Halal Hub Hyper market Design Brief  The proposed Hypermarket builds up area of approx 160,000 sq. ft. Construc ti on gr id 105.00m x 85.00m de pe nd ing on si te configuration and levels. Façade and Floor heights shall conform to client’s requirements. A soft copy is enclosed for easy reference. Provision for car parking lots is min 500 units (Covered or semi- covered) Al l open space par king shall be semi-c ove red wi th min 1350 width for walkway car park bay shall include wheels stopper. Provision for motorcycle bay shall be included. Ingress-Egress, external boundaries parameters landscape shall comply with PBT’s/Authority requirements. A.  The gross build up area shall be segmented into three (3) major areas of activities. i. Loading area, storage, mechanical space, staf f canteen and admini str ati on off ice = 15% of bui ld up area (appro x 20,000.00 – 25,000.00 sq. ft.) ii. Supermarket area: 55% of build up area (approx 85,000.00 – 90,000.00 sq. ft.) iii. Mall: 30% of build up area (approx 45,000.00 – 50,000.00 sq.ft.) iv. For maximum space, AHU’s shall be elevated where appropriate. v. Loading area shall have a raise d platf orm o f min 900 to 1200, vi. Min of four (4) loading bays is requires with provision for receiving boxes and a receiving office.

PIHB Hypermart Design Brief

Embed Size (px)

Citation preview

Page 1: PIHB Hypermart Design Brief

8/6/2019 PIHB Hypermart Design Brief

http://slidepdf.com/reader/full/pihb-hypermart-design-brief 1/9

Halal Hub Hyper market Design Brief 

•  The proposed Hypermarket builds up area of approx 160,000 sq.ft.

• Construction grid 105.00m x 85.00m depending on siteconfiguration and levels.

• Façade and Floor heights shall conform to client’s requirements.

• A soft copy is enclosed for easy reference.

• Provision for car parking lots is min 500 units (Covered or semi-

covered)• All open space parking shall be semi-covered with min 1350width for walkway car park bay shall include wheels stopper.

• Provision for motorcycle bay shall be included.

• Ingress-Egress, external boundaries parameters landscape shallcomply with PBT’s/Authority requirements.

A.   The gross build up area shall be segmentedinto three (3) major areas of activities.

i. Loading area, storage, mechanical space, staff canteen andadministration office = 15% of build up area (approx 20,000.00 –

25,000.00 sq. ft.)ii. Supermarket area: 55% of build up area (approx 85,000.00 –

90,000.00 sq. ft.)iii. Mall: 30% of build up area (approx 45,000.00 – 50,000.00 sq.ft.)iv. For maximum space, AHU’s shall be elevated where appropriate.v. Loading area shall have a raised platform of min 900 to 1200,

vi. Min of four (4) loading bays is requires with provision for receivingboxes and a receiving office.

Page 2: PIHB Hypermart Design Brief

8/6/2019 PIHB Hypermart Design Brief

http://slidepdf.com/reader/full/pihb-hypermart-design-brief 2/9

vii. For double storey unit, provision for a wet and dry goods lift isnecessary.

viii. Storage area shall be partition off with security mesh.ix. An inventory office shall be provided within the storage area.x. Staff canteen requirement is approx 50 to 60 pax.

Staff access, male/ female Toilets, Suraus, Lockers security guard roomand scanning device shall be located strategically whilst theAdministration office shall include the Followings:

a. Meeting room 1 No (20pax)b. Discussion room 1 Noc. Head of Department 2 Nod. Accountant 1 Noe. Computer Server 1 Nof. Strong room 1 No

1. Supermarket Commercial Area Proper:• Min. of Twenty-four (24) paying counters bare necessities.

• Costumers service counter,

• Redeems and return goods’ counters.

