GPEC

Global Delivery Readiness

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

1830 PSS 32/16 System Turn Up and Commissioning 4 May 2012

Release 5.0

Page 2: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Module Outline

Part 4 - System Turn Up and Commissioning

1. System Provisioning

1. Establish connection to the network

2. Connect outside plant fiber

3. DCU Adjustment

2. Commissioning

3. Verifications and Backup

Page 3: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning System Provisioning

Establish connection to the network

Page 4: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Starting 1354 RM-PhM

Make sure services are started (apache ftp, MySQL, PhM…)

1. Start the 1354 RM-PhM application on your PC.

2. Click the “Change Server/Port”

3. Enter the IP address of your PC(localhost) in the Server, or the server

provided for Management.

User name and Password: If this is your first time logging in, the User

name is admin and Password is tropxnms. You will then be required to

change the password. (exple:tr0pxnms)

Page 5: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Establish connection to the network

This procedure will establish connection to the network and discover all the

network elements.

Refer to your 1830 PSS-32/16 Installation Guide, Part IV, Chapter 10, and perform

“Establish connection to the network” procedure.

Connect the Line Fiber to the NE’s of the Network

Connect the craft terminal to CIT port of the EC board

1. Change the CIT IP address to a unique subnet within the entire DCN

2. Start the 1354 RM-PhM

3. select Maintenance /Auto Discovery/ “Auto Discovery by IP”

4. Select File /New NE/ create network element with CIT IP address

Additional network elements will being appearing in the map view.

Page 6: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Connecting local 1354 RM-PhM throughout the Network via CIT port

While connecting through the CIT port of the EC board, the CIT IP address should be modify so as to be able to reach the next NEs in the network. The purpose is to change the CIT IP address on which you are connected to a unique subnet within the entire DCN. In CLI type: config interface ec cit ip 172.16.2.1/24 Re-connect to CLI: config int ec cit red enable

You are then able to establish connection with all NE of the Network.

NE 1 NE 2 NE 3

172.16.2.1/24 172.16.0.1/24 172.16.0.1/24

Local (craft Terminal) 1354 RM-PhM

OK

CIT IP

NE 1 NE 2 NE 3

172.16.0.1/24 172.16.2.1/24 172.16.0.1/24

Local (craft Terminal) 1354 RM-PhM

NOK

CIT IP

NE 1 NE 2 NE 3

172.16.11.1/24 172.16.12.1/24 172.16.13.1/24

Local (craft Terminal) 1354 RM-PhM

CIT IP

OK

At the end of the operation on this NE, you may change the CIT IP address back to its default (172.16.0.1)

However, during the deployment process, you may be willing to connect your local 1354 RM-PhM to another site. You may then perform the same steps and meet this configuration.

The 1354 RM-PhM has already allocated the CIT address to NE1 in its database and it will encounter a conflict.

Hence it is recommended, during the time of the deployment, to modify the CIT IP address of every NE of the network by defining a unique subnet for every NE, as shown:

You will then be able to connect you local 1354 RM-PhM to any site.

Observed with1354 RM-PhM R7.x

Page 7: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning System Provisioning

Connect outside plant fiber

Page 8: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up steps

CPB Provision using Plan

Greenfield Connect outside plant fiber

System Type ?

TOADM RING

system

Establish Network

Connection

NE provisionning

Yes

Unkeyed Och System?

No

specific

Line with External Raman Pump ?

Yes

No

Set LD Power Managment type to Manual Mode

FOADM only System ? No

Yes

Do not perform Greenfield

Wizard

Execute Greenfield using Plan

Line with External Raman Pump ?

Yes

No

Set LD Power Managment type to Auto Mode

Delete service- Power

Commissioning END

TOADM LINEAR System / Mixed FOADM

Provision required Wavelength Service

Power A-Z & Z-A Adjustment

Is the Status of all LD in the system « completed »

?

Adjust Un-completed EGRESS and

INGRESS points

No

Yes

Applied to: •Terminal end EGRESS

•Neighbour to Terminal INGRESS

To be discussed

Page 9: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Connect outside plant fiber

Span loss calculation should be as close as possible from the minimum Loss given

in EPT file

The EPT file will be updated if calculation does not match the actual loss !

Note:

The OSC span loss calculation in not a Fiber Optic Characterisation.

