipment it controls. It can be located adjacent to other equipment.

    Ref. RE1 and RJ1 are exceptionally hazardous items. The basic spacing for

    these items there applies.

    Where it is necessary for reasons of plant layout to locate emergency shut-off

    valve manifolds closer to a heater than 15 metres, a fire wall shall be provided

    between the manifold and the heater at a minimum distance of 7.5 metres from

    the heater.

    6.1.23 Roads of width 6 metres or more

    Maintain a minimum of 10m between roads and any hydrocarbon containing

    equipment.

  • 8/3/2019 Piping Group & Equipment Space

    21/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 21 OF 41

    REV: D2

    Fig. 5 Off-Site Spacing Chart

    30

    45

    15

    45 30 60 45 45 45 45 45 4.5

    45 45 45 45 45 45 45 45 4.5

    7.5 15 15 7.5 7.5 7.5 45 N.A. 4.5

    45 45 30 60 15

    45 45 30 60 30

    45 N.A. 15 N.A. N.A.

    30 N.A.

    X

    30 7.5 30 60 7.5 7.5

    30 45 15 15 45 45

    45 X 30 60 X X

    7.5 60 45 7.5

    30 45 15 4.5

    X 45 45 4.5

    45 60 30 60 45 45 45 45 45 4.5

    6 15 4.5 X 7.5 4.5

    45 60 30 60 45 45

    45 45 45 60 45 45

    4.5 45 15 N.A.

    45 45 N.A.

    45 N.A.

    60 N.A. 45

    15 45 X

    45 N.A.

    N.A.

    15

    30 X 15 60 X X

    30 X 15 60 X N.A.

    X X 45 60 X

    X

    60 60 60 N.A.

    30 45 X

    30 X

    X

    FACILITIES FOR HEAT SENSITIVE

    MATERIALS EG TEL. & TML.

    MAIN EFFLUENT TREATMENT

    PLANT RAIL FACILITIES

    RAILWAY MAIN LINES

    MAJOR PUMP AREAS

    BOUNDARY FENCE

    PROCESS AREAS

    MAJOR OFFSITE PIPE TRACKS

    LOADING RACKS FOR LOW FLASH

    PRODUCTS

    FIRE TRAINING AREA

    MAIN FIRE WATER PUMPS

    FIRE STATION

    MAIN ELECTRICAL SUB-STATIONS

    JETTIES (LOADING ARM MANIFOLD)

    COOLING TOWERS

    BUILDINGS, MAIN OFFICES, WORK-

    SHOPS, LABORATORIES, ETC

    30

    45

    15

    60

    15

    45

    45

    4.5

    45

    45

    45

    45

    45

    60

    15/30

    45

    30

    RR2

    RQ2

    RP2

    RO2

    RN2

    RM2

    RL2

    RK2

    RJ2

    RH2

    RG2

    RF2

    RE2

    RD2

    RC2

    RB2

    RA2

    This chart to be used with Off-site spacing guide.

    Note: All distances in metres

    N.A. Not applicable

    X Provide spacing based on access for operation and maintenance.

    Basic spacing is the recommended distance required between a given facility and

    other general processing equipment.

    See notes in section 8.1: Off-site spacing guide.

    FACILITY

    REF.

    BASIC SPACING

    BOILER HOUSES AND POWER

    STATIONS

  • 8/3/2019 Piping Group & Equipment Space

    22/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 22 OF 41

    REV: D2

    7.0 OFFSITE SPACING

    Facilities outside the confines of a Process Block, e.g. boiler houses and powerstations, administration offices, workshops, effluent treatment, flare stacks,

    jetty and rail loading, blending facilities etc., are referred to as off-site

    facilities.

    It is customary to combine the utility type facilities, e.g. steam generation,

    water treatment, plant air etc., within a utility area or block.

    Effluent treatment, flare and similar high hazard off-site facilities are generally

    located remote from process facilities, utility areas and administration areas.

    Spacing of flare stacks requires special consideration based on relief loads andthermal radiation levels. Reference shall be made to the Process Engineer.

    The recommended spacing off-site equipment is indicated in Off-site Spacing

    Chart, Fig. 5.