• Kiosks for ancillaries merchandise

• Ample spaces for cold room bulk storage,

• Chillers, wet and cold storage display selves,

Page 3: PIHB Hypermart Design Brief

8/6/2019 PIHB Hypermart Design Brief

http://slidepdf.com/reader/full/pihb-hypermart-design-brief 3/9

• Dry gondolas, racks, shelves’, island shelves,

• Columns wrap-around shelves display, 

• electrical and household shelves (provisional to meet client’srequirements)

2. Mall area shall consist of :-

•  Trolley space Shop lots,

• Fast food Corner,

• children play land (optional)

• Male/ Female/ Handicapped Toilet,

• Surau,

• Kiosks,

• Fire control and Security room.• Basic amenities such as phone booths, ATM, Mail boxes etcshall be included,

• Nos of kitchen cum serving counters shall be between fiveto seven (5-7) units

• Provision for storage chamber, wash area, grease trap andstainless steel grating on scupper drainage.

Page 4: PIHB Hypermart Design Brief

8/6/2019 PIHB Hypermart Design Brief

http://slidepdf.com/reader/full/pihb-hypermart-design-brief 4/9

• Common storage and lockers permitting.

General Rules1. Location of escape staircase shall comply with uniform BuildingBy-Laws where each riser shall no exceed 175mm and thread

should be 250mm vertically spaced.

2. All floors/ Walls finishes shall refer to client’s schedule asspecified.

3. The submitting Architect shall liaise with the Local Authoritiesand shall comply fully with all statutory building by-laws.

Page 5: PIHB Hypermart Design Brief

8/6/2019 PIHB Hypermart Design Brief

http://slidepdf.com/reader/full/pihb-hypermart-design-brief 5/9

Construction and working drawings detail are required for theimplementation and construction used for the above works.

1.1 External WorksAction

a. Fencing and gate b. Compound drain/ external drain access panels and culvertc. Drains grating and typical sump pitd. Typical discharge pointe. Settlement joint/ expansion jointf. Kerb, Footpath and wheel stopg. Drainage system for turfing/ landscapeh. Planter box and conceal weep holei. Covered car park structure

A code j. Light bollards for trolleys

k. Project signboard and hoarding

2.1 Internal worksa. Roof gutter and down pipes b. Fascia, ridge/ gable endc. Roof scupper drain and vent pipe over metal sheetd. Roof insulation formate. Roof flashingf. Other relevant details

2.2 Railings & Ornamental Finishing

a. Lift (if applicable) b.  Travelator’s and core setting outc. Conceal gutterd. Railings and other fixed and integrated elements which apply

vertically or horizontally throughout the building min. scale 1:5(working detail) 1:50 (construction detail)

e. Lift Façade (if applicable)

3.1 Architectural Detailing Schedules:a. Doors & windows schedules, b. Overhead roller-shutters & security grilles schedules

c. Shop front scheduled. Other decorative and metal and aluminum related work,e. Office prefabricated curtain claddings and blinds or otherwisef. Inter-tenancy partition (between shop lots)

A codeg. Bulkhead A

code

Page 6: PIHB Hypermart Design Brief

8/6/2019 PIHB Hypermart Design Brief

http://slidepdf.com/reader/full/pihb-hypermart-design-brief 6/9

h. Service Counter Acode

i. Reflected ceiling plan, duct access doors  j. Internal partitions, walls, screen and space divider (plan and

elevation)

k. Floor finish layout and patternA codel.  Typical waterproofing detail (Floor and r.c.roof)

4.1 Lavatories & Restrooms:a. Male and Female toilets, Surau and wash area. Typical plan/

section/ elevation showing urinal height, sensor, dryer, toilet rollwaste dispenser mirrors etc:

b. Build in fittingsc. Vanity basins or full length slab and mirrorsd. Cubical compartments and scupper drainage.

e. Handicap layout and rails

5.1 Food & Eatery Preparation Area:a. Kitchen and serving counter b. Grease trap and scupper drainagec. Fast food counter and frontage

A code

6.1 Covered car park a. Drainageb. Duet protection guard/ column guard

c. Krebs and Islandd. Car park/ motorcycle markingse. Bollard/ Chain post (if applicable)f. Angle guard to square edges (walls)

7.1 Loading and Unloading Baya. Edge bumper protection-rubber/ h.wb. Ramp finishes-groove, ringsc. Heavy duty floor finish-granolithic screedd. Receiving box roller shutter

e. Receiving office counter

8.1 Ceilinga. Gypsum plasterboard/ fibrous plasterboardb. Interfacing of ceilingc. Modular acoustic mineral board (office)d. Gondolas, racks, cold area multi deck display by other?

