Pad Mounted Threephase Transformer

Embed Size (px)

Citation preview

  • 8/11/2019 Pad Mounted Threephase Transformer

    1/29

  • 8/11/2019 Pad Mounted Threephase Transformer

    2/29

    What is a Three-Phase Pad Mounted Transformer?

    What are its Applications?

    How is it Installed?How is it Wired?

    The Specification Package

    The Specification Letter

    Miscellaneous

    What We Will Cover

  • 8/11/2019 Pad Mounted Threephase Transformer

    3/29

    What is a Three-Phase Pad Mounted Transformer?

    Outside

    Metal Encased, Tank, Fins, Cabinet

    Sits on a Three Piece Vault

    Fragile Enclosure, Not for Storage

    Inside Contains

    Oil Tank, Windings, Terminals

    Primary and Secondary Compartments

    Grounding Loop

    Cables and Terminations

  • 8/11/2019 Pad Mounted Threephase Transformer

    4/29

    What is a Three-Phase Pad Mounted Transformer?

    Steps Down Primary Voltage to Secondary

    Primary Side (4kV, 13kV, or both)

    Secondary Side (120/208v, 277/480v)

    Three Phase Wye Configuration Only

    Pad Mounted, or Submersible

    Di-Electric Fluid (insulates and cools)

    LIPA Sizes Range From:

    75KVA to 1000KVA for 120/208

    75KVA to 1500KVA for 277/480

    Special Order 2500KVAs

  • 8/11/2019 Pad Mounted Threephase Transformer

    5/29

    The outside of a Three-Phase Pad Mounted Transformer

    Side View of a 150KVA Pad Mounted Transformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    6/29

    The Outside of a Three-Phase Pad Mounted Transformer

    Orientation Away From Building

    Clearances

    5 From Transformer to Building Wall

    10 to Vent Openings, Doors, Windows

    25 to Non-Fire-Rated Openings

    Auditorium Exits

    Truck Accessible (delivery & removal purposes)

    NEC Class 1, Division 1, and 2 Locations Shall Require a

    Minimum 25 ft. Clearance (oil, gas, etc)

    Set Vault Level, Grade to Slope Away

    Traffic Protection

  • 8/11/2019 Pad Mounted Threephase Transformer

    7/29

    The Inside of a Three-Phase Pad Mounted Transformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    8/29

    Inside a Three-Phase Pad Mounted Transformer

    Primary Compartment(left side)

    Primary Connections(radial, or loop)

    Incoming - H1C, H1A,H1B

    Outgoing - H2B, H2A,H2C

    No Load Tap Changer

    A Through E (2.5%increments, middleis zero boost)

    Bayonet Fuses, ProtectPrimary Side ofTransformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    9/29

    Primary Compartment

    Load Break Elbows

    Sizes: #2, 1/0, 3/0

    Lightning ArrestorElbows (radials, and

    open points)

    Static Drain Wires(#14, and #10 Cu.)

    Grounding Loop

    #2BTN, One HLC

    Primary Bushings

    Standoff BushingSlots (open point)

    Inside a Three-Phase Pad Mounted Transformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    10/29

    Primary L/B Elbow

    Load Break Elbow, Bushing,Static Drain Wire, and PrimaryCable

    Detail in Spec. Package

    Follow Mfg. Instructions

    Pulling Eye

    Test Point, & Cap

    5 of Taped Neutral

    #2 EPR Insulated May beHylinked

    Sealing Strip, 36 Below HoseClamp

    Inside a Three-Phase Pad Mounted Transformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    11/29

    Primary Bushing

    Supplied by LIPA withL/B, L/A Elbow

    Screws in

    Must be Kept Clean,Contamination WillCause ElectricalFailure

    #14 Static Drain WireFrom Eyelet toGrounding Split Bolt

    L/B Elbow ShouldCover Yellow (nowRED) Band

    Inside a Three-Phase Pad Mounted Transformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    12/29

    Secondary Compartment(right side)

    Secondary Spades;X0, X1, X2, X3

    Nema 2 Hole Lugs(tinned alum. Or Cu.)

    Al Lug - ExtraBelleville Washer Req

    Oxide Inhibitor on Al

    Cu to be Tinned, orAlloy plated

    750 Cu now Accepted

    Buss Supports

    Inside a Three-Phase Pad Mounted Transformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    13/29

    SecondaryCompartment

    Color Coding

    120/208v or

    277/480v

    Integrated/Isolated

    8 Sets Max

    Grounding Pads,Loop, Split Bolts,Ground Rods

    Oil Drain Valve

    Inside a Three-Phase Pad Mounted Transformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    14/29

    SecondaryCompartment

    Pressure

    Relief ValveDo Not Pull

    Oil Fill Level

    Oil

    TemperatureGauge

    Oil Level

    Gauge

    Inside a Three-Phase Pad Mounted Transformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    15/29

    Nameplate

    Identifies Primary andSecondary Voltage

    Indicates Voltage onDifferent Tap Settings

    Shows Internal CoilConfiguration

    Indicates TransformerWeight

    Indicates TransformerImpedance

    Inside a Three-Phase Pad Mounted Transformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    16/29

    Common equipment

    Primary Cable

    Sizes: 3-2/c#2, 1/0, 3/0

    Secondary Cable

    Sizes: Minimum #2, Maximum 750

    Maintain 5 min. Slack in Vault

    Maintain as Much Physical Separation as Possible

    Grounding Pads, Lugs, and Split Bolts

    Bare #6 Cu to Ground Rods

    Bare Tinned Copper #2 for Ground Loop

    Inside a Three-Phase Pad Mounted Transformer

  • 8/11/2019 Pad Mounted Threephase Transformer

    17/29

    What are its Applications?

