Philadelphia’s Spring Garden St. Greenway Master Plan

Embed Size (px)

Citation preview

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    1/40

    June 2013

    rEIMAGINED

    THE

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    2/40

    The Pennsylvania Environmental Council (PEC) is one of thestates leading environmental organizations and has beenprotecting and restoring natural and built environmentsthrough innovation, collaboration, education, and advocacyfor over 40 years. One of PECs major initiatives has beendeveloping greenway corridors throughout the GreaterPhiladelphia area. The Spring Garden Street Greenway isone of the latest projects which PEC has been engagedin to add to Pennsylvanias green infrastructure.

    This project was financed in part by a grant from theCommunity Conservation Partnerships Program, EnvironmentalStewardship Fund, under the administration of the PennsylvaniaDepartment of Conservation and Natural Resources, Bureauof Recreation and Conservation. Funding from the WilliamPenn Foundation and Delaware Valley Regional PlanningCommissions Regional Trails Fund also supported this project.

    Consultant TeamPEC Team

    Contact Information

    Sam Schwartz Engineering

    Birdsall Services Group

    Interface StudioReal Estate Strategies

    Traffic Planning and Design

    Devine + Partners

    Patrick Starr

    Spencer Finch

    Jeff Knowles

    (215) 545-4570

    www.SpringGardenStreetGreenway.com

    1315 Walnut Street, Ste. 532

    Philadelphia, PA 19107

    thethe

    A ProudMember

    of:

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    3/40

    Why Spring Garden Street? 4

    History & Context 10

    Public & Stakeholder Outreach 13

    Selection of the Median Greenway 17

    Design Features & Components 20

    Design Functionality 28

    Costs & Benefts 34

    Implementation 36

    Supporters 38

    I

    II

    III

    IV

    V

    VI

    VII

    VIII

    IX

    Table of Contents

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    4/40

    2008

    Calais, ME to Key West, FL 3000 miles

    Durham

    Newark

    The 2.1-mile Spring Garden Street Greenway (SGSG) will connect two existingand developing riverfront trail systems along the Delaware and Schuylkill rivers.At its western end, SGSG will link to the Schuylkill River Trail via PennsylvaniaAvenue while the greenway will join with the developing Delaware River Trailat Columbus Boulevard/Delaware Avenue on the eastern end. The greenway

    will be central Philadelphias link in the East Coast Greenway, a bikeway underdevelopment running 3,000 miles from Maine to Florida. SGSG will add to theregions growing trail network, known as The Circuit. When complete, The Circuitwill include 750 miles of bicycle and pedestrian trails in Greater Philadelphia; over250 miles are complete, and another 50 miles are currently under development.

    Why Spring Garden Street?I.

    Philadelphia

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    5/40

    Pennsylvania Environmental Councils (PEC) involvement with SpringGarden Street started four years ago with two key questions:

    To New Brunswick,Newark, and NYC

    To Wilmington, Baltimore,and Washington, DC

    To Harrisburg

    To Reading, Pottsville &Appalach ian Tr.

    To Bethlehem

    To Easton, the Poconos &

    Wilkes-Barre

    To Bridgeton

    CHESTERVALLEYEXTENSION

    CHESTERVALLEYTRAIL

    BRANDYWINETRAIL

    STRUBLETRAIL CYNWYD

    TRAIL

    PEMBERTONTRAIL

    DELAWARERIVERHERITAGETRAIL

    WISSAHICKONTRAIL

    LIBERTYBELLTRAIL

    EASTBRANCHPERKIOMEN

    MERCHANTVILLETRAIL

    JOHNHEINZNWRTRAIL

    SKIPPACKTRAIL

    CROSSCOUNTYTRAIL

    FORGETOREFUGETR.

    CHESTERVALLEYTRAIL

    DOYLESTOWN-NEW HOPECONNECTOR

    TIDALSCHUYLTR

    COBBS(ECG)

    MONROETWP.BIKEPATH

    GLOUCESTERCOUNTYLIGHTRAIL W/ TRAIL

    COOPERRIVERTRAIL

    EASTALANTICBIKEWAY

    RANCOCASGREENWAY

    KINKORATRAIL

    D&RCANAL(ECG)D&RTOWPATH

    NESHAMINYCREEK

    STRUBLETRAIL

    UWCHLANTRAIL

    SCHUYLKILLRIVERTRAIL(SRT)

    PERKIOMENTRAIL

    LIBERTYBELLTRAIL

    D&L TRAIL

    EASTCOASTGREENWAY

    DELAWARERIVERHERITAGETRAIL

    BRIDGETONRAILTRAIL

    LAWRENCE-HOPEWELLTRAIL

    BLACKWOODRAILTRAIL

    OCTORARATRAIL

    DARBYCREEKTRAIL

    RADNORTRAIL

    EASTCOASTGREENWAY

    TOOKANY-TACONY

    PENNYPACKTRAIL

    POWERLINETRAIL

    202PARKWAY

    TRAIL

    D& LTRAIL

    D& LTRAIL(ECG)

    SRT

    SRT ECG

    SRT/ECG

    the

    CHESTERCREEKTRAIL

    CRESHEIMVALLEY

    NEWTOWNSQRBRANCHTRAIL

    Ma y 2 0 1 2

    0 105

    PHOENIXVILLE

    POTTSTOWN

    DOWNINGTOWN

    DOYLESTOWN

    NEW HOPE

    QUAKERTOWN

    GLASSBORO

    BURLINGTON

    TRENTON

    PRINCETON

    MT. HOLLY

    BURLINGTON

    CAMDEN

    MERCER

    BUCKS

    DELAWARECHESTER

    Existing Trails

    Planned Trails

    Trai ls in P rogress

    Spring Garden Street Greenway, a link in the East Coast Greenway, will be the main Circuit connection across

    Center City Philadelphia linking the Schuylkill River Trail and the developing Delaware River Trail.

    In 2009, PEC conducted the Center City Greenway Feasibility Study to answer these questions. Thestudy concluded that a greenway along Spring Garden Street was the best option. Spring GardenStreet is an existing east-west bicycle route with standard bike lanes and unique in the Center Cityarea has space within the right-of-way for a greenway. The connection to both riverfronts is clear anddirect and is well known by local bicyclists. SGSG will improve the driving experience for motorists,maintain parking, andwith reconstruction of the medianthe route will provide a fully separatedgreenway experience for a variety of users. The feasibility study identified Spring Garden Street as thepreferred location for a greenway and began the process of realizing Spring Garden Streets potentialto be a more complete street that better serves those traveling via foot, bicycle, car, bus, or train.

