PHASE ACTIVITY OUM TASK ID OUM TASK NAME PAD PS Project Start Up PS.ACT.RBC Review Bid and Contract PS.BT.010 Review and Analyze Bid Material 15 PS.BT.020 Review and Confirm Business Case 15 PS.BT.030 Identify Project Stakeholders 15 PS.BT.040 Review and Accept Project Budget 15 PS.RKM.020 Conduct Baseline Risk Assessment 15 PS.ACT.RPAC Review Project Assets with Client PS.BT.050 Review Contract with Client 25 PS.BT.060 Review Project Approach with Client 25 PS.BT.070 Create Project Management Framework 25 PS.ACT.VSSOS Validate Scope, Stakeholders and OCM Strategy PS.SM.010 Define and Confirm Scope 10 PS.CMM.010 Conduct Project Stakeholder Analysis 15 PS.OCHM.010 Understand Customer's Organizational Change Management Strategy 15 PS.ACT.DW Develop Workplan PS.WM.010 Develop Baseline Project Workplan 10 PS.ACT.DSPB Develop Staff Plan and Budget PS.FM.010 Refine Project Budget 15 PS.STM.010 Plan Resource Requirements 15 PS.STM.030 Staff Project 15 PS.STM.040 Prepare Orientation Guide(s) 15 PS.QM.030 Conduct Project Team Quality Management Orientation 15 PS.ACT.CPMP Complete Project Management Plan PS.SM.020 Develop Scope Change Management Processes 10 PS.FM.020 Develop Financial Management Plan 15 PS.WM.020 Develop Work Management Execution and Control Processes and Policies 15 PS.RKM.010 Develop Risk Management Plan 15 PS.IPM.010 Develop Issue Management Strategy 15 PS.IPM.020 Develop Problem Management Strategy 15 PS.STM.020 Develop Staff Management Plan 15 PS.CMM.020 Develop Project Team Communication Plan 15 PS.QM.010 Develop Quality Management Plan 15 PS.QM.020 Develop and Document Quality Control and Reporting Process 15 PS.CM.010 Develop Configuration Management Strategy and Processes 15 PS.CM.030 Create Project Documentation Management Plan 15  PS.IFM.010 Develop Infrastructure Management Plan 15 PS.PCM.010 Develop Procurement Strategy and Process 15 PS.OCHM.020 Identify Change Management Warning Signs 15 PS.ACT.EPI Establish Project Infrastructure PS.FM.030 Set Up Time and Expense Tracking 15 PS.RKM.030 Develop Risk Management System 15 PS.IPM.030 Develop Issue and Problem Management System 15 PS.CM.020 Obtain Configuration Management Tools 5 PS.IFM.020 Establish Team Work Environment 15 PS.IFM.030 Establish Technical Infrastructure 15 PS.PCM.020 Procure Goods and Contracted Services 15 PEC Project Execution and Control PEC.ACT.MSAA Manage Scope, Acceptance and Approvals PEC.SM.030 Manage Scope 15 PEC.SM.040 Manage Acceptance 15 PEC.WM.050 Manage Approvals 15 PEC.ACT.MPF Manage Project Finances PEC.FM.040 Manage Project Finances 10 PEC.ACT.MPW Manage Project Workplan PEC.WM.030 Manage Project Workplan 15

OUM Roles Mapping

Embed Size (px)

Citation preview

Page 1: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 1/29

PHASE ACTIVITY OUM TASK

ID

OUM TASK NAME PAD

PS Project Start UpPS.ACT.RBC Review Bid and Contract

PS.BT.010 Review and Analyze Bid Material 15

PS.BT.020 Review and Confirm Business Case 15

PS.BT.030 Identify Project Stakeholders 15

PS.BT.040 Review and Accept Project Budget 15PS.RKM.020 Conduct Baseline Risk Assessment 15

PS.ACT.RPAC Review Project Assets with Client

PS.BT.050 Review Contract with Client 25

PS.BT.060 Review Project Approach with Client 25

PS.BT.070 Create Project Management Framework 25

PS.ACT.VSSOS Validate Scope, Stakeholders and OCM StrategyPS.SM.010 Define and Confirm Scope 10

PS.CMM.010 Conduct Project Stakeholder Analysis 15

PS.OCHM.010 Understand Customer's Organizational Change Management Strategy 15

PS.ACT.DW Develop WorkplanPS.WM.010 Develop Baseline Project Workplan 10

PS.ACT.DSPB Develop Staff Plan and Budget

PS.FM.010 Refine Project Budget 15PS.STM.010 Plan Resource Requirements 15

PS.STM.030 Staff Project 15

PS.STM.040 Prepare Orientation Guide(s) 15

PS.QM.030 Conduct Project Team Quality Management Orientation 15

PS.ACT.CPMP Complete Project Management PlanPS.SM.020 Develop Scope Change Management Processes 10

PS.FM.020 Develop Financial Management Plan 15

PS.WM.020 Develop Work Management Execution and Control Processes and Policies 15

PS.RKM.010 Develop Risk Management Plan 15

PS.IPM.010 Develop Issue Management Strategy 15

PS.IPM.020 Develop Problem Management Strategy 15

PS.STM.020 Develop Staff Management Plan 15

PS.CMM.020 Develop Project Team Communication Plan 15PS.QM.010 Develop Quality Management Plan 15

PS.QM.020 Develop and Document Quality Control and Reporting Process 15

PS.CM.010 Develop Configuration Management Strategy and Processes 15

PS.CM.030 Create Project Documentation Management Plan 15

  PS.IFM.010 Develop Infrastructure Management Plan 15

PS.PCM.010 Develop Procurement Strategy and Process 15

PS.OCHM.020 Identify Change Management Warning Signs 15

PS.ACT.EPI Establish Project InfrastructurePS.FM.030 Set Up Time and Expense Tracking 15