(who)

Page 7: PIHB Hypermart Design Brief

8/6/2019 PIHB Hypermart Design Brief

http://slidepdf.com/reader/full/pihb-hypermart-design-brief 7/9

9.0 Accessoriesa. Letter boxes b. Car park trolley barriersc. Conceal I section column (to Bomba requirement)

d. Conceal rwdp & other services (with leaks trays & protections)

General & All other construction and termination details for constructorused

Schedules of Finishes

Item Facilities Floor Finishes

  GROUND FLOOR

G1Car Park &Driveway

Carpark: Floor HardenerDriveway: premixed macadam

G2 Loading/unloading Area &Parking Heavy-duty Interlocking Block(80mm)

G3 Ramp 4kg/m² Floor Hardener

G4 Loading Platform 4kg/m² Floor Hardener

G5 Surau 1 Floor board 1m strips

G6 Ablulation 1

300x300 Ceramic Tiles wall &channelCeramic & rubber mate modulargrips

G7 Storage Area 4kg/m² Floor Hardener

G8 Receiving Bay 4kg/m² Floor Hardener

G9

Personnel

Scanner/pasasage/security 300x300 homogeneous tilesG10 Locker room areas Cement Render

G12 Male & Female Toilet 2 300x300 Ceramic Tiles

G13 Staff Canteen 300x300 Homogeneous Tiles

G14 Staff Kitchen 300x300 Homogeneous Tiles

G15 Male & Female Toilet 1 300x300 Ceramic Tiles

G16 Wash Area 300x300 Homogeneous Tiles

G17 Refuse Chamber 200x200 Ceramic Tiles

G18 Store Cement Render

G19 Food Court 600x600 Homogeneous Tiles

G20 Food Court Kitchen 300x300 Homogeneous Tiles

G21 Childcare 600x600 Homogeneous TilesG22 Lift Lobby 600x600 Porcelain Tiles

G23 Security Room 600x600 Porcelain Tiles

G24 Shop Cement Render

G25 Entrance Lobby & Kiosk 600x600 Porcelain Tiles

G26 Sub Lease 600x600 Porcelain Tiles

G27 TNB & Genset Room Cement Render

G28 Male & Female Toilet 3 300x300 Ceramic Tiles

Page 8: PIHB Hypermart Design Brief

8/6/2019 PIHB Hypermart Design Brief

http://slidepdf.com/reader/full/pihb-hypermart-design-brief 8/9

G29 Babes Changing 300x300 Ceramic Tiles

G30 Mail Room 300x300 Ceramic Tiles

G31 Surau 2 Timber Stripe

G32 Ablulation 2 300x300 Ceramic Tiles

G33 Staricase 300x300 Homogeneous Tiles

G34 Verandah/Walkway 300x300 Homogeneous TilesG35 Entrance Ramp Pebbles Wash

 

Page 9: PIHB Hypermart Design Brief

8/6/2019 PIHB Hypermart Design Brief

http://slidepdf.com/reader/full/pihb-hypermart-design-brief 9/9

  FIRST FLOOR  

F1 Super Market 600x600 Homogeneous Tiles

F2 Storage 4kg/m² Floor Hardener

F3 Inventory Room 4kg/m² Floor Hardener

F4 Computer Server Room Cement RenderF5 Strong Room Cement Render

F6 Office Vinyl Tiles

F7 HOD Vinyl Tiles

F8 Kiosk & Walkway 600x600 Porcelain Tiles

F9 Shop Cement Render

F10 Security Room 600x600 Porcelain Tiles

F11 Store Cement Render

F12 Customer Service 600x600 Porcelain Tiles

F13 Baggage Counter 600x600 Porcelain Tiles

F14 Male & Female Toilet 300x300 Ceramic Tiles

F15 External Flat Roof Water Proof Cement Render