    1. How best to connect our regions growing trail network

    2. How best to connect Philadelphias two riverfronts in the densest part of the region

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    6/40

    SGSG will transform Spring Garden Street into one of the most vibrant streetsand commercial corridors in Philadelphia, while also making it a calmer andsafer street to drive, bike, and walk. Spring Garden Street will act as a linearpark and urban trail within central Philadelphia with a new bikeway separatedfrom vehicular traffic. SGSG will offer additional recreation and commutingspace for walkers, joggers, and cyclists. It will sustainably manage stormwaterrunoff, connect neighborhoods, and catalyze economic investment.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    7/40

    SGSG will not only connect communities to eachother and the rest of the city, but it will benefit usersby providing a safe and enjoyable connection tolarge natural resources such as Fairmount Park,Boathouse Row, and Kelly Drive on the west end,and the Delaware River, Penns Landing, andthe new Race Street Pier to the east. SGSG willalso connect many of the citys signature culturalattractions and destinations, such as the PhiladelphiaMuseum of Art, the Philadelphia Zoo, the FairmountWaterworks, the new Barnes Foundation Museum,

    the Edgar Allan Poe House, the German Society,the Festival Pier, Chinatown, the IndependenceSeaport Museum, and the Convention CenterDistrict. The greenways proximity to high densityneighborhoods and its link between two majortrails creates the potential for SGSG to becomeone of Pennsylvanias most heavily used trails.

    The visionBy making thoughtful physical changes to Spring Garden Street, we can create aplace where more people can safely travel, work, live, shop, and recreate.

    Greenway

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    8/40

    Proposed,

    Spring Garden v

    Project Goals

    RECREATION & HEALTHYLIFESTYLES

    Make it easier for peopleto get outside and exercisenear where they live andwork by providing a greendestination for walking, strolling,skateboarding, rollerblading, andbiking between the Schuylkilland Delaware River Trails.

    TRANSPORTATION

    Increase safety and accessibilityfor drivers, walkers, bicyclists,and transit riders.

    ECONOMIC INVESTMENT

    Encourage reinvestmentand support existing

    businesses by bringingcustomers to the corridor.

    COMMUNITYDEVELOPMENT

    Become the front door todiverse communities.

    BEAUTIFICATION

    Beautify the street through newlandscaping and trees to provideshade and help meet the Citysstormwater management goals.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    9/40

    A protected, landscaped bikeway within the streets median

    Pedestrian amenities, including reconstruction of substandardsidewalks, curb extensions at corners, and pedestrian refuge islands

    New street trees and landscaping, street furniture, and lighting

    State-of-the-art synchronized traffic signals to expedite traffic

    Improved SEPTA bus operations and access

    A subsurface stormwater storage and infiltration system

    Transformed Spring Garden Street

    The conceptual design phase of the project began in June 2011. It has involvedover 1,600 hours of engineering and planning consulting time, three publicmeetings, and three Steering Committee meetings. The Steering Committeeincludes key stakeholders, such as local and state government agencies, bicycleand pedestrian advocacy organizations, neighborhood groups, businesses,and cultural institutions (see Supporters section on page 38). At each step inthe project, PEC consulted with the Steering Committee for review and input.The Mayors Office of Transportation and Utilities, the Philadelphia Water andStreets departments, and the Pennsylvania Department of Transportation(PennDOT) have also provided valuable on-going input to the process.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    10/40

    0

    History &Context

    II.

    PEC invited noted historic

    preservationist and local trails

    expert Bob Thomas of CampbellThomas and Company to provide a

    brief history of Spring Garden Street

    specifically for the project.

    In the 19th century, Spring Garden Street was an elegant,leafy boulevard that accommodated an interesting mix ofuses. It had little through traffic since it extended only from6th Street to the reservoir atop Fairmount Park where thePhiladelphia Art Museum stands today. The early predecessorof the Spring Garden Bridge, a suspension bridge knownas the Wire Bridge, linked instead to Callowhill Street.

    There was a huge landscaped median with sculpture, ironfencing, trees, and fountains on the blocks from 6th to Franklinstreets, and from 12th to Broad streets. Market sheds, likethose on 2nd Street in Society Hill, extended all the wayfrom Franklin to 12th streets. In this area, instead of six lanesof traffic as there are today (including turn lanes), therewere only two lanes on each side of the broad median.

    Many important institutions churches, schools, and societies lined Spring Garden Street, particularly east of BroadStreet. The German Society of Pennsylvania, featured in thephotograph below, is an excellent example which remains.The street hosted its share of industry as well, ranging fromthe Baldwin Locomotive Works to later examples such as theU.S. Mint, now part of the Community College of Philadelphia.

    German Society

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    11/40

    With the great period of industrialization following the CivilWar, many of the nouveau-riche, being rejected from more

    established areas such as Rittenhouse Square, settledin North Philadelphia. Spring Garden Street thus saw thedevelopment of the huge brownstones and other elegantmansions west of Broad Street, many of which survivetoday as part of The Spring Garden Historic District.

    The cross section of western Spring Garden Street resembledCommonwealth Avenue in Boston broad sidewalks, richlylandscaped front gardens (a few of which survive today),ornate iron fencing, and a grand mix of facades featuringelaborate brickwork, brownstone, marble, and limestone.Elegant stairways, complex bay windows, and richly

    detailed dormers are found on many of these mansions.

    [21st & Spring Garden]

    [Ridge & Spring Garden] [4th & Spring Garden]

    But what happened to the street inthe 20th century? With the building ofthe Delaware River Bridge (now theBenjamin Franklin Bridge) in the 1920s,plans were drawn and then executed forinner and outer rings of circulator roads.Spring Garden Street was selected for

    this system because of its wide right-of-way. Its green medians were turnedover to heavy motorized traffic. Manyof the wealthy residents migrated toquieter, more suburban locales, andmany of the grand homes were dividedinto apartments. Iron fencing was soldoff or donated to war efforts, frontgardens were paved over, and maturetrees were not replaced. The greenboulevard became a noisy urban arterial.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    12/40

    2

    Other issues that affectSpring Garden Street:

    Vacant lots, abandoned buildings, or blankwalls line 49% of the street

    Neighborhoods disconnected from each other

    Psychological barrier/safety/security

    Combined sewer overows

    Substandard trafc signals

    Decrepit sidewalks

    Largely forgotten history (allay of trees, fountains, statues)

    History & Context

    These issues give way to opportunities: Real estate redevelopment, such as at the former State Office Building

    New businesses (for example, Union Transfer)

    Existing intersecting initiatives (North Broad vision plan, conversion of theReading Viaduct to a linear park, Delaware River Waterfront Corporations(DRWC) plan for the central Delaware River waterfront, casino development)

    Existing Institutions (Philadelphia Museum of Art, CommunityCollege of Philadelphia, Social Security Administration, PhiladelphiaFire Marshall, Edgar Allan Poe National Historic Site)

    Strong neighborhood leadership

    Existing Conditions

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    13/40

    The SGSG design is the result of a process that included

    extensive public and stakeholder outreach:

