29
PAVEMENT CONDITION INDEX METHOD compiled by Basil David Daniel Main Reference: M.Y. Shahin, Pavement Management for Airports, Roads and Parking Lots, Springer, New York, 2005

Pavement Condition Index

Embed Size (px)

Citation preview

Page 1: Pavement Condition Index

PAVEMENT CONDITION INDEX

METHOD

compiled by Basil David Daniel

Main Reference:

M.Y. Shahin, Pavement Management for Airports, Roads and Parking Lots, Springer, New York, 2005

Page 2: Pavement Condition Index

Pavement Condition Index (PCI) Method

Background

The Pavement Condition Index (PCI) method is used to obtain a Pavement Condition Index

(PCI) value for pavements through a visual survey of the pavement. The Pavement Condition

Index (PCI) is a numerical rating of the pavement condition that ranges from 0 to 100 (refer

to Figure 1), with 0 being the worst possible condition and 100 being the best possible

condition. The Pavement Condition Index (PCI) method was developed by the Construction

Engineering Research Laboratory of the U.S. Army Corps of Engineers. This method can be

used on both asphalt surfaced as well as jointed portland cement concrete (PCC) pavements.

Figure 1: Pavement Condition Index (PCI) Rating Scale and the corresponding Level of

Service and Maintenance Activity

Performing a Pavement Condition Survey on Asphalt Surfaced Pavements

Equipment: Inspectors need a hand odometer or measuring tape to measure distress lengths

and areas, a straight edge, a ruler to measure the depth of ruts or depressions, and the PCI

distress manual (to assist in identifying distresses and determining their severity levels).

Procedure: A sample unit is inspected by measuring the distress type and severity according

to the PCI distress manual, and recording the data on the flexible pavement survey sheet (as

shown in Figure 2). One data sheet is used for each sample unit.

Page 3: Pavement Condition Index

Figure 2: Pavement Condition Survey Sheet

Page 4: Pavement Condition Index

Dividing a Pavement Section Into Sample Units

A sample unit is defined as the portion of pavement section designated only for the purpose

of pavement inspection. Figure 3 shows an example of sample units.

Figure 3: Example of a pavement section divided into sample units

The number of sample units in a pavement section to be inspected can be determined using

Figure 4. When performing initial inspection, the PCI standard deviation for asphalt concrete

is assumed to be 10.

Figure 4: Selection of the minimum number of sample units

Pavement Section 6.5 m x 780 m

100 m 100 m 100 m 100 m 100 m 100 m 100 m 80 m

1 2 3 4 5 6 7 8

Page 5: Pavement Condition Index

14 15 17 18 19 20

It is recommended that the sample units to be inspected be spaced equally throughout the

section, and that the first one be chosen at random (this technique is known as ‘systematic

random’). Sampling interval is determined using the following equation:

Interval, i = n

N where N = total number of sample units in section

n = minimum number of sample units to be inspected

The sampling interval is rounded off to the smaller whole number (e.g. 3.6 is rounded to 3).

Example:

If N = 20,

n = 9 (determined from Figure 4)

Interval, i = 20/9 = 2.2 ≈ 2.0

Hence sample units to be inspected are 1, 3, 5, 7, 9, 11, 13, 15 and 17 (as indicated in Figure

5).

Figure 5: Sampling interval

1 2 3 4 5 6 7 8 9 10 11 12 13 16

Page 6: Pavement Condition Index
Page 7: Pavement Condition Index
Page 8: Pavement Condition Index
Page 9: Pavement Condition Index
Page 10: Pavement Condition Index
Page 11: Pavement Condition Index
Page 12: Pavement Condition Index
Page 13: Pavement Condition Index

Example

The table below shows a pavement condition survey for sample unit 07, section JPB-KM2 of

Jalan Parit Botak. Determine the Pavement Condition Index for this sample unit.

JALAN PARIT BOTAK (ASPHALT SURFACED ROAD)

CONDITION SURVEY DATA SHEET

BRANCH: TRAFFIC LABORATORY UTHM DATE: 25 AUGUST 2007

SURVEYED BY: BDD SAMPLE UNIT: 07

SECTION: JPB-KM2 SAMPLE AREA: 6 m x 100 m

01. Alligator Cracking (m2)

02. Bleeding (m2)

03. Block Cracking (m2)

04. Bumps and Sags (m) 05. Corrugation (m

2)

06. Depression (m2)

07. Edge Cracking (m) 08. Joint Reflection Cracking (m) 09. Lane/Shoulder Drop Off (m) 10. Longitudinal & Transverse Cracking (m)

11. Patching & Utility Cut Patching ((m

2)

12. Polished Aggregate (m

2)

13. Potholes (no.) 14. Railroad Crossing (m

2)

15. Rutting (m2)

16. Shoving (m2)

17. Slippage Cracking (m

2)

18. Swell (m2)

19. Weathering/ Ravelling (m

2)

DISTRESS SURVEY

QUANTITY TOTAL DENSITY

% DEDUCT VALUE

03 M 7.8 4.1

01 L 2.5 4.2 1.8

01 H 6.3

11 M 3.1 0.4

13 M 0.5 0.8

10 L 0.8 1.2 0.3 0.5

10 M 0.7 1.1 0.4

Page 14: Pavement Condition Index

Solution:

(1) Determine the Distress Density and Deduct Value

DISTRESS SURVEY

QUANTITY TOTAL DENSITY

% DEDUCT VALUE

03 M 7.8 4.1 11.9

100*(11.9/600)

= 1.98 6

01 L 2.5 4.2 1.8 8.5

100*(8.5/600)

= 1.42 13

01 H 6.3 6.3

100*(6.3/600)

= 1.05 32

11 M 3.1 0.4 3.5

100*(3.5/600)

= 0.58 7

13 M 0.5 0.8 1.3

100*(1.3/600)

= 0.22 50

10 L 0.8 1.2 0.3 0.5 2.8

100*(2.8/100)

= 2.80 2

10 M 0.7 1.1 0.4 2.2

100*(2.2/100)

= 2.20 6

(2) Maximum allowable number of deducts, m

Highest deduct value, HDV = 50

m = 1 + (9/98)(100 – HDV)

= 1 + (9/98)(100 – 50)

= 5.6

Deduct values in descending order: 50, 32, 13, 7, 6, 6, 2

Number of deduct values = 7

Since the maximum allowable number of deducts is 5.6, therefore only the first 5 and 0.6 of

the 6th

deduct value are selected, i.e. 50, 32, 13, 7, 6, and 0.6*6 = 3.6.

(3) Maximum corrected deduct value, CDV

Number of deduct values greater than 2, q = 6

Total deduct value = 50 + 32 + 13 + 7 + 6 + 3.6 = 111.6

From Figure B-45, CDV = 58

Reduce the smallest individual deduct value to 2 (q is now 5) and determine the CDV.

Repeat until q reaches 1.

Page 15: Pavement Condition Index

No. Deduct Values Total q CDV

1

50 32 13 7 6 3.6 111.6 6 58

2

50 32 13 7 6 2 110 5 58

3

50 32 13 7 2 2 106 4 61

4

50 32 13 2 2 2 101 3 65

5

50 32 2 2 2 2 90 2 63

6

50 2 2 2 2 2 60 1 60

7

8

9

10

Maximum CDV = 65

(4) Determine the Pavement Condition Index

PCI = 100 – CDVmax

= 100 – 65

= 35

Based on the rating for PCI value of 35, this section of pavement is in very poor condition.

Page 16: Pavement Condition Index

APPENDIX

Asphalt Concrete Roads: Deduct Value and

Corrected Deduct Value Curves

Page 17: Pavement Condition Index
Page 18: Pavement Condition Index
Page 19: Pavement Condition Index
Page 20: Pavement Condition Index
Page 21: Pavement Condition Index
Page 22: Pavement Condition Index
Page 23: Pavement Condition Index
Page 24: Pavement Condition Index
Page 25: Pavement Condition Index
Page 26: Pavement Condition Index
Page 27: Pavement Condition Index
Page 28: Pavement Condition Index
Page 29: Pavement Condition Index