Remind that additional loss might be introduced within the head of the Line Cable and

the NE (such as bad connectors, dirty fibers, ODF Insertion loss, etc…)

NE2 NE1

LD

OSC

LD

OSC

Span loss= OPT NE1 –OPR NE2

Span loss= OPT NE2 –OPR NE1

NE side NE side LINE

Page 10: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Connect outside plant fiber

This procedure will connect the outside plant fiber to the ingress and

egress LD circuit packs on the Alcatel-Lucent 1830 PSS-32/PSS-16. The

fiber loss will be checked and proper connectivity verified. Refer to your 1830 PSS-32/16 Installation Guide, Part ///, Chapter 9, and perform

“Connect outside plant fiber” procedure.

1. Connect the outside plant fibers to the appropriate LINE ports

2. From WebUi, select the OSC port of an LD pack facing a line that has been

connected at the neighbor node

3. Select: Performance / Clear bins

4. Select: Performance / PM Group / OPT

5. Select: Performance / PM Group / OPR

6. Repeat for each of the lines as they are connected to the neighbor nodes.

7. Calculate the span loss. These values should be provided to the EPT owner to

compare with the EPT span loss

Page 11: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Commissioning

DCU Adjustment

Page 12: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning

DCU Adjustment The DCU is provided with an attenuator to pad out the loss to 10 dB for use with

legacy amplifiers that require 10 dB mid-stage loss

If a double DCU, or different DCU has to be installed, make the adjustment of interstage with a Power Meter so as to get 10dB attenuation.

Note: Modulare Amplifier AM2125A & B

Modular Amplifier with low loss DCM have a mid-stage attenuation of 4dB

DCM bypass does not require an attenuator

Line Driver

SIG

Mid-stage LOSS

min 9 db

Max 11 dB

xdB PAD

Mid stage LOSS = DCU Loss +

PAD + connector loss

measure 10+/-1 dB attenuation with Power Meter

LINE

DCU 2 DCU1

Page 13: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Module Outline

Part 4 - System Turn Up and Commissionning

1. System Provisioning

2. Commissioning

NE Provisioning

Power Commissioning on TOADM Ring System

Commission a TOADM linear system

Provision New Wavelength Services

Complete commissioning on TOADM Linear System

Commission a FOADM linear system

3. Verifications and Backup

Page 14: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Commissioning

NE Provisioning

Page 15: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Preconditioning

This procedure will ensure that the network and PC are ready for commissioning

using the 1354 RM-PhM.

1. Ensure that all the outside plant fibers (or test set) have been properly

connected to the correct line driver cards on each network element.

2. Verify one pair of OT cards is installed and fibered on the end terminals for a

TOADM system.

3. Obtain the loop back IP addresses of all the NE’s in the network.

4. Determine which NE in the network will be used as the connection

commissioning process, as directed by your instructor. Obtain the OAMP port

IP address.

5. Obtain the xml commissioning file produced by EPT and used for

commissioning.

6. Ensure that both the client and server 1354 RM-PhM software has been

installed on the PC. Refer to the 1354 RM-PhM Photonic Manager EMS

Reference Guide for detailed procedures on installing and configuring the

software.

Page 16: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Provision the system

This procedure will provision the cards, power attributes and topological links for all the NE’s in a system as defined in the EPT output file.

Refer to your 1830 PSS-32/16 Installation Guide, Part IV, Chapter 10, and perform “Provision the system” procedure.

1. From PhM / Provision -> Launch CPB

2. Type the 1354 RM-PhM user name and password

3. Select Commissioning -> Provision System (using plan)

4. Select NE (one or several)

5. Next/Next/ then “Browse” button and browse to the folder containing the EPT commissioning file for the system to be commissioned

Review the error report and troubleshoot any problems encountered.

Page 17: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Provision the system (continue)

Provisioning Steps:

1. validates any existing card slot assignments.

2. provisions topological links for NEs.

3. preprovisions any required cards defined in the plan (optional).

4. provisions non-OT cards admin states to "up" (optional).

5. provisions Optical Power Level Management (optional).

Page 18: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Provision the system (continue)

validates any existing card slot

assignments.

provisions topological links for NEs.