    Mayors Office of Transportationand Utilities

    Philadelphia Streets Department

    Philadelphia Water Department

    Philadelphia Parks andRecreation Department

    Philadelphia City PlanningCommission

    Mayors Office of Sustainability

    Delaware Valley RegionalPlanning Commission

    Pennsylvania Departmentof Transportation

    Southeastern PennsylvaniaTransportation Authority

    Pennsylvania Department ofConservation and Natural Resources

    Delaware River Waterfront Corporation

    Schuylkill River DevelopmentCorporation

    Bicycle Coalition ofGreater Philadelphia

    Center City District

    Pennsylvania Horticultural Society

    East Coast Greenway Alliance

    At the start of the project, PECestablished a Steering Committeeof key government and non-governmental organization partners.PEC coordinated three criticalSteering Committee meetings

    (August 3, 2011; November 8, 2011;and April 10, 2012) with the followingagencies and non-profit partners:

    Steering Committee Starting in 2010, meetings with neighborhood leaders,

    elected officials, and staff from several City of Philadelphiadepartments, including Streets, Water, Planning, MayorsOffice of Sustainability, and Parks and Recreation

    In 2011 and 2012, over 25 individual meetings with propertyowners, businesses, schools, churches, and institutionslocated on Spring Garden Street and presented in front ofthe membership for each civic association on the corridor

    Three community meetings along the corridor,

    attended by over 350 people Over 500 posters, flyers, and postcards to

    businesses and residents and placed in the spokesof bicycles along Spring Garden Street

    Online presence through a project website(springgardengreenway.com), Twitter account(@SGSGreenway), and Facebook page (facebook.com/SpringGardenStreetGreenway, with 319 followers) with specifictools for users to register comments and share input

    Community walkability audit

    319

    COMMUNITY WALKABILITY AUDIT

    www.facebook.com/SpringGardenStreetGreenway

    @SGSGreenway

    springgardengreenway.com

    Public &StakeholderOutreach

    III.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    14/40

    4

    COMMUNITY MEETING 1: PROJECT BACKGROUND & CONTEXT

    October 27, 2011 Community College of Philadelphia(1700 Spring Garden Street)

    The project team presented the project background and context, including existingconditions and factors influencing the greenway design. Participants used stickerson a large-format poster map to indicate where they live, work, shop, and travel in thecorridor. They also filled out postcards to the future, an exercise used to determineparticipants vision for the future greenway. To help select a preferred designoption, participants indicated their opinions regarding two different design optionson inspiration boards with photographs of different greenway types and features.

    postcards to the future

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    15/40

    December 6, 2011 German Society of Pennsylvania(611 Spring Garden Street)

    The workshop focused primarily on the selection of a preferred design option.Participants worked through a series of exercises to express their opinionson the strengths and weaknesses of a curbside bikeway versus a medianbikeway from a number of different perspectives: that of a parent with astroller, a resident, a new business owner, a timid cyclist, and their personalperspective. A straw poll was conducted at the end of the workshop, withparticipants asked to indicate their preference for a curbside or medianbikeway; the vote was roughly evenly split, with no clear majority.

    COMMUNITY MEETING 2 - DESIGN WORKSHOP

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    16/40

    6

    June 20, 2012 Community College of Philadelphia(1700 Spring Garden Street)

    The project team displayed large-format drawings of the selectedmedian-based greenway design, and project team members answeredquestions and discussed design details. The project team alsoprovided details about the selection of the median greenway, estimatedconstruction costs, and a potential implementation strategy.

    COMMUNITY MEETING 3 - PRESENTATION OF FINAL DESIGN

    Before

    After

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    17/40

    Center City GreenwayFeasibility StudySummer 2009

    PECs 2009 Center City Greenway Feasibility Study

    identified two options for the greenway design: a

    curbside option, in which a protected bikeway wouldbe created between the curb and parking lane, and

    a median option, in which the median would be

    expanded to incorporate a bikeway. An initial task

    for the SGSG project was to evaluate both options in

    detail and choose one to advance into a preliminary

    design.

    As part of the evaluation of the two options, thefollowing elements were analyzed in detail:

    Potential for vehicle/bicycle conflict

    Impact to parking supply

    Pedestrian improvements

    Impact on motor vehicles and bicyclesturning off of Spring Garden Street

    Movements through and design of atypical locations,such as under the Reading Viaduct and I-95

    Impact to bus operations

    Mid-block conflicts at both side streets andcurb cuts and also analyzed curbside activities(deliveries, lunch trucks, and parking)

    Underground utility conflicts and potentiallocations for stormwater structures

    Design functionality, such as intuitivenessand adequate sight lines

    Landscaping opportunities

    The public and the Steering Committeeprovided input for the evaluation. At the

    second public meeting on December 6,2011, participants identified the strengthsand weakness of each option and votedfor their preference. Attendees wereevenly split. Similarly, in an online surveyof the Steering Committee, neither optionwas clearly preferred over the other.

    Further developing both optionsand conducting additional meetingswith key stakeholders helped guidethe project team toward a decision.

    The median greenway had clearadvantages in the following areas:

    Pedestrian improvements

    Impact to bus operations

    Mid-block conflicts

    Impact to parking supply

    Utility conflicts

    Locations for stormwater structures

    Selection ofthe MedianGreenway

    IV.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    18/40

    8

    Pedestrian improvements

    The median design allows for consistent neckdowns,or curb extensions, at every corner along the corridor.The curbside design would vary at the corners, withfloating pedestrian refuges, floating bus bulbs, orstandard neckdowns, depending on the corner.

    Mid-block conflicts

    Vehicle/bicycle conflict points along thecorridor consist of intersections (bothsignalized and unsignalized) and curbcuts. The curbside option was foundto have 77 conflict points, while themedian option had 25. Of the medianconflict points, five of the 25 locationsare unsignalized intersections, fourof which are proposed to be closed

    in the SGSG design (as discussedon page 29 in the Minor Intersectionsection), thus reducing the numberof median conflict points to 21.

    Additionally, under the curbsideoption, the parking lane would bemoved approximately eight feet awayfrom the curb to accommodate thebikeway. This floating parking lanedoes not meet the current PennDOTrequirement that cars parallel park

    against a curb and could have requiredthe construction of a second, lowercurb separating parallel-parked carsfrom the bikeway. This second curbwould increase the cost of the curbsideoption by several million dollars.

    Utimately, the following factors led to the selection ofthe median-based bikeway as the preferred option

    Impact to bus operations

    The median options impact on bus operations isless than the curbside option because bicyclists will

    be significantly distanced from bus stops. With thecurbside option, bicyclists would ride between afloating bus bulb and the curb, resulting in a conflictpoint between bicyclists and bus passengers walkingto and from the bus bulb. (Bus bulbs are described indetail on page 33.) Furthermore, under the curbsideoption, the existing bus layover zone under I-95at the Southeastern Pennsylvania TransportationAuthority (SEPTA) Spring Garden Station wouldbe either eliminated or, given space constraints,bicyclists would have to cycle around buses on astandard bike lane, rather than a protected bikeway.This layout would result in a sub-standard facilitywith potential conflicts for both buses and cyclists.

