Upload
ianthe
View
47
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Overview of the mu2e magnet system Collaboration mu2e-COMET R. Ostojic Based on presentation of M. Lamm in ASC2010. All credit goes to the members of the mu2e magnet design team. What is mu2e?. Measure the Rare Process: m - + N e- + N - PowerPoint PPT Presentation
Citation preview
1. Overview of the mu2e magnet system2. Collaboration mu2e-COMET
R. Ostojic
Based on presentation of M. Lamm in ASC2010.All credit goes to the members of the mu2e magnet design team.
Measure the Rare Process: m- + N e- + N→ It will be world class experiment in the “Intensity
Frontier”…• 4 orders of magnitude improvement over
existing measurements• Judged by the US Department of Energy and the
High Energy Physics Community to be a high priority for Fermilab
→ …either with or without a signal….• WITH: Indicate new physics beyond the “standard
model”• WITHOUT: Put severe limits on theories beyond the
standard model• It will compliment Large Hadron Collider (LHC)
Experiments
2
What is mu2e?
3
Plan View of Solenoid System8 GeV P
•Production Solenoid
• 8 GeV P hit target. Reflect and focus p/m’s into muon transport
• Strong Axial Gradient Solenoid Field
• Sign/momentum Selection• Negative Axial Gradient in S.S. to
suppress trapped particles
•Transport Solenoid
• Graded field to collect conv. e-
• Uniform field for e- Spectrometer
•Detector Solenoid
24 meters
4
Tentative schedule
Start of Magnet Construction 2013
CD-2/3 Mid-2012
CD-1 Review March 1, 2011
CDR complete Jan. 15, 2011
Final cost & schedule and associated documentation.
Jan. 15, 2011
Director’s Design Review Nov. 1, 2010
CD-0 Nov, 2009
Time
Fermilab will act as a “General Contractor”: PS and DS will likely be built in industry
Need to develop a strong conceptual design and technical specifications for vendors
Final engineering design done by industry Similar strategy for most detector solenoids
TS will likely be designed/built “in house” Cryostat, mechanical supports built by outside vendors Coils wound in-house or industry depending on technology
choice Final assemble and test at Fermilab
Solenoid task has co-responsibility for all interfaces Significant magnet coupling between PS-TS and TS-DS Tight mechanical interfaces Cryoplant, power supplies, instrumentation…
5
Procurement strategy
6
Detector solenoid
Two functions:1. Axial Gradient Field for particle collection (2T1T)
Uniformity of axial gradient along axis: 5%2. Uniform field for spectrometer and calorimeter
Most like a HEP detector magnet but stricter field specs! ~3 meter high uniform field 0.2% request
Significant Axial Forces between Iron, DS and TS7
DS Challenges
Coils wound on separate mandrels, bussed in series, Iop ~5kA
Cold mass in “single cryostat” Use Al stabilized NbTi conductor
More experience with detector solenoid vendors Considerably less weight
Two layer coils throughout Achieve axial gradient by effectively changing winding density
by introducing spacers and varying conductor thickness. 8
DS Design Concept
9
DS 5-Coil Design
MECO(blue) field is overlapped on the field of this design(red)
Unusual field requirements “S”-shaped to reduce line of sight
PS to DS; momentum selection negative axial gradient in SS to
prevent trapped/out of time particles
Effect of magnetic coupling between TSn and PS/DS and S shape:
significant non-axial excitation forces
complicated stresses during cooldown
Removable TS3 to service collimator and vacuum break
10
Transport Solenoid Challenges
11
TS Design Concept
150
150
200
200
200
TS2/4 assembled using 3-coil modules
•Conductor in copper channel•Sections welded or bolted together•Coils bussed in series•I op ~1000 Amperes
12
Production Solenoid
Axially Graded Field: 5 T2.5 T ~5.7 T on conductor
Wide aperture 1.5 m, 4 m long Large stored energy (~100MJ)
There’s a target in the aperture…
25 kW off target, 25-50W into coils…depending on absorber design and beam intensity
Heat load and Radiation issues on conductor, insulator and stabilizers
Strong Magnetically Coupled with Iron and TS
Unlike typical detector solenoid significant axial forces >100 T of axial force
13
PS Challenges
• Gradient made by 3 axial coils same turn density but increase # of layers (2,3,4 layers)• Wound on individual bobbins
• Aluminum stabilized NbTi • reduce weight and nuclear
heating• Indirect cooling
• High Current/low inductance• Efficient energy extraction• Less layers: simplify winding,
minimize thermal barriers from conductor to cooling channels.
• I operation ~10 kA
14
PS Design Decisions
15
Conductor and Coil Support
Doped Al
NbTi/Cu
Cable cross-section
Outer supportshell
Pure Al sheets (RRR>500)
Coil Configuration
•4 Layer Coil•“Hardway bend”•Epoxy impregnated
Parameter Unit MU2E PS
Strand diameter mm 1.200 Number of strands - 36 Cable bare width mm 30.00 Cable bare thickness mm 6.50 Strand Cu/non-Cu ratio - 1.0 Overall stabilizer/non-stabilizer ratio in bare cable - 8.58
5.7 T peak field in the coil; >5 T peak field on the axis; ~2.5 T at the TS interface; <1.5 T field in the yoke
body; <2.4 T in the yoke end caps.