    Typical for Large Load, Non-Residential Customers; Long

    Distance From ExistingFacilities; and LoopedCommercial Industrial Parks

    Pad Mounted Transformers areLIPAs Standard Installation,Non-Standard is Submersible, orNetwork

    Transformer is Delivered,Owned, and Maintained by LIPA

    for Secondary Metered Service

  • 8/11/2019 Pad Mounted Threephase Transformer

    18/29

    How is the Three-Phase Pad Mounted TransformerInstalled?

    Set on a Three Piece Vault, Always Providedby Contractor (see approved vendor list)

    Pad Orientation

    Primary Side, Secondary Side

    Doors to Face Away From Building

    10 Clear in Front of Pad for Switching

    Grade Away 1% Slope

    Old Way Poured Foundation (slab) Primary and Secondary Cables Have no

    Slack

    Boom Truck Delivers Transformer, Lifts itonto Vault

  • 8/11/2019 Pad Mounted Threephase Transformer

    19/29

  • 8/11/2019 Pad Mounted Threephase Transformer

    20/29

  • 8/11/2019 Pad Mounted Threephase Transformer

    21/29

    How is the Three-Phase Pad Mounted Transformer

    Installed?

    Boom Truck

    Can Deliver All

    Transformers

    Line Truck

    Delivers up to500 kVA

  • 8/11/2019 Pad Mounted Threephase Transformer

    22/29

  • 8/11/2019 Pad Mounted Threephase Transformer

    23/29

    Radial Installation

    Contractor Installs Primary and Secondary Cable

    Contractor Wires L/B and L/A Elbows

    Contractor Makes Secondary Connections

    Contractor Wires All Grounding

    Contractor Supplies Secondary Lugs, Static Drain

    Wires, Ground Rods, Ground Wire, and Grounding

    Split BoltsCIPUD Installation

    Contractor Supplies and Wires Secondary

    LIPA Wires Primary & Grounding

    Who Wires the Three-Phase Pad MountedTransformer?

  • 8/11/2019 Pad Mounted Threephase Transformer

    24/29

    Specification Package Details

    Provides Information Common to All Jobs

    Pad Specifications, Vault Details

    Primary Side, Secondary Side

    Contractor to Discuss Location Before Pad is Set

    Knock Outs: 4 PVC Sleeve Flush With Wall, Concreted in Place

    Duct Seal or Cap Unused Conduits

    Galvanized Conduits Require Bonding

    Protection From Traffic

    Bollard 3.5 Heavy Steel Wall (minimum)

    Concrete Filled

    Must be Painted Yellow

    Doors Must be Able to Open

    Required on All Sides Subject to Vehicular Traffic

  • 8/11/2019 Pad Mounted Threephase Transformer

    25/29

    Primary Cables

    Phases Must be Identified (1, 2, 3 rings), on BothExtremities

    15kV Tree-Retardant Cross-Linked Polyethylene for

    Aluminum (TR-XLPE)

    Ethylene Propylene Rubber (EPR) for Copper

    Semi-Con 12 Mil

    Insulation 220 Mil, Insulation Shield 30 Mil Semi-Con

    Jacket 50 Mil Semi-Con

    Specification Package Details

  • 8/11/2019 Pad Mounted Threephase Transformer

    26/29

    Secondary Services

    480v - One Service

    Exception: Fire Pumps

    208v - Multiple Services

    Services Must be Labeled

    Cables

    480v (must be installed in conduit)

    USE-2, XHHW-2, or RHW-2

    8 Sets Max

    208v

    USE-2, THW-2, THWN-2, XHHW-2, or RHW-2*

    *With neoprene or hypalon jacket only

    Specification Package Details

  • 8/11/2019 Pad Mounted Threephase Transformer

    27/29

    Three-Phase Specification Letter

    Gives Project Specific Details, Such as:

    Reiterates Customer Load Letter

    Designated Riser Pole, or Point of Termination

    Describes Cable Ownership

    Provides Costs, if Any

    Inrush Information, Motor Starting Limitations

    Restates Basic Installation Rules,

    Call Before You Dig

    Repeats Primary and Secondary Cable

    Specifications

  • 8/11/2019 Pad Mounted Threephase Transformer

    28/29

    Miscellaneous

    Provide Advance Notification of Projects

    Access to an Energized Vault is Forbidden

    Industrial Code Rules 753, and 57

    These Requirements Conform to the NEC

    Contractor to Comply With:

    Applicable Codes

    Three Phase Transformer Spec. Package

    Redbook

    Lists Distribution Design Representatives

    www.lipower.org

  • 8/11/2019 Pad Mounted Threephase Transformer

    29/29

    QUESTIONS

    ?