35
Department of Energy & Climate Change Development Consents and Planning Reform Team 3 rd Floor Area A 3 Whitehall Place London SW1A 2HD www.decc.gov.uk Tel: 0300 068 5770 Email: [email protected] 11 November 2010 Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham Northumberland NE46 4NU ELECTRICTY ACT 1989 (“the Act”) TOWN AND COUNTRY PLANNING ACT 1990 APPLICATION FOR CONSENT TO CONSTRUCT AND OPERATE A WIND TURBINE GENERATING STATION ON LAND AT RAY ESTATE, NEAR KIRKWHELPINGTON, NORTHUMBERLAND I THE APPLICATION 1.1 I am directed by the Secretary of State for Energy and Climate Change (“the Secretary of State”) to refer to the application dated 12 December 2005 (“the application”) on behalf of AMEC Project Investments Limited (“the company”) for both the consent of the Secretary of State unde r section 36 of the Act (“section 36 consent”) to construct and operate a 56MW wind turbine generating station on land at Ray Estate near Kirkwhelpington, Northumberland (“the Development”), and a direction under section 90(2) of the Town and Country Planning Act 1990 (“section 90 direction”) that planning permission for the Development be granted.

Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

Department of Energy

& Climate Change

Development Consents and Planning

Reform Team

3rd

Floor Area A

3 Whitehall Place

London SW1A 2HD

www.decc.gov.uk

Tel: 0300 068 5770

Email: [email protected]

11 November 2010

Mr David Hodkinson

Vattenfall Wind Power Ltd Bridge End Hexham Northumberland NE46 4NU

ELECTRICTY ACT 1989 (“the Act”)

TOWN AND COUNTRY PLANNING ACT 1990

APPLICATION FOR CONSENT TO CONSTRUCT AND OPERATE A WIND

TURBINE GENERATING STATION ON LAND AT RAY ESTATE, NEAR

KIRKWHELPINGTON, NORTHUMBERLAND

I THE APPLICATION

1.1 I am directed by the Secretary of State for Energy and Climate Change

(“the Secretary of State”) to refer to the application dated 12 December

2005 (“the application”) on behalf of AMEC Project Investments Limited

(“the company”) for both the consent of the Secretary of State under

section 36 of the Act (“section 36 consent”) to construct and operate a

56MW wind turbine generating station on land at Ray Estate near

Kirkwhelpington, Northumberland (“the Development”), and a direction

under section 90(2) of the Town and Country Planning Act 1990 (“section

90 direction”) that planning permission for the Development be granted.

Page 2: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

II PUBLIC INQUIRY

2.1 Following objections from the relevant planning authorities, Tynedale

District Council and Northumberland County Council, to the Application,

the Secretary of State was obliged to cause a public inquiry into the

Application to be held under Schedule 8 to the Electricity Act 1989. The

public inquiry also considered an application made by Steadings

Windfarm Limited, under section 36 of the Electricity Act 1989, to

construct and operate a wind turbine generating station on land near

Kirkwhelpington, Northumberland (“Steadings”) and an appeal by Wind

Prospect Developments Limited against the failure of Tynedale District

Council to determine within the statutory time period an application for

the erection and operation of 18 wind turbines on land at Green Rigg

Fell, Birtley Parish, Tynedale (“Green Rigg”).

2.2 The Secretary of State appointed Mr David M H Rose BA (Hons) MRTPI

(“the Inspector”), to preside over the public inquiry. The public inquiry

was governed by the Electricity Generating Stations and Overhead Lines

(Inquiries Procedure) Rules 2007 (“the Inquiries Procedure Rules”).

2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport,

between 15 January 2008 and 18 December 2008. The Inspector

submitted his Report of the public inquiry to the Secretary of State on 30

November 2009.

2.4 The Inspector‟s formal recommendation in relation to the Development was

as follows:

16.4 “I recommend that consent be refused under Section 36 of the Electricity

Act 1989 to construct, operate and decommission a wind farm generating

station of up to 56 megawatts capacity comprising 16 wind turbine

generators up to 125 metres high; site access roads; an electrical

Page 3: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

substation and compound; a wind farm monitoring mast; four temporary

borrow pits; and a temporary compound and temporary component

storage area on land at Ray Estate, near Kirkwhelpington,

Northumberland; and that a direction under section 90(2) of the Town

and Country Planning Act 1990 be not given.

16.5 In summary, the only reason for recommending refusal is the uncertainty

surrounding the implementation of appropriate measures to mitigate the

adverse impacts of the proposal on the operations of NERL and NIAL.

Such uncertainty would undermine the rationale for imposing a Grampian

condition in that the condition might not be fulfilled; and consent for the

project could preclude other wind farm projects from coming forward in

the locality.

16.6 In the event that the Secretary of State disagrees with my conclusions

and recommendation, a list of recommended conditions to be imposed

on any consent and deemed approval is set out in Appendix B(ii) for

consideration.”

III PREVIOUS SECRETARY OF STATE‟S CONSIDERATION OF THE

APPLICATION

3.1 After receiving the Inspector‟s Report, the then Secretary of State

carefully considered it, together with the views of the relevant planning

authorities, the objections received, other representations made to him

by various bodies, the environmental information (see section VIII below)

and all other matters he considered relevant.

3.2 His conclusions are set out in a letter dated 25 March 2010 addressed to

David Hodkinson of Amec Wind Energy (“the minded to letter”). A copy of

that letter is annexed to this letter.

Page 4: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

3.3 In summary, the then Secretary of State was minded to agree with the

Inspector‟s conclusions with the exception of his conclusion in respect of

the imposition of a “Grampian” condition concerning mitigation of impacts

on the operations of National Air Traffic Services (“NATS”) (En-Route)

Limited (“NERL”) and Newcastle International Airport Limited (“NIAL”).

The then Secretary of State disagreed with the Inspector‟s conclusion in

that respect after taking account of developments since the close of the

public inquiry.

IV DEVELOPMENTS SINCE THE PUBLIC INQUIRY CLOSED

4.1 The Department of Energy and Climate Change (DECC) and its

predecessor Departments have been working for several years with

NERL and the sole supplier of NERL‟s radar, Raytheon Canada, to find a

technical solution to the unacceptable impacts of wind turbines on

aviation radar. Following a Department of Trade and Industry funded

feasibility study in 2007, NERL put forward a proposal for a 2-year

research and development project to develop and test a software

upgrade to the Raytheon radar to mitigate wind turbine interference.