    The information on this chart is supplemented by explanatory notes contained

    in Section 7.1 Off-site Spacing Guide.

    It is essential that reference is made to Section 7.1 when using Off-site

    Spacing Chart, Fig. 5.

    Against each item a basic spacing dimension is quoted. This basic spacing is

    the recommended distance in metres between the item and other

    equipment/facilities. The recommended spacing between different items is

    given at the intersection of the horizontal line from one item and the vertical line

    from another.

    In general, this shall be the greater of the basic spacing dimensions for the two

    items, otherwise explanatory notes can be found in Section 7.1.

    The spacing between similar equipment/facilities is given in the first box

    adjacent to the item.

    7.1 Off-site Spacing Guide

    (Use with off-site spacing chart Fig. 5)

    7.1.1 Ref. RA2 Boiler Houses and Power Stations

    (Basic spacing 30 metres)

    The basic spacing protects critical equipment from fire or explosion in process

    equipment.

    Ref. RB2 buildings are not considered hazardous to boilers and generating

    plant and vice versa. Therefore, spacing less than basic for buildings is

    acceptable.

  • 8/3/2019 Piping Group & Equipment Space

    23/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 23 OF 41

    REV: D2

    Ref. RK2 spacing protects pipe track from possible fire in boiler house.

    Ref. RO2 railway main lines are not at risk from facilities and do not present arisk to facilities. Boiler basic spacing applies.

    Ref. RP2 rail sidings present a minimum risk to facilities. Siding basic spacing

    applies.

    Note that steam generators forming an integral part of a process unit are

    considered as fired heaters. In such cases, on-site basic spacing will apply.

    7.1.2 Ref. RB2 Buildings, Main Office Block, Workshops, Laboratories etc.

    (Basic spacing 45 metres)

    The basic spacing protects personnel from fires and explosions in process

    equipment.

    For high hazard process equipment, spacing in excess of basic is applied.

    Items Ref. RD2, RJ2, RL2 fall into this category.

    Items Ref. RA2, RK2, RO2, RP2 are not considered high-risk items. Spacing

    less than basic building space is applied.

    7.1.3 Ref. RC2 Cooling Towers

    (Basic spacing 15 metres and 30 metres)

    Two basic spacing are given for Cooling Towers.

    The lower basic spacing is for equipment that is lower than the cooling tower.

    The higher basic spacing is for equipment that is taller than the cooling tower

    and where it is necessary to minimise the corrosion, visibility and ice formation

    problems, resulting from the impingement of the cooling tower exhaust plume.

    A cooling tower can become a source of hazard due to release at atmosphere of

    flammable vapours, caused by tube failure in water cooled exchangers. The

    higher basic spacing distance is considered adequate for dispersal of these

    vapours.

    Spacing greater than cooling tower basic is applied from highly hazardous

    sources, e.g. items Ref. RD2 and RH2.

    Items Ref. RF2, RG2 and RO2 do not present a hazard to these cooling towers.

    Cooling tower basic spacing is therefore applied.

    Items Ref. RJ2 and RL2 are possible sources of fire. Higher cooling tower basicspacing is applied to these items.

    Items Ref. RM2 and RO2 do not present a hazard to the cooling tower. Cooling

    tower higher basic spacing is applied for environmental considerations.

  • 8/3/2019 Piping Group & Equipment Space

    24/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 24 OF 41

    REV: D2

    Item Ref. RK2 the cooling tower is not considered to be at risk from the pipe

    track. Pipe track basic spacing is applied.

    7.1.4 Ref. RD2 Jetties

    (Loading arm manifold basic spacing 60 metres)

    The basic spacing protects facilities from fires at loading manifolds or on

    tankers and vice versa.

    Items Ref. RN2, RP2, RQ2 are not considered as sources of hazard. Basic

    spacing for these items will apply.

    7.1.5 Ref. RE2 Main Electrical Sub-stations

    (Basic spacing 45 metres)

    The basic spacing protects electrical equipment from explosion or fire in

    process areas. By using blast resistant construction, this basic spacing may be

    reduced.

    Items Refs. RK2, RO2, RP2 are not considered as major sources of hazard.

    Spacing less than basic is allowed.

    7.1.6 Ref. RF2 Fire Station

    (Basic spacing 45 metres)

    The basic spacing provides protection to the fire station and equipment in the

    event of fire in the process areas.

    Items Ref. RA2, RC2, RK2, RO2 and RP2 are not considered as major sources

    of hazard. Spacing less than basic is allowed.

    Items Ref. RB2, RE2, RG2 and RM2 are not hazardous to the fire station.

    Location is determined by access and maintenance considerations.

    7.1.7 Ref. RG2 Main Fire Pumps

    (Basic spacing 45 metres)

    The basic spacing provides protection to prevent loss of pumps from fire

    exposure.

    Items Ref. RA2, RC2, RK2, RN2, RO2 and RP2 are not considered sources of

    major hazard. Spacing less than basic is allowed.

    Items Ref. RB2, RE2, RF2 and RM2 are not hazardous to fire pumps. Location isdetermined by access and maintenance considerations.

  • 8/3/2019 Piping Group & Equipment Space

    25/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 25 OF 41

    REV: D2

    7.1.8 Ref. RH2 Fire Training Area

    (Basic spacing 45 metres)

    The basic spacing protects vulnerable process equipment from a source of

    ignition. Spacing also allows smoke dispersal.

    7.1.9 Ref. RJ2 Loading Racks

    (Basic spacing 45 metres)

    The basic spacing is considered adequate for the dispersal of spillage or vapour

    releases. During unloading it also protects the equipment in the event of fires

    at process areas and vice versa.

    In locating main loading racks, consideration shall be given to access from

    outside and to minimising the flow of traffic through process areas.

    Spacing shall be sufficient to allow the safe manoeuvring of road tankers and

    for rail sidings where applicable.

    Items Ref. RC2, RK2 and RN2 are not considered hazardous with respect to the

    loading area. Spacing less than loading rack basic is acceptable in these

    instances.

    For item Ref. RB2 spacing greater than basic is applied to reduce hazard to

    personnel.

    7.1.10Ref. RK2 Major Off-site Pipe Tracks

    (Basic spacing 4.5 metres)

    The basic spacing of 4.5 metres minimises hazard to off-site piping in the event

    of fires at major plant areas.

    For items Ref. RC2, RF2, RL2, RM2, RN2, RP2, RQ2 and RR2, this criterion

    applies.

    For items Ref. RA2, RB2, RE2, RH2, RJ2 and RO2 greater spacing is applied for

    commodity criticality or personnel hazard requirement.

    7.1.11Ref. RL2 Process Areas

    (Basic spacing 45 metres)

    The basic spacing minimises damage to other areas or equipment in the event

    of fire or explosion in the process area and vice versa.

    For item Ref. RB2 spacing greater than basic is applied to reduce hazard topersonnel.

    Items Ref. RC2, RK2 and RN2 are not considered at high hazard from process

    areas. The basic spacing for these items is therefore applied.

  • 8/3/2019 Piping Group & Equipment Space

    26/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 26 OF 41

    REV: D2

    A process to process area spacing of 15 metres is considered sufficient to

    permit independent shutdown at turnaround.

    In the case of light end units this shall be increased to 25 metres. Where

    several process units are integrated, the internal spacing shall be based on

    maintenance, operational and fire fighting access.

    7.1.12Ref. RM2 Boundary Fence

    (Basic spacing 45 metres)

    The basic spacing provides protection to personnel and property outside the

    boundary fence in the event of explosion or fire. It also protects the facilities

    inside the fence from external hazard.

    Item refs. RC2 and RK2 are reduced hazard items. Spacing less than the basic

    boundary spacing is acceptable in these instances.

    Item refs. RB2, RE2, RF2 and RG2 are not hazardous. Spacing from boundary

    fence is based on access or environmental consideration.

    7.1.13Ref. RN2 Major Pump Areas

    (Basic spacing 15 metres)

    The basic spacing affords protection to pump areas in the event of fire or

    explosion in process facilities and allows access for fire fighting.

    Pump areas, because of their low inventory, do not present a major hazard to

    other equipment.

    Spacing less than basic item spacing is therefore permitted from these items,

    e.g. items Ref. RD2, RG2, RJ2, RL2, RO2 and RQ2.

    7.1.14Ref. RO2 Railway Main Lines

    (Basic spacing 60 metres)

    The basic spacing protects personnel and railway property from fire or

    explosion inside plant.

    Items Ref. RA2, RC2, RJ2 and RN2 present a reduced hazard to railway

    property. Spacing less than basic is permitted in these cases.

    7.1.15Ref. RP2 Rail Sidings

    (Basic spacing 15 metres)

    A rail siding can be considered as a source of ignition from a locomotive engine.The basic spacing protects flammable equipment or sources of vapour emission

    from this hazard.

    Items Ref. RC2, RD2, RN2 and RR2 fall in this category.

  • 8/3/2019 Piping Group & Equipment Space

    27/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 27 OF 41

    REV: D2

    Non-hazardous items may be located at less than the basic spacing. Items Ref.

    RB2, RE2, RF2, RG2 and RK2 fall in this category.

    For item Ref. RQ2, additional spacing is required to permit dispersal of vapours.

    7.1.16Ref. RQ2 Main Effluent Treatment

    (Basic spacing 45 metres)

    A basic spacing of 45 metres from process areas or other sources of ignition

    allows for dispersal of vapours, which are likely to be emitted at a separator.

    Items Ref. RA2 to RJ2, RL2, RM2 and RR2 fall in this category.

    Lower risk facilities, not representing a source of ignition, may be located not

    less than 30 metres from a separator. Items Ref. RN2 and RP2 fall in this

    category.

    Item Ref. RK2, off-site pipe tracks, is a minimum risk item. Its basic spacing

    applies.

    7.1.17 Ref. RR2 Facilities for Heat Sensitive Materials

    (Basic spacing 30 metres)

    Heat sensitive materials are liable to decomposition explosions on prolonged

    exposure to heat. The basic spacing of 30 metres protects the facilities from

    such exposure.

    Items Ref. RK2 and RP2 are not sources of fire. Spacing less than basic 30

    metres will be acceptable in these instances.

    8.0 TANKAGE

    This section gives basic guidance for the spacing and bund capacities ofstorage tanks, storage spheres and cylinders. In cases where a conflict may

    occur between this document and the Thai Fuel Storage act B.E. 2474, then

    that Act shall always take precedence.

    For specific spacing direction, particularly for LPG and LNG duties, refer to the

    relevant listed standard(s).

    Other types of bulk storage, e.g. underground caverns, are not covered by this

    standard.

    8.1 Flammable Liquids

    Petroleum products by their nature are potentially hazardous, the degree of

    hazard being directly related to their volatility and flash point.

  • 8/3/2019 Piping Group & Equipment Space

    28/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 28 OF 41

    REV: D2

    These are classified:

    Class 0 Liquified petroleum gasClass I Liquids having flash points below 21C

    Class II (1) Liquids with flash points from 21C to

    55C stored below flash point

    Class II (2) Liquids with flash points from 21C to

    55C stored at or above flash point

    Class III (1) Liquids with flash points from 56C to

    100C stored below flash point

    Class III (2) Liquids with flash points from 56C to

    100C stored at or above flash point

    Unclassified Liquids which have flash points above

    100C

    8.2 Types of Tankage

    8.2.1 The type of tank used to store a particular product is generally specified by

    Clients requirements. In the absence of such requirements, type selection

    should be referred to the Process Design Co-ordinator.

    8.2.2 Fixed or Cone Roof Tanks (CR)

    For the storage of Class III (1) and Class III (2) and Unclassified products. Other

    classes of product may be stored in this type of tank, provided that the vapour

    pressure at storage temperature is less than atmospheric pressure (e.g. refrig.

    atmosphere storage of LPG/LNG).

    8.2.3 Floating Roof Tanks (FR)

    For the storage of Class II (1) and Class II (2) flammable products in the middle

    flash point range.

    8.2.4 Spheres and Cylinders (SP and CYL)

    For the storage of Class 0 and Class I highly flammable products, which have

    flash points below 21C, e.g. pressure storage of LPG products.

    8.2.5 Table 1

    This table gives typical examples:

    Product Type of Tank or Vessel Class Comments

    C3 CYL 0 Pressure Storage

    C4 SP 0 Pressure Storage

    C3 CR 0 Refrig. Atmos. Storage

    C4 CR 0 Refrig. Atmos. Storage

    LPG/LNG CR 0 Refrig. Atmos. Storage

    Benzene FR I

    Xylene FR I

  • 8/3/2019 Piping Group & Equipment Space

    29/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 29 OF 41

    REV: D2

    Product Type of Tank or Vessel Class Comments

    Reformate FR I

    Gasoline FR INaphtha FR I

    Kerosene FR II (1)

    Jet Fuel FR II (1)

    Crude Oil FR II (2) Boil/roll Over

    Tendencies

    Gas Oil/Diesel FR III (1)

    LFO CR III (2)

    MFO CR III (2)

    HFO CR III (2)

    Heavy Oil/Residue CR III (2)

    Asphalt/Bitumen CR UnclassifiedNote: Certain produce classifications may change if operational temperatures

    are increased.

    8. 3 Definitions

    8.3.1 Bund or Firewall

    A wall of pre- determined height constructed of concrete, earth, or any other

    suitable material and designed to confine spillage of tank contents.

    8.3.2 Bunded Area

    An area bounded by bund walls to confine spillage.

    8.3.3 Exposed Bunded Area

    The nett effective area bounded by a bund wall after the deduction of tank

    areas contained within the bunded area.

    8.3.4 Secondary or Intermediate Bunds

    As for bund above, but usually no higher than 600mm in order to contain local

    spillage within a sub-area of the main bunded area.

    8.3.5 Bund Capacity

    The volume in cubic metres that can be contained within the exposed bunded

    area.

    8.3.6 Tank Group

    A number of tanks contained within a common bund.

    8.3.7 Small Tanks

    A tank of 10 metres diameter or less and capacity of 8000 cubic metres of

    water or less is deemed to be a small tank.

  • 8/3/2019 Piping Group & Equipment Space

    30/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 30 OF 41

    REV: D2

    8.4 Grouping and Spacing of Tanks

    8.4.1 It is desirable to group tanks for the storage of the same products in one groupwithin a bund area, subject to the prescribed limitations of the bunded capacity.

    8.4.2 It is desirable that LPG or other liquefied flammable gases should be stored

    remote from other products.

    8.4.3 Intermediate and component tankage should be located in areas local to their

    respective units where possible so that lines can be kept to a minimum length.

    8.4.4 Account should be taken of the possibility of storing more than one class of

    material in certain tanks or of changing the tank service at some future date.

    Where future changes of service of the storage tanks are anticipated, the layout

    and spacing should be for the most stringent case.

    8.4.5 Wherever possible storage tanks should not be located on high ground

    overlooking the facilities. This prevents spillage of flammable liquid flowing

    downhill and endangering the operating plant.

    8.4.6 For fire fighting reasons there should be no more than two rows of tanks

    between adjacent access roads.

    8.4.7 Intermediate bunds may be provided to divide the tankage into groups of a

    convenient size so as to contain small spillage and act as firebreaks.

    8.4.8 For Class III (1) and Unclassified petroleum stocks spacing of tanks is governed

    only by constructional and operational convenience.

    Note that the spacing of Class III (1) tankage from Class I, II or III (2) tankage is

    governed by the latter.

    8.5 Sizing of Bunds

    8.5.1 Tank bund volumes shall comply with the requirements summarised below:

    110% of the capacity of the largest storage vessel located within the bund

    after deducting the volume up to top of bund height of all other tanks in the

    same bunded area. (HSE ref.)

    8.5.2 The effective height of the bund used in calculating the capacity of the

    enclosure shall be the constructed height less an amount sufficient to allow for

    future consolidation, settlement and possible erosion of the fill. This freeboard

    allowance shall be:

    150mm for 0.6 to 1.2 m effective height

    225 mm for 1.5 m effective height

    300 mm for 1.8 m effective height, plus 50 mm for each 0.3 m of height over

    1.8 m.

  • 8/3/2019 Piping Group & Equipment Space

    31/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 31 OF 41

    REV: D2

    8.5.3 Bund Walls shall generally be constructed using earth embankments having a

    crest of 600-mm minimum width.

    8.5.4 For bunds over 1.2 m in height, stairs shall be provided for personnel.

    8.5.5 In the event that there is inadequate space for construction of earthen bund

    walls due to restricted site dimensions, the use of reinforced concrete retaining

    walls will be permitted.

  • 8/3/2019 Piping Group & Equipment Space

    32/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 32 OF 41

    REV: D2

    Example 1 Cone Roof Tanks (CR)

    Tanks greater than 10 metres dia. Class II and III (2) Storage

    Maximum Total Tankage Capacity of Group:

    60,000m3 should not be exceeded (HSE ref)

    Minimum Bund Capacity:

    See Paragraph 8.5

    Spacing

    A to suit construction and operating conditions but not less than half tank height.

    B The least of (i) half the diameter of largest tank (ii) diameter of the smaller tank. -

    Shall be minimum of10 metres and need not exceed 15m

    C & D See Table 2

    B

    D C

    INSIDE TOP OF

    BUND

    EQUIPMENT/FACILITY REFERENCE LINE. SEE TABLE 2

    AA

    A A

    AA

    B

    B

    B C RC R

    C R C R

  • 8/3/2019 Piping Group & Equipment Space

    33/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 33 OF 41

    REV: D2

    Example 2 Floating Roof Tanks (FR) Class I, II and III (2) Storage

    Maximum Total Tankage Capacity of Group

    120,000m3 should not be exceeded. (HSE ref.)

    Minimum Bund Capacity

    See Paragraph 8.5. For tanks larger than 60,000m3 not more than 2 tanks in same

    compound.

    Spacing

    A to suit construction and operating conditions but not less than half of tank height.

    B 10 metres for tanks up to and inc. 45m dia. For tanks above 45m dia., half the

    diameter of largest tank or the diameter of smaller tank - but not less than15 metres

    (HSE ref.)

    C & D See Table 2

    EQUIPMENT/FACILITY REFERENCE LINE. SEE TABLE 2

    B

    D C

    INSIDE TOP OF

    BUNDAA

    A A

    AA

    B

    B

    B F RF R

    F R F R

  • 8/3/2019 Piping Group & Equipment Space

    34/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 34 OF 41

    REV: D2

    Example 3 Cone Roof (CR) and Floating Roof (FR) in a Common Bund Class I and II

    Maximum Total Tankage Capacity of Group

    No of FR Tanks x 60,000 +60, 000m3

    No of Tanks in group

    Minimum Bund Capacity:

    See Paragraph 8.5.

    Spacing

    A Distance equal to not less than height of tank.

    B The least of (i) half the diameter of largest tank (ii) diameter of the smaller tank.

    Shall be minimum of10 metres and need not exceed 15m

    C & D See Table 2

    EQUIPMENT/FACILITY REFERENCE LINE. SEE TABLE 2

    B

    D C

    INSIDE TOP OF

    BUNDAA

    A A

    AA

    B

    B

    B F RF R

    C R C R

  • 8/3/2019 Piping Group & Equipment Space

    35/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 35 OF 41

    REV: D2

    Example 4 Cone and Floating Roof Tanks not exceeding 10 metres diameter

    Class I and II.

    Fixed or floating roof tanks not exceeding 10 metres diameter may be grouped

    together up to a total of 8000m3 and treated as one tank if grouped with other tanks.

    Total overall tank capacity including other tanks in common bund not to exceed

    60,000m3 if other tanks are fixed roof type, or 120,000m3 if other tanks are floating

    roof type.

    (HSE ref.)

    Spacing

    A to suit construction or operating requirements

    B Half the diameter of larger tank but not less than 10 metres and need not be more

    than 15 metres.

    GROUP OF TANKS

    NOT EXEEDING

    8000m3 TREATED

    AS ONE TANK (ref.HSE doc.)

    INSIDE TOP OF

    BUND

    OTHER TANKAGE IN

    COMMON BUND

    A

    A A

    A

    B

    B

  • 8/3/2019 Piping Group & Equipment Space

    36/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 36 OF 41

    REV: D2

    Example 5 Refrigerated Storage (LPG Products at low temperatures) Fixed Roof

    Tanks (CR) not more than 3 tanks in one compound.

