39
March 12, 2014

Northgate Station 90% design Presentation

Embed Size (px)

Citation preview

Page 1: Northgate Station 90% design Presentation

March 12, 2014

Page 2: Northgate Station 90% design Presentation

Tonight’s Agenda

6:00 p.m. - Open house

6:30 p.m. - Presentation

• Introductions Fred Wilhelm, Station Project Manager

• Maple Leaf Portal Construction Update Fred Wilhelm, Station Project Manager

• Northgate Station 90% design

David Hewitt, Station Architect

Cris Bruch, Station Artist

Mary Ann Peters, Station Artist

• Questions and answers

7:45 p.m. – Return to Open house

8 p.m. - Close

2

Page 3: Northgate Station 90% design Presentation

Link Light Rail System

• 16 miles of light rail with 13 stations

currently in service

• University Link under construction;

opens 2016

• ST2 Plan funded extensions to

Overlake, South King County, and

Lynnwood

• 54 mile system

3

Page 4: Northgate Station 90% design Presentation

Northgate Link Extension

• 4.3-mile light rail extension

• Stations at U District, Roosevelt, and

Northgate

• Open for Service: 2021

• 62,000 daily boardings added to

system by 2030

4

Page 5: Northgate Station 90% design Presentation

5

Northgate Station Schedule

Page 6: Northgate Station 90% design Presentation

Portal construction area 6

Page 7: Northgate Station 90% design Presentation

Construction sequencing

Portal Construction

• NE 95th St ductbank relocation

• Jet grouting

• Drill and install soldier piles

• Excavation and lagging

• Build Tunnel Boring Machine

(TBM) launch and support platform

• Build retaining walls

• Install construction wall

7

Page 8: Northgate Station 90% design Presentation

Construction activities - 3 week look ahead

Upcoming Construction Work

• Surface restoration of NE 95th St

• Continue excavation and lagging,

tieback installation and shotcreting

of head wall

• Storm drain installation

• Complete site preparation for Tunnel

Boring Machine (TBM) movement

8

Page 9: Northgate Station 90% design Presentation

Construction sequencing

Tunneling

• Assemble and launch tunnel

boring machines

• Remove tunneling spoils

• Supply tunnel construction

materials

9

Page 10: Northgate Station 90% design Presentation

1st Ave NE traffic detour - update

1st Ave NE Traffic Revision

• Southbound only between NE 92nd

Street and NE 100th St

• Currently in-effect through March

2014

• Potential extension through the

end of May as requested by the

contractor

10

Page 11: Northgate Station 90% design Presentation

Northgate Interim Park and Ride

Transit Parking Replacement

• New interim park and ride lot opens

for use on Monday March 17, 2014.

• North Seattle Park and Ride and

interim lot at Marie Callenders to

close same day.

• Interim lot (approx. 162 spaces) in

place through construction of

Northgate Station.

11

Page 12: Northgate Station 90% design Presentation

Alignment Plan – Community Connections 12

Page 13: Northgate Station 90% design Presentation

13

1st Ave NE Alignment

Page 14: Northgate Station 90% design Presentation

1st Ave NE - Support Facilities

14

Page 15: Northgate Station 90% design Presentation

Site Looking Northeast 15

Page 16: Northgate Station 90% design Presentation

Plaza looking Northwest 16

Page 17: Northgate Station 90% design Presentation

Plaza looking Northwest 17

Page 18: Northgate Station 90% design Presentation

Station Site and Section 18

Page 19: Northgate Station 90% design Presentation

19

Site Section at South Plaza

Page 20: Northgate Station 90% design Presentation

Site Section 20

Page 21: Northgate Station 90% design Presentation

Site Section at North Plaza 21

Page 22: Northgate Station 90% design Presentation

Sculpture Plan Rendering 22

Page 23: Northgate Station 90% design Presentation

Plaza looking Northwest 23

Page 24: Northgate Station 90% design Presentation

Site looking Northwest 24

Page 25: Northgate Station 90% design Presentation

25 Surface Plan/Longitudinal Section

Page 26: Northgate Station 90% design Presentation

Mezzanine Plan – East Elevation 26

Page 27: Northgate Station 90% design Presentation

Mezzanine looking North 27

Page 28: Northgate Station 90% design Presentation

Platform Plan – West Elevation 28

Page 29: Northgate Station 90% design Presentation

Platform looking North 29

Page 30: Northgate Station 90% design Presentation

Glass: Mezzanine Concept 30

Page 31: Northgate Station 90% design Presentation

Glass: Mezzanine Plan 31

Page 32: Northgate Station 90% design Presentation

Glass: Platform Concept 32

Page 33: Northgate Station 90% design Presentation

Glass: Platform Plan/Rendering 33

Page 34: Northgate Station 90% design Presentation

Glass: Elevations 34

Page 35: Northgate Station 90% design Presentation

Platform looking North 35

Page 36: Northgate Station 90% design Presentation

North Entry 36

Page 37: Northgate Station 90% design Presentation

Night view looking Northeast 37

Page 38: Northgate Station 90% design Presentation

Questions 38

Page 39: Northgate Station 90% design Presentation

Get Involved and Stay Informed

• Attend Final Design Open Houses

Learn more about your neighborhood

station’s design including bike

facilities, pedestrian and bike

connections and public art

• Sign Up to Receive Email Updates

www.soundtransit.org/subscribe

• Sound Transit Website

www.soundtransit.org/northlink

• Contact Rhonda Dixon:

206.398.5300

[email protected]

39