16
Flux densities
17
Axial gradient
No heat load:Operating point is at
68% of the SSL along load line or at 25% of the SSL at the constant field;
Under heat load:The temperature
increment of 5.32 K-4.50 K = 0.82 K allows to operate at 80 % of the SSL along the load line or at 40 % of the SSL at the constant field.
18
Critical current
0 1 2 3 4 5 6 7 8 9 10 110
2
4
6
8
10
12
14
16
18
20SSL @4.50K (68%)SSL @5.32K (80%)SSL @6.18K (100%)Load lineOperating point
Peak field (T)
Curr
ent (
kA)
19
3D field distribution
The second end cap was added to the iron yoke (vs. MECO) to eliminate the net axial self-Lorentz force (TS=off);
When all magnets are powered, the net axial force is +116/-124 tons, depending of the current direction;
MECO axial force of 140 tons was used for the design of axial supports;
Due to the force directions, the coil to coil interfaces are always under compression.
20
Axial forces22
.46
MN
10.6
5 M
N10
.65
MN
• The Lorentz forces are reacted by the outer shells made or Al 6061-T6;
• The shells are assembled around the coils with no prestress;
• All gaps are filled with epoxy.
Coil support concept
Dimensions are in [m]
Materials:8.35% NbTi8.35% Cu17.33% G1065.97% Al100% Al 6061-T6100% Stainless steel100% Low carbon steel
21
• The Lorentz forces are reacted by the outer shells made or Al 6061-T6;
• The shells are assembled around the coils with no prestress;
• All gaps are filled with epoxy.
22
Cryostat design
Thermal syphon cooling
Suspension system
8 GeV proton beam, Au target (r=0.3 cm, H20, Ti), 25 kW, I=2E13, σx= σy= 1 mm
23
Baseline absorber configuration
24
Neutron flux >100 keV and power deposition
Absorbed dose (Gy/s) = Power density (mW/g), i.e., peak in the coils ~ 100 kGy/yr
25
DPA (displacements/atom)
Peak DPA in Al ~2x10-5/yr
26
NbTi degradation (Al Zeller, 2003) http://supercon.lbl.gov/WAAM/
5% degr.
15-20 years to accumulate 5 % of Ic degradation (w/o annealing)
Under the expected dose of 2÷6·10-5 DPA/year, Al resistivity degrades by a factor of: 5÷10 at B = 0
T 2.5÷5 at B = 5
T
27
Al resistivity degradation
1 10 7 1 10 6 1 10 5 1 10 4 1 10 3 0.011 10 11
1 10 10
1 10 9
1 10 8
1 10 7
1 10 6
0.2
0.4
0.6
0.8
Al rho inducedRRR=2450, B=0TRRR=500, B=0TRRR=500, B=5T
Aluminum at 4.5K
DPA
Irrad
iatio
n-in
duce
d re
sistiv
ity, r
ho_i
(Ohm
*cm
)
Res
istiv
ity d
egra
datio
n, rh
o/(rh
o_i+
rho)
Al resistivity recovers during the thermal cycle: by 60 % at 80
K; by 100 % at
300 K.
28
Al resistivity recovery
29
Quench protection
0
10
20
30
40
50
60
70
80
90
100
0
2000
4000
6000
8000
10000
12000
0 20 40 60 80 100 120
Tem
pera
ture
(K)
Curr
ent (
A)
Time (s)
PS quench study
all_500_CURR(A)
10m_200_CURR(A)
10m_50_CURR(A)
all_500_TEMP(K)
10m_200_TEMP(K)
10m_50_TEMP(K)
Pion Capture Solenoid
Muon Transport Solenoid
Spectrometer Solenoid
Detector Solenoid
proton beam
pion productiontarget
radiation shield
iron yoke
CSMS1
MS2
COMET SC Magnets
R&D Program Model coils of Al-
stabilized superconductor with high yield strength Development of conductor Model coil in the COMET-
Mu2e collaboration Neutron irradiation test
Expect 1021 n/m2 for 30 day operation in COMET
Need to check degradation of high yield strength aluminum
1x10-11
1x10-10
1x10-9
1x10-8
1x10-7
1x10-6
0
100
200
300
400
500
10-7 10-6 10-5 0.0001 0.001 0.01
RRR degradation by DPA
Al DeltaRhoCu DeltaRho
Al RRR(500)Cu RRR(200)D
elta
Rho R
RR
DPA
“Isochronal recovery of fast neutron irradiated metals,” J.A. Horak and T.H. Blewitt, Journal of Nuclear Materials, Volume 49, Issue 2, December 1973, Pages 161-180
Neutron irradiation facility Check degradation of
stabilizer up to 1021 neutrons/m2
degradation of resistivity recovery by annealing to RT
Kyoto Univ. Research Reactor ( KUR ) 5MW at maximum Low temperature facility
available 10K-20K 9.8 x 1011 n/cm²/s
32
The design of the mu2e experiment and its magnet system is vigorously proceeding with the goal of obtaining the DOE CD-1 approval in Spring 2011.
The mu2e magnet design uses many of the features developed for the latest generation of detector magnets. Its specific issues are: high field gradient, tight field tolerances and high radiation level.
The magnets will be built in industry and at Fermilab and should be operational by 2016. Their construction could be regarded as a technological bridge between the solenoids built for ATLAS and CMS and those proposed for the LC experiments.
A collaboration has been established between mu2e and COMET in view of resolving joint concerns, in particular obtaining improved data on properties of superconductors and stabilizers after irradiation.33
Summary