PS.RKM.030 Develop Risk Management System 15

PS.IPM.030 Develop Issue and Problem Management System 15

PS.CM.020 Obtain Configuration Management Tools 5

PS.IFM.020 Establish Team Work Environment 15

PS.IFM.030 Establish Technical Infrastructure 15PS.PCM.020 Procure Goods and Contracted Services 15

PEC Project Execution and ControlPEC.ACT.MSAA Manage Scope, Acceptance and Approvals

PEC.SM.030 Manage Scope 15

PEC.SM.040 Manage Acceptance 15

PEC.WM.050 Manage Approvals 15

PEC.ACT.MPF Manage Project FinancesPEC.FM.040 Manage Project Finances 10

PEC.ACT.MPW Manage Project WorkplanPEC.WM.030 Manage Project Workplan 15

Page 2: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 2/29

PEC.WM.040 Track Schedule Performance 15

PEC.ACT.MRIP Manage Risks, Issues and ProblemsPEC.RKM.040 Manage Risk 15

PEC.RKM.050 Monitor and Control Risk 15

PEC.IPM.040 Manage Issues and Problems 15

PEC.ACT.OMT Orient and Manage TeamPEC.STM.050 Conduct Team Orientation(s) 15

PEC.STM.060 Manage Project Team 15

PEC.ACT.MCOP Manage Communications and OCM Plans  PEC.CMM.030 Manage Project Team Communication 10

PEC.OCHM.030 Execute Change and Communication Plan 15

PEC.ACT.MPQ Manage Project QualityPEC.QM.040 Manage Quality Control 15

PEC.QM.050 Perform Quality Assurance 15

  PEC.CM.040 Create and Execute Software Configuration Management Plan 15

PEC.CM.050 Create and Execute Software Release Management Plan 15

PEC.CM.060 Create and Execute Environment and Patch Management Plan 5

PEC.CM.070 Create and Execute Configuration Management Control Plan 15

PEC.ACT.MMI Manage and Maintain InfrastructurePEC.IFM.040 Manage and Maintain Infrastructure 15

PEC.PCM.030 Administer Procurement of Goods and Contracted Services 15

PC Project ClosurePC.ACT.GA Gain Acceptance

PC.SM.050 Gain Acceptance 15

PC.ACT.CPC Close Processes and ContractPC.SM.060 Close Scope Management 15

PC.SM.070 Identify Future System Enhancements 15

PC.FM.050 Close Project Financials 15

PC.WM.060 Close Work Management 15

PC.RKM.060 Conduct Post-Production Risk Assessment 15

PC.IPM.050 Produce Final Issue and Problem Report and Close Log(s) 15

PC.STM.070 Release Staff 15

PC.QM.060 Conduct Post Production Quality Review 15

PC.CM.080 Close Configuration Management 5

PC.IFM.050 Close Infrastructure 15

PC.PCM.040 Close Contract 15

PC.OCHM.040 Establish Follow-Up Process 15

PC.ACT.DLLAP Document Lessons Learned and Archive ProjectPC.CMM.040 Document Lessons Learned 10

PC.CMM.050 Turn Over Project Documentation (Project Archives) 15

PC.CMM.060 Submit Final Reports 15

PEC.ACT.APGCS Administer Procurement of Goods and Contracted Services

PEC.ACT.CECRM Create and Execute Configuration and Release Management

Page 3: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 3/29

PM Project

Lead(s)

Functional

Lead(s)

Technical

Lead(s)

Team

Members

User Roles

85 CPS

85 CPS

85 CPM, CPS

85 CPS85 CPS

75 CPM, CPS

75 CPM, CPS

75 CPM, CPS

60 30 CPM, CPS

85 CPM, CPS

85 CPS

65 25 CPS

85 CPS

85 CPS

85 CPS

85 CPS

85 CPS

70 20 CPS

85 CPS

85 CPS

85 CPS

85 CPS

85 CPS

85 CPS

85 CPM, CPS85 CPS

85 CPS

85 Advisory CPM, CPS

85 CPS

85 Advisory CPM

85 CPS

85 CPS

85 CPS

85 CPS

85 CPS

15 80 CPS

85 CPS

85 CPS85 CPS

85 CPS

85 CPS

85 CPS

40 50 CPM, CPS, SCM

85 CPS

Page 4: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 4/29

85 CPS

85 CPS

85 CPS

85 CPS

85 CPM, CPS

85 CPS

65 25 CPM, CPS

85 CPS

85 CPS

85 CPS

85 Advisory Advisory CPM, CPS

85 Advisory Advisory CPM, CPS

15 30 50 CPM, CPS

85 Advisory Advisory CPM, CPS

85 CPS

85 CPS

85 CPS

85 CPS

85 CPS

85

85 CPS

85 CPS

85 CPS

85 CPS

85 CPS45 50 CPS

85 CPS

85 CPS

85 CPS

65 25 CPS

85 CPS

85 CPS

Page 5: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 5/29

Page 6: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 6/29

Page 7: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 7/29

PHASE ACTIVITY OUM TASK

ID

OUM TASK NAME

INIT InitiateINIT.ACT.PEF Prepare Envision Foundation

INIT.ER.010 Create Business Case for Envision Engagement

INIT.EA.001 Justify and Engage Enterprise Architects

INIT.ER.040 Gather Enterprise Diagnostic Information

INIT.ER.045 Establish Executive Sponsorship

INIT.BA.010 Identify Business Strategy

INIT.BA.012 Define Business Scope

INIT.BA.015 Conduct Enterprise Stakeholder Assessment

INIT.GV.010 Define Governance Strategy

INIT.BA.017.1 Determine Metrics Collection and Reporting Strategy

INIT.BA.018.1 Establish Current Baseline Metrics

INIT.BA.020 Document Enterprise Organization Structures

INIT.BA.025 Determine Operaing Model

INIT.EA.002 Review External Reference Architectures

INIT.ER.015 Conduct Enterprise Maturity Assessment

INIT.ER.020 Determine Envision Engagement Strategy

INIT.ACT.PD Prepare for DiscoveryINIT.EOCM.010 Create and Manage Ad Hoc Communications