    Curbside Conceptual Rendering

    Proposed Median Rendering

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    19/40

    Impact to Parking Supply

    The addition of neckdowns and near-side bus bulbs may result in a negligiblereduction in parking spaces along thecorridor. There are approximately 720parking spaces on Spring Garden Streetand on the cross streets 50-feet to thenorth and south. With the implementationof SGSG, there would be approximately700 spaces. However, the parking supply

    can be increased somewhat by replacingtraditional parking meters with kiosks,which allow for greater parking flexibility.

    Utility conflicts and locationsfor stormwater structures

    The design team analyzed Highway Supervisory Plans andPhiladelphia Water Department (PWD) Plans to determine thelocation of underground utilities. The team looked for areaswith few utility conflicts where stormwater storage and thenew bikeway could be co-located to avoid full reconstructionof the right-of-way. The team also avoided other relevantinfrastructure, such as train trestles and tunnel crossings.

    In the curbside design option, there were significant utilityconflicts on the north side of Spring Garden Street onevery block as well as no areas suitable for the stormwaterstructures; on the south side of the street, only eight of25 blocks had appropriate areas. In the median designoption, 18 of 25 blocks had sufficient median space forstormwater structures; on the remaining seven blocks, thestructures could be located under the vehicle travel lanes.

    Curbside utility conflicts were ultimately the fatal flaw forthe curbside option, as utility relocation costs and therisk of unexpected utility issues are likely significantlyhigher than they would be in the median option.Construction of stormwater structures requires significantreconstruction of the street regardless of their location,but the selection of the median option allows both theconstruction of the median bikeway and those structuresto occur in generally the same area at a lower cost.

    Curbside Stormwater Management

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    20/40

    0

    Maintain existing

    vehicle capacity

    Maintain turn

    lanes and cross-

    street access

    Maintain parking

    and curbside

    loading zones

    Limit impacts to

    bus operations

    Implement

    a protected

    bikeway

    As one of central Philadelphias primary arterialstreets, Spring Garden Street serves a critical

    transportation function for both through traffic andtraffic needing access to adjacent neighborhoods.

    The current layout of Spring Garden Street typically alternatesby street block, with some blocks featuring a median(concrete or landscaped) and other blocks featuring left-turn lanes. On blocks with left-turn lanes, a concrete striptypically separates the left-turn lanes from on-coming traffic.The streets curb-to-curb width varies on either side of BroadStreet. Spring Garden Street is 80 feet wide to the west ofBroad Street and 88 feet wide east of Broad Street. The streetincludes two travel lanes in each direction for through traffic.

    Existing]

    The following assumptions guided the design process:

    In general, the SGSG design followsa context-sensitive, Complete Street

    approach. A Complete Street designaccommodates all potential users andserves multiple functions, consistentwith adjacent land uses. In the case ofSGSG, pedestrians will feel safer andmore comfortable walking, the bikewaydesign will attract a wider range ofbicyclists, stormwater will be managedin a more sustainable manner, busaccess and operations will be improved,and vehicle access and connectivity

    will be maintained for motorists.

    DesignFeatures &Components

    V.

    Early in theprocess, retentionof the streets fourtravel lanes was

    deemed essentialgiven its relativelyhigh traffic volumes.

    Impacts to theareas street grid,connectivity, andthe functionality

    of the streetfor vehiculartraffic shouldbe minimized.

    Parking demandin the area isrelatively high,and stakeholders

    requested nosignificantreduction inparking.

    Spring GardenStreet is a heavilyused bus corridorwhere bus

    operations andaccess shouldbe maintainedor enhanced.

    The bikeway shouldbe above thegrade of vehicletravel lanes and

    separated fromadjacent vehiculartraffic by curbsand landscaping(exceptions to thisare described onpages 24 and 25).

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    21/40

    Conform the design to the following

    dimensions:

    Maintain

    sidewalk width

    Limit impacts to city services and

    curbside activity

    [Proposed]

    What could Spring GardenStreet look like?

    General design details forthe greenway segments eastand west of Broad Street,followed by additional detailsfor atypical locations, such asthe connection to ColumbusBoulevard/Delaware Avenue

    Minimum 10-foot-wide bikeway withminimum 5-foot-wide buffer between thebikeway and vehicle lanes (exceptionsto this are described in the West

    of Broad] section on page 22).

    11-foot-wide travel lanes, reducedto 10 feet in certain locations ifthere is no adjacent curb.

    10-foot-wide left-turn lanes.

    8-foot-wide curbside parking lanes(exceptions to this are described in the[West of Broad] section on page 22).

    West of BroadStreet, sidewalksare typically 20feet wide, although

    the effective widthis usually lessgiven the presenceof street trees,building stoops,etc.; sidewalkseast of BroadStreet are typically16 feet wide.

    The design should not hinder refusecollection, street sweeping, and snowremoval. Curbside access should bemaintained for the numerous food trucks

    serving customers from businessesand institutions along the corridor.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    22/40

    2

    The design for the 0.8-mile section of Spring Garden Street west of Broad Street, which is 80 feet

    wide, is as follows:

    Blocks without left-turn lanes

    A 20-foot-wide raised medianencompassing a 10-foot-wide bikewaywith five-foot-wide landscaped buffers

    between the bikeway and travel lanes Two eight-foot-wide parking lanes

    and four 11-foot-wide travel lanes

    Blocks with left-turn lanes

    Mid-block sections are similar to theabove, with a raised and landscapedmedian bikeway. Adjacent to the turnlanes, space is more constrained andthe bikeway is at-grade, separatedfrom adjacent travel lanes by a stripedbuffer and flexible plastic posts

    These blocks also include twoseven-foot-wide parking lanes andfour 10-foot-wide travel lanes

    [West of Broad]

    [West of Broad]

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    23/40

    For the 1.3-mile section of Spring Garden Street east of Broad Street, which is 88 feet in width, the

    design is as follows:

    Blocks without left-turn lanes

    A 28-foot-wide raised median,encompassing a 12-foot-wide bikewaywith eight-foot-wide landscaped buffers

    between the bikeway and travel lanes Two eight-foot-wide parking lanes

    and four 11-foot-wide travel lanes

    16-foot-wide sidewalks

    [East of Broad]

    Blocks with left-turn lanes

    A 20-foot-wide raised median,encompassing a 10-foot-wide bikewaywith five-foot-wide landscaped buffersbetween the bikeway and travel lanes

    Two eight-foot-wide parking lanes,two 11-foot-wide travel lanes, two10-foot-wide travel lanes, andone 10-foot-wide turning lane

    16-foot-wide sidewalks

    [East of Broad]

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    24/40

    4

    Dedicated bus lanes fromFront Street to 2nd Street

    Given that the street is constrained bythe I-95 bridge supports, the bikeway atthis location is at-grade, separated fromadjacent vehicle traffic by a three-footstriped buffer and flexible plastic posts.