4.2 DECC, The Crown Estate (TCE) and developers contracted with NATS

to deliver an R&D programme for the Raytheon radar. Each party

committed to funding a specific proportion of the work. This is a 19 month

programme of work, which is being undertaken by NATS staff and

Raytheon Canada Ltd. It is jointly funded by DECC, TCE and NATS,

under a contract signed in October 2009.

4.3 Work on the project commenced in September 2009 and should be

complete in July 2011. The Secretary of State was not aware at the time

of the minded to letter of any reason to suggest that the trial would not be

concluded satisfactorily.

Page 5: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

V. PREVIOUS SECRETARY OF STATE‟S PROPOSED DECISION ON

THE APPLICATION

5.1 The minded to letter set out the reasons why the then Secretary of State

was minded to grant section 36 consent and issue a section 90 direction

for the Development.

5.2 He accepted the Inspector‟s findings on the section 36 application in all

respects other than the question of whether it was appropriate to impose

a Grampian condition to ensure mitigation of the adverse impacts on the

operations of NIAL and NERL where he was minded to accept that the

new information referred to in paragraphs 4.1– 4.3 of the minded to letter

changed the planning balance to the extent that it would be appropriate

to impose such a condition. In his judgment, this information indicated

that there was a reasonable prospect that the new Raytheon radar

would, within the next five years, be available and capable of mitigating

to a satisfactory extent adverse impacts on the operations of NIAL and

NERL.

5.3 He believed that planning conditions set out in Appendix B(ii) of the

Inspector‟s report would form a sufficient basis on which the

development might proceed. He was therefore minded to give a section

90 direction that planning permission for the Development be deemed to

be granted subject to planning conditions in substantially the form to be

found at Annex E to the minded to letter.

5.4 However, in accordance with regulation 21(6) of The Electricity

Generating Stations and Overhead Lines (Inquiries Procedure) (England

and Wales) Rules 2007, he was first required to notify in writing the

persons entitled to appear at the inquiry, who appeared at it, of his

disagreement with the Inspector‟s recommendations and the reasons for

it; and afford them an opportunity of making written representations to

Page 6: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

him or of asking for the re-opening of the inquiry. This was because, in

disagreeing with the Inspector, he proposed to take into account new

evidence or matters of fact in relation to the new Raytheon radar which

were not available to the Inspector.

VI. REPRESENTATIONS RECEIVED IN RESPONSE TO THE MINDED TO

LETTER

6.1 Responses to the minded to letter were received from Vattenfall Wind

Power Ltd, NERL, NIAL, The Revd John Wylam (a former Chairman of

Thockrington Parochial Church Council), Mr Malcolm Reid and the

Campaign for Responsible Energy Development in Tynedale (CREDIT).

The responses are summarised below with the Secretary of State‟s

observations on those responses in italicised text below the responses.

6.2 NERL made representations in respect of the “minded to grant consent

letter” on 29 April 2010. They made the following points:

6.2.1 “SoS has provided insufficient details of the new evidence on

which he is relying to depart from Inspector’s recommendations

6.2.1.1 It is unfair for SoS to proceed to a decision without

providing full details of the new evidence.”

DECC has provided full details of the new evidence to all parties in

subsequent correspondence.

6.2.2 “SoS has insufficient factual basis to depart from Inspector’s

recommendations

6.2.2.1 The “new evidence” reveals nothing that was not known to /

anticipated by the Inspector:

Page 7: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

(a) it was expected that matters would reach the stage that

they now have (and indeed, that they would do so sooner than

they in fact have);

(b) NERL gave expert evidence that design and prototyping

would take 3 years and procurement and instalment a further 2

years;

(c) the Inspector concluded that the balance of the evidence

was that “assuming no material setbacks”, it could be delivered

within a period of some 5 years;

(d) NERL did not suggest at the inquiry that the R&D

programme would not begin, merely that there had been delays at

this stage.”

On point (a), the Secretary of State is of the view that the fact that the

research and development trial of the Raytheon radar has been funded

and has begun since the conclusion of the Inquiry is a new material fact.

It cannot have been known for certain during the Inquiry that the

research would proceed. Indeed the fact that in NERL’s opinion progress

has been slower than anticipated merely shows the level of uncertainty

that surrounded the potential funding and progress of the Raytheon

research at the time of the inquiry. Points (b) and (c) are true but in

themselves do not undermine the Secretary of State’s conclusions. On

point (d), as before, the anticipated timescales at inquiry have been

overtaken by events and actual progress made in the R&D programme,

which in the view of the Secretary of State must be taken into account in

the consideration of his decision.

Page 8: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

6.2.3 “At present, there is no justification for consenting the

Development subject to a Raytheon-based suspensive condition on

radar impact mitigation

6.2.3.1 SoS has stated that he does not disagree with the

Inspector‟s conclusions as reached based on the material before the

Inquiry, but considers that securing of funding for R&D into Raytheon

solution changes the planning balance.”

It is the Secretary of State’s opinion that the securing of funding and the

progress made to date in the R&D does indeed change the planning

balance in respect of potential for successful mitigation of civil aviation

radar impacts within the timescale of the consent. The securing of the

funding for the R&D is a not insignificant stage to reach and the financial

investment made in the project so far would suggest, if the research

continues to progress satisfactorily, that future funding might be rather

more likely to be forthcoming (as participants are likely to be keen to

ensure that the current investment is not wasted and the benefits of a

successfully developed Raytheon system, which could apply to many

developments, can be unlocked).

6.2.3.2 “The Inspector said that given the “high hurdles” to be

overcome and “fundamental uncertainties” as to Raytheon‟s success, “it

was not possible to say with any reasonable degree of confidence that

Raytheon was likely to be available within a foreseeable and reasonable

time-frame”.”

The SoS is of the view that there is now a reasonable prospect of

Raytheon being available within 5 years of the date on which the consent

for the Development is being issued.

Page 9: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

6.2.3.3 “The high hurdles referred to were success in the R&D

project and securing of funding for the next stage (not commencement of

the R&D project). Neither of these has yet been overcome.”

The Secretary of State takes the view that the funding and

commencement of the R&D project was a high hurdle in terms of the

overall project and given that the funding for that stage had not been

secured by the close of the inquiry, it seems unlikely that the Inspector

would have viewed it differently. While the Secretary of State accepts

that there will be other “high hurdles” for the project to clear before it is

successfully concluded, he is unaware of any information to suggest that

the project is not progressing satisfactorily.