INIT.ER.025 Educate Enterprise on Area of Focus

INIT.ER.030 Set and Agree on Plan for Envision Engagement

INIT.ER.050 Validate and Agree on Envision Engagement Plan

INIT.ACT.CEAWE Conduct Executive Alignment Workshop - EnvisionINIT.EOCM.020 Prepare for Executive Alignment Workshop

INIT.EOCM.030 Conduct Executive Alignment Workshop

INIT.EOCM.040 Build and Deploy Sponsorship Program

INIT.ACT.DMCEC Define and Maintain Common Enterprise ConceptsINIT.BA.030.1 Develop Enterprise Glossary

INIT.EA.010.1 Review Architecture Principles, Guidelines and Standards

INIT.ER.070 Define Modeling Strategy for the Enterprise

INIT.ACT.EDGI Execute Discovery - Gather Information (As Is)INIT.EOCM.050 Assess Enterprise Change Readiness

INIT.EOCM.060 Prepare Project Team for Client Culture

INIT.EOCM.070 Identify Change Agent Structure

INIT.ER.080 Obtain Existing Reference Material

INIT.ER.090 Conduct Solution Readiness Assessment

INIT.GV.015 Review Current Governance Model

INIT.GV.020.1 Determine Regulatory and Business Mandates

INIT.BA.040 Create Enterprise Function or Process Model  INIT.BA.050 Develop Enterprise Domain Model (Business Entities)

INIT.BA.055 Develop Enterprise Knowledge Flow

INIT.BA.058 Develop Business Architecture

INIT.BA.060.1 Perform High-Level Use Case Discovery

INIT.EA.030 Identify Current Enterprise Architecture

INIT.EA.040 Analyze Capabilities

INIT.GV.030.1 Discover or Define Policies

INIT.EA.050 Identify Current Architectural Challenges

Page 8: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 8/29

INIT.GV.092 Determine Projects Meta Data Description

INIT.IP.010 Inventory Projects

INIT.GV.094 Determine Applications Meta Data Description

INIT.IP.012 Inventory Applications

INIT.IP.015 Conduct Portfolio Analysis

INIT.BA.065 Review Business-IT SLA

INIT.BA.067 Review Business Volumetrics

INIT.GV.096 Determine Services Meta Data Description

INIT.GV.098 Determine Other Meta Data Descriptions

INIT.IP.014 Inventory Services

INIT.ER.100 Define Supplemental Enterprise Requirements

INIT.EA.057 Review Business Capacity Plan

INIT.ACT.EDBPD Execute Discovery - Brainstorm, Prioritize and Discover Entry PointsINIT.BA.045 Develop Enterprise Business Context Diagram

INIT.GV.040 Determine Organizational Impact of Governance

INIT.EA.060 Identify Architectural Gaps and Improvement Options

INIT.EA.065 Identify Enterprise IT Strategy

INIT.ER.110.1 Perform Benefit Analysis

INIT.BA.060.2 Perform High-Level Use Case Discovery

INIT.EA.075 Develop Technology Reference Architectures

INIT.BA.070 Identify Candidate Services

INIT.IP.020 Analyze Services

INIT.IP.025 Populate Services Repository

INIT.BA.080 Identify Candidate Enterprise Business Rules

INIT.IP.030 Analyze Business Rules

INIT.BA.090 Identify Process Improvement Options

INIT.ER.120.1 Identify and Mitigate Future State Risks

INIT.ER.130.1 Produce MoSCoW Improvement List

INIT.EA.095 Review Enterprise Software Development Process

INIT.IP.040 Identify Candidate Projects

INIT.ACT.EDF Execute Discovery - Finish  INIT.ER.140 Share Product Strategies with Enterprise

INIT.ER.150 Review Discovery Findings

INIT.ACT.DSPC Develop Solution and Present to ClientINIT.GV.050.1 Define Policy Implementation Processes

INIT.GV.060.1 Define Policy Implementation Tooling

INIT.GV.070.1 Define Policy Metrics

INIT.GV.080.1 Define Policy Monitoring Processes

  INIT.GV.090.1 Determine Funding Model

INIT.GV.100.1 Implement Governance

INIT.ER.160 Develop Desired Future State

INIT.ER.165 Identify Capability Challenges

INIT.ER.167 Determine Remediation Approaches

INIT.EA.110 Develop Future State Enterprise ArchitectureINIT.EA.120 Develop Information Architecture

INIT.EA.130 Develop Technology Architecture

INIT.EA.140 Develop Applications Architecture

INIT.EA.150 Define Transitional Architectures

INIT.EA.160 Define Business Rules Implementation Strategy

INIT.EA.170 Identify Integration Requirements

  INIT.ER.170 Develop Future State Transition Plan

INIT.IP.050.1 Prioritize Projects

INIT.ER.110.2 Perform Benefit Analysis

  INIT.IP.060 Develop IT Portfolio Plan

Page 9: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 9/29

  INIT.EA.190 Define Product Implementation Prioritization

INIT.ER.180 Prepare for and Present Solution Recommendations

INIT.EA.200 Determine Development Framework and Policy Guidelines

INIT.ACT.PTI Plan Transition to Implementation  INIT.ER.190 Review Business Feedback and Identify Opportunities

