    NTPC HYDRO LIMITED

    ( A WHOLLY OWNED SUBSIDIARY OF NTPC Ltd.)

  • 7/31/2019 Nhl Presentation 14 12

    2/24

    BACKGROUND

    To be a partner in the hydro power development program, NTPC Ltd has made aforay into hydro power through its maiden venture KOLDAM HEPP and drawn up

    an ambitious plan of adding approx. 3500 MW in hydro sector by the end ofeleventh plan i,e by 2012.

    As estimated by Central Electricity Authority / Central Water Commission, 1/3rd oftotal hydro electric potential is from medium sized hydro electric project.

    Keeping this in mind and to boost NTPC Ltds capacity addition program in hydrosector, the corporation has set up a wholly owned subsidiary company named NTPCHydro Limited in December 2002 to provide exclusive thrust for accelerateddevelopment of medium scale hydro power projects.

    The main objective of the company is to develop small to medium size Hydroelectricpower project up to 250 MW capacity for generation of electricity.

    NHL started its maiden venture through LATA-TAPOVAN HEP, in the state ofUttarakhand.

  • 7/31/2019 Nhl Presentation 14 12

    3/24

    Since nature of NHLs business is similar to NTPC Ltds business, it is decided to follow DOP and other

    guidelines/ Circulars of NTPC Ltd

    Role of NHL:-

    Development of HydroElectric Power

    Construction Transmission line

    Manufacturing Trading and Other business

    Organization Structure

    Hydro Business development

    Presently NHL is having two prjects- Lata- Tapovan HEP and Ramam St. III HEP

    NHL - BOARD

    CEO

    Sh. R. Khetarpal

    C&M

    Headed by

    Sh. K.R. Mondal

    DGM (C&M)

    ENGINEERING

    Headed by

    Sh. A.K. Aggarwal

    DGM (Engineering)

    FINANCE

    Headed by

    Sh. S.S. Nagpal

    DGM (Finance)

    P&S

    Headed by

    Ms. Rashmi Varma

    Sr. Manager (P&S)

    HR

    Headed by

    Sh. S.N. Ramachandran

    Chief Manager (HR)

  • 7/31/2019 Nhl Presentation 14 12

    4/24

    LATA-TAPOVAN HYDRO ELECTRIC PROJECT

    (171 MW)

  • 7/31/2019 Nhl Presentation 14 12

    5/24

    LOCATION PLAN

    LATA TAPOVAN

    HEP

    TAPOVAN VISHNUGADHEP

    NTPC HYDRO

    LTD

    NTPC

    MANA

    BADRINATH

    CHAMOLI

    PIPALKOTHI

    LATA

    MARKURA

    MALARI

    GULABKOTHI

    TAPOVAN

    JOSHIMATH

  • 7/31/2019 Nhl Presentation 14 12

    6/24

    PROPOSED BARRAGE LOCATION

    128 M

  • 7/31/2019 Nhl Presentation 14 12

    7/24

    LATA-TAPOVAN HEP

    LOCATION : 270 KM FROM RISHIKESH AND

    27 KM FROM JOSHIMATH

    (ON JOSHIMATH-MALARI ROAD)

    POWER HOUSE : UNDERGROUND, 500 M

    UPSTREAM OF TAPOVAN-

    VISHNUGAD BARRAGE

    BARRAGE : 12 KM FROM TAPOVAN-

    VISHNUGAD BARRAGE

  • 7/31/2019 Nhl Presentation 14 12

    8/24

    LATA-TAPOVAN HEP

    TECHNICAL DETAILS

    TYPE OF SCHEME : Run of the River

    RIVER : Dhauli Ganga INSTALLED CAPACITY : 171 (3x57 MW)

    DIVERSION STRUCTURE : Barrage, 199.5 m,

    GATES : Radial, 11 M x 13.2 M

    HEAD : 309 M

    COST OF ENERGY : Rs 1.35 / Kwh

  • 7/31/2019 Nhl Presentation 14 12

    9/24

    LATA-TAPOVAN HEP

    TECHNICAL DETAILS

    HEAD RACE TUNNEL : 4.8 m Dia. , 7315 m Long

    ADITS : Two

    SURGE SHAFT : 7 m Dia., 140 m High PENSTOCKS : 3 nos, 2.2 m Dia., 299.5 m long

    POWERHOUSE : Underground, 91.4x20x42.5 m

    TURBINE : Francis Vertical Shaft, 3 Nos.

    TAIL RACE : 310 m, 4.8 m Dia.

    ANN. GEN. : 869 MU (54 % PLF)

    CONST. SCHEDULE : 5 years

  • 7/31/2019 Nhl Presentation 14 12

    10/24

    LATA-TAPOVAN HEP

    MOU between NHL and GOUA for execution ofLata Tapovan HEP signed on 18.08.03.

    Implementation Agreement between NHL andGOUA for execution of Lata Tapovan HEPsigned on 21.11.05.

  • 7/31/2019 Nhl Presentation 14 12

    11/24

    CEA accorded TEC for 171 MW i.e. 3x57 MWcapacity of the project on 08.02.06 at anEstimated Present Day Cost (Oct. 2005 PriceLevel) of Rs. 792.00 crores

    Environmental Clearance of MOEF obtained on

    21.02.07.