6.2.3.4 “Inspector concluded and SoS has accepted that there may

be circumstances where a suspensive condition should not be imposed

where the lack of a reasonable prospect of implementation would have

harmful planning consequences or there is no prospect whatsoever of

the specified action being performed within the time limit of the

permission.”

The same paragraph of the Inspector’s report (15.395) also notes: “the

Secretary of State’s current policy is that the imposition of Grampian

conditions should not be precluded solely because there is no

reasonable prospect of the action in question being performed within the

time limit of the permission”. Elsewhere in the Report, reference is made

to the fact “the House of Lords established that the mere fact that a

desirable condition, worded in a negative form, appears to have no

reasonable prospects of fulfilment does not mean that planning

permission must necessarily be refused as a matter of law”. But in any

event this is not a case where the Inspector found that there was no

reasonable prospect of the proposed suspensive condition being fulfilled.

What he said was: “it is not possible to say with any reasonable degree

of confidence that Raytheon is likely to be available within a foreseeable

Page 10: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

and reasonable time-frame”. That is a different point, and when the

Inspector goes on to say: “For this reason, I consider that it would be

inappropriate to rely on this as an imminent mitigating technology and the

basis for a suspensive condition”, the Secretary of State is entitled to,

and does, take a different view, not least given the passage of time and

progress of the R&D project.

6.2.4 “Consenting the Development subject to a Raytheon-based

suspensive condition is contrary to DECC’s policy because it would

make it harder for other wind farm applications in the area to

succeed”

6.2.4.1 “A “banked” Ray consent would diminish the prospects of

consent for other projects because it would form part of the baseline for

cumulative impact assessments, whether of radar or other adverse

effects. Since the suspensive condition might never be fulfilled and Ray

therefore never built, it might be better not to let it potentially obstruct

other proposals in this way. Consenting Ray therefore militates against

the promotion of renewable energy.”

In respect of radar, for any given turbine in another project, one of two

outcomes is possible: either the presence of the Development would give

rise to cumulative adverse impacts or the presence of the Development

would not give rise to cumulative adverse impacts. The outcome of there

being no cumulative impacts presents no problems for present purposes.

The outcome of there being cumulative impacts would only be a problem

if cumulative adverse impacts were not addressed by a Raytheon

solution. But the purpose of the suspensive condition is that such

impacts should be addressed, which is why it requires the putting in

place of measures to prevent or remedy any adverse impacts on the

relevant radar systems: there is no reason to suppose that this

requirement will not include prevention or remedying of cumulative

effects. Similarly, the minded to grant consent letter was clear that “no

Page 11: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

potential solution to mitigate the impacts of (the Development) on

NERL’s and NIAL’s operations would be acceptable unless the

cumulative level of impacts on the primary radars were to remain at an

acceptable level after the implementation of the proposed mitigation.”

It is possible that other proposed wind farms may have cumulative

impacts, other than radar impacts, when assessed alongside the

Development which they would not otherwise have. However, the

Secretary of State notes the Inspector’s opinion that the Development

proposal was “well developed with few impediments to implementation”

and that “any other proposals, which might be waiting to come forward,

are likely to take some time to come to fruition”. With that in mind and

with due consideration of the amount of renewable energy that the

Development would provide and the need for that energy, he takes the

view that there is no clearly better alternative proposal which would be

certain of benefitting should the Development not be granted consent.

6.2.4.2 “There is no basis for Secretary of State‟s view that other

projects in the area are likely to require similar mitigation and therefore

are unlikely to have a greater chance of success than the Development:

(a) In 2007, NERL raised no objections to 94% of wind farm

consultations received, even though at least 81% were predicted to

have some form of detrimental impact on NATS‟s systems.

(b) The mere fact of other projects being in the same part of

Northumberland as the Development does not mean they would give

rise to similar radar issues.”

(a) The Secretary of State notes the 2007 figures quoted by NERL but

does not consider that they have any specific relevance to the

Development.

Page 12: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

(b) The Secretary of State also notes that according to the annex

supplied by NERL, they have objected to 8 proposed wind farms in

the area. While he accepts that there may be sites which do not give

rise to radar issues, he does not consider that he is able to assert that

applications brought forward would have a greater chance of

success, taking into account all impacts, than the Development, the

application for which is at an advanced stage.

6.2.4.3 “Raytheon remains inherently uncertain and even if

successful, is not expected to work in all cases or be 100% effective.

This means that if the Development is consented, NERL will have to

maintain objections to developments comprising 42 turbines as a result,

because until a Raytheon solution is in place and shown to be fully

effective, NERL will have to assume a significant degree of visibility of

any other proposal which relies on a Raytheon suspensive condition for

radar impact mitigation.”

Any objection by NERL will be a matter for the decision maker in such

future cases. The decision on the Development does not set a precedent

for how such applications should be treated.

6.2.5 "SoS should re-open the public inquiry before deciding to consent 6.2.5.1 New evidence should be tested before the Inspector,

subject to cross-examination etc. (“as a matter of fairness, NERL should

be entitled to an oral hearing with the opportunity to present detailed

technical evidence on what is a very technical and esoteric subject…”).”

NERL has not disputed the substance of the new evidence. Therefore

there is nothing to be gained by “testing” it in front of any Inspector. It is a

matter of what weight the Secretary of State chooses to place on the new

evidence.

Page 13: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

6.2.5.2 “Without a public inquiry, SoS cannot properly consider the

implications of granting consent to Ray with a suspensive radar condition

based on Raytheon, in terms of the knock-on adverse effect on other

projects coming forward.”

The Secretary of State does not agree with this assertion as, taken to its

logical conclusion, it might mean postponing decisions on any project

which raises radar concerns in the area until the Raytheon solution is

implemented. Such delay is unnecessary given that suspensive

conditions such as that included in this consent provide full protection for

civil aviation interests. As stated above, the Secretary of State is aware

that granting consent to the Development may produce cumulative

impacts for other proposals but does not consider that that outweighs the

benefits of granting the Development subject to a suspensive condition.

6.2.6 “Form of suspensive condition proposed is unsatisfactory 6.2.6.1 It is wrong to refer to the Civil Aviation Authority (“CAA”) rather

than NERL as the body to be consulted on proposed mitigation.”