    Sixteen-foot-wide sidewalks (asin the existing condition)

    Connection to Columbus Boulevard/Delaware Avenue

    Since Columbus Boulevard/Delaware Avenue has an existing bike lane and a proposed north-south greenway on the east side of the street, the SGSG design features a number of treatments tofacilitate the movement of bicyclists through the intersection and between these bicycle routes:

    Interstate 95/Spring Garden Station

    The existing configuration and proposed design of SGSG at the I-95 underpass are shown inthe figures below. The Spring Garden Station on the SEPTA Market-Frankford Line is located atthe I-95 underpass. To accommodate the large number of pedestrians attracted to this SEPTA

    bus and Market El transfer point, the design at this location includes the following:

    For bicyclists turning from southbound Delaware Avenue ontowestbound SGSG, a bike box positions them ahead of vehiculartraffic, and bicycle intersection markings guide them to SGSG.

    For bicyclists turning from SGSG to southboundColumbus Boulevard, a bike box facilitates theirmovement to the right side of the street.

    Eastbound bicyclists seeking the northbound bike lane onDelaware Avenue or the future greenway on the east side ofDelaware Avenue would cross the intersection on a separatebicycle signal phase. High-visibility bicycle intersectionmarkings (chevrons and peg-a-traks) would guide bicyclistsacross the intersection and alert motorists to their presence.

    Westbound bicyclists traveling from northbound ColumbusBoulevard would cross the intersection in a similar manner.

    EXISTING CONDITIONS MEDIAN DESIGN

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    25/40

    Reading Viaduct

    The right-of-way at this location (between9th and 10th streets) is particularlyconstrained, yet the design still maintainsfour 11- to 12-foot-wide travel lanes,accommodates left turns for motorists,includes a protected bikeway, andretains sidewalks. All vehicular traffic,except for left-turning vehicles, usesthe two outer tunnels of the viaduct.

    The greenway continues through thecenter tunnel, along with left-turningvehicles. Sidewalks are narrowed inthe outer tunnels to accommodate twotravel lanes, while maintaining sufficientwidth for pedestrians. In addition, theoutside travel lanes adjacent to thesidewalks are moved closer to thecenters of two outer tunnels, wherethe tunnel height is highest; thusclearance is improved for tall trucks.

    Connection toPennsylvania Avenue

    At Pennsylvania Avenue, a number ofdesign features facilitate the movementof bicyclists to and from the medianbikeway through the intersection:

    For westbound bicyclists headingtowards the Eakins Oval, a bike boxfacilitates their movement from themedian bikeway to the right side of thestreet. Bicycle intersection markingsguide riders through the intersection.

    For eastbound bicyclists riding

    from the Eakins Oval, a bike boxfacilitates their movement from theright side to the left side of the street.Bicycle intersection markings guideriders into the median greenway.

    EXISTING CONDITIONS

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    26/40

    6

    dry weather the pipe contains only sewage, whichflows into water treatment plants. When it rains,however, stormwater falling on the surface runsinto storm inlets and is added to the system.This eventually fills the pipes beyond theircapacity and as a result, some of this sewage-stormwater is discharged directly into local riversand streams through an overflow system.

    The proposed SGSG stormwater managementsystem will capture up to 1.5 inches of rainfall anddivert it to an alternative drain system. Basedon current City design standards, rainfall will becaptured via green inlets. Green inlets are locatedupslope of existing inlets where they can divertand intercept runoff into a subsurface trenchsystem. The subsurface trench system retains andinfiltrates stormwater rather than allowing it to flowdirectly into the combined sewer system. A typicalsubsurface system trench will be under the center

    of the street on each block, and about 208 feetlong, nine feet wide, and four feet deep. The trenchis filled with stone and wrapped in a permeablegeotextile liner; stormwater fills the voids betweenthe stones. When rainfall exceeds 1.5 inchesand fills the alternative drain system to capacity,curbside stormwater would flow past the now fullgreen inlets and into the existing corner inlets.

    Stormwater Management

    The SGSG approach to landscaping reflects anideal marriage of beautification and stormwatermanagement and complements PECs intentto create a world-class greenway design. TheSGSG design takes an innovative and integratedapproach by incorporating stormwater managementtechniques into the streets redesign. Thisapproach improves infrastructure sustainabilityand assists PWD in meeting city-wide goals ofreducing stormwater flows into the sewer system.

    SGSG will incorporate tree trenches and raingardens as stormwater features. Tree trencheswill appear to be conventional on the surface,but will store rainwater below the sidewalk inspecially designed trenches shared by multiplestreet trees. This available water will make forhealthier trees and reduce the amount of runoffthat burdens the sewer system. Rain gardenswill be incorporated into expanded curbs atintersections. These gardens will capture waterthrough plants, soil, and gravel and slow the flow ofwater into the sewer system. The gardens will alsoprovide attractive landscaping for the corridor.

    The SGSG design also includes undergroundstructures to reduce the volume of stormwaterflowing to the sewer system. The SGSG stormwatersystem will retain runoff from Spring Garden Streetand its sidewalks. At the request of PWD, the systemwill also handle runoff from adjacent side streets andcould accommodate future connections, such as inredeveloped vacant lots. As shown in the figure onthe right, Spring Garden Street is located near thetop of its sewer drainage area, making it ideal forcapturing stormwater before it overloads the system.

    Most Philadelphia streets are crowned, or sloped,in order to drain stormwater from the center ofthe street to the curb and then into drainageinlets at the downslope corner of each block.Similarly, sidewalks generally slope towards thestreet, allowing stormwater to drain to the curband into the same inlets. These corner inletsthen connect to a local collection system thatconnects to the larger, regional collection system.

    In a combined sewer system, which is commonin many older cities such as Philadelphia, thestormwater collection system handles bothstormwater and sewage in the same pipes. During

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    27/40

    The system envisioned for Spring GardenStreet would capture 126,000 cubic feetof stormwater falling over 1,008,000square feet, helping implement the CitysGreen City, Clean Waters plan. Thatsa surface area equivalent to 21 footballfields with the volume of approximately1 Olympic-size swimming pools!

    Green City, Clean Waters

    The benefits of building this new system are clear: the

    project would help prevent combined sewer overflow

    events that pollute Philadelphias rivers and cause

    flooding at the same time making Spring Garden

    one of the greenest, most livable streets in the city.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    28/40

    8

    Narrower travel lanes

    To accommodate the expanded median with abikeway and landscaped buffers, the width ofthrough travel lanes east of Broad Street would benarrowed from 12 feet to 10 or 11 feet, dependingthe presence of left-turn lanes. Reduced lanewidths have been shown to reduce vehicle speedsand improve safety. West of Broad Street, existing

    10- and 11-foot-wide lanes are maintained.

