Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
1
OConnor, Michael
From: James Coffin <[email protected]>
Sent: Thursday, May 18, 2017 2:43 PM
To: OConnor, Michael
Cc: Josh Platt ([email protected])
Subject: Masse Dam Removal
Attachments: DEP Response.pdf; Attachments 7&8.pdf; DEMO.pdf; C-2.pdf; C-3.pdf; C-4.pdf
Hi Mike,
I’ve attached the information that you asked for in your letter dated May 1st
for the Masse Dam removal. Let me know if
you have any questions.
Thanks,
Jim
James E. Coffin, P.E. Vice President E.S. Coffin Engineering & Surveying, Inc. P.O. Box 4687 432 Cony Road Augusta, Maine 04330
(207) 623-9475 Phone 1-800-244-9475 Toll Free (207) 623-0016 Fax
432 Cony Road (207) 623-9475 P.O. Box 4687 Fax (207) 623-0016 Augusta, ME 04330 1-800-244-9475
Professionals Delivering Quality Solutions H:\Land Projects 3\16049\DEP\DEP Response.doc
May 18, 2017
To: Michael O’Connor, Licensing Project Manager
Bureau of Land Resources, Land Division
17 State House Station
Augusta, Maine 043330017
Re: DEP Application #L273963EAN
Masse Dam Removal
Vassalboro, Maine
Dear Mr. O’Connor,
I have reviewed your letter dated May 1st
, 2017 in regard to the Masse Dam Removal Project and the
Full NRPA permit application that has been submitted to the DEP. The DEP has requested additional
information for the following:
1. Update Attachment 1 and Plan Drawings to include dimensions of Masse Dam and the
dimensions of the dam section you propose to remove.
We have added another detail sheet (C4) that depicts the dimensions and sections of the
dam that will be removed. In addition the length (39.78’) is depicted on the DEMO Sheet.
2. Update Plan Drawings depicting the location of the cofferdam and pump as well as the
route of the pumped water. Also update Attachment 8 with cofferdam details.
We have added a cofferdam and pump onto the Demo Plan (DEMO) and updated
Attachment #8 with the dewatering notes. We do specify the type of cofferdam as either
concrete waste blocks or sandbags wrapped in poly. We also show where the cofferdam
is located along with the pump, sediment forebay, etc. A detail of the sediment forebay
and spillway have been added to Sheet C3.
3. Provide additional information in Attachment 7 including estimated timeframes and
detailed descriptions for each step. For example, under “dewatering of the construction
site with cofferdam and pump”, provide a description of when this action will approximately
occur; the size, composition, and location of the cofferdam; where the water will be
pumped downstream; time it will take to construct and dewater the work zone; etc. Please
provide this level of detail for each step of the remaining work listed in Attachment 7.
This information has been added to Attachment #7.
This concludes our response to your letter and if you have any questions, please feel free to call
me at 6239475.
Sincerely,
James Coffin, P.E.
Attachment 7 – Construction Plan/Sequence
Removal of the Masse Dam and adjacent buildings will be accomplished using a multistep
process which will include the following:
� Stream draw down 7/20/2016
� Removal of the sawmill building and adjacent building to the south – 8/30/2016
� Revegetation planning with residents – 9/2016
� Seeding exposed banks with annual cover crop – 9/2016
� Work done in 2016 was completed under a DEP Permit by Rule
Remaining work will take place during the construction window in 2017.
Dewatering of the construction site with coffer dam and pump. This work will take
place immediately once the contractor arrives on site. A pooling area will be dug
adjacent to the cofferdam. The cofferdam can be constructed out of a variety of
different methods, but Cross Excavation will utilize stacked concrete waste blocks
(3’x6’x2’) or one cubic yard stacked sandbags, both of which will be wrapped with poly
up and over the top and keyed in at the bottom. The cofferdam location is shown on
the DEMO Plan along with the pump and hose. The water will be pumped out of the
cofferdam and into a sediment forebay immediately downstream from the work. The
forebay will allow solids to settle out and then the water will go through the spillway
and into the stream. A turbidity curtain provides the last measure of treatment before
flowing offsite. The time for this work is heavily dependent upon the water level
behind the dam and the weather, where rain will result in the work being prolonged.
Removal of existing dam and sluiceway down to original ledge. Once the water level has
been reduced, the dam and sluiceway removal will begin and this work should take no
more than three days. A hoe ram will be used to break up the dam and sluiceway and
then an excavator will load the rubble into dump trucks where it will be trucked away.
Stabilizing banks and existing retaining walls. Repairing the existing retaining walls and
Grist Mill foundation wall will also take place in dry conditions and will take one to two
weeks to complete. This involves the reuse or replacement of existing granite blocks
and filling in the voids with mortar. The retaining walls will also have a perforated 4”
diameter underdrained installed to alleviate hydrostatic pressure.
Final grading and seeding of site along with removing cofferdam, turbidity curtain,
sediment forebay, etc. This work will take three to seven days to complete depending
on weather conditions. It involves removing the cofferdam, turbidity curtain, filling in
the sediment forebay and pooling areas. Once complete the loaming and seeding of all
disturbed areas will take place. Hay mulch will be placed once the seeding is complete.
Watering will be needed on a daily basis to assure growth.
*Rebuilding of existing retaining walls along sections of north and south side of stream will
primarily utilize stone from existing wall for rebuild (See plan C3).
Attachment 8 – Erosion & Sedimentation Control Plan
The Erosion & Sedimentation Control Plan is included as Sheet C2. A dewatering section has
been added to Sheet C2 that explains how to dewater the site. The contractor will likely utilize
concrete waste blocks wrapped with poly and keyed in at the bottom for the cofferdam
construction. If not then sandbags wrapped with poly will be installed the same way as
mentioned above.