The Secretary of State is content to refer to NERL rather than CAA in

the condition. Further he has decided to amend the draft conditions

dealing with mitigation of radar impacts which the Inspector suggested, in

order to avoid unnecessary complexity so that there should be only one

condition to deal with the radar impacts on both national air traffic

services and Newcastle International Airport. Because of the

understandable sensitivity of this issue, which may also attend the

discharge of the condition, he has decided that the mitigation of impacts

of aviation should be dealt with by a condition in the s36 consent and that

he will be responsible for discharging it (in consultation with air traffic

service providers as set out in the full condition).

6.3 In a letter dated 5 May 2010 NIAL adopted the findings of NERL and

asked that the Secretary of State review his position and refuse consent

for Ray or re-open the inquiry in order to allow the Inspector to consider

Page 14: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

whether there is any „new evidence or matters of fact‟. Our consideration

of NERL‟s response therefore also covers NIAL‟s response.

6.4 In a letter dated 14 April 2010, the Campaign for Responsible Energy

Development In Tynedale (“CREDIT”) considered that as high hurdles

still remain in respect of financing the Raytheon solution, the Secretary of

State‟s „optimism about overcoming what the Inspector referred to as

these “high hurdles” appears to be somewhat misplaced‟.

The Secretary of State acknowledges that hurdles do remain before it

can be shown for certain that the Raytheon solution will provide

appropriate mitigation for the radar impacts of the Development.

However, he considers that not all of those hurdles need to cleared

before it is reasonable to grant consent with a suspensive condition and

that the progress made since the close of the Inquiry is sufficient to justify

that course of action.

6.5 Although the “minded to grant consent” letter did not invite

representations on issues other than civil aviation, CREDIT also

responded that to grant consent for the Development would be

inconsistent with Regional Spatial Strategy (RSS) and that the proposed

noise condition would not be suitable to deal with complaints in respect

of cumulative wind farm noise.

As to the RSS, this was considered at the public inquiry and dealt with by

the Inspector in his report where he found “no material conflict with the

development plan as a whole”. The Inspector also specifically

considered cumulative noise impacts and stated that “In relation to the

concerns expressed by CREDIT … about the ability to monitor the noise

from one wind farm with one or more other wind farms operating at the

same time, the recommended conditions … are designed to provide the

appropriate mechanism.” The Secretary of State agrees with the

Page 15: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

Inspector that the proposed noise conditions would allow for investigation

in the case of complaint about cumulative noise from wind farms.

6.6 The Revd John Wylam cited the effect of the development on the

„unique and highly specialized Spadeadam facility.‟

As to military aviation, the Inspector had found that there was “no robust

evidence to show that any of the schemes, or any combination of the

schemes, would result in material adverse effects on operations as a

whole or on the efficacy of training at RAF Spadeadam”.

6.7 Vattenfall agree with the “minded to grant consent” position in that the

information that has been made available since the Inquiry should lead to

consent being granted. They are content for any consent to be

conditioned in respect of the aviation issues and have no objection to the

condition including a provision where „parties (are) required to be

consulted prior to an approval of and implementation of the mitigation

scheme‟ which would protect the interests of NERL and NIAL. They see

no reason or justification for the re-opening of the inquiry.

6.8 Mr Malcolm Reid has written in favour of granting consent to the Ray

windfarm and cites aviation as a problem in the consenting process.

VII. SECRETARY OF STATE‟S CONSIDERATION OF THE APPLICATION

7.1 The Secretary of State has carefully considered the Inspector‟s Report,

the views of the relevant planning authorities, the objections received,

other representations made to him by various bodies, the environmental

information (see paragraphs 8.1 to 9.3), the responses to the minded to

letter and all other matters he considers relevant.

7.2 He notes that, amongst other matters, the Inspector considered:

Page 16: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

whether the proposed developments are in accordance with the relevant

development plans

whether the proposed developments are consistent with energy policy

the justification of the sites

the visual and landscape impact of the proposed developments including

on the Northumberland National Park and North Pennines AONB

noise impacts

aviation interests

impact on the historic environment

·tourism and economic impacts

construction traffic

ecology and hydrology

borrow pits

grid connections

human Rights.

7.3 The Secretary of State has carefully studied the Inspector‟s report, and in

particular the Inspector‟s conclusions and recommendations, which, with

Page 17: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

the exception of his conclusion and recommendation in respect of the

imposition of a “Grampian” condition concerning mitigation of impacts on

the operations of NERL and NIAL, the Secretary of State is minded to

accept. The Secretary of State‟s reasons for disagreeing with the

Inspector on this one point are those which are set out in the minded to

letter which are repeated above at paragraphs 5.2 to 5.4 and to which he

adheres notwithstanding the responses to that letter which he has

received from objectors to the Development for the reasons set out in

paragraphs 6.1 to 6.6 above.

VIII. SECRETARY OF STATE‟S CONSIDERATION OF THE ENVIRONMENTAL INFORMATION

8.1 The Secretary of State is satisfied that the Environmental Statement is

sufficient to allow him to make a determination of the section 36

application.

8.2 The Electricity Works (Environmental Impact Assessment) (England and

Wales) Regulations 2000 (the 2000 Regulations”) prohibit the Secretary

of State from granting section 36 consent unless he has first taken into

consideration the environmental information, as defined in those

regulations.

8.3 The Secretary of State has considered the environmental information

carefully; in addition to the Environmental Statement (ES), he has

considered the comments made by the local planning authority, those

designated as statutory consultees under regulation 2 of the 2000

Regulations and other consultees and objectors.

8.4 Taking account of the extent to which any adverse environmental effects

will be modified and mitigated by measures that the company has agreed

to or will be required to take either under the conditions attached to the

section 36 consent or the planning conditions which he has decided to

Page 18: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

include in the section 90(2) direction, the Secretary of State believes that

any remaining adverse environmental effects will not be such that it

would be appropriate to refuse section 36 consent for the Development

or the deemed planning permission.

IX SECRETARY OF STATE‟S CONSIDERATION OF THE

CONSERVATION OF HABITATS AND SPECIES REGULATIONS 2010

9.1 Regulation 61 of The Conservation of Habitats and Species Regulations

2010 (“the 2010 Regulations”, which so far as is material for the

consideration of the company‟s application have replaced the

Conservation (Natural Habitats, &c.) Regulations 1994) requires the

Secretary of State to consider whether the development would be likely

to have significant effects on a European Site, as defined in the 2010

Regulations.