    Neckdowns

    Neckdowns would be provided at eachintersection along the corridor. These designfeatures would effectively reduce pedestriancrossing distances, reduce pedestrian exposureto vehicles, and slow the speed of turningvehicles. Turning radii remain sufficient to still

    allow larger vehicles to turn the street corners.

    Motor Vehicles

    Given that four travel lanes and nearly all left-turn lanes are maintained in the

    SGSG design, future motor vehicle operations on the corridor are similar to

    existing conditions. The project team, however, proposed a number of traffic

    calming treatments and signal modifications to improve safety on the street.

    Modifications affecting motorists include the following:

    Left-turn bay length

    In order to maximize the mid-block space for thelandscaped, above-grade bikeway, left-turn bays

    are shortened to the minimum length necessaryto accommodate peak volumes of left-turningvehicles. Preliminary analysis of five left-turn baysindicates that the turn bay lengths may generallybe reduced without negatively impacting trafficoperations. For instance, the westbound left-turnlane at 21st Street and the eastbound left-turn and at22nd street, both which are currently 200 feet, couldbe shortened to 105 feet and 125 feet respectivelybased on analysis of peak hour queue lengths.

    Motor Vehicles Bicycles Pedestrians BusesDesignFunctionality

    VI.

    A

    B

    C

    D

    A D

    B

    C

    Improved pedestrian crossing times

    The signal timing at each intersection would bemodified to provide the recommended pedestriancrossing time per the latest updates to the Manualon Uniform Traffic Control Devices (MUTCD), whichassumes an average walking speed of 3.5 feetper second. The signal cycle lengths along thecorridor would be increased at most intersectionsfrom 60 seconds to 90 seconds. For the streetsegment between Broad Street and 12th Street/Ridge Avenue, the cycle length would increase to120 seconds due to higher cross-street volumes,additional signal phases, and longer crossingtimes (existing cycle varies between 60 and 120

    seconds, depending on the intersection).

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    29/40

    Signal Progression

    Although a few intersections on SpringGarden Street are coordinated, currentlyit appears that the traffic signalsgenerally operate independently ofeach other and that the timing is notdesigned to minimize travel time orvehicle delay. SGSG will allow for signaltiming to be adjusted and coordinatedto improve the traffic flow and traveltimes on the corridor for both vehiclesand bicyclists. Signal timing makesit possible to travel through severalintersections without encountering a redlight. The signal coordination analysisfor SGSG is based on an assumedvehicle travel speed of 26 mph (thespeed limit on Spring Garden Street is

    25 mph) and a bicycle speed of 13 mph.

    Left-turn traffic signalization

    Left-turn signals generally operate with protected-permitted left-turn phasing. This means that vehicles can turn left from SpringGarden Street during one of two phases: (1) the protected phasein which motorists have a left-turn arrow, or (2) the subsequentphase in which they are permitted to turn left after yielding tooncoming through traffic once the turn arrow changes to a solidgreen light. With implementation of the median bikeway, theleft-turn phasing would be modified from protected-permittedto a protected left-turn phase in order to protect cyclistsfrom vehicles turning left across the bikeway. Bicyclists andopposing through traffic would stop while vehicles turn leftfrom Spring Garden Street, and eastbound and westboundleft-turning vehicles would be stopped when bicyclists andthrough traffic have a green light. Eliminating the permittedleft-turn phase results would delay left-turning vehicles, but

    at an acceptable level based on level of service standards.

    Parking

    The addition of neckdowns and near-side bus bulbs may result in a negligiblereduction in parking spaces alongthe corridor. There are approximately720 parking spaces on Spring GardenStreet and on the cross streets 50feet to the north and south. With theimplementation of SGSG, there wouldbe approximately 680 spaces. However,the parking supply can be increasedsomewhat by replacing traditionalparking meters with kiosks, whichallow for greater parking flexibility.

    Minor intersection closure/signalization

    To protect bicyclists from vehicles turning left across thebikeway, left turns by vehicles would be allowed at signalizedintersections only where they have a protected left-turnphase, as described previously. While almost all of the SpringGarden Street intersections are signalized, left turns arecurrently permitted from eastbound Spring Garden Street atfive unsignalized minor intersections east of Broad Street:Beach Street, Front Street, Hope Street, American Street,and Marshall Court. Under the proposed SGSG design, theFront Street intersection would be signalized and the leftturn maintained. At the other minor streets, the intersectionswould be closed to left-turning vehicles from eastbound

    Spring Garden Street, resulting in minimal traffic impact.

    E

    F

    G

    H

    F

    G

    H

    E

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    30/40

    0

    Bicycles

    Would use the bikewaysright-turn bay to position

    themselves away

    from the travel path of

    through bicyclists.

    Move to the bike box in the vehicle left-turn bay whenthe left-turn signal is red and the cross-street signal is

    green (i.e., not yellow). And then, when the left-turn signal

    is green, turn left in advance of left-turning vehicles.

    When the signal for Spring

    Garden Street turns red

    and the cross street turns

    green, bicyclists would

    use the bike box to move

    towards the sidewalk and

    complete their right turn

    onto the cross street.

    If the signal for through traffic on Spring Garden Street is

    green, move to the bicycle queue box within the intersection.

    When the cross-street signal turns green, complete the left

    turn by proceeding through the intersection. This movement

    is known as a two-stage left turn or a Copenhagen left.

    Bicyclists turning rightBicyclists turning left (Two Options)

    For bicyclists turning from the bikeway to a side street, the design includes

    several features to facilitate this movement:

    The SGSG project would widen the existing median of Spring Garden Street

    by removing the existing bike lanes and narrowing the vehicle travel lanes.

    The median would include a 10- to 12-foot-wide bikeway, separated fromadjacent travel lanes by five- to eight-foot-wide landscaped buffers or, on

    the blocks west of Broad Street with left-turn lanes, three-foot-wide striped

    buffers with flexible plastic posts.

    A B

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    31/40

    The SGSG design includes high visibility bicycle intersectionmarkings (chevrons and peg-a-traks) to facilitate bicyclistsmovement through the intersection and to alert motorists

    to watch for bicyclists within the intersection.

    There are a number of existing bicycle routes thatintersect Spring Garden Street at several cross streets,and additional cross-street bicycle routes are identifiedfor future implementation in the Citys bicycle masterplan. The SGSG design includes bicycle intersectionmarkings for these cross-street bicycle routes at ColumbusBoulevard/Delaware Avenue; 2nd, 5th, 6th, 11th, 13th,

    15th, 21st, and 22nd streets; and Ridge Avenue.

    A

    B

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    32/40

    2

    Pedestrians

    The SGSG design incorporates numerous features to

    improve the corridors appeal, comfort, and safety for

    pedestrians, including the following:

    High-visibility crosswalks to alertdrivers to be aware of pedestrians

    Relocation of vehicle stop bars to10 feet in advance of crosswalks toimprove pedestrian visibility and reduce

    vehicle encroachment into crosswalks

    Replacement of substandard, broken,or missing sidewalks and reconstructionof all corners to make them compliantwith the Americans with Disabilities Act

    Neckdowns would be provided at eachintersection along the corridor. Thesedesign features would effectively reducepedestrian crossing distances, reduce

    pedestrian exposure to vehicles, andslow the speed of turning vehicles.