View from WebUI:

Connection / Physical Topology

•Port highlighted in blue are admin up •Green logo underneath indicate connection •Click on the port to check its connection

Page 19: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Provision the system (continue)

provisions Optical Power Level Management

Line driver SIG port detail:

• Default values before provisionning

• LD values provisionned

Page 20: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Provision the system (continue)

provisions Optical Power Level Management (optional).

• Default values before provisionning

Note that Commissioned status is IN PROGRESS

Page 21: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Commissioning

Power Commissioning on TOADM Ring System

Page 22: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Power Commissioning of a TOADM Ring System

The Power Commissioning of a Linear System requires to perform the

power adjustement using the CPB/ Greenfield Wizard.

1. Perform System Provisioning

2. Perform Greenfield using Plan

For a Ring System, all Line Drivers adjustment will be in state

completed after the process.

TOADM RING System

LD

LD

Thru

A

A

LD

CW

R8

LD

CW

R8

Thru

A A LD

CWR8

LD

CWR8

Thru

A

A A

LD

CW

R8

LD

CW

R8

Thru

A

CWR8

CWR8

Page 23: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Thru LD

CWR8

OMD CLS

CWR-8 LD

OMD CLS

LD

CW

R-8

LD

OM

D C

LS

ASE

1 2 3

Thru

CWR8

OMD CLS

CWR-8 LD

OMD CLS

Adjustment

Completed

EGRESS

Adjustment

completed

Light emitting

INGRESS

Adjustment

completed

4 5 EGRESS

Adjustment

completed

6

7 INGRESS

Adjustment

completed

Adjustment

Completed 8

1. In A to Z direction, LD emit light (ASE) toward Egress LD through CWR. 2. EGRESS point is adjusted. 3. Next NE receive Light INGRESS point is adjusted. 4. In Z to A direction, LD emit light (ASE) toward Egress LD through CWR. 5. EGRESS point is adjusted. 6. The LD adjustement is completed 7. Next NE receive Light INGRESS point is adjusted. 8. The LD adjustement is completed 9. Process is applied on every span.

A to Z

Z to A

Power Commissioning of a TOADM Ring System CPB tool - Greenfield

Page 24: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Commissioning

Commission a TOADM linear system

Page 25: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Commission a TOADM Linear System

The auto managed lines on a linear system adjacent to the terminal sites as well as the terminal sites themselves will not complete using the commissioning wizard. Those lines must have further power adjustments to complete commissioning.

Identify the two terminal nodes and their immediate neighbors in the linear system. These four nodes have lines that will need power adjustments.

A service must be created to complete the commissioning on these nodes

LD

CW

R8

LD

CW

R8

Thru

LD

CW

R8

LD

CW

R8

Thru

LD

CW

R8

LD

CW

R8

LD

CW

R8

Thru

A

1

A A A LD

CW

R8 A A A

2 3 4

A

Service Service

Page 26: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

LD

Commission a TOADM Linear System Greenfield

Perform GREENFIELD using Plan:

1. Intermediate spans are adjusted with ASE

2. LD neighbours of Line Terminal are partially adjusted

3. No Emitting light can achieve the adjustment

4. The LD adjustment at End Terminal & neighbours is skipped

A service must be created to complete adjustment

CWR-8

OMD CLS

1

2

3

LD Thru

CWR8

OMD CLS

CWR-8 LD

OMD CLS

CWR-8 LD

OMD CLS

LD Thru

CWR8

OMD CLS

CWR-8 LD

OMD CLS

EN

D T

ER

MIN

AL

E

ND

TE

RM

INA

L

NE A NE B

NE C NE Z

Adjustment

completed

EGRESS

completed

Adjustment

completed

2

EGRESS

completed

INGRESS

completed

INGRESS

completed

3

Page 27: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

EN

D T

ER

MIN

AL

LD

Commission a TOADM Linear System complete Commissioning

Completing commissioning: 1. Create a service between A and Z NE and run Power Management 2. Adjust Egress Power 3. Terminal A EGRESS LD is adjusted and LD completed 4. Adjust Ingress Power 5. Next INGRESS point is adjusted and LD completed 6. Repeat steps for Z to A direction (NE Z and NE C)

A to Z

CWR-8

OMD CLS

1

2

3

4

LD Thru

CWR8

OMD CLS

CWR-8 LD

OMD CLS

5

CWR-8 LD

OMD CLS

LD Thru

CWR8

OMD CLS

CWR-8 LD

OMD CLS

EN

D T

ER

MIN

AL

NE A NE B

NE C NE Z

Z to A

EGRESS

completed

Adjustment

completed

INGRESS

completed

Adjustment

completed

6

EGRESS

completed

Adjustment

completed

INGRESS

completed

Adjustment

completed

commission Greenfield system

Page 28: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Power Commissioning

This procedure will perform power commissioning on the network using

parameters provided by the EPT output file.