9.2 In the event of such an effect he must undertake an appropriate

assessment of the implications for the European site in view of its

conservation objectives. The section 36 consent may only be granted if it

has been ascertained that the development will not adversely affect the

integrity of such a site unless there are no feasible alternatives and

imperative reasons of overriding public interest apply.

9.3 The Secretary of State notes there are European interest features in the

vicinity of the site: namely Hen Harriers, blanket bogs and potentially,

bats. He has been informed by Natural England that provided the

proposed Development is constructed and operated in accordance with

the details contained in the Environmental Statement, and the conditions

proposed by Natural England, the proposal would not adversely affect

these features. The Secretary of State notes that Planning Conditions

(21) – (30) cover these matters including restrictions on the timing of

construction and a hen harrier management plan. The Secretary of State

Page 19: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

does not therefore believe that the Development is likely to have a

significant effect on any European interest feature and finds no reason

for refusing section 36 consent on these grounds.

X SECRETARY OF STATE'S DECISION ON THE APPLICATION

10.1 The Secretary of State, having regard to the matters specified in

sections, VII, VIII and IX above, has decided to grant consent for the

Development pursuant to section 36 subject to: (i) a condition that the

Development shall be in accordance with the particulars submitted with

the Application, (ii) a condition as to time within which the Development

must commence, and (iii) a condition in respect of civil aviation impacts.

10.2 The Secretary of State believes the Planning Conditions form a sufficient

basis on which the Development might proceed, and therefore he

has decided to issue a section 90(2) direction that planning permission

be deemed to be granted subject to the Planning Conditions. The section

90(2) conditions follow those attached to the minded to letter apart from:

(i) the removal of the two conditions on radar matters and their

replacement by a single condition of the section 36 consent (see above);

(ii) the insertion of explicit requirements on the local planning authority to

consult Natural England in relation to various environmental matters

when administering the Planning Conditions; and (iii) alterations

designed to improve the clarity of individual provisions; and (iv) pure

drafting changes made for reasons of style or internal consistency.

10.3 I accordingly enclose the Secretary of State's consent under section 36

of the Electricity Act 1989 and a direction under section 90(2) of the

Town and Country Planning Act 1990.

XI. DISTRIBUTION

Page 20: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

Copies of this letter have been sent to the main parties and individuals

listed in the Inspector‟s Report.

XII. GENERAL GUIDANCE 12.1 The validity of the Secretary of State‟s decision may be challenged by

making an application to the High Court for leave to seek a judicial

review. Such application must be made as soon as possible and in any

event not later than three months after the date of the decision. Parties

seeking further information as to how to proceed should seek

independent legal advice from a solicitor or legal adviser, or alternatively

may contact the Administrative Court at the Royal Courts of Justice,

Strand, London WC2 2LL (General Enquiries 020 7947 6025/6655).

12.2 This decision does not convey any approval or consent or waiver that

may be required under any enactment, by-law, order or regulation other

than section 36 and Schedule 8 of the Electricity Act 1989 and section 90

of the Town and Country Planning Act 1990.

XIII. COSTS

The company made an application for an award of costs against the

Ministry of Defence during the course of the inquiry. The Secretary of

State is still considering matters arising from the Inspector‟s separate

report on the question of such an award and will issue a decision on it in

due course.

Yours faithfully Giles Scott Head of Development Consents and Planning Reform

Page 21: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

DEPARTMENT OF ENERGY AND CLIMATE CHANGE ELECTRICITY ACT 1989

CONSTRUCTION AND OPERATION OF A WIND TURBINE GENERATING STATION ON LAND AT RAY ESTATE NEAR KIRKWHELPINGTON, NORTHUMBERLAND

1. Pursuant to section 36 of the Electricity Act 1989 the Secretary of State for Energy and Climate Change (“the Secretary of State”) hereby consents to the construction by AMEC Project Investments Limited (“the Company”), on the area of land delineated by a solid red line on Drawing Drg No 6106-530-PA-001, annexed hereto and duly endorsed on behalf of the Secretary of State, of a wind turbine generating station on land at Ray Estate near Kirkwhelpington, Northumberland (“the Development”), and to the operation of that generating station. 2. Subject to paragraph 3(1), the Development shall be over 50MW capacity and up to 56 MW capacity and comprise:

(a) Up to 16 wind turbine generators with a capacity of 3MW or more, each with a height no greater than 125 metres from the ground to blade tip;

(b) One anemometry mast, not exceeding 80 metres in height; (c) An electricity substation building and underground electrical cabling

connections; (d) 14 kilometres of maintenance tracks for access to the wind turbines; (e) Four temporary borrow pits; and (f) Associated plant, buildings and civil engineering works.

3. This consent is granted subject to the following conditions:

(1) The Development shall be constructed and operated in accordance with the details contained in paragraph 2 of this consent, the application dated 12 December 2005 and the accompanying Environmental Statements, subject to such minor changes as may be approved by the local planning authority pursuant to the requirements of deemed planning permission.

(2) The commencement of construction of the Development shall not be later than five

years from the date of this consent, or such longer period as the Secretary of State may hereafter direct in writing.

(3) No turbine forming part of the development shall begin to be constructed until the Secretary of State, having consulted with the air traffic services providers, is satisfied that civil aviation impact mitigation will be implemented and maintained for the life of the development and that arrangements have been put in place to ensure that such mitigation is implemented before the development gives rise to any adverse impact on air traffic services for civil aviation.

In this condition:

“air traffic services providers” means NERL, NIAL, or any other person who, in the future, shall be under a duty to provide the air traffic services to civil aviation which NERL or NIAL is, at the date of this consent, obliged to provide in an area which includes the development;

Page 22: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

“civil aviation impact mitigation” means measures to prevent or remove any adverse impacts which the operation of the development would, but for the implementation of such measures have on the air traffic services providers‟ ability to provide safe and efficient air traffic services to civil aviation in an area which includes the development during the lifetime of the development in respect of which any necessary stakeholder consultation has been completed and any necessary approvals and regulatory consents have been obtained;

“NERL” means NATS (En Route) plc, registered under the Companies Act (4129273) whose registered office is 5th Floor, Brettenham House South, Lancaster Place, London WC2E 7EN; and

“NIAL” means Newcastle International Airport Limited, Newcastle Airport, Woolsington, Newcastle upon Tyne, NE13 8BZ, registered under the Companies Act (02077766).