    Pedestrian refuge islands east of Broad Street, where the streetis wider these islands are effectively median extensionsthat provide waiting space for pedestrians who may nothave time to fully cross the street in one signal phase

    Retiming of traffic signals to MUTCD pedestrian standards,described above (see Motor Vehicles section, page 28)

    New street trees and landscaping

    New lighting to improve safety and security forbusinesses, residents, motorists and greenway users

    In addition, the traffic calming effect of other elements in the design (narrowed travel lanes, expandedmedian, etc.) should reduce vehicle speeds. A pedestrians mortality risk in a crash increases exponentiallywith vehicle speed, and even a small vehicle speed reduction can significantly improve pedestrian safety.

    A

    E

    F

    B

    C

    D

    C G

    E

    A

    D

    B

    F

    H

    G

    H

    Crosswalks

    Vehicle Stop Bars

    Sidewalk Safety

    NeckdownsLandscape

    Lighting

    Traffic Signals

    Refuge Islands

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    33/40

    A

    B

    BA

    Buses

    SEPTA bus route 43follows the length of Spring Garden Street. Additionally,

    other bus routes travel on shorter segments of the street, with numerous

    routes crossing Spring Garden Street on intersecting streets. The SGSGdesign includes several design features intended to improve bus operations

    on the street.

    SEPTARoute43

    Currently, buses maneuver from the outside travel lane tocurbside bus stops. Many of the no-parking zones withinthe bus stops are too short for buses to properly accessthe bus stop. With the bus at an angle to the curb, ratherthan parallel to it, boarding and exiting the bus can be

    inconvenient, particularly for those with disabilities. It alsotakes time for buses to maneuver in and out of stops.

    Bus Bulbs

    To address these issues, the SGSG design includesbus bulbs at the bus stops along the corridor. Busbulbs effectively extend the sidewalk into the busstop/curbside parking lane, allowing buses to pullclose to the bus stop without maneuvering out ofthe travel lane. This speeds bus travel and allows forconvenient and efficient boarding and exiting of the

    bus, as the side of the bus is flush with the curb.

    As shown in the above figure, the bus bulbs arelocated at the existing bus stops on the near side of theintersection. While not included in the design due tostakeholder concerns, relocating the bus stops to thefar side is generally considered a best practice amongtransit planners and could improve bus operations byreducing bus delay at red lights. Bus stop consolidationcan further improve bus speeds by removing five lowridership stops of the 24 existing bus stops on SpringGarden Street at 6th, 9th, 13th, 18th, and 21st streets.

    Bus Lay-By Area

    As discussed previously, the SGSGdesign replaces the no parking/bus zone between 2nd and Frontstreets with a wider (10 foot)dedicated bus lane/bus lay-byarea. Bus activity is heavy at thislocation as it is a transfer point tothe Spring Garden Station of theSEPTA Market-Frankford Line.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    34/40

    4

    $5M

    $

    $10M

    $15M

    $20M

    HardC

    ost

    Traffic

    Control

    Concrete Curb

    & Sidewalk

    Lighting

    Stormwater

    Management

    Prep Work

    Resurfacing

    Street

    Street Trees

    & Furniture

    Traffic

    Signals

    Signage &

    Wayfinding

    $20.3M

    Implementation of SGSG would have a number of

    positive impacts on the surrounding neighborhood and

    the city. The project team conducted a detailed cost-

    benefit analysis, the results of which are summarizedhere. The benefits that are leveraged by this

    investment include the following:

    Increased employment and economic activity

    related to the construction of SGSG

    Real Estate Strategies (RES) estimated the economic impact of constructingSGSG using the Regional Input-Output Modeling System developed by theU.S. Department of Commerce Bureau of Economic Analysis. These benefitsrepresent an addition of nearly $40 million in economic activity, including $6million in earnings and the creation of 127 jobs during the construction period.

    Increased property values, real estate, and transfer tax revenues

    Several academic studies have documented increased property values associatedwith proximity to green space, streetscape improvements, and the installation ofimproved pedestrian and bicycle facilities. One of the most recent and rigorousanalyses was completed in 2006 by University of Pennsylvania researchersSusan Wachter and Kevin Gillen. Wachter and Gillen found that property valuesfor Philadelphia properties located adjacent to greenstreetscape improvements have values 28 percenthigher than similar parcels on unimproved streets.

    RES reviewed the September 2011 Office of PropertyAssessment (OPA) file of market and assessed valuation forthe 455 parcels fronting Spring Garden Street. Contiguousparcels under the same ownership as the parcel frontingSpring Garden Street were also included. The OPA marketvalue for all properties (taxable and tax-exempt) totaled$357.2 million. Applying the 28 percent premium to the OPAmarket values of these parcels results in the following:

    Increased real estate market value of more than $100 million

    Increased assessed valuation of $13.2 million based

    on current assessments of taxable real estate Increased annual real estate tax revenues (from

    taxable properties) of $1.25 million

    Increased total real estate transfer taxescollected from sales of property along SGSG,as a result of higher property sales prices

    This analysis only considers the impact on existingproperties. New development will add to the tax base aswell, subject to any tax abatement period in effect.

    The required capital investment to

    construct the preferred option is

    estimated to be $20,300,000.

    Annual maintenance costsare estimated to be $15,638.

    Costs &Benefts

    VII.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    35/40

    SoftCo

    sts

    Construction &Utility Contingency

    Construction

    Management

    Design &

    Permitting

    $10.4M

    Improved mobility and recreation

    and health benefits

    For each $1.00 invested in implementing SGSG,

    the project yields between $1.18 and $1.92 inimproved mobility and health benefits. Mobilitybenefits are quantified based on the premiumresearch shows bicycle commuters are willing topay for the opportunity to ride on protected bikelanes rather than riding on a street with no bicyclelanes and parallel-parked cars. Health benefits arequantified based on the median value of findingsfrom ten separate studies on the medical costs ofphysical inactivity. The model applies this figure tothe estimated number of new cyclists generatedby establishment of the bicycle facility. If recreationbenefits are added to the analysis, then the benefitgenerated for each $1.00 invested increases tobetween $3.42 and $25.18. Recreation benefits arecalculated based on the concept of implied valueof a recreational activity over and above the valueof time spent to take part in the activity. Universityof Minnesota researchers reviewed an extensivebody of literature on the economic value consumersascribe to many forms of outdoor recreation,including cycling. The values estimated in theliterature cluster around $10 per hour, and this is

    the figure used in the model, assuming one hourof cycling activity per day. The calculation is basedon the total of new cyclists less new commutersgenerated by the establishment of the bicycle facility.