    Defence Clearance obtained on 22.06.07.

    LATA-TAPOVAN HEP

  • 7/31/2019 Nhl Presentation 14 12

    12/24

    LATA-TAPOVAN HEP

    Transfer of Forest Land (70.83 Ha): GOUA vide order dtd.23.06.07 diverted forest land for project use.

    Pvt. Land (3.804 Ha): Possession obtained on 4th and 5th

    Oct07. Mutation completed on 10.03.08.

    One time rehabilitation grantRs. 1 Lac per nalli to land

    losers

    ( including land cost)

  • 7/31/2019 Nhl Presentation 14 12

    13/24

    LATA-TAPOVAN PROJECT

    Geological and Geo-technical investigation was done by WAPCOS

    DPR was prepared by TCE Consulting Engineers Ltd

    Engineering Consultancy job placed on M/s Consulting Engineering

    Services (India) Pvt. Ltd.

    Implementation of project will be done in two EPC packages

    Civil including HM works package

    EM works package

    NIT for Civil including HM works package has been issued on12.11.2008

  • 7/31/2019 Nhl Presentation 14 12

    14/24

    RAMMAM St-III HEP (3 x 40 MW)

  • 7/31/2019 Nhl Presentation 14 12

    15/24

    PROJECT LAYOUT

  • 7/31/2019 Nhl Presentation 14 12

    16/24

    RAMMAM St-III HEP

    LOCATION : 130 KM FROM SILIGURI/ NEWJALPAIGURI AND 150 KM FROMBAGDOGRA AIRPORT / 80 KMFROM DARJEELING

    POWER HOUSE : SURFACE (DEEP SEATED)APPROX. 10KM FROMJORETHANG (SIKKIM) 80KMFROM SILIGURI

    BARRAGE : AT LODHOMAHAT(DARJEELING)- 130KM FROMSILIGURI

  • 7/31/2019 Nhl Presentation 14 12

    17/24

    RAMMAM St-III HEPTECHNICAL DETAILS

    TYPE OF SCHEME : Run of the River

    RIVER : RAMMAM

    INSTALLED CAPACITY : 120 (3x40) MW DIVERSION STRUCTURE : Barrage, 55 m

    GATES : Radial, 11 M x 7 M

    POWER INTAKE : Tunnel, D-Shape, 2 Nos.

    2.85 M Dia

    HEAD : 499 M COST OF ENERGY : Rs 1.67 / Kwh

  • 7/31/2019 Nhl Presentation 14 12

    18/24

    RAMMAM St-III HEPTECHNICAL DETAILS

    HEAD RACE TUNNEL : 3.5 m Dia. , 8200 m Long

    ADITS : One

    SURGE SHAFT : 14.5 m Dia., 52.5 m High

    PENSTOCKS : 1 no., 2.7 m Dia., 1526 mlong

    POWERHOUSE : SurfaceDeep Seated

    TURBINE : Vertical Pelton, 3 Nos.

    TAIL RACE CHANNEL : 4x3 M, 740 M ANN. GEN. : 474.36 MU

    CONST. SCHEDULE : 5 years

  • 7/31/2019 Nhl Presentation 14 12

    19/24

    RAMMAM StIII HEP

    Implementation Agreement between NHL and WBSEBfor execution of Rammam St- III HEP signed on28.04.05.

  • 7/31/2019 Nhl Presentation 14 12

    20/24

    RAMMAMSt-III HEP

    CEA accorded TEC for 120 MW i.e. 3x40 MWcapacity of the project on 12.09.06 at an

    Estimated Present Day Cost (Feb. 2006 PriceLevel) of Rs. 633.92 crores

    Environmental Clearance of MOEF obtained on17.08.07

    Defence Clearance obtained on 25.02.08

  • 7/31/2019 Nhl Presentation 14 12

    21/24

    RAMMAM StIII HEP

    ( IN SIKKIM )

    Transfer of Forest Land (1.927 Ha) Possession received on

    18.10.08

    Pvt. Land (5.256 Ha)Compensation distribution completed on

    23.09.08 and possession received on 26.09.08

    One time settlement on R & R package decided in VDAC

    meeting held on 22.05.07

  • 7/31/2019 Nhl Presentation 14 12

    22/24

    RAMMAM StIII HEP

    ( IN DARJEELING

    WB )

    Pvt.+ Govt. Land (64.496 Ha)

    Possession of land received on 15.09.08

    One time settlement on R & R package decided

    in VDAC meeting held on 18.12.07

  • 7/31/2019 Nhl Presentation 14 12

    23/24

    RAMMAM StIII HEP

    Geological, Geo-technical investigation and DPR was prepared by WAPCOS

    Engineering Consultancy job placed on M/s Karnataka Power CorporationLtd.

    Bridges and Approach Roads Package palced on M/s Nar Bahadur Dahal

    Implementation of project will be done in two EPC packages

    Civil including HM works package

    EM works package

    NIT for Civil including HM works package is expected to be issued on19.12.2008