Mu2e
Mu2e Status
Andy Hocker, Technical Division
All-Experimenters Meeting
8-JUN-2015
Mu2e
Project Highlights
• Received CD2/3b in March 2015– CD3b green-lit civil construction for Mu2e building, Transport
Solenoid coil module procurement
• CD3c in Spring 2016
A. Hocker, All-Experimenters Meeting2 8-JUN-2015
Mu2e
Mu2e Groundbreaking: 18-APR-2015
A. Hocker, All-Experimenters Meeting3 8-JUN-2015
8-JUN-2015
Mu2e
Solenoids
• Contract for Production and Detector Solenoids placed with General Atomics in CA
• Commercial bids for Transport Solenoid modules under review
• Prototype TS module test at CHL delayed due to compressor failure– ~1 month recovery, re-start
cooldown 22-JUN– Successful test ->
Production Readiness Review -> Place TS contract
• Seeking out alternatives to CHL for production module tests
A. Hocker, All-Experimenters Meeting4 8-JUN-2015
Mu2e
Cosmic Ray Veto (CRV) test beam run
A. Hocker, All-Experimenters Meeting5 8-JUN-2015
3m long scintillator extrusions w/ embedded fibers, SiPM readout at both ends
Mu2e
CRV test beam results
A. Hocker, All-Experimenters Meeting6 8-JUN-2015
Scan at near end only Read out at both ends
<#PE>/MIP = 85
Exceeds requirement by a factor of 1.8
Detailed studies of detector response
underway
Thanks Mandy R. and FTBF staff
Y. Oksuzian
Y. Oksuzian
Mu2e
Other recent highlights
• Review of remote target handling in March– Focus now on air handling, contamination control, robot design
• Software/computing review in March• Test of CsI (alternative) calorimeter prototype with 100 MeV
e- beam at Frascati in April– Time resolution exceeds requirements, E resolution OK
• AlCap test beam (+Al23 X) at PSI– Optimize internal shielding, STM– Finalize p multiplicity, E spectrum studies now– Additional run in fall for n multiplicity studies
• Prototype straw tracker panel built– Leak checking now, vacuum testing next
A. Hocker, All-Experimenters Meeting7 8-JUN-2015
Mu2e
Summary
• Good progress since last AEM– Received CD2, cost/schedule/scope now baselined– Long lead items (CD3a, 3b) are go
• 77 km of superconducting cable starts to arrive this summer• Solenoid fabrication starts next year• Experimental hall construction started
• Next major milestone is CD3c in spring 2016– Major simulation campaign underway (14M CPU-hrs)
• Running >10k jobs per day on OSG• Excellent support from SCD
– More design reviews, detector prototyping, beam tests