INIT.ER.200 Prepare for Transition to Sales or Services

ME Maintain and EvolveME.ACT.ME Maintain and Evolve

ME.BA.017.2 Metrics Collection and Reporting Strategy

ME.BA.018.2 Establish Current Baseline Metrics

ME.BA.100 Maintain Enterprise Business Models

ME.BA.110 Maintain Business Rules

ME.BA.030.2 Develop Enterprise Glossary

ME.EA.010.2 Review Architecture Principles, Guidelines and Standards

ME.GV.020.2 Determine Regulatory and Business Mandates

ME.GV.030.2 Discover or Define Policies

ME.GV.050.2 Define Policy Implementation Processes

ME.GV.060.2 Define Policy Implementation Tooling

ME.GV.070.2 Define Policy Metrics

ME.GV.080.2 Define Policy Monitoring Procedures

ME.GV.090.2 Funding Model

ME.GV.100.2 Implement Governance

ME.GV.110 Monitor, Analyze and Improve Governance Processes

ME.ER.120.2 Identify and Mitigate Future Enterprise Architecture Risks

ME.ER.130.2 Produce MoSCoW Improvement List

ME.EA.210 Maintain Enterprise Architectural Models

ME.IP.050.2 Prioritize Projects

ME.IP.070 Execute and Maintain IT Portfolio and Programs

ME.IP.080 Maintain Repository of Art ifacts

ME.ER.210 Monitor Current Situation and Pursue Relevant Updates

Page 10: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 10/29

CMS EA SOLA PAD PM SM Other Client Roles

80 20 CS

50 50

50 50

100 SM

100 CEA, CS

100 CEA, CS

100 CEA, CS

60 (EA)

40 (BAR)

CEA, CS

100 CEA

100 CEA

100 CEA

100 CS

50 50

100 CS

80 20 PM CS

100 PM CCS

10 90 CS

100 PM

100 PM CPM, CPS

50 50 PM CPM, CPS

100 PM CPM, CPS

70 30 PM CPM, CPS

100 CEA

100 CEA

100 CEA

100 PM

100 PM

100 PM CCML, CPM, CPS

100

100

100 CEA

100 (BAR) CEA

100 CEA20 80 (IA) CEA

20 80 (IA) CEA

100 (BAR) CEA, CE

50 (EA)

50 (BAR)

CEA

100

(20-50)

0

(50-80)

CEA

100 CEA

EA (20)

BAR (80)

CEA

100 CEA

Page 11: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 11/29

100 CEA, CSOLA, CPM, CIO

100 CEA, CIO, CTO, CPMs

100 CEA, CSOLA, CIO

80 20(AA) CEA, CIO, CSE

100 CEA

50 (EA)

50 (BAR)

CEA

100 CEA

100 CEA, CSOLA, CSDLC, CIO100 CEA, CSOLA, CSDLC, CIO

100 CEA, CTO, CSE, CPMs

50 50 CEA, CS

20 80 (TA) CSOLA

100 CEA

30 (EA)

70 (BAR)

CEA

100 CEA

100 CEA, CE

100 CEA, CPM, CS

50 (EA)

50 (BAR)

CEA

20 80 (TA) CEA

50 50 (AA) CSOLA

50 50 (AA) CEA

30 70 (TA)

100 CSOLA

70 30 (AA) CEA

50 (EA)

50 (BAR

CEA

100 CEA

100 CEA, CPS

50 50 CSDLC

100 CEA, CIO

30 70 CEA, CS

90 10 CEA, CPS

60 (EA)

40 (BAR)

CEA

20 80 CEA

100 CEA

100 CEA, CPS

100 (BAR) CEA, CPS, CIO

100 CEA

50 50 CEA, CSOLA

100 CEA, CS

100 CEA

100 CEA

40 60 (IA) CSOLA

20 80 (TA) CSOLA

40 60 (AA) CSOLA

100 CEA, CE

30 70 (TA)

30 70

60 40 CEA

100 CEA, CIO

100 CEA, CPM, CS

40 60 CS

Page 12: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 12/29

40

60 (BAR)

CEA

100 CEA, CS

100

80 20

70 30 PM

100 CEA

100 CEA

100 CEA

100

100 CEA

100 CEA

100 (BAR) CEA

20 (EA)

80 (BAR)

CEA

60 (EA)

40 (BAR)

CEA

20 80 CEA

100 CEA

100 CEA, CPS

100 (BAR) CEA, CPS, CIO

100 CEA

100 CEA

100 CEA

100 CEA, CPS

100 CEA

100 CEA, CIO

20 80

100 CERM

100 SOLA CPS

Page 13: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 13/29

Page 14: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 14/29

Page 15: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 15/29

Page 16: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 16/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

A InceptionA.ACT.GBRI Gather Business Requirements - Inception

 A.RD.001 Detail Business and System Objectives

 A.RD.003 Identify Viewpoints

 A.RD.005 Create System Context Diagram

 A.RD.011.1 Develop Future Process Model

 A.RD.020 Obtain High-Level Business Descriptions

 A.RA.010 Simulate Business Process

 A.RA.015 Develop Business Use Case Model

 A.RD.065 Develop Domain Model (Business Entities) (Class Diagram)

 A.RD.012 Document Present and Future Organization Structures

 A.RD.015 Determine KPI Collection and Reporting Strategy

A.ACT.ECBB Establish Current Business Baseline

 A.RD.030 Develop Current Business Process Model

 A.RD.034 Document Current Business Baseline Metrics

A.ACT.GR Gather Solution Requirements A.RD.042.1 Develop Glossary

 A.RD.045.1 Prioritize Requirements (MoSCoW)

 A.RD.055 Detail Supplemental Requirements

 A.RD.130.1 Develop Baseline Architecture Description

 A.RA.019 Define Project Reference Architecture

 A.RA.021.1 Tell User Story

 A.RA.023.1 Develop Use Case Model

 A.RA.025.1 Identify Candidate Services

 A.RA.027.1 Identify Candidate Business Rules

 A.RA.028.1 Populate Business Rules Repository

A.ACT.PSUIA Perform Software Upgrade Impact Analysis A.TA.004 Perform Technical Architecture Impact Analysis

