RENCANA ANGGARAN BIAYA PENGUKURAN JALAN TANI DAN JARINGAN IRIGASI KABUPATEN LUWU UTARA - PROVINSI SULAWESI SELATAN I. BIAYA LANGSUNG PERSONIL ITEMS UNIT VOL A. Tenaga Ahli Team Leader prsn 1 5 300,000.00 Operator Alat Ukur prsn 1 5 200,000.00 Drafter prsn 1 1 ### 3 B. Tenaga Pendukung Tenaga Lokal (Helper) prsn 2 5 75,000.00 Sopir prsn 1 5 100,000.00 3 Sub Total A II. BIAYA LANGSUNG NON PERSONIL ITEMS UNIT VOL Unit Cost A. Sewa Alat GPS Garmin 76 Csx Unit 1 5 50,000.00 Total Station Set 1 5 350,000.00 B. Transportasi Mobilisasi Team Return-Prsn 2 2 200,000.00 Transportation Lokal Unit 1 5 200,000.00 Bensin Ltr 10 5 7,500.00 C. Akomodasi dan Konsumsi Konsumsi Orang/Hari 4 5 50,000.00 Penginapan Return-Prsn 1 5 200,000.00 D. Gambar Gambar dan Print Doc 1 - 500,000 Sub Total B TOTAL COST (I+II) IDR Durasi (hari) Harga Satuan (IDR) Duration (day)

Pengukuran Jalan Tani Dan Irigasi Tersier Rab

  • Upload
    alan

  • View
    663

  • Download
    25

Embed Size (px)

DESCRIPTION

pengukuran

Citation preview

Page 1: Pengukuran Jalan Tani Dan Irigasi Tersier Rab

RENCANA ANGGARAN BIAYAPENGUKURAN JALAN TANI DAN JARINGAN IRIGASI

KABUPATEN LUWU UTARA - PROVINSI SULAWESI SELATAN

I. BIAYA LANGSUNG PERSONIL

ITEMS UNIT VOL TOTAL COST

A. Tenaga AhliTeam Leader prsn 1 5 300,000.00 1,500,000.00Operator Alat Ukur prsn 1 5 200,000.00 1,000,000.00Drafter prsn 1 1 ### 2,000,000.00

3 4,500,000.00B. Tenaga Pendukung

Tenaga Lokal (Helper) prsn 2 5 75,000.00 750,000.00Sopir prsn 1 5 100,000.00 500,000.00

3 1,250,000.00

Sub Total A 5,750,000.00

II. BIAYA LANGSUNG NON PERSONIL

ITEMS UNIT VOL Unit Cost TOTAL COST

A. Sewa AlatGPS Garmin 76 Csx Unit 1 5 50,000.00 250,000.00Total Station Set 1 5 350,000.00 1,750,000.00

2,000,000.00B. Transportasi

Mobilisasi Team Return-Prsn 2 2 200,000.00 800,000.00Transportation Lokal Unit 1 5 200,000.00 1,000,000.00Bensin Ltr 10 5 7,500.00 375,000.00

2,175,000.00C. Akomodasi dan Konsumsi

Konsumsi Orang/Hari 4 5 50,000.00 1,000,000.00Penginapan Return-Prsn 1 5 200,000.00 1,000,000.00

2,000,000.00

D. GambarGambar dan Print Doc 1 - 500,000 500,000.00

500,000.00

Sub Total B 6,675,000.00

TOTAL COST (I+II) IDR 12,425,000.00

Durasi (hari)

Harga Satuan (IDR)