1. Lauch CPB

2. Execute Commission Greenfield system using plan

3. Check if the process has been achieved successfully: check the

warning message in the logs.

4. Proceed to View Report and check the presence of errors

5. Check the Commissioning Status of Amplifiers :

1. Select Line port of Ingress amplifier

2. Select Power adjustment Tab

3. Check if Status is Completed or In progress

4. On PhM, select Line port of the Ingress LD and check Power commissioning

mngt

5. True means complteted/false for in progress..

6. Proceed to Power Balancing to achieve commissioning

Page 29: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Commissioning

Provision New Wavelength Services

Page 30: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Provision New Wavelength Services With 1354 RM-PhM

Use this procedure to establish a new wavelength service.

1. Double Click the NE from the Network Map to enter the Inventory View.

2. Branch the Equipment Tree down to view the cards.

3. Highlight the Transponder Network Port and in the Right Side Pane set the Programmed ITU Channel and then click Apply.

4. Right Click on the Transponder Network Port and set it to Admin Up AINS.

5. Right Click on the Transponder Client Port and set it to Assigned.

6. Set the Client Signal Type if required.

7. Right Click on the Transponder Client Port and set the Signal Timeslot if required.

8. Right Click on the Transponder Client Port and set it to Admin Up AINS.

9. Exit the Inventory Window and return to the Network Map.

10. Highlight the NE and click on the Topology Button on the Tool Bar.

11. Create the Transponder Line Port Topology Link to either a Filter Port or a Colorless Port as required.

12. Exit the Topology Window and return to the Network Map.

Page 31: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Provision New Wavelength Services (continue) With 1354 RM-PhM

Use this procedure to establish a new wavelength service.

13. Highlight both Nodes that are end points for the new Wavelength Service and then go to Provisioning and Provision New Wavelength Service.

14. Enter all of the necessary information for the new wavelength service and create it.

15. Check Force cross-connection

16. Verify both A to Z and Z to A directions of the circuit through Wave Tracker and enable the 10 second auto refresh function.

17. When both directions are all green, a test set can be setup at one client port end and a fiber loop at the other client port end to perform the Error Free Testing – observe optical TX and RX levels and install attenuators as needed.

18. Capture the test results from the test set as proof of the Error Free Tests.

Page 32: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Commissioning

Complete commissioning on TOADM Linear System

Page 33: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Power Commissioning Complete Commissioning

1. Lauch CPB

2. One wavelength has been created through the system

3. Execute Power Balance System using plan

4. Check if the process has been achieved successfully: check the

warning message in the logs.

5. Proceed to View Report and check the presence of errors

Page 34: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Commissioning

Commission a FOADM linear system

Page 35: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Commission a FOADM System

This procedure will verify the “Commission Greenfield System wizard” procedure

completed successfully for each NE in the FOADM linear system.

1. Refer to your 1830 PSS-32/16 Installation Guide, Part IV, Chapter 10, and

perform “Commission a FOADM system” procedure.

LD

SFD

LD SFD

PAD

Thru

LD SFD

LD

SFD

LD SFD

PAD

Thru

LD

SFD

Thru Band Thru Band

NE 1 A

1 NE 2

M

M

2

3 NE 4

A

4 NE 3

M

M

2

3

Service

Page 36: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Manual Power Adjustment All Line Drivers in Manual Mode

Adjust OT Power Z-bar to mid range

Adjust INGRESS LD

Gain

until ch. Level is green within the Z-bar at LD EGRESS point

Adjust EGRESS LD

(OT Tx)

Measure Power at the Ingress SIG

OUT port

Calculate delta between actual and expected

value

Add delta to Power Gain value

until ch. Level is in the middle of Z-bar at SIG OUT point

Adjust EGRESS LD (Add PAD)