Reason: To ensure that the development does not adversely affect the ability of the air traffic services providers to provide safe and efficient air traffic services in the area of the development by means of air traffic control radar.

Page 23: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

DIRECTION TO DEEM PLANNING PERMISSION TO BE GRANTED UNDER SECTION

90 OF THE TOWN AND COUNTRY PLANNING ACT 1990

CONSTRUCTION AND OPERATION OF AN OVER 50MW AND UP TO 56MW WIND

GENERATING STATION AT RAY ESTATE, NORTHUMBERLAND

Definitions

References in these conditions to the carrying out or implementation of any scheme,

or the carrying out of work in accordance with any details, plan, statement or

methodology, approved by the local planning authority shall be construed as permitting

the scheme to be carried out or implemented or the work to be carried out subject to

such amendments or modifications of the scheme, details, plan, statement or

methodology as originally approved as shall have been agreed in advance in writing by

the local planning authority, and as permitting the local planning authority to approve

one scheme in place of another relating to the same matters.

In these conditions unless the context otherwise requires –

‚bank holiday‛ means a day that is, or is to be observed as, a Bank Holiday or a holiday

under the Banking and Financial Dealings Act 1971

‚BS 4142: 1997‛ means British Standard 4142:1997 – Method for rating industrial

noise affecting mixed residential and industrial areas

‚commissioning‛ means the date on which the Development first supplies electricity

on a commercial basis

‚emergency means‛ circumstances in which there is reasonable cause for

apprehending imminent injury to persons, serious damage to property or danger of

serious pollution to the environment

‚schedule 1 raptors means‛ any raptor defined under part I or part II or schedule 1 to

the Wildlife and Countryside Act 1981 (as amended)

‚the development‛ means the onshore windfarm generating station on land at Ray

Estate near Kirkwhelpington, Northumberland

‚the local planning authority‛ means Tynedale District Council or Northumberland

County Council as appropriate and their successors

Commencement of development

1. The development hereby permitted shall be commenced within 5 years from

the date of this decision.

Reason: To strike a balance between ensuring that the development is constructed in a timely

manner; allowing the Company an appropriate degree of flexibility as regards the timing,

finance and other arrangements for its construction, including the resolution of issues arising

from the need to mitigate potential radar problems; and minimising the impact of any period of

uncertainty for those who may be affected by the existence of the deemed planning

permission pending the company’s decision to begin construction. The default planning

Page 24: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

permission duration of 3 years provided for in s.91 is not considered sufficient for all these

purposes.

Duration of permission

2. The generation of electricity from the development shall cease no later than

25 years after the first commercial generation of electricity at the site, after

which time the site shall be restored in accordance with the approved

Decommissioning and Site Restoration Scheme as referred to in condition 4

below.

3. The operator shall, within one month of the first commercial generation of

electricity from the wind farm, notify the local planning authority in writing of

the date on which the first commercial generation of electricity occurred.

Reason: To comply with the requirements of section 91 of the Town and Country Planning Act

1990.

Decommissioning and Site Restoration

4. No later than 3 years before the expiry of the planning permission hereby

deemed to be granted, a Decommissioning and Site Restoration Scheme shall

be submitted to the local planning authority. The scheme shall, in particular,

include the methods and measures and timetable to secure the removal of

the turbines, turbine bases, buildings, site compound and related mitigation

measures arising from the proposed operations. The scheme shall be

implemented as approved.

5. If any turbine fails to produce electricity for a continuous period of 12 months,

the turbine and any ancillary equipment shall be dismantled and removed from

the site (unless the developer has demonstrated to the local planning

authority that the turbine is under repair and that there is a remedy) in

accordance with a restoration plan, which shall include a time-table for the

works. The restoration plan shall be submitted to the local planning authority

within 2 months after the expiry of the 12 month period; and the relevant

turbine shall thereafter be removed and that part of the site shall be restored

in accordance with the approved scheme.

Reason: To ensure the site is not allowed to become derelict after the cessation of electricity

generation.

Details of the development

6. No development shall take place until details of the external appearance of the

turbines, including blade configuration, direction of rotation, design, colour and

surface finishes, have been submitted to and approved in writing by the local

planning authority. The development shall be carried out in accordance with

the approved details.

7. No development shall take place until a scheme for the lighting of the turbines

and other parts of the site has been submitted to the local planning authority

and approved in writing. The scheme shall be implemented as approved.

8. No development shall take place until details of the proposed temporary site

compound, and a scheme for its subsequent clearance and restoration, has

been submitted to and approved in writing by the local planning authority.

Page 25: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

The details shall include means of enclosure; the siting of temporary buildings;

areas for the storage of materials and machinery and operative parking; oil/fuel

and chemical storage and related measures for secure bunding; and any

proposals for temporary lighting. The compound shall be constructed and laid

out in accordance with the approved details and within a period of 12 months

of the final commissioning of the wind farm it shall be restored in accordance

with the approved restoration scheme.

9. No development shall take place until a scheme containing details of turning

facilities for all vehicles likely to enter the site, and a timetable for its

implementation, has been submitted to the local planning authority and has

been approved in writing. The scheme shall be implemented as approved.

10. No development shall take place until detailed access and road improvement

drawings, and a timetable for the implementation of access and road

improvement works, have been submitted to the local planning authority and

agreed in writing. The details shall be implemented as approved.

11. No development shall take place until the location of the sub-station building

and its compound, together with a scheme for its external treatment, its

access from the public highway and its landscaping, including a timetable for

implementation, has been submitted to the local planning authority and

approved in writing. The development shall be carried out in accordance with

the approved details.

12. No development shall take place until details of the height, siting, appearance

and construction of all permanent means of enclosure to be erected on the

site, including a timetable for implementation, have been submitted to the

local planning authority and have been approved in writing. The development

shall be carried out in accordance with the approved details.

13. All interconnecting cabling between the turbines and the sub-station within

the site shall be installed underground apart from where it joins to the

appropriate apparatus.

14. No development shall take place until details of the alignment, width,

construction, surface treatment and drainage of new temporary and

permanent tracks, lay down and storage areas, turbine bases, crane standings

and cable routing (including any necessary mitigation measures) have been

submitted to the local planning authority and have been approved in writing.

Where access tracks cross peat that is 0.5 metres in depth, or greater,

measures to protect the peat and to safeguard water movement shall be

submitted. The details shall also include a timetable for implementation and

measures for the restoration of temporary works. The development shall be

carried out in accordance with the approved details.