    No refrigerated LPG storage tank shall be located within a bund enclosing any other

    tank. Each refrigerated storage tank shall have an individual bund unless spills can be

    directed safely away from adjacent tanks and equipment by means of drainage and

    diversion walls (as required) to an impounding basin located within the site boundary.

    Double containment storage tanks do not require a bund except for local containment

    of leakage from pipework, valves etc.

    Total recommended maximum tank capacity for bund not greater than 60,000m3 .

    Minimum Bund Capacity:

    See Paragraph 8.5.

    Spacing:

    A Minimum 30 metres

    B (Dia. of large tank + dia. of small tank) divided by two.

    C & D See Table 2

    A

    BA

    A

    A

    B B

    C R C R

    D C

    INSIDE TOP OF

    BUND

    EQUIPMENT/FACILITY REFERENCE LINE. SEE TABLE2

    C R

    A

  • 8/3/2019 Piping Group & Equipment Space

    37/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 37 OF 41

    REV: D2

    Example 6 Group of LPG pressure storage vessels (Class 0 products) Bullets and

    Spheres

    Notes:

    1. Horizontal LPG tanks with capacities of 45 cu.m or greater shall not be formed into

    groups of more than six tanks each. Horizontal vessels used to store LPG shall be

    oriented so that their longitudinal axes do not point towards other containers,

    process equipment, control rooms loading or unloading facilities, or flammable or

    combustible liquid storage facilities located within the vacinity of the horizontal

    vessel.

    2. Grading of the area under and surrounding the vessels shall direct any leaks or

    spills to a remote impoundment area. The remote impoundment area shall be

    located at least 15 metres from the vessels draining to it and from any hydrocarbon

    piping or other equipment.

    Maximum number of vessels in any one group 6. Recommended maximum capacity

    of all vessels within one group = 3 times capacity of largest vessel with in the

    group.

    Spacing:

    A = sum of diameters of 2 adjacent tanks, but not less than 2 metres, for bullets.

    (Reference IP LPG Vol1. Model Code of Safe Practice, Part 9)

    D See Table 2

    A A

    d 1

    D

    d 2d 1

    A

    BL

    SP

    EQUIPMENT/ FACILITY REFERENCE LINES. SEE TABLE 2

    D

    BL BL

    SP

    d 1

    3 m (API 2510) EDGE OF CATCHMENT

    AREA

  • 8/3/2019 Piping Group & Equipment Space

    38/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 38 OF 41

    REV: D2

    Example 7 Group of fixed roof refrigerated atmospheric storage tanks containing

    LNG (Class O product) - Double Containment Tanks

    Single Containment Tanks shall have a bunded [impounding] area. Minimum distance

    from tank to bund not to be less than: height of liquid level +LP gas pressure bund

    height (See NFPA 59A).

    Spacing

    A = Minimum distance to give a max. thermal radiation flux = 32 kW/m2 in the

    event of fire (approximately equivalent to 30m).

    D See Table 2

    A

    D

    d 1 d 2

    EQUIPMENT/FACILITY REFERENCE LINE. SEE TABLE2

  • 8/3/2019 Piping Group & Equipment Space

    39/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 39 OF 41

    REV: D2

    Table 2 Minimum Tankage Spacing (Dimensions in Metres) (see tankage spacing

    examples 1,2,3,4,5,6 &7)

    Dimension C is a dimension from facility/equipment reference line to inside top of

    tank bund.

    Dimension D is a dimension from facility/equipment reference line to tank shell.

    Examples 5,6 &7: Refer to the listed Standards for more detailed spacing requirements

    regarding spillage catchment (impounding) areas and drainage. Spacing will need to be

    considered for individual cases.