Measure Power at the EGRESS LD

OUT port

Calculate delta between actual and expected

value

Add PAD of the delta value

until ch. Level is green within the Z-

bar at LD EGRESS point

1 2 4 3

Adjust INGRESS LD

Gain

Measure Power at the Ingress SIG

OUT port

Calculate delta between actual and expected

value

Add delta to Power Gain value

5

Synchronize Wave Key expected

Power

Repeat steps for Z to A

Power Adjustment

until ch. Level is green within the Z-bar at LD EGRESS point

NE 1

Service

M

A to Z

1 NE 2

M

M

2

3 NE 3

M

4

PAD

Page 37: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Commission a System Case of double amplification

LD Power Management in FOADM Linear System with double Amplification

SFD

SFD

PAD

Thru

SFD

PAD

SFD

Thru Band Thru Band

NE 1 A

NE 2 M

A NE 5

A NE 3

A

M

LD LD

LD LD

LD LD

LD LD

LD LD

LD LD

SFD

SFD

LD

LD

LD

LD

A

A NE 4 ILA

Page 38: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Complete Commissionning steps

Provisionn the required wavelength

service

Power A-Z managment

Manually adjust OT output Power

Is the first NE in signal path AUTO

Managed ?

Yes No

Execute Power control EGRESS

Egress point adjusted

Is the INGRESS Line of next NE AUTO

Managed ?

Yes No

Execute Power control INGRESS

Manually Adjust INGRESS LD Gain Power

Adjust EGRESS LD

with upstream PAD

Execute Power control EGRESS

Is the EGRESS Line of same NE AUTO

Managed ?

No Yes

Egress point adjusted

Ingress point adjusted

Is the INGRESS Line of next NE ending

the path?

No

Is the INGRESS Line of last NE AUTO

Managed ?

Yes No

Execute Power control INGRESS

Ingress point adjusted

Adjust INGRESS LD Gain Power

Power Z-A managment

END Delete Wavelength

service

1

2

3

4

Check all LD status are completed

(commissioning flag set to true)

Page 39: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

FOADM End Terminal - Commissionning

1. OA provisioned , parameters before Greenfield

Power Management attributes

Gain adj checked

Power / channel not checked

Identical for TOADM

Page 40: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Module Outline

Part 4 - System Turn Up and Commissioning

1. System Provisioning

2. Commissioning

3. Verifications and Backup

understanding Loss Report

Wavelength Tracker

Perform Backup with PhM

Perform Backup with WebUi

Page 41: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Verification and Backup

Understanding Loss Report

Page 42: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Generating and Understanding the Loss Report

Refer to your 1830 PSS-32/16 Installation Guide, Part IV, Chapter 10, and review

the sample loss report “Generate and review network element loss report” and

“Understanding the loss report” procedures.

Pre requisite: complete provisioning of the EPT parameters for the

target system (Provision System using plan)

1. From CPB: Commissioning /Create System Loss Report (using plan)...

2. Follow instruction/Next>” button until the system loss report stages

window will display Minimum EPT parameters for network element

EPT Commissioning Parameter

Tag in planning tool commissioning

.xml file Applicable Port

LD Gmin AmpMinGain LD Sig Out

LD Gmax AmpMaxGain LD Sig Out

Ingress LD target output power TargetOutputPower LD Sig Out

Ingress LD power deviation out DeviationOut LD Sig Out

Egress target output power TargetOutputPower LD Line Out

Egress power deviation out DeviationOut LD Line Out

Page 43: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Wavelength Tracker – Coding Example

Page 44: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Generating and Understanding the Loss Report

Launch CPB / Commissioning / Create system loss report (using plan…)

Span Margin + connecto loss

Span Loss from design

CWR-8 1/8

LD

PSS32-5

SFD ALPHG

1/6

LD

AHPHG

1/7

Thru CWR-8 1/8 LD

LD CWR-8 1/4 LD

PSS32-6

AHPHG

1/3

ALPHG

1/2

ALPHG

1/6

LD

DCM 50

18.6 dB

17.9 dB

75km

AHPHG

1/7

LIN

E

SIG

LIN

E

LIN

E

SIG

LIN

E

Page 45: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Generating and Understanding the Loss Report

CWR-8 1/8

LD

PSS32-5

SFD ALPHG

1/6

LD

AHPHG

1/7

Thru CWR-8 1/8 LD

LD CWR-8 1/4 LD

PSS32-6

AHPHG

1/3

ALPHG

1/2

ALPHG

1/6

LD

DCU 50

18.6 dB

17.9 dB

75km

AHPHG

1/7

LIN

E

SIG

LIN

E

LIN

E

SIG

LIN

E

Page 46: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Generating and Understanding the Loss Report