15. No development shall take place until the exact siting of the turbines has been

submitted to the local planning authority and has been approved in writing.

Thereafter the turbines shall be erected in the approved positions subject to a

micro-siting tolerance not exceeding 30 metres.

Reason: To enable the local planning authority to exercise reasonable and proper control over

the design and appearance of the Development.

Page 26: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

Construction Hours

16. No construction activities shall be carried out on the site on any Sunday or

Bank Holiday or outside the hours of 08:00 to 18.00 Mondays to Fridays, or

outside the hours of 08:00 to 13.00 on Saturdays.

Reason: To ensure reasonable and proper control to be exercised over noise during

construction activities. Construction Method Statement

17. No development shall take before a Construction Method Statement has been

submitted to the local planning authority and has been approved in writing.

Thereafter construction works shall be carried out in accordance with the

approved Statement. The Construction Method Statement shall include the

following details:-

(a) dust management;

(b) measures to secure the cleaning of site entrances, bound or covered site tracks

and the adjacent public highway including the provision of a wheel wash facility

in an agreed location for vehicles leaving the site;

(c) measures for the protection of water courses, including submission of details

of watercourse engineering works and crossing points, and mitigation

measures to protect ground water and soils;

(d) sewage disposal;

(e) noise management during the construction phase;

(f) vibration control;

(g) any temporary site illumination;

(h) the disposal of surplus materials;

(i) any temporary on-site diversions of public rights of way, or temporary closures

of Access Land, and associated signage;

(j) the protection of private water supplies; and

(k) a construction schedule and programme of the proposed works.

Reason: To ensure that satisfactory measures are in force so as to alleviate any impact dust

and dirt may have on the local environment during construction and to protect watercourses.

Environmental Management Plan

18. No development shall take place until an Environmental Management Plan

covering all aspects of the construction process has been submitted to the

local planning authority and has been approved in writing. The development

shall be carried out in accordance with the approved details.

Reason: To ensure that satisfactory measures are in place to protect the environment.

Transport Management Plan

19. No development shall take place until a Transport Management Plan has been

submitted to the local planning authority and has been approved in writing.

Page 27: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

The plan shall include details of routing; a schedule and timing of abnormal

traffic movements; details of escorts for abnormal loads; details of temporary

warning signage; and proposed mitigation measures. The Transport

Management Plan shall be implemented as approved.

Reason: To reduce the impact of traffic on the local population and other users of the road

network.

Archaeology

20. No development shall take place until an Archaeological Scheme of Works has

been submitted to the local planning authority and has been approved in

writing. The scheme shall be implemented as approved.

Reason: To allow the surveying of the site for archaeological artefacts and the recovery of any

important archaeological discovery before the construction of the main Developments begins.

Ecology

21. No development shall take place until the developer has appointed an

Ecologist Clerk of Works to oversee site preparation works and the

construction of the wind farm having particular regard to the requirements of

the planning conditions relating to ecology and to address any other ecological

matters that might arise; the appointed person, or a successor to that person,

shall remain in post for the duration of the construction works.

22. No development shall take place until a Habitat Management Plan has been

submitted to the local planning authority and in consultation with Natural

England has been approved in writing. The Habitat Management Plan shall be

implemented as approved.

23. No development shall take place until a scheme for checking and updating the

protected species surveys submitted as part of the Environmental Statement,

including methodology, implementation and timing, has been submitted to

and approved in writing by the local planning authority in consultation with

Natural England. The updated survey results shall be submitted to the local

planning authority with a programme of works to mitigate any significant

effects which shall be implemented following the written approval of the local

planning authority in consultation with Natural England.

24. No development shall take place until pre-construction surveys for Schedule 1

raptors have been undertaken within 500 metres of any proposed

construction works and the results have been submitted to the local planning

authority. If any Schedule 1 raptors are found nesting, mitigation measures

shall be agreed in writing by the local planning authority in consultation with

Natural England in advance of any construction work. The agreed mitigation

measures shall be implemented as approved.

25. In the bird breeding season preceding the commencement of construction

work on the proposed wind farm site, ornithological monitoring at the site

shall be undertaken in accordance with a methodology previously submitted

to and approved in writing by the local planning authority in consultation with

Natural England. The results of the survey shall be submitted to the local

Page 28: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

planning authority within a period of three months following the end of the

monitoring period.

26. No tree felling, vegetation removal or ground clearance shall be undertaken

between 1 March and 31 August unless the on-site Ecologist Clerk of Works

has first confirmed to the local planning authority in writing that no birds’ nest

which is being constructed or is in use, or live bird’s egg or bird will be

damaged or harmed. In any instance where any active nest site is identified

as that belonging to a species protected under Schedule 1 of the Wildlife and

Countryside Act 1981 (as amended), no construction works associated with

the development shall take place within 500 metres of the site identified until

dependant young have moved from the nest site or the nest has been

abandoned. If an active nest of any other species is found, the on-site

Ecologist Clerk of Works shall determine measures to protect it from damage

and to minimise disturbance while adults and dependent young are present.

27. None of the turbines within the development shall commence operation

between 1 March and 31 August unless the results of a breeding bird survey

carried out in accordance with a methodology approved in advance by the

local planning authority demonstrate that there would not be a significant risk

to breeding birds from the operation of the wind farm.

28. Before the first commissioning of the wind farm a specification for the long

term post construction monitoring of bats shall have been submitted to the

local planning authority and have been approved in writing in consultation with

Natural England. The approved scheme of monitoring shall be undertaken

annually for a period of 10 years following the first commercial generation of

electricity, unless, following any two year consecutive period demonstrating a

lack of significant bat activity, the local planning authority agrees that

monitoring shall cease. Annual monitoring reports shall be submitted to the

local planning authority within three months of the end of the monitoring

period to which they refer.

29. Before the first commissioning of the wind farm a methodology for a post

construction ornithological monitoring scheme shall have been submitted to

the local planning authority and in consultation with Natural England have

been approved in writing. The approved scheme of monitoring shall run for a

period of three years and shall be implemented as approved. Annual

monitoring reports shall be submitted to the local planning authority within

three months of the monitoring period to which they refer.

30. No development shall take place until a hen harrier monitoring and

management plan has been agreed in writing with the local planning authority

in consultation with Natural England. The management plan shall provide for

surveys to determine the presence of displaying and nesting birds, location of

any nests and sensitivity to collision; the duration of and method of

monitoring; and measures for mitigation in the event that the local planning

authority identifies a potentially suitable hen harrier nesting habitat within 500

metres of the wind farm. The hen harrier management plan shall be

implemented as approved.

Page 29: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

Reason: To ensure reasonable and proper control to be exercised over construction activities at

the site so that it does not have an undue adverse effect on habitats or on birds or bats using

the site.

Borrow Pits

31. No development shall begin until details of the proposed borrow pits, for the

extraction of stone to be used in the proposed development, have been

submitted to the local planning authority and have been approved in writing.

The development shall be carried out in accordance with the approved

details. These details shall include:-

(a) the location and proposed extent of the borrow pits;

(b) volume and type of material to be extracted;

(c) timescale for the works;

(d) method of working including details of plant to be used;

(e) mineral stockpiling;

(f) soils handling and storage;

(g) noise and vibration management;

(h) dust management;

(i) blasting;

(j) restoration and aftercare proposals for a period of five years; and

(k) surface and ground water management.

None of the extracted materials shall be removed from the site; and no

materials shall be brought on to the site to be deposited into, or used in the

restoration of, the borrow pits.

Reason: To maintain the integrity of the borrow pits.

Noise

32. The rating level of noise from the combined effects of the wind turbine

generators on the wind farm hereby approved shall not at any time exceed the

levels derived according to the procedure set out below (‘Maximum permitted

noise levels’) at any dwelling which is in existence (or for which planning

permission has been granted) at the date of this permission. The noise levels

shall be measured and calculated in accordance with the Guidance Notes at

Appendix A to these conditions.

Maximum permitted noise levels

The noise level dB (LA90, 10minutes) at any dwelling shall not exceed:-

The Reference Background Noise Level at that dwelling, at any stated wind

speed, plus 5dB or a level of ‘x’ dB, whichever is greater.

The values of ‘x‘ are as follows:-

(i) For properties where the occupier has no financial involvement with the

wind farm, the value of ‘x’ is 43dB LA90,10minutes between the hours 23.00

– 07.00 and 40dB LA90,10minutes at all other times;

Page 30: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

(ii) For properties where the occupier has financial involvement with the

wind farm, the value of ‘x’ is 45dB LA90, 10minutes at all times.

The maximum permitted noise levels at any location are to be derived from

the Reference Background Noise Levels (LA90, 10minutes) set out in Tables A and

B below:-

Table A - Reference Background Noise Levels dB(LA90, 10 minutes

) 23:00 hours – 07:00 hours

Wind speed at 10 metres above ground level - metres/second

Location 1 2 3 4 5 6 7 8 9 10 11 12

Ottercops 27 27 27 27 28 30 31 33 36 39 42 45

Ray Cottage 26 26 26 26 28 31 34 38 41 43 46 49

Summit Cottage 20 22 23 25 26 28 30 32 34 36 39 41

Lough House 30 31 32 33 33 34 35 36 38 40 42 45

Wishaw 23 23 23 23 24 25 27 28 30 33 35 38

Any other dwelling 25 26 26 29 30 32 33 35 37 39 42 44

Table B – Reference Background Noise Levels dB(L

A90, 10 minutes

) 07:00 hours – 23:00 hours

Wind speed at 10 metres above ground level - metres/second

Location 1 2 3 4 5 6 7 8 9 10 11 12

Ottercops 30 30 30 33 35 37 39 40 42 44 45 46

Ray Cottage 30 30 30 30 31 33 36 38 41 43 46 49

Summit Cottage 19 22 25 27 29 32 34 35 37 39 41 42

Lough House 30 30 30 34 35 36 37 39 40 42 43 46

Wishaw 26 26 26 26 28 31 34 37 40 44 48 51

Any other dwelling 27 28 28 30 32 34 36 38 40 42 45 47

Note: Wind speed at 10 metres above ground level means the wind speed at 10 metres above local ground level at a position to be agreed with the local planning authority, either measured at this position or calculated from measurements at another position by means of a calculation procedure to be agreed with the local planning authority.

33. No development shall take place until a scheme for the monitoring of the

noise of the operational wind turbines, to confirm compliance with the noise

limits set out in Condition 32 above, has been submitted to the local planning

authority and has been approved in writing. The noise monitoring survey shall

be carried out as approved and the results submitted to the local planning

authority within the timescale agreed in the noise monitoring scheme.

34. No development shall take place until the wind farm developer/operator has

notified the local planning authority of a nominated representative to act as a

point of contact for local residents and liaison with the local planning authority

in relation to any complaints made about noise and any other matters arising

during construction, operation and decommissioning of the wind farm.

35. At the reasonable request of the local planning authority, following a

complaint relating to noise from the wind turbines, the operator of the

development shall employ a suitably qualified independent consultant to

measure and assess the level of noise emissions resulting from the operation

of the wind turbine generators. The assessment shall be undertaken in

accordance with a methodology to be agreed in writing by the local planning

Page 31: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

authority and in accordance with the procedures described in the Guidance

Notes at Appendix A to these conditions.

36. (i) Not later than the first commercial generation of electricity, and for a

period of three years thereafter, the wind farm operator shall log wind

speed (in metres per second) and wind direction data (in degrees from

north) for each ten-minute period at a grid reference location previously

approved in writing by the local planning authority.

(ii) After the three year period the same data shall be taken from turbine

nacelle anemometers and wind vanes or similar and shall be retained for

a period of not less than 12 months.

(iii) At the reasonable request of the local planning authority the recorded

data at 10 metres height above ground level, at the agreed location, and

relating to any periods during which noise monitoring took place, or any

periods when there was a specific noise complaint, shall be made

available to the local planning authority.

(iv) Where wind speed is measured at a height other than 10 metres above

local ground level the wind speed data shall be converted to 10 metres

height, accounting for wind shear, by a methodology which shall be

submitted to and approved in writing by the local planning authority.

(v) At the reasonable request of the local planning authority the wind farm

operator shall provide, within 28 days of the request, a list of ten-minute

periods during which any one or more of the turbines was not in normal

operation. This information will only be required for periods during

which noise monitoring is being undertaken in accordance with other

conditions attached to this permission.

(vi) For the avoidance of doubt ‘normal operation’ is defined in the Guidance

Notes at Appendix A to these conditions.

Reason: To ensure the proper control of noise during the operation of the Development and to

ensure that any complaints on the grounds of noise are properly dealt with so as to reduce the

impