Pipelines LOC

Embed Size (px)

Citation preview

  • 8/10/2019 Pipelines LOC

    1/28

  • 8/10/2019 Pipelines LOC

    2/28

    Location of Hazard

    HS1 - Rigid Riser

    HS2 - Flexible and comliant Risers

    HS3 - Pipeline - Tie-in spools, Seabed pipeline, tees

    HS4 - Riser Emergency shutdown valves (ESDV)

    HS5 - Subsea Isolation Valves (SSIVs)

    HS6 - Pig Trap

    Subsea systems: manifolds, well flowlines, process equipment

    Initiators

    G1 - External Corrosion, coating damage, cathodic protection failure

    G2 - Internal Corrosion, water, wax, scale

    G3 - Erosion, sand, scale

    G4 - Overpressure

    G5 - High Temperature

    G6 - Low Temperature Joule Thomson effect

    G7 - Fatigue / vibration

    G8 - Fire [Section 2.3.3]

    G9 - Fitting failure

    G10 - Incorrect installation or fabrication

    Operator error [Section 11]

    G11 - Inadequate Training [Section 11]

    G12 - Inadequate competency [Section 11]

    G13 - Violation [Section 11]

  • 8/10/2019 Pipelines LOC

    3/28

  • 8/10/2019 Pipelines LOC

    4/28

    F4 - Equipment layout

    F5 - Company standards / competence

    F6 - Corrosion / erosion allowance

    F7 - Operations and maintenance procedures

    F8 - Safety Integrity Level (SIL) standards

    F9 - Equipment selection

    Riser jet fire effects

    Risk Management Measures

    F14 - Inherent Safety

    fully rated pipelines & risers

    riser and pipeline routing

    Riser ESDV locations

    Concrete ballast + protection coating

    Pipe protection trenching burial rock dump covers

    Fire protection

    Damage Prevention

    F15 - Relief systems

    F16 - High Integrity Pressure Protection Systems (HIPPS)

    F17 - Shutdown systems ESD system ESDVs

    F18 - Alarms / trips

    F19 - Cathodic protection anodes impressed current systems

    F20 - operational procedures - control of erosion / internal corrosion, temperature during

    blowdown, pigging, chemical inhibition

  • 8/10/2019 Pipelines LOC

    5/28

    F21 - Competent personnel

    F22 - Monitoring & Audit systems

    F23 - Isolation and permit to work controls

    F24 - Intelligent pigging

    F25 - Wall thickness monitoring

    F26 - Inhibition performance monitoring

    F27 - Fire protection passive/active

    F28 - Mooring controls

    F30 - Strength & leak testing

    F31 - Non-destructive testing (NDT) inspection

    Performance Standards

    Temperature & Pressure Rating

    Material specification: strength, corrosion resistance, impact resistance

    Cathodic protection (CP) potential

    Remaining fatigue life

    Frequency and type of inspection

    Pressure relief arrangements, set point, capacity

    Reliability of protective systems

    Supports: number, locations, adequacy

    Integrity of pig trap closures and seals

    Fire protection, risers, ESDVs

    Valves: closure mode, seal type, leak rate, fire resistance

  • 8/10/2019 Pipelines LOC

    6/28

    HS0 The Pipeline System

    4. Relevant Legislation, Approved Codes of Practice (ACOPs) and Guidance

    includes:

    Pipelines Safety Regulations 1996

    A Guide to the Pipelines Safety Regulations 1996 (HSE Books, L82, ISBN

    9780717611829)

    Offshore Installations (Safety Case) Regulations 2005

    A guide to the Offshore Installations (Safety Case) Regulations 2005 (HSE Books,

    L30, ISBN 9780717661848)

    Offshore Installations (Prevention of Fire and Explosion, and Emergency Response)

    Regulations 1995

    Prevention of fire and explosion, and emergency response on offshore installations

    (HSE books, L65, ISBN 9780717613861)

    Assessment Principles for Offshore Safety Cases [APOSC], in particular paragraphs

    9, 14, 16, 95, 115

    Provision and Use of Work Equipment Regulations 1998, in particular Regulations 4,

    5 and 12

    The Health and Safety at Work etc. Act 1974 (Application outsideGreat Britain) Order

    2001

    1. Duties

    The pipeline operator has responsibility for the entire length of the pipeline (including risers,

    pig traps etc and risers on other operators installations). Pipeline operators should be

    identified and limits of responsibility should be defined in the safety case. The pipeline

    operator is responsible for starting up the pipeline following a shutdown, and for procedures

    and checks that are made before start up. The installation dutyholder should ensure that

    the pipeline operator carries out these duties and should co-operate with the pipeline

    operator. The safety case should state these responsibilities.

    2. Pipelines Hazard Identification and Risk Assessment

    The description of the pipeline system should address all hazards from and to pipelines and

    their contents.

  • 8/10/2019 Pipelines LOC

    7/28

    Hazard identification should include pipeline systems aspects such as management

    interfaces between installations, inter-platform control, leak detection and pipelines

    emergency procedures.

    All hazards that could result in a loss of pipeline integrity at any location within the hazard

    limit distance should be identified and included in the overall risk assessment for the

    installation. The hazard limit distance is that distance from the installation beyond which a

    pipeline release could not conceivably be a hazard to the installation.

    The safety case should consider hazards to installations close to pipelines and risers or in

    combined operations: jack-ups, flotels, crane vessels, diving support vessels. It should also

    identify the hazards from or to any pipeline attached to subsea wells or manifolds that could

    endanger drilling rigs or diving support vessels.

    The safety case should evaluate the risks and the results should be included in the overall

    risk assessment for the installation. The proposed hazard minimisation and risk reduction

    measures should be consistent with the overall risk assessment.

    3. Pipelines Description

    Within the installation description the duty holder should include all interconnecting facilities

    i.e. pipelines and subsea facilities, including:

    a description or diagram of connections to pipeline systems and of any pipeline withthe potential to cause a major accident;

    dutyholders, owners and operators of connected installations and pipelines and

    interface points;

    fluids, pipeline sizes, directions, and approximate flow rates;

    subsea valves, tees, wyes, remotely operable valves, etc.;

    all potential pressurising sources: subsea wells, other pipelines connected subsea,pumps, compressors

    process flow diagrams of subsea production facilities,

    special subsea operations such as hot water circulation, dual (or multi) purpose

    lines, round-trip pigging, liquid/gas separation, pumping/compression facilities;

    a description of the pipeline over-pressure protection system (see below);

    a description of the leak detection system (see below); and

  • 8/10/2019 Pipelines LOC

    8/28

    pipeline pigging philosophy and practice: scale and wax removal, biociding, inhibitor

    distribution, intelligent pigging, liquids removal, semi-intelligent pigging, tethered riser

    inspection etc

    Specific pipeline data in the safety case should include:

    pipe diameter;

    wall thickness (including thicknesses for different parts of the pipeline where these

    vary), stating any allowance for corrosion;

    the pipeline to platform approach route;

    the riser route including the topsides part of it and any demarcation points;

    the riser ESD valve location(s) and any subsea isolation valves;

    the fluids in the pipeline;

    pipeline inventory at maximum allowable operating pressure between the pipeline

    extremities (i.e. from installation to installation, including any branches connected

    subsea);

    design configurations: rigid pipe, flexible, bundle, piggy back, internal cladding,

    weight coating, with key dimensions etc

    construction methods used: conventional lay, reeled, towed, pipe-in-pipe, riser

    caisson (wet/dry), J-tube etc

    the standard or code used to design the pipeline;

    the current safe operating pressure;

    the safe operating temperature range;

    the grade(s) of steel and materials of construction of the pipeline, riser and topsides

    pipework, sour/non-sour service rating, types of corrosion resistant alloys

    corrosion management arrangements, including monitoring and control of corrosion,internally and externally, reliability of corrosion inhibition, cathodic protection etc

    systems, sand and scale management, inspection arrangements

    any other element of the design or operation of the pipeline which is critical to the

    safety of the installation.

    4. Design of the Pipeline

  • 8/10/2019 Pipelines LOC

    9/28

    The duty holder and pipeline operator should ensure that the pipeline riser has been

    designed and constructed and is operated safely in accordance with recognised standards

    and guidance.

    Where a recognised standard/code of practice has not been employed, the duty holder

    should provide justification on a case-by-case basis that the applied standard or code or

    method is appropriate.

    5. Design for Extreme Weather

    Most North Seainstallations are designed to withstand a wave which occurs on average

    every 100 years or every 50 years. However structural design standards now require

    design for a wave that occurs every 10,000 years. Further information is available via this

    link: http://www.hse.gov.uk/offshore/extremeweather.htm.

    The 10,000 year wave level can rise well above the current elevations of riser ESD valves.Floating installations being restrained by moorings and inertia can be likewise affected. The

    safety case should demonstrate that dutyholders and pipeline operators have assessed the

    ability of risers, ESD valves and other facilities to survive such extreme weather.

    6. Pipeline Damage Prevention

    The safety case should include a description of pipeline damage prevention arrangements,

    including: a list of identified hazards (e.g. dropped freight, caissons, tubulars, equipment,anchors, mooring lines, vessels, submerged flexible risers etc.); pipeline route information

    issued; operational measures (no anchoring areas, vessel size limitations, approach routes,

    etc); and permanent protection measures. The pipeline should be protected from third party

    or construction damage caused by vessel anchors and mooring wires and chains, by pipe

    lay abandon and retrieval wires, and by fishing trawls.

    HSE has issued guidance on the management of anchor hazards for pipeline operators,

    this is available via the following link: http://www.hse.gov.uk/pipelines/pipeline-anchor-

    hazards.pdf

    Anchoring procedures for standby vessels, supply vessels, diving support vessels, heavy

    lift crane vessels, flotels, drilling rigs, etc should be included in the safety case. Risks come

    from dropped objects such as freight being loaded and from vessel collisions with risers,

    and from dropped objects such as caissons. Pipelines and risers should be routed safely or

    protected. Procedures should limit vessel sizes and types, weather conditions for loading,etc.

  • 8/10/2019 Pipelines LOC

    10/28

    Pipelines located under platform cranes should be protected from dropped freight

    containers, tubulars, etc. Procedures should limit the types and weights of freight to be

    handled so as to not exceed the design capabilities of the pipeline protection.

    Safety cases for non-production installations should include a description of arrangements

    for identifying the routes and locations of pipelines, wells and other subsea equipment and

    assessing the risks that they pose to the installation (SCR05 Schedule 3 para 12).

    Particulars of the plant and arrangements to minimise the effects of damage to subsea

    equipment by drilling equipment should be included (SCR05 Schedule 3 para 6).

    Combined operations notifications should include a suitable diagram(s) showing the

    location of risers, pipelines and other subsea equipment in relation to the layout of the

    combined operation. Safe operating limits of the installations, mooring lines, crane radii etc

    should also be provided (A guide to the Offshore Installations (Safety Case) Regulations

    2005 L30 para 295 page 69).

    Jack-up spud cans making deep holes in the seabed into which a pipeline can slip should

    be considered within the safety case as appropriate.

    7. Modifications and Repairs

    The safety case should include a description of procedures to be followed for modifications

    and repairs, including hazard identification, risk assessment, notifications, isolation

    arrangements (topsides and subsea), standards of work inspection and testing.

    A description should be included of past modifications and repairs to the pipelines that

    could affect the safety case hazard identification and risk assessment: i.e. where

    modifications fall below the standard of the rest of the pipeline.

    8. Pipeline Over-pressure Protection

    The safety case should describe the type and operation of any pipeline over-pressureprotection

    Pressure breaks should be examined critically. The primary protection should be by design

    for the highest foreseeable pressure (inherently safe design). Secondary protection may

    include relief valves, High Integrity Pressure Protection System (HIPPS) (section

    2.3.1.F16), etc.

  • 8/10/2019 Pipelines LOC

    11/28

    The well head shut-in pressure of a subsea well connected to the installation should be at

    or below the safe operating pressure of the relevant riser. The maximum output pressure or

    the high pressure shut down set points for pumps and compressors and other pressure

    sources connected to the pipeline should be at or less than the riser safe operating

    pressure. The maximum allowable operating pressures (or safe operating pressure) of

    pipelines connected subsea to a riser should be so as to prevent overpressurisation from or

    of a third party pipeline or installation.

    The considerations mentioned above must be satisfied, using a suitable HIPPS system or

    similar if necessary. See Safety Instrumented Systems for the Overpressure Protection of

    Pipeline Risers, SPC/Tech/ED/31 at

    http://www.hse.gov.uk/foi/internalops/hid/spc/spctED31.htm. SPC/Tech/ED/31 describes

    various levels of pipeline and riser design, additional protection measures, HIPPS design,

    operational testing and maintenance.

    9. Pipeline Safety Systems

    The safety case should include a hazard identification that identifies the critical safety

    system components. The duty holder should describe all the safety systems in place for

    safe operation, safety of personnel and prevention of hazard escalation. The performance

    standards required of these systems should be described, stating for example the action

    and shutdown levels. These components should be tested and maintained. The safety

    systems should cover the greatest and most frequent hazards, and they should provide the

    fastest response and warning of hazards. Emergency procedures are intended to cover the

    rest.

    10. Pipeline Emergency Shut-Down Functions

    The safety case should describe the emergency shut-down facilities. The levels of shut-

    down should be clearly defined. The level at which the riser ESD valves are closed should

    be stated. ESD system data (e.g. riser valve closure) transmitted to or from connected

    installations should be described. If SSIVs are installed, their mode of operation should be

    described: i.e. automatic or manual.

    11. Connection to Pipeline Systems

    When communication data or control links between installations connected by pipeline are

    lost there are usually temporary manual procedures after which the pipeline should be shut

    down. In some cases remotely controlled action can be taken under major accident

  • 8/10/2019 Pipelines LOC

    12/28

    conditions by connected installations. The sequence and timing of such actions, including

    emergency shut-down arrangements should be described in the safety case.

    12. Pipeline Leak Detection

    The safety case should describe the type and operation of the pipeline leak detection

    system, including data and control functions monitored, monitoring locations (e.g. at each

    end of the pipeline) and the alarm and shutdown set points for these functions.

    13. Emergency Response

    The safety case should describe emergency arrangements, which should cover all

    identified hazards and interfaces and roles of other operators (at other installations) for the

    safety of the installation and of other installations.

    14. Integrity Management

    The safety case should confirm that the inspection, maintenance and integrity management

    arrangements in place for the pipeline include the entire length of the pipeline.

    A description should be included in the safety case of the inspection assessment and

    maintenance arrangements. This should summarise: the methods of inspection of the

    pipelines and risers; the management system for carrying out the inspection work; and

    decision making processes used to determine the scope and programme for remedial work

    or operations.

    A description should be included in the safety case of procedures to satisfy the operation,

    maintenance and testing requirements for the emergency shutdown (ESD) valves,

    demonstrating that seat leakage is measured, assessed and remedial action taken if

    required.

    15. Subsea Operations

    The safety case should describe pipeline and control connections between the installation

    and subsea manifolds wells and other installations.

    The safety case should contain a summary description of procedures for simultaneous

    production (if applicable) and diving, or other pipeline works or maintenance, on a pipeline,

    at a subsea manifold or well connected by pipeline to the installation. This should detail the

    measures in place to control any pipeline hazards that could affect the diving support

    vessel, its crew or divers, the installation or another installation.

  • 8/10/2019 Pipelines LOC

    13/28

    HS1 Rigid Risers

    16. Pipeline Operations

    The duty holder should state the expected frequency and purposes of pigging throughout

    the field life, covering routine scale, wax, water/liquids removal, inhibitor / biocide

    distribution, to intelligent pigging inspection.

    The duty holder should summarise the inspection scheme for each part of the pipeline,

    describing the techniques and frequencies used and justifying their adequacy.

    The duty holder should assess the effects of leaking seats on riser ESD valves and

    appropriate action to take should be documented. This should be covered in the safety

    case as the summary of a study assessing the effects of the maximum allowable seat

    leakage.

    The design and operation should take account of safe operating temperature limits to avoid

    hydrates, condensates in gas systems, wax, ice, steel embrittlement, failure of blowdownsystems and failure of polymers in flexible risers and pipelines.

    Process upset conditions include slugs, surges and emergency shut-downs. Some system

    designs rely upon the processes remaining within certain parameters, and suitable controls

    must operate effectively to prevent excursions.

    17. Decommissioning and Abandonment

    Taking a pipeline out of use involves cleaning out of hazardous substances from pipelines,

    risers and topsides, and ensuring safe disconnection from live plant, and decommissioning

    or removal of facilities as required. This involves ensuring the safety of divers and that of

    other personnel involved with platform abandonment, and leaving the facilities in a safe

    state. The safety case should address these issues as appropriate.

    Riser integrity has to be assured. The following applies to rigid risers and to the topsides

    elements connected to flexible risers. The safety case should include information relating to

    risers, from the seabed to either the emergency shutdown valve (ESDV) or the pig trap (if

    fitted) as follows.

    Approximate route, showing relevant module decks, bulkheads and structural

    members, riser supports / guides;

  • 8/10/2019 Pipelines LOC

    14/28

    ESDV location;

    Mechanical joints, e.g. flanged and insulation joints;

    Splash zone corrosion resistant cladding;

    Any branches outboard of the ESDV as far as their respective isolation valve(s) and

    their nominal diameter; and

    Fire, explosion, impact or other protection provided for the riser and ESDV.

    1. Riser Routing and Design

    The safety case should, with the aid of diagrams, describe the riser routing in relation to the

    topsides layout, installation structure, pipeline to installation approaches and field layout.

    This enables assessment of the full impact of layout versus topsides and vessel activities.

    The riser should, where possible, be routed away from fire, explosion and impact hazards.

    The riser route should be chosen so as where possible to obtain a good ESDV location and

    pig trap arrangement (such that the ESDV is located as low as reasonably practicable

    along the length of the riser), such that, subject to other design constraints, the ESDV is

    close to the top end of the vertical part of the riser.

    Riser routes are sometimes chosen with little consideration of the ESDV location, this may

    be because subsea and topsides design are considered separately. The constraints of the

    topsides layout can result in a poor ESDV location, with a horizontal section of outboard

    riser below deck that cannot be isolated by the ESDV.

    Caisson risers should be terminated on the topside of the installation as low as is

    reasonably practicable, so that the ESDVs can be located as required.

    Specific issues to be addressed include:

    position of cranes for loading vessels;

    external risers located on the prevailing weather side of the installation, (being

    vulnerable to impacts from drifting vessels);

    fire protection;

    access for inspection, i.e. when located in caissons, J-tubes or platform legs;

    gas risers in concrete platform legs, which could leak and pressurise the leg causing

    it to collapse;

    adequate support of the riser, especially in the wave zone;

  • 8/10/2019 Pipelines LOC

    15/28

    HS2 Flexible and Compliant Risers

    dead weight supports should be with an anchor flange or similar, located out of the

    splash zone (for inspection).

    Risers should ideally be located in-board of jacket braces or other structural members to

    protect them from vessel impact. If not, there should be fenders or other means installed

    which can absorb impact energy without touching the riser. Parts of risers routed inboard of

    acket frames are vulnerable to impact by objects dropped from the topsides; there have

    been instances of caissons falling and landing near to a riser.

    Where risers are located in J-tubes (conduits) or in caissons, the J-tubes or caissons

    should be sealed off at both ends and filled with inhibited water to protect the riser from

    corrosion. A number of incidents have resulted from the failure to properly manage the

    integrity of pipelines in J-tubes of caissons. HSE guidance Hydrocarbon Risers in

    Caissons and I/J Tubes Inspection issues and become potential sources of leakage in a

    fire.

    Riser integrity has to be assured. The topsides parts of flexible and compliant risers are

    covered in the section 2.3.2.HS1. The safety case should include information relating to

    risers from the seabed to either the ESDV or the pig trap (if fitted). In particular:

    the approximate route in the extreme riser and vessel configurations showing

    moorings, relevant module decks, bulkheads structural members, I tubes, hangoffs,

    bend restrictors, midwater arches, seabed connections;

    ESDV location;

    mechanical joints, e.g. flanged joints, hang offs;

    any branches outboard of the ESDV as far as their respective isolation valve(s), and

    their nominal diameter; and

    fire, explosion, impact or other protection provided for the riser and ESDV.

    Flexible risers are vulnerable to damage from vessels, dropped objects, fatigue overstress

    and internal damage. The stress analysis described in the safety case should cover all

    applicable cases. Top end connections should be configured, either by their layout or by

    bend restrictors, to avoid the flexible pipe being damaged by bending at the connection.

  • 8/10/2019 Pipelines LOC

    16/28

    HS3 Pipeline - Tie-in spools, Seabed Pipeline

    Riser stress analysis should cover extreme static installation offsets from its station, static

    wind, wave and current loading, natural frequency analysis, dynamic response to wave

    frequencies (stresses and fatigue damage assessment) and dynamic transient responses.

    Operators should demonstrate awareness of the fatigue lives of their flexible risers,

    including in damaged condition, and the limiting sea states for the riser system.

    A description of fire, explosion and impact protection should address:

    passive fire protection;

    explosion protection - blast walls and plated decks;

    dropped object protection;

    operational protection against dropped objects: avoiding lifting over risers.

    In operation each flexible riser annulus should be piped separately (to avoid interaction

    between risers) to a safe area to vent gas pressure. Operator inspection should includeperiodic testing of each flexible riser annulus by vacuum and positive pressure testing as

    applicable, to test for and find a failed external polymer layer. Where the outer layer has

    failed there should be measures to prolong the life of the outer tensile wires, fatigue

    analysis to determine the remaining life of the outer tensile wires, and replacement of the

    riser when required.

    The safety case should take account of the pipeline within the hazard range of the

    installation, including features such as:

    layout of tie-ins, spool pieces, crossovers, subsea isolation valves (SSIVs), other

    subsea equipment and extent of protection measures such as mattresses, rock

    dump, trenching, protection covers, etc.

    other pipeline(s);

    no-anchoring areas;

    anchor patterns and jack-up footprints for vessels normally moored in the vicinity.

    All hazards that could result in a loss of pipeline integrity at any location (within the hazard

    limit distance i.e. where the installation could be affected) should be identified and

    included in the overall risk assessment for the installation.

  • 8/10/2019 Pipelines LOC

    17/28

    HS4 Emergency Shutdown Valves (ESDV)

    The safety case should assess the interaction between the installation and others linked by

    pipeline(s) and the effect an interconnected pipeline system could have on the installation

    or upon other installations.

    1. Pipeline to Platform Approaches

    The duty holder should describe, with suitable diagrams:

    the layout and configuration of the plant;

    the connections to any pipeline or installation; and

    any wells connected or to be connected to the installation.

    The plan of the location should be large enough to show any features that may be

    significant in the assessment of the hazard or risk associated with the site.

    The safety case should include a pipeline to installation approaches plan from the hazard

    distance to the installation, showing the installation(s), pipelines (including any not

    connected to the installation), direction of geographical (true /grid) and installation north, no

    -anchoring areas, subsea wells, manifolds, control umbilicals, anchor patterns for vessels

    normally moored in the vicinity, layout of tie-ins, spool-pieces, crossovers, SSIVs, extent of

    protection measures such as mattresses, rock dump, trenching, protection covers, supports

    and any significant changes in the seabed elevation.

    For a flotel located over the pipelines, dropped object and anchor/ mooring line damage

    should be considered. Similarly jack-up temporary moorings used during jacking

    operations, construction vessels, diving support vessels, and standby vessels should be

    considered.

    Moorings for drilling semis (usually but not always located away from fixed platforms) and

    ack-ups drilling satellite wells and exploration wells should be considered in connection

    with the in-field pipeline layout. Pipelay initiation, abandon and recovery lines should be

    considered.

    The pipeline integrity management system should address spans, including those close to

    the installation.

    1. ESDV Location

  • 8/10/2019 Pipelines LOC

    18/28

    The ESDV shall be located in a position:

    in which it can be safely and fully inspected, maintained and tested;

    such that the ESDV is above water (for normal design conditions); and

    subject to the above, such that the distance along the riser from the ESDV to the

    base of the riser is as short as reasonably practicable.

    The duty holder should indicate the ESDV location(s) on the riser drawing. See theparagraphs in 2.3.2.HS1 on ESD valve location, explaining how the riser should be

    designed for this, as well as how to locate a riser ESDV on a given riser route.

    The valve should be located as low as is reasonably practicable, and so as to eliminate

    unnecessary horizontal lengths of riser outboard of the ESDV. Operators often provide a

    small underdeck area containing only the ESDV.

    A risk assessment may seem to show that a change of location makes no difference to the

    overall risk of the installation. The safety case should confirm that the ESDV has been

    properly located regardless of any such risk assessment.

    Locating the ESDV correctly is a higher priority than providing protection for it. Grouping a

    number of ESDVs in a well protected area (against fire explosion and impact) with poor

    ESDV locations is not appropriate. The priority is to correctly locate the ESDVs.

    ESDV location should not be compromised because an SSIV is fitted. The SSIV serves a

    different function, does not shut as fast as a topsides riser ESDV, does not isolate the

    contents of the pipeline and riser between the SSIV and the riser ESDV, and is usually not

    tested etc for seat leakage.

    2. Riser Branches Outboard of ESD Valves

    Branches outboard of ESDVs compromise the ability of the main ESDV to isolate the

    installation from the pipeline. Such branches are part of the riser. The safety case should

    demonstrate that any such branch in use, as a bypass for example, has been fitted with an

    ESDV that meets the requirements of Schedule 3 of the Pipelines Safety Regulations. If the

    branch is not in use it should be cut back and isolated permanently, as close as possible to

    the main riser, or removed altogether. Valves on branches should be locked closed.

    3. ESDV Fire, Explosion and Impact Protection

  • 8/10/2019 Pipelines LOC

    19/28

    The duty holder should demonstrate, through description and general layout drawings, that

    adequate fire, explosion and impact protection is provided for the ESDV and its actuating

    mechanism. The actuator and any stored energy device (e.g. spring return or accumulator

    and hydraulic piping) required for fail-safe close purposes should be protected. A

    description of the protection of these items should be included in the safety case.

    Risers and riser supports should be protected against fire where necessary. At locations

    close to ESDVs the riser should be protected as for the ESDV against fire, explosion and

    impact.

    4. Fire Protection

    The safety case should provide assurance that the ESDV actuator and all components

    necessary for ESDV fail-safe closure will remain fully operable under anticipated fire

    conditions. The pressure containing capability of the ESDV, including any out-board

    maintenance valves and any flanged connections to the riser, should survive the

    anticipated fire conditions.

    Whilst both passive and active fire protection systems may be used, it should be noted that

    passive systems (coatings, covers, etc) do not require prime movers, distribution systems

    and an initiation signal, and are therefore likely to be more reliable and have higher integrity

    (subject to proper inspection and maintenance) than active systems (deluge, etc).

    Accordingly, active fire protection systems acting on their own may not be sufficient.

    There should be fire and gas detection in the vicinity of the ESDV.

    5. Explosion Protection

    Explosion protection measures in place should be described in the safety case. Explosion

    protection is usually best achieved by locating the ESDV well outside congested equipment

    modules and away from entries to these areas, to avoid high explosion over-pressures and

    damage. In many cases blast walls are provided.

    6. Impact Protection

    The main impacts to be considered by the safety case are:

    dropped and falling objects;

    missiles resulting from explosions; and

    vessels/ships.