    An improved real estate

    development environment

    The corridors development potential improvesthanks to increased property values, a morefunctional and attractive streetscape environment,

    and the opportunity for relief from stormwater feesand mitigation/retrofit costs potentially offered bythe stormwater management features of SGSG.The implementation of SGSG, in conjunctionwith the improving real estate market in the areassurrounding Center City Philadelphia, may spurdevelopment projects along Spring GardenStreet that have been on hold for years.

    Increased retail sales andsales tax receipts

    University of Pennsylvania researchers concluded

    that transformation of Spring Garden Street into aComplete Street would result in increased levelsof bicycle and pedestrian activity over currentconditions. The Penn Health Impact Assessment(HIA) cited studies of areas with improvedcycling and pedestrian facilities that found thatpeople who bike or walk to a business visit moreoften and spend more than those who drive.

    The Philadelphia City Planning Commission (PCPC)tracks 382 commercial corridors in Philadelphia.Four of the PCPC-defined commercial corridors

    would be impacted by implementation of SGSG: 20thand Green streets; 15th and Spring Garden streets;5th and Spring Garden streets, and 2nd Street andFairmount Avenue. An Econsult study indicatedthat these corridors had more than $30 million insales in 2005. Implementation of SGSG shouldresult in incremental sales above existing levels,particularly in those corridors east of Broad Street.

    The City of Philadelphia collects a 2 percent salestax on many retail items, and additional retail saleswill result in increased sales tax revenue to the City.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    36/40

    6

    Phase 1:Short Term Improvements & Final Design | 2 years

    The City of Philadelphia has designed bicycle and pedestrian improvements for the western end of SpringGarden Street from the Art Museum/Kelly Drive to the intersection of Spring Garden and 25th streets. Fundedin part by the William Penn Foundation through PEC, these improvements include new directional signage,bicycle lane striping, and pavement markings. These changes are expected in late 2013 or early 2014.

    On the east end of Spring Garden Street, DRWC is in the process of designing sidewalkimprovements on Spring Garden Street from 2nd Street to Delaware Avenue. Artist LeniSchwendinger has also been hired to design a light installation under I-95 to make theSEPTA Spring Garden Street Station a more inviting gateway to Northern Liberties and theDelaware River waterfront. DRWC will invest $2 million in these improvements in 2014.

    Amenities such as banners, new trees, bicycle parking, and other low-cost improvements are being discussed along the corridor.

    Finally, PEC and PWD are jointly applying for funding to produce final engineering designson a four-block section. These final designs will also yield detailed cost estimates that can beextrapolated across the corridor and provide a better sense of the total funding required.

    Year 1

    Phase 2:Public & Private Fundraising | 4 years

    SGSG will require investments from public agencies at the city, state, and federal level as wellas private sources. The Parks and Recreation Department has indicated willingness to plantnew trees for the corridor, and PWD is prepared to commit significant resources to installunderground stormwater retention basins as part of their Green City, Clean Waters program.

    In January 2013, PEC convened the Greenway Leadership Group (GLG). Composed ofbusiness owners, civic associations, and institutional leaders, the GLG represents a broadcoalition of stakeholders with a committed interest in seeing Spring Garden Street revitalized.The GLG meets on a quarterly basis to review progress and make strategic decisions abouthow to proceed with the project development. PEC provides staff support to the GLG.

    PEC and the GLG will be working with elected officials to place the project on the regions TransportationImprovement Plan, which makes it eligible for federal transportation funding. Grant applications to thePennsylvania Department of Conservation and Natural Resources and Department of Community andEconomic Development will be submitted. Project sponsors will also work with city council membersto place elements such as sidewalk repairs, lighting, and neckdowns in the Citys Capital ImprovementPlan. Grants will also be submitted to private foundations to supplement public funding streams.

    Year 4

    ImplementationVIII.

    SGSG will require investments from public agencies at the city, state, and

    federal level as well as private sources. By aligning investments already

    programmed for Spring Garden Street, such as street resurfacing and signal

    replacements, the overall project costs can be distributed among multiple

    agencies.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    37/40

    Relationship to Other Planning Efforts

    SGSG is not only a 2.1-mile river-to-river greenway, but also key component of other planning effortsto improve connectivity, mobility, accessibility, recreation, and open space and spur economicrevitalization in Philadelphia and the region. These include the following City initiatives:

    Trail Master Plan

    Callowhill - Chinatown North Strategic Plan

    Master Plan for the Central Delaware

    Green2015 Action Plan for parks, recreation, and open space

    Phase 3:Construction | 3 years

    SGSG could be constructed in two sections Delaware Avenue to Broad Street or Broad Streetto Pennsylvania Avenue however, significant cost savings can be generated by packaging theconstruction into one phase. The earliest construction is expected to begin is 2017 followingat least one year of final engineering design and permitting. While parking impacts would bekept to a minimum during the construction phase, there may be traffic delays on certain blocks

    where the median is being rebuilt. Additional community meetings and clear communicationto the public and property owners would be provided in advance of this phase.

    Year 5

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7

    Phase 1

    Phase 2

    Phase 3

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    38/40

    8

    Greenway Leadership Group

    Civic Associations

    Spring Garden Civic Association

    Logan Square Neighborhood Association

    West Poplar CommunityDevelopment Corporation

    Callowhill Neighborhood Association

    Northern Liberties Neighbors Association

    Non-Profit & Cultural Institutions

    Community College of Philadelphia

    Spring Garden Senior Center Advisory Council

    Bicycle Coalition of Greater Philadelphia

    East Coast Greenway Alliance

    Government

    National Park Service Edgar Allan Poe House

    Business

    Thomson Reuters

    Stantec

    Finnigans Wake

    The Greenway Leadership Group (GLG) is a partnership among public, private, andnon-profit organizations working to make the Spring Garden Street Greenway a reality.

    Please reach out to PEC to learn how your organization can be involved.

    For a complete list of supporters, go to the project website: www.SpringGardenStreetGreenway.com

    SupportersIX.

  • 7/29/2019 Philadelphias Spring Garden St. Greenway Master Plan

    39/40

    SUPPORT THE SPRING GARDENSTREET GREENWAY PROJECT

    LIKE US ON FACEBOOKStay informed about promotional events and project updates at

    SEND A LETTER OF SUPPORTWrite to Deputy Mayor Rina Cutler announcing your organizations official endorsement of the project

    ATTEND A PUBLIC MEETINGSign up at to receive email updates on upcoming events

    MAP YOUR THOUGHTSGo to to Map Your Thoughts to share place-specific insights

    GIVE US A CALL!Want to contact us directly to offer support for the project or just to voice your opinion?Contact the Pennsylvania Environmental Council at (215) 545-4570.

    facebook.com/SpringGardenStreetGreenway

    SpringGardenStreetGreenway.com

    SpringGardenStreetGreenway.comSpringGardenStreetGreenway.com