    EXAMPLES

    1,2,3,4

    EXAMPLE

    5 (note d)

    EXAMPLE

    6 (note e)

    EXAMPLE

    7 (note f)

    FACILITY/EQUIPMENT C D C D C D C D

    BOUNDARY FENCE 15 30 30 90 NA 90 NA 100

    EQUIPMENT LINE PROCESS

    AREA

    15 30 30 50 NA 50 NA 50

    BUILDINGS 15 30 30 60 NA 60 NA 60

    FIXED SOURCE OF IGNITION 15 30 30 60 NA 60 NA 60

    HAZARDOUS FACILITIES

    (e.g. Jetty, Loading)

    15 30 30 90 NA 90 NA 100

    PUMP AREAS a 15 30 50 NA 50 NA 50

    TANK SHELL (adjacent group) 15 30 30 50 h NA 50 NA 50 hREFRIG. FIXED ROOF TANKS 15 50 d 30 NA 30 NA 30

    PRESSURE STORAGE LPG b 15 NA c 30 NA 25 NA 30

    EDGE OF SITE ROADS 15 30 30 60 NA 60 NA 60

    CRITICAL AREAS 15 30 30 90 NA 90 NA 100

    Notes:

    a To suit maintenance and operation requirements

    b Assumed fitted with water deluge system.

    c See notes on example 6

    d, e & f: The equipment spacing listed for pressure or refrigerated storage of LPG

    and the refrigerated storage of LNG, within this standard, is for initial layout purposes

    (see also notes for examples 5, 6 &7). The detail design spacing will be a function of

    the allowable thermal radiation flux values (permitted for fire protection) and a

    hazardous assessment review. A summary of values and typical distances (in

    brackets), based on a 10m height above grade from liquid product containment, is as

    follows:

  • 8/3/2019 Piping Group & Equipment Space

    40/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 40 OF 41

    REV: D2

    d Typical maximum thermal radiation flux values* for refrigerated storage of LPG are:

    The outer surfaces of adjacent refrigerated storage vessels or surfaces thermallyprotected. =32 kW/m2 (30m)

    Outer surface of adjacent storage thermally protected tanks containing

    flammable products =32 kW/m2 (30m)

    Unprotected metal surfaces of adjacent storage tanks, pressure vessels and

    process facilities = 8 kW/m2

    (50m)

    Protected work area, filling/discharge points = 8 kW/m2 (50m)

    Urban areas, work area = 5 kW/m2 (60m)

    Critical areas = 1.5 kW/m2 (90 m)

    (* Reference IP LPG Vol1. Model Code of Safe Practice, Part 9)

    e. Typical maximum thermal radiation flux values for pressure stored LPG are:

    The outer surfaces of adjacent pressure storage vessels or surfaces thermally

    protected. =44 kW/m2 (25m)

    Outer surface of adjacent storage thermally protected tanks containing flammable

    products =32 kW/m2 (30m)

    Unprotected metal surfaces of adjacent storage tanks, pressure vessels and

    process facilities = 8 kW/m2

    (50m)

    Protected work area, filling/discharge points = 8 kW/m

    2

    (50m) Urban areas = 5 kW/m2 (60m)

    Critical areas = 1.5 kW/m2 (90m)

    ( Reference IP LPG Vol1. Model Code of Safe Practice, Part 9)

    f Typical maximum thermal radiation flux values for LNG storage are:

    Concrete outer surface of adjacent storage tanks or surfaces behind thermal

    protection =32 kW/m2 (30m)

    Unprotected metal surfaces of adjacent storage tanks, pressure vessels and

    process facilities =15 kW/m2

    (45m)

    Control rooms, workshops, laboratories and warehouses = 8 kW/m2 (50m)

    Administration building, work area = 5 kW/m2 (60m)

    Urban areas = 3 kW/m2 (66m)

    Critical areas = 1.5 kW/m2 (100m)

    ( Reference EN 1473:1997 for LNG storage- distances based upon IP LPG Vol1.

    Model Code of Safe Practice, Part 9)

    h Where multiple groups are required, each group shall be separated from

    unprotected adjacent groups by a minimum horizontal shell-to-shell distance of 50

    metres for heights up to 10m (increase to 60m for unprotecteditems above 10m).

  • 8/3/2019 Piping Group & Equipment Space

    41/41

    PIPING GROUP

    EQUIPMENT SPACING

    PTT PUBLIC COMPANY LIMITED

    ENGINEERING SPECIFICATION

    SPC-0804.02-50.03

    PAGE: 41 OF 41

    REV: D2

    General:

    Where space is limited in tank layout areas, the use of firewalls, thermal protectionscreens, etc. may be considered.

    Special spacing is required between the listed items and oxygen and/or gaseous

    hydrogen storage. Refer to the relevant standard or guide.