 A.RD.134 Identify New Software Release Changes

 A.RD.136 Perform Custom Extension Impact Analysis

 A.RD.138 Perform Data Impact Analysis

 A.MC.090.1 Conduct Reporting Fit Analysis

A.ACT.CR Consolidate Solution Requirements A.RD.140.1 Create Requirements Specification

 A.RD.150.1 Review Requirements Specification

A.ACT.CCPI Create Conceptual Prototype - Inception A.IM.005.1 Develop Conceptual Prototype

16

Page 17: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 17/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

 A.RA.030.1 Validate Conceptual Prototype

A.ACT.GSP Gather Supporting Requirements A.CV.010 Define Data Acquisition and Conversion Requirements

 A.TE.005.1 Determine Testing Requirements

 A.PT.010 Conduct Performance Management Workshop

 A.TA.010 Conduct Technical Architecture Workshop A.DO.010 Define Documentation Requirements and Strategy

 A.RD.070 Determine Audit and Control Requirements

A.ACT.SKSD Specify Key Structure Definition A.MC.010.1 Define Business Data Structures

 A.MC.020 Define Business Data Structure Setups

A.ACT.CMAHC Create and Manage Ad Hoc Communications A.OCM.010 Create and Manage Ad Hoc Communications

A.ACT.CEAW Conduct Executive Alignment Workshop A.OCM.020 Prepare for Executive Alignment Workshop

 A.OCM.030 Conduct Executive Alignment Workshop

 A.OCM.040 Build and Deploy Sponsorship Program

A.ACT.TPT Train Project Team

 A.TR.010.1 Define Training Strategy A.TR.020 Prepare Project Team Learning Plan

  A.TR.030 Prepare Project Team Learning Environment

 A.TR.040 Develop Project Team Learningware

 A.TR.050 Conduct Project Team Learning Events

A.ACT.CAWI Conduct Alignment Workshops - Inception A.OCM.050 Prepare for Team-Building Workshop

 A.OCM.060 Conduct Team-Building Workshop

 A.OCM.070 Design Managers' Project Alignment Workshop

 A.OCM.080 Conduct Managers' Project Alignment Workshop

 A.OCM.090 Design Change Agent Workshop

 A.OCM.100 Conduct Change Agent Workshop

A.ACT.CCRA Conduct Change Readiness Assessment A.OCM.110 Develop Change Readiness Assessment Strategy and

Tools

 A.OCM.120 Conduct Change Readiness Assessment and Analyze Data

 A.OCM.130 Build Communication Strategy and Change Management

Roadmap

A.ACT.DCMRCCI Deploy Change Management Roadmap / Communic

17

Page 18: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 18/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

 A.OCM.140 Develop Communication Campaign

 A.OCM.150.1 Conduct Change Management Roadmap / Communication

Campaign

A.ACT.LCOB Lifecycle Objective Milestone Summary A.PMC.LCOB Lifecycle Object Milestone

B ElaborationB.ACT.DPS Define Project Strategy

B.DS.020 Define Application Extension Strategy

B.TE.005.2 Determine Testing Requirements

B.TE.010 Develop Testing Strategy

  B.CV.020 Define Data Acquisition, Conversion and Data Quality

Strategy

B.DO.020 Define Documentation Standards and Procedures

B.TR.010.2 Define Training Strategy

B.TS.020.1 Define Cutover Strategy

B.ACT.DI Define Infrastructure  B.TA.020 Define Technical Architecture Requirements and Strategy

B.TA.030 Define Integration Requirements and StrategyB.TA.040 Define Reporting and Information Access Strategy

B.TA.050 Define Disaster Recovery Strategy

B.TA.060 Define System Operations and Management Strategy

B.TA.070 Define Initial Architecture and Application Mapping

B.TA.080 Define Backup and Recovery Strategy

B.TA.090 Develop Security and Control Strategy

B.ACT.PEE Prepare Environments-Elaboration  B.IM.007.1 Prepare Development Environment

B.TE.018.1 Prepare Static Test Data

B.TE.038.1 Prepare Integration Test Environment

B.TE.060.1 Prepare System Test Environment

B.CV.030.1 Prepare Conversion Environment (Initial Load)

B.DO.040 Prepare Documentation Environment

B.ACT.GBRE Gather Business Requirements - ElaborationB.RD.011.2 Develop Future Process Model

B.RA.055.1 Document Business Procedures

B.MC.030 Map Business Requirements

B.TA.006 Define Technical Prototype Subprojects

18

Page 19: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 19/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

B.ACT.DTP Develop Test PlansB.TE.015.1 Develop Integration Test Plan

B.TE.050.1 Develop System Test Plan

B.TE.080 Develop Systems Integration Test Plan

B.TE.082 Develop Acceptance Test Plan

B.MC.010.2 Define Business Data Structures

B.MC.040 Gather Setup Information

B.MC.050.1 Define Application Setups

B.MC.060 Document Functional Security

B.TE.025.1 Create System Test Scenarios

B.MC.070 Prepare Configuration Prototype Environment

B.MC.080 Conduct Configuration Prototyping Workshop

B.MC.090.2 Conduct Reporting Fit Analysis

B.ACT.PGA Perform Gap AnalysisB.MC.100 Define and Estimate Application Extensions

B.MC.110 Define Gap Resolutions

B.ACT.DUCM Develop Use Case Model

B.RA.021.2 Tell User StoryB.RA.023.2 Develop Use Case Model

B.ACT.CCPE Create Conceptual Prototype - ElaborationB.IM.005.2 Develop Conceptual Prototype

B.RA.030.2 Validate Conceptual Prototype

B.ACT.CS Consolidate SpecificationB.RD.042.2 Develop Glossary

B.RD.045.2 Prioritize Requirements (MoSCoW)

B.RD.140.2 Create Requirements Specification

B.RD.150.2 Review Requirements Specification

B.RA.025.2 Identify Candidate Services

B.RA.027.2 Identify Candidate Business Rules

B.RA.028.2 Populate Business Rules Repository

B.RA.180.1 Review Use Case Model

B.ACT.BSA Baseline Software ArchitectureB.RA.035 Develop High-Level Software Architecture Description

B.AN.040.1 Develop Analysis Architecture Description

B.DS.040.1 Develop Design Architecture Description

B.ACT.DUCD Develop Use Case DetailsB.RA.024.1 Develop Use Case Details

B.ACT.SSC Specify Software Configuration (Multiply Instantiated)

B.ACT.PVC Prototype and Validate Configuration

19

Page 20: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 20/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

B.ACT.AE Analyze - Elaboration  B.AN.035.1 Update Existing Analysis Specification

  B.AN.050.1 Analyze Data

B.AN.060.1 Analyze Behavior 

B.AN.070.1 Analyze Business Rules

B.AN.080.1 Analyze ServicesB.AN.085.1 Define Service

B.RA.026.1 Populate Services Repository

B.AN.090.1 Analyze User Interface

B.AN.100.1 Prepare Analysis Specification

B.AN.110.1 Review Analysis Model

B.ACT.DE Design - Elaboration  B.DS.035.1 Update Existing Design Specification

B.DS.050 Determine Design and Build Standards

B.DS.060 Define Business Rules Implementation Strategy

B.DS.070.1 Define SOA Implementation Strategy

B.DS.080.1 Design Software Components

B.DS.090.1 Design Data

B.DS.100.1 Design Behavior 

B.DS.110.1 Design Business RulesB.DS.120.1 Design Services

B.DS.130.1 Design User Interface

B.DS.140.1 Prepare Design Specification

B.DS.150.1 Develop Database Design

B.DS.160.1 Review Design Model

B.ACT.DCCTSE Develop Custom Component Test Scripts - Elaborati  B.TE.020.1 Develop Unit Test Scripts

  B.TE.035.1 Create Integration Test Scenarios

B.ACT.DSTSE Develop System Test Scenarios – ElaborationB.TE.025.2 Create System Test Scenarios

B.ACT.DVCSP Develop and Validated Custom Software Prototypes  B.IM.010 Develop Functional Prototype

  B.RA.085 Validate Functional Prototype

B.IM.020 Develop Architectural FoundationB.IM.085 Develop User Interface Standards Prototype

B.RA.095 Validate User Interface Standards Prototype

B.IM.040.1 Implement Database

B.IM.053.1 Register Services

B.IM.055.1 Perform Business Rules Implementation (Rules Engine)

20

Page 21: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 21/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

B.IM.060.1 Perform Component Review

B.ACT.PCCTE Perform Custom Component Testing - ElaborationB.TE.030.1 Perform Unit Test

B.TE.040.1 Perform Integration Test

B.ACT.PSTE Perform System Test – Elaboration

B.TE.070.1 Perform System Test

B.ACT.VUPE Validate Upgrade Process - Elaboration  B.TE.072.1 Test Pre-Upgrade Steps

B.TE.073.1 Test Packaged Software Upgrade

B.TE.074.1 Test Post-Upgrade Steps

B.TE.075.1 Perform Post-Upgrade Reconciliation Testing

B.TE.076.1 Review Upgrade Test Results

B.ACT.PPM Plan Performance Management  B.PT.020 Define Performance Management Requirements and

Strategy

B.PT.030 Define Performance Testing Strategy

B.PT.040 Identify Performance Testing Models and Scenarios

B.PT.050 Design Performance Test Scripts and Programs

B.PT.060 Design Performance Test Data and Load Programs

B.ACT.PACDE Prepare to Acquire and Convert Data - Elaboration

B.CV.025 Define Data Acquisition and Conversion Standards

B.RA.160 Conduct Business Data Source Gap Analysis

B.CV.027.1 Perform Data Mapping

B.RA.170.1 Conduct Data Quality Assessment

B.CV.035.1 Define Manual Conversion Procedures (Initial Load)

B.CV.040.1 Design Conversion Components (Initial Load)

B.CV.050.1 Prepare Conversion Test Plans (Initial Load)

B.CV.055.1 Implement Conversion Components (Initial Load)

B.CV.060.1 Perform Conversion Component Unit Test (Initial Load)

B.CV.062.1 Perform Conversion Component Business Object Test

(Initial Load)

B.CV.063.1 Perform Conversion Component Validation Test (Initial

Load)

B.ACT.PBPII Prepare Business Process Impact InventoryB.OCM.160 Prepare Business Process Impact Inventory

B.ACT.DCMRCCE Deploy Change Management Roadmap / CommuniB.OCM.150.2 Conduct Change Management Roadmap / Communication

Campaign

21

Page 22: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 22/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

B.OCM.155.1 Monitor Change Management Roadmap / Communication

Campaign Effectiveness

B.ACT.LCAR Lifecycle Architecture Milestone SummaryB.PMC.LCAR Lifecycle Architecture Milestone

C ConstructionC.ACT.FR Finalize Requirements  C.RD.042.3 Develop Glossary

C.RD.045.3 Prioritize Requirements (MoSCoW)

C.RD.130.2 Develop Baseline Architecture Description

C.RA.021.3 Tell User Story

C.RA.023.3 Develop Use Case Model

C.RA.024.2 Develop Use Case Details

C.RA.025.3 Identify Candidate Services

C.RA.027.3 Identify Candidate Business Rules

C.RA.028.3 Populate Business Rules Repository

C.RA.180.2 Review Use Case Model

C.ACT.AC Analyze - ConstructionC.AN.035.2 Update Existing Analysis Specification

C.AN.040.2 Develop Analysis Architecture Description

  C.AN.050.2 Analyze Data

C.AN.060.2 Analyze Behavior 

C.AN.070.2 Analyze Business Rules

C.AN.080.2 Analyze Services

C.AN.085.2 Define Service

C.RA.026.2 Populate Services Repository

C.AN.090.2 Analyze User Interface

C.AN.100.2 Prepare Analysis Specification

C.AN.110.2 Review Analysis Model

C.ACT.DC Design - ConstructionC.DS.035.2 Update Existing Design Specification

C.DS.040.2 Develop Design Architecture Description

C.DS.080.2 Design Software Components

C.DS.090.2 Design Data

C.DS.100.2 Design Behavior 

C.DS.110.2 Design Business Rules

C.DS.120.2 Design Services

C.DS.130.2 Design User Interface

C.DS.140.2 Prepare Design Specification

C.DS.150.2 Develop Database Design

22

Page 23: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 23/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

C.DS.160.2 Review Design Model

C.ACT.PTP Perform Test Planning  C.TE.015.2 Develop Integration Test Plan

C.TE.050.2 Develop System Test Plan

C.ACT.PEC Prepare Environments - Construction

  C.IM.007.2 Prepare Development EnvironmentC.TE.018.2 Prepare Static Test Data

C.TE.038.2 Prepare Integration Test Environment

C.ACT.DCCTSC Develop Custom Component Test Scripts - Construc  C.TE.020.2 Develop Unit Test Scripts

  C.TE.035.2 Create Integration Test Scenarios

C.ACT.DSTSC Develop System Test Scenarios - Construction  C.TE.025.3 Create System Test Scenarios

C.ACT.DSITS Develop Systems Integration Test Scenarios  C.TE.090 Develop Systems Integration Test Scenarios

C.ACT.ICC Implement Custom Components  C.IM.040.2 Implement Database

C.IM.050 Implement Components

C.IM.053.2 Register Services

C.IM.055.2 Perform Business Rules Implementation (Rules Engine)

C.IM.060.2 Perform Component Review

C.IM.070 Assemble Components

C.IM.080 Integrate Services

C.IM.090 Create Instal lation Routines

C.TE.065 Perform Installation Test

C.ACT.PCCTC Perform Custom Component Testing - ConstructionC.TE.030.2 Perform Unit Test

C.TE.040.2 Perform Integration Test

C.ACT.PST Prepare for System TestC.MC.050.2 Define Application Setups

C.TE.060.2 Prepare System Test Environment

C.ACT.PSTC Perform System Test - ConstructionC.TE.070.2 Perform System Test

C.RA.055.2 Document Business Procedures

C.TE.019.1 Collect, Assess and Refine KPI Measurements

C.ACT.PSIT Perform Systems Integration Test

23

Page 24: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 24/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

C.TE.085 Prepare Systems Integration Test Environment

C.TE.100 Perform Systems Integration Test

C.ACT.PPT Prepare for Performance Testing  C.PT.070 Build Performance Test Scripts and Programs

C.PT.080 Construct Performance Test Environment and DatabaseC.PT.090 Conduct Performance Test Dress Rehearsal

C.ACT.PT Prepare for Transition  C.TA.100 Define System Management Procedures

C.TA.110 Define Operational Testing Plan

C.TA.150 Define Final Platform and Network Architecture

C.TA.160 Define System Capacity Plan

C.ACT.PCO Prepare for Cutover C.TS.020.2 Define Cutover Strategy

C.TS.030 Develop Installation Plan

C.TS.040 Design Production Support Infrastructure

C.ACT.TI Test Infrastructure  C.TA.120 Conduct Operational Testing

C.TA.130 Conduct Backup and Recovery Test

C.TA.140 Conduct Disaster Recovery TestC.ACT.PACDC Prepare to Acquire and Convert Data - Construction

C.CV.027.2 Perform Data Mapping

C.RA.170.2 Conduct Data Quality Assessment

C.CV.035.2 Define Manual Conversion Procedures (Initial Load)

C.CV.040.2 Design Conversion Components (Initial Load)

C.CV.050.2 Prepare Conversion Test Plans (Initial Load)

C.ACT.ACDC Acquire and Convert Data-ConstructionC.CV.030.2 Prepare Conversion Environment (Initial Load)

  C.CV.055.2 Implement Conversion Components (Initial Load)

C.CV.060.2 Perform Conversion Component Unit Test (Initial Load)

C.CV.062.2 Perform Conversion Component Business Object Test

(Initial Load)

C.CV.063.2 Perform Conversion Component Validation Test (Initial

Load)C.CV.064.1 Install Conversion Components (Initial Load)

C.CV.065.1 Convert and Verify Data (Initial Load)

C.CV.068.1 Clean Data

C.ACT.VUPC Validate Upgrade Process - ConstructionC.TE.072.2 Test Pre-Upgrade Steps

24

Page 25: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 25/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

  C.TE.073.2 Test Packaged Software Upgrade

C.TE.074.2 Test Post-Upgrade Steps

C.TE.075.2 Perform Post-Upgrade Reconciliation Testing

C.TE.076.2 Review Upgrade Test Results

C.ACT.PD Produce Documentation

  C.DO.060 Publish User Reference ManualC.DO.070 Publish User Guide

C.DO.080 Publish Technical Reference Material

C.DO.100 Produce Online Help

C.ACT.DCMRCCC Deploy Change Management Roadmap / CommuniC.OCM.150.3 Conduct Change Management Roadmap / Communication

Campaign

C.OCM.155.2 Monitor Change Management Roadmap / Communication

Campaign Effectiveness

C.ACT.CJIA Conduct Job Impact AnalysisC.OCM.170 Collect and Analyze Job Change Data