CWR-8 1/8

LD

PSS32-5

SFD ALPHG

1/6

LD

AHPHG

1/7

Thru CWR-8 1/8 LD

LD CWR-8 1/4 LD

PSS32-6

AHPHG

1/3

ALPHG

1/2

ALPHG

1/6

LD

DCM 50

18.6 dB

17.9 dB

75km

AHPHG

1/7

LIN

E

SIG

LIN

E

LIN

E

SIG

LIN

E

LIN

E

SIG

LIN

E

75km

Page 47: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Failed Adjustment (Examples)

Refer to your 1830 PSS-32/16 Installation Guide, Part IV, Chapter 10, and review the sample loss report “Troubleshooting failed Adjustment”.

no through services provisioned: 1. Provision at least one present wavelength on the through path.

2. Re-try adjustment.

loss too high (ingress adjustment) 1. Identify the source of the excess loss using the loss report

2. If the span loss is too high, perform the following sub steps and re-try the adjustment after each step. If not, go to Step 8.

3. Clean the fiber connection between the patch panel and the LD Line In port.

4. Perform an in-service adjustment from the PhM light path trace power management interface.

5. If the Loss too high error remains, check the loss on the affected segment and if the span loss is too high field personnel will need to try to correct the span loss.

6. If the Loss too high error remains, clean the fiber connection between the patch panel and the LD Line Out port of the upstream network element.

7. If the span loss cannot be reduced to meet the planned limit, then a re-plan of the system will be required using the EPT.

8. If the message is generated during ASE commissioning, re-run the commissioning wizard.

9. If the message is generated as a result of an in-service power adjustment, perform a power adjustment on the affected span using the PhM, CLI, or WebUI.

Page 48: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Verification and Backup

Wavelength Tracker

Page 49: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Wavelength Tracker

Page 50: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Wavelength Tracker – Light Path Power Trace (1354 RM-PhM)

Page 51: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Wavelength Tracker Data (CLI)

Example of Wavelength Tracker parameter

data (from CLI):

Type: show wavekey wtsource keys

Type: show wavekey wtsource power

ITU Channel : 28

Expected WaveKey 1: 428

Expected WaveKey 2: 972

WaveKeys Received : Yes

Channel AINS : Disabled

Expected Power : -19.90 dBm

Power Deviation : 2.50 dB

Power Tolerance : 0.00 dB

Measured Power : -19.82 dBm

Keys

Power

Page 52: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Verification and Backup

Perform Backup with PhM

Page 53: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Perform database backups with PhM

Database backups are performed using TFTP server, which is provided with the 1354 RMPhM Photonic Manager Refer to your 1830 PSS-32/16 Installation Guide, Part IV, Chapter 12, and review

the sample loss report “Perform database backups” procedures. Refer to the Alcatel-Lucent 1354 RM-PhM Photonic Manager EMS Reference Guide

for more information.

1. From Phm: Admin /Settings /System Settings /File Transfer 2. TFTP Root Directory : Verify the root directory is /tftpfiles 3. select FTP & Remove Prefix 4. Select the NE you want to backup 5. Maintenance / NE Database Backup & Restore 6. Right click on the NE / select “Details...” 7. check “Use the EMS Server as Backup host recommended” and “Use default

backup directory recommended”. 8. click on the Backup

Page 54: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

System Turn Up and Commissionning Verification and Backup

Perform Backup with WebUI

Page 55: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

All Rights Reserved © Alcatel-Lucent 2011

Exercises - Perform database backups with WebUi

Database backups can be performed with WebUI and a TFTP Server (3CDaemon in this example)

1. Run a TFTP server and browse directory 2. From WebUi: Administration/ database / backup and restore 3. Protocol/TFTP 4. Enter the local host server IP 5. Enter path to directory from the TFTP server root directory 6. Enter backup filename 7. Apply 8. Backup 9. Verify progression in TFTP server window

Enter a new folder name of required

Page 56: Part_4 1830PSS R5.0 System Turn Up & Commissioning.pdf

GPEC

Global Delivery Readiness

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

End of Module System Turn Up and Commissionning