Upload
jimbuston
View
402
Download
4
Embed Size (px)
Citation preview
OMS SmartFitTM
Overview of Method
Two Steps:
Measuring
Fit-Up
Measuring
The separate video shows OMS setting up a laser measurement tool and measuring pipes
Measuring
Pipes Delivery by Cargo Barge
Cargo barge alongside Laybarge
Offloading Cargo Barge to Laybarge
Using the Crane to move measured pipe to the Laybargemain deck
Pipes Holding Area
Note Pipe Numbers
Diagram of Holding Area Pipes
632A 561B 922A 180A 672A
383A 579A 465B 429A 305A
472A 657A 649A 338A 534A309B
923A
Note physical position, pipe number, end
designator, and any anode pipes
Sequence Pipes
564_A to 831_B
0.8 mm HiLo 0.5 mm HiLo 0.15 mm HiLo
Step 3 – Number Pipes for Riggers
Bevelling
Sorted pipe loaded to bevelling inbound rack
Bevelling is done
Rotation Marking
Datum Marking
Best Rotation
Spacer crew aligns rotation mark
Pipe easily/quickly moved to best rotation
Minimise Hilo → line up clamp works better
Meet project HiLo specification
Best fit-up → best welding → avoid repairs
Tangible productivity benefit
Welding
Root Bead
Further welding passes
Check Fit-up
NDT & Field Joint Coating
Pipe exits the firing line
Installation
Pipeline is laid from the stinger
2
1
3
4
5
6
1. Note pipe numbers at stack on main deck
2. Use SmartFitTM PC to determine sequence
3. Mark sequence for riggers to load for bevelling
4. Rotation marking of pipes on ready rack
5. Datum marking of pipes on ready rack
6. Check spacer crew aligned pipes correctly
The whole process:
Recap…
Improve both fit-up speed and quality with OMS SmartFit™
‘The secret weapon for Project Managers’