C.OCM.180 Determine Impact of Job Changes

C.OCM.190 Prepare HR Transition Plan

C.ACT.CMAWC Conduct Managers' Alignment Workshop - ConstructC.OCM.200 Design Managers' Unit / Department Impact Workshop

C.OCM.210 Conduct Managers' Unit / Department Impact Workshop

C.ACT.DEUT Design End-User TrainingC.TR.060 Conduct User Learning Needs Analysis

C.TR.070 Develop User Learning Plan

C.ACT.BEUT Build End-User TrainingC.TR.080 Develop User Learningware

C.TR.090 Prepare User Learning Environment

C.ACT.TEUC Train End Users - ConstructionC.TR.100.1 Conduct User learning Events

C.ACT.IOCM Initial Operational Capability Milestone SummaryC.PMC.IOCM Initial Operational Capability Milestone

D Transition

D.ACT.SUAT Support User Acceptance Test  D.TE.105 Prepare Users for Testing

D.TE.110 Prepare Acceptance Test Environment

D.TE.120 Support Acceptance Test

25

Page 26: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 26/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

D.ACT.CPTST Conduct Performance Test  D.PT.100 Execute Performance Test

D.PT.110 Create Performance Test Report

D.ACT.PPE Prepare Production Environment  D.TS.050 Prepare Production Environment

D.TS.054 Perform Pre-Upgrade StepsD.TS.055 Upgrade Production Environment

D.TS.056 Perform Post-Upgrade Steps

D.TS.057 Revise Application Setups

D.ACT.CDT Convert Data - TransitionD.CV.064.2 Install Conversion Components (Initial Load)

  D.CV.065.2 Convert and Verify Data (Initial Load)

D.CV.068.2 Clean Data

D.ACT.DCMRCCT Deploy Change Management Roadmap / CommuniD.OCM.150.4 Conduct Change Management Roadmap / Communication

Campaign

D.OCM.155.3 Monitor Change Management Roadmap / Communication

Campaign Effectiveness

D.ACT.CITA Conduct IT AlignmentD.OCM.220 Prepare Assessment of Impact on IT Groups

D.OCM.230 Prepare IT Transition Plan

D.ACT.TEUT Train End Users - TransitionD.TR.100.2 Conduct User Learning Events

D.ACT.FD Finalize Documentation  D.DO.110 Finalize Documentation

D.ACT.GP Go ProductionD.TS.052 Implement Production Support Infrastructure

D.TS.058 Verify Production Readiness

D.TS.060 Go Production

D.TS.070 Shut Down Legacy System

D.ACT.SIP System in Production Milestone SummaryD.PMC.SIP System in Production Milestone

E ProductionE.ACT.MPSP Manage Production System Performance

E.PT.120 Conduct Production Performance Management

E.ACT.EPS Evaluate Production SystemE.TE.019.2 Collect, Assess and Refine KPI Measurements

E.PS.010 Audit System

26

Page 27: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 27/29

OUM to AIM Mapping

PHASE ACTIVITY OUM

TASK ID

OUM TASK NAME

E.ACT.RPP Resolve Production ProblemsE.PS.050 Analyze Problems

E.PS.060 Monitor and Respond to System Problems

E.ACT.DCMRCCP Deploy Change Management Roadmap / CommuniE.OCM.150.5 Conduct Change Management Roadmap / Communication

Campaign

E.OCM.155.4 Monitor Change Management Roadmap / Communication

Campaign Effectiveness

E.ACT.PF Plan for FutureE.RD.160 Convert Project Views to Reusable Viewpoints

E.PS.135 Determine Future Functional Enhancements

E.PS.140 Plan Enhancements

E.OCM.250 Measure Organizational Change Effectiveness

E.ACT.DITTP Deploy IT Transition PlanE.OCM.260 Implement IT Transition Plan

E.ACT.SO Sign Off Milestone SummaryD.PMC.SO Sign Off Milestone

27

Page 28: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 28/29

Manage Roles Implement RolesRole ID Role Name Role ID Role Name Specialized (Sub)RoPAD Project Administrator APS Application/Product Specialist

PM Project Manager BA Business Analyst

Project Lead(s) CMS Change Management Specialist

Functional Lead(s) DBA Database Administrator

Technical Lead(s) DD Database Designer

Team Members DES Designer

CPS Client Project Sponsor DV Developer

CPM Client Project Manager NE Network Engineer

SCM Steering Committee Member QM Quality Manager

SAD System Administrator

SAN System Analyst

SA System Architect IA - Information Architect

TRS Training Specialist

TE Tester

TW Technical Writer

Envision RolesRole ID Role Name Specialized (Sub)Ro

CMS Change Management Specialist

EA Enterprise Architect BAR - Business Architect

 AA - Application Architect

DA - Domain Architect

IA - Informaton Architect

TA - Technical Architect

SM Sales Manager

Solution ArchitectSOLA

Page 29: OUM Roles Mapping

8/10/2019 OUM Roles Mapping

http://slidepdf.com/reader/full/oum-roles-mapping 29/29

  lesRole NameBusiness Line Manager 

Client Assessment Team

Client Change Management Lead

Client Communication Specialist

Client Data Administrator Client Development Database Administrator 

Client Executive

Client Enterprise Archtiect

Client Enterprise Repository Manager 

Client Funtional Specialist

Client HR Specialist

Client Chieft Information Officer 

Client Production Database Administrator 

Client Project Manager 

Client Project Sponsor 

Client Stakeholder(s)

Client System Architect

Client System Administrator 

Client Software Development Lifecycle Staff 

Client System Expert

Client Staff Member 

Client Solution Architect

Client Chief Technology Officer 

Independent Quality Auditor 

IS Manager 

 Ambassador User 

IS Operations Staff 

IS Support Staff 

User 

Validation Coordinator 

Visionary