  • 8/10/2019 Pipelines LOC

    20/28

    HS5 Subsea Isolation Valves (SSIVs)

    Protection from impacts may be achieved by blast walls and plated decks.

    The operator should carry out a study of the possible impacts, including those which could

    be experienced following another incident, such as heavy machinery falling from above,

    and should assess what protection is necessary.

    Some of the protection may be in the form of procedural control, e.g. for crane handling,

    boat approach, etc.

    7. ESDV Operation and Testing

    The duty holder should assess and mitigate the risks of the ESDV failing to operate on

    demand; An SSIV can only partly address this risk.

    The safety case should describe arrangements for periodic valve seat leakage testing and

    timing of closure tests. The associated performance standards should take account of

    potential escalation of an incident and be consistent with the risk assessment for the

    installation.

    8. Actuators and Control Panel

    The duty holder should describe the types of actuators used on the ESDVs.

    The ESDV, its actuator, the local control panel, and where fitted, its accumulators and any

    ESDV dedicated maintenance valves, should be located close together.

    SSIVs are not a mandatory requirement. However, the duty holder/pipeline operator is

    expected to take account of the Cullen Report and in particular recommendation 44 to "....

    demonstrate in the safety case that adequate provision has been made, including if

    necessary the use of SSIVs, against hazards from risers and pipelines". The Cullen Public

    Inquiry reported on the 1988 Piper Alpha disaster in which gas pipelines ruptured outboard

    of the riser ESDVs. This led to major fires fed from the pipelines, which caused the total

    destruction of the platform and 167 deaths.

    Where the safety case identifies that riser failure can lead to a major release of

    hydrocarbons, including liquids, then a SSIV should be fitted to reduce the risk to as low as

    is reasonably practicable. Where an SSIV is not fitted, the safety case should justify thisdecision.

  • 8/10/2019 Pipelines LOC

    21/28

    For liquids pipelines with a significant gas content a riser failure can lead to a major release

    of liquid driven out by the expansion of the gas. Specialised software can quantify such a

    release. A major part of a release can occur in the time taken for systems to be shut down

    to depressurise the pipeline, especially where such systems are located elsewhere.

    The decision as to whether or not an SSIV is to be fitted should be taken based upon an

    analysis of the potential consequences and risks of a riser release, and of damage due to

    escalation from another riser.

    The safety case should fully assess the consequences of a failure. The cost of an SSIV

    must be compared to the far greater cost if one is not fitted but is needed in an emergency.

    In addition to fire/explosion risks, major pipeline releases can upset the stability/buoyancy

    of floating production installations and vessels.

    Where pipelines are branched into main transportation lines or third-party imports, without

    an SSIV, there can be an unlimited supply of fuel into a fire. Emergency actions required by

    third parties can take a considerable amount of time to achieve and tests have shown lack

    of reliability; this must be factored into the assessment of whether an SSIV should be fitted.

    The risk of the riser ESDV failing to operate on demand should be considered in the

    assessment

    Dutyholders/operators should consider combining several SSIVs into a single skid to

    reduce installation costs and so make the fitting more reasonably practicable. Combining

    import and export riser SSIVs can be done such that the flow goes from import pipeline to

    export pipeline without going to the risers, thus reducing risks, the risers only being used for

    pigging. Connection points for future pipelines can be added at negligible cost.

    Pipelines to comment please? What is meant by this paragraph?

    Due to the location of an SSIV, a significant inventory of hydrocarbons will be present

    between the subsea valve and the top of the riser. Therefore, failure of the riser or

    connected pipeline (at the installation) will result in an unavoidable discharge of

    hydrocarbons under pressure, with the potential for a serious fire or vapour cloud explosion.

    An SSIV cannot prevent this initial discharge from taking place and cannot protect

    personnel in the open or working near the riser. Where the riser ESDV seat leaks the SSIV

    cannot affect the short and medium term leakage rate in an incident. SSIVs are often only

    function tested and not tested for valve seat leakage.

    1. Non-return or Check Valves

  • 8/10/2019 Pipelines LOC

    22/28

    On some risers a non-return valve (NRV) or check-valve may be used as a means of

    isolation. Where this is the case, the safety case should justify the use of an NRV, taking

    the following into consideration.

    The NRV has the advantages of being a self-contained operation and of rapid closure in the

    event of a pipeline rupture. Due to the closure times of actuated valves, there will be some

    initial hydrocarbon discharge which will last longer than for an NRV.

    An actuated SSIV has the advantage that it can be closed as a precaution in the event of a

    small leak or a fire in the vicinity of the riser, whereas an NRV cannot be shut.

    NRVs do not work on import lines. For export pipelines an NRV would prevent the normal

    flow being reversed for operational reasons, such as for pipeline depressurisation. An NRV

    makes it more difficult to pig the line, and NRVs are liable to be damaged by pigging. An

    NRV may not prevent a small leak (i.e. may not give a tight seal).

    Where appropriate, the safety case should demonstrate that the duty holder has

    determined the exact criteria expected for the NRV operation and efficiency. NRVs may be

    cheaper than SSIVs but the safety benefit is less, with the disadvantages noted above.

    2. Location of an SSIV / NRV

    The location of an SSIV should be determined from the balance of risks of

    1. a release from the riser or pipeline inboard of the SSIV and

    2. a release from the pipeline outboard of the SSIV.

    SSIVs are usually located some distance away from the installation they are intended to

    protect. This is necessary to reduce the risks due to any possible line failures resulting from

    objects dropped from the platform, supply boats, etc. on the platform side of the valve.

    The safety case should evaluate the risk of a rupture on the outboard (away from the

    installation) side of the valve, in which case it is necessary to address:

    gas cloud or oil pool dispersion;

    protection of the pipeline; and

    protection of the SSIV which can itself be an extra leak path.

    In some cases an operator will wish to locate an SSIV for ease of construction - examples

    are floating production installations with riser base valves, flowline bundles which arrive

  • 8/10/2019 Pipelines LOC

    23/28

    close to an installation, SSIV skids serving several pipelines, spool-piece flanges being

    used to avoid the cost of hyperbaric welds, etc.

    The pipeline to platform approach layout should be considered carefully to ensure that each

    SSIV is located on a sound risk-balancing basis, and that the overall layout addresses all

    risks.

    3. Description of SSIV

    The duty holder should describe the SSIVs installed. There should be a description with

    layout giving the location, modes of operation, type of valve and actuator and failure modes

    (e.g. fail close on loss of hydraulics/signal).

    The description must include the modes of closure/operation and the failure modes.

    Dutyholders/Operators are sometimes reluctant to install fail-safe closed valves in case,

    during a test or following a spurious failure, they close and remain jammed shut. It ishowever, of no benefit to fit an SSIV that is almost impossible to use or is functionally

    locked open.

    There should be fail safe modes of closure or similar in event of loss of hydraulics/other

    platform signals. The system should include local energy storage (such as a spring or

    hydraulic accumulator) to close the valve, and it should not rely on platform based hydraulic

    or other power supply for closure in an emergency.

    4. Protection

    The safety case should demonstrate that the SSIV is protected from impact and snag loads

    from anchor lines and fishing trawls. Usually a structure is provided for this purpose.

    5. Inspection, Testing and Maintenance

    The duty holder should describe the philosophy for carrying out inspection, testing and

    maintenance on SSIVs and NRVs.

    As with any safety system, the reliability needs to be assured, and this is normally done by

    carrying out periodic tests. The duty holder should describe the extent, type and frequency

    of these tests. There should be detailed procedures in place for this purpose. Some

    dutyholders/operators are reluctant to carry out tests in case the valves are damaged or

    cannot be opened again. Regular testing however improves the reliability of valves. Testing

    should include:

  • 8/10/2019 Pipelines LOC

    24/28

    HS6 Pigging Operations and Pig Traps

    full (and, if desired, partial) closure;

    valve seat leak tests; and

    checks for confirming closure, e.g. provision of local (visual) valve position indicators

    as well as the remote system indicators.

    1. Design for intelligent pigging

    Pipelines described in the safety case should be designed and built from end to end so that

    intelligent or inspection pigging can be done. This means having a consistent internal

    diameter, bends with a radius of at least 5 diameters, and providing pig launchers and

    receivers of sufficient length for intelligent pigs, with sufficient space in which to load and

    unload the pig traps. With subsea production systems connections should be provided for

    pig launchers, or ideally there should be the facility for round trip pigging or similar: i.e. no

    subsea operations required.

    When a pipeline has been used for several years the question arises as to whether its

    integrity can be assured. The only known method today to assure integrity is to carry out

    periodic intelligent pigging runs.

    Pipelines should be regularly scraped clear of water scale and wax by suitable pigging

    operations as required to avoid the risk of internal corrosion. Spheres or pigs can be used

    to apply inhibitor or biocide along the length of the pipeline.

    Some gas pipelines are regularly cleared of liquid slugs into a slug catcher.

    2. Pig traps

    The safety case should demonstrate that pig traps have been suitably designed. Pig trap

    closures should face outboard. Adequate protection (by double blocking of hydrocarbons,

    interlocks etc) should be provided against accidental opening of closures whilst under

    pressure. Pig traps should have facilities for venting, draining, purging, pressure testing,

    water and nitrogen supplies and lifting aids as applicable.

  • 8/10/2019 Pipelines LOC

    25/28

    Annex 1, Pipeline Reference Documents

    1. Pipeline Design and Construction Standards

    BS EN 14161:2011 Petroleum and Natural Gas Industries - Pipeline

    Transportation Systems

    BS PD 8010 Part 2:2004 Code of Practice for Pipelines. Part 2: Subsea Pipelines

    DNV Offshore Standard DNV-OS-F101 Submarine Pipeline Systems 2010

    ISO 13623:2009 Petroleum and Natural Gas Industries Pipeline Transportation

    Systems (but see BS EN 14161)

    ASME B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and Other

    Liquids

    ASME B31.8 Gas Transmission and Distribution Piping Systems

    ISO 13628-11 Design and Operation of Subsea Production Systems Part 11:

    Flexible Pipe Systems for Subsea and Marine Applications

    API RP 17B Recommended Practice for Flexible Pipe (equivalent to ISO 13628-11)

    BS EN ISO 16708:2006 Petroleum and Natural Gas Industries Pipeline

    Transportation Systems Reliability BasedLimitStateMethods

    2. Pipeline materials and construction standards

    BS 4515-1 Specification for the Welding of Steel Pipelines on Land and Offshore

    Part 1: Carbon and Carbon Manganese Steel Pipelines

    BS 4515-2 Specification for the Welding of Steel Pipelines on Land and Offshore

    Part 2: Duplex Stainless Steel Pipelines

    ISO 13847 Petroleum and Natural Gas Industries: Pipeline Transportation Systems

    Field and Shop Welding of Pipelines

    ISO 15590 Petroleum and Natural Gas Industries: Induction Bends, Fittings and

    Flanges for Pipeline Transportation Systems. Part 1: Induction Bends

    ISO 15590 Petroleum and Natural Gas Industries: Induction Bends, Fittings and

    Flanges for Pipeline Transportation Systems. Part 2: Fittings

    ISO 15590 Petroleum and Natural Gas Industries: Induction Bends, Fittings and

    Flanges for Pipeline Transportation Systems. Part 3: Flanges

  • 8/10/2019 Pipelines LOC

    26/28

    ISO 15589 Petroleum and Natural Gas Industries Cathodic Protection for Pipeline

    Transportation Systems Part 2: Offshore Pipelines

    ISO 3183 Petroleum and Natural Gas Industries Steel Pipe for Pipeline

    Transportation Systems

    API 5L Specification for Line Pipe (equivalent to ISO 3183)

    API Specification 17J Specification for Unbonded Flexible Pipe

    NACE Standard MR0175-2002 Sulphide Stress Cracking Resistant Metallic

    Materials for Oilfield Equipment

    BS EN ISO 13628-2 Petroleum and natural gas industries Design and operation

    of subsea production systems Part 2: Unbonded flexible pipe systems for subsea

    and marine applications

    BS EN ISO 13628-10 Petroleum and natural gas industries Design and operation

    of subsea production systems Part 10: Specification for bonded flexible pipe

    BS EN ISO 15156-1:2009 Petroleum and natural gas industries. Materials for use in

    H2S-containing environments in oil and gas production.

    BS EN ISO 15156-2:2009 Petroleum and natural gas industries. Materials for use in

    H2S-containing environments in oil and gas production. Cracking-resistant carbon

    and low-alloy steels, and the use of cast irons.

    BS EN ISO 15156-3:2009 Petroleum and natural gas industries. Materials for use inH2S-containing environments in oil and gas production. Cracking-resistant CRAs

    (corrosion-resistant alloys) and other alloys.

    3. Safety systems standards

    API RP 14C Recommended Practice for Analysis, Design, Installation and Testing of

    Basic Surface Safety Systems for Offshore Production Platforms 7th Edition March

    2001

    BS EN ISO 13628-14 (Draft) Petroleum and Natural Gas Industries: Design and

    Operation of Subsea Production Systems. Part 14. Subsea High Integrity Pressure

    Protection Systems (HIPPS)

    SPC/TECH/ED/31 Safety instrumented systems for the overpressure protection of

    pipeline risers

    API Spec 6D Specification of Pipeline Valves

  • 8/10/2019 Pipelines LOC

    27/28

    ISO 14313 Petroleum and Natural Gas Industries Pipeline Transportation Systems

    - Pipeline Valves

    Department of Energy Guidance Notes in Support of the Offshore Installations

    (Emergency Pipeline Valve) Regulations 1989 SI 1989/1029

    SPC/TECH/ED/49 Riser Emergency Shut Down Valve (ESDV) Leakage Assessment

    Pipeline Riser emergency shut down valves - Inspection issues and

    recommendations

    (http://www.hse.gov.uk/pipelines/resources/emergencyshutdown.htm)

    BS EN ISO 14723 Petroleum and natural gas industries. Pipeline transportation

    systems. Subsea pipeline valves

    4. Pipeline Integrity management standards

    DNV Recommended Practice DNV-RP-F116 Integrity Management of Submarine

    Pipeline Systems, 2009

    DNV Recommended Practice DNV-RP-F206 Riser Integrity Management

    Oil and GasUKGuidance Note: Monitoring Methods and Integrity Assurance for

    Unbonded Flexible Pipe Rev 5 Oct 2002

    API Technical Report 17TR2 The Ageing of PA-11 in Flexible Pipes

    Oil and GasUKOP010 State of the Art Report on Flexible Pipe Integrity and

    Guidance Note on Monitoring Methods and Integrity Assurance for Unbonded

    Flexible Pipes

    Energy Institute: Guidelines on integrity management of subsea facilities

    PD 8010 Part 4 Risk-based integrity management of steel pipelines on land and

    subsea pipelines (in preparation)

    5. Pipeline operations

    ISO 21329 Petroleum and natural gas industries. Pipeline transportation systems.

    Test procedures for mechanical connectors

    SPC/TECH/ED/18 Health & Safety Issues Associated with Changes from Dry Gas to

    Wet Gas Operations

    HSG 253 The safe isolation of plant and equipment, HSE Books, 2006, ISBN

    9780717661718

    HSE SPC/TECH/GEN/18 Underlagging Corrosion of Plant & Pipework

  • 8/10/2019 Pipelines LOC

    28/28

    6. Other guidance and sources of information

    HSE/IP/UKOOA PARLOC 2001: The Update of Loss of Containment Data for

    Offshore Pipelines 5th Edition

    ED Hydrocarbon Release Database (https://www.hse.gov.uk/hcr3/)

    Guidelines for the Safe and Optimum Design of Hydrocarbon Pressure Relief and

    Blowdown Systems, 2001, Oil and GasUK/ Energy Institute, ISBN 978-0-85293-287-

    2

    Guidelines for the Management of Integrity of Joints in Pressurised Systems, 2007,

    Oil and GasUK/ Energy Institute, ISBN 978-0-85293-461-6

    Guidelines for the Management, Design, Installation and Maintenance of Small Bore

    Tubing Systems, 2000,UKOil and Gas / Energy Institute, ISBN 978-0-85293-275-9

    Guide to the Application of IEC 61511 to Safety Instrumented Systems in

    theUKProcess Industries, EEMUA, ISBN 0-85931-168-6

    TWI/DNV/SINTE Project Guideline for Engineering Critical Assessments for Pipeline

    Installation Methods Introducing Cyclic Plastic Strain, DNV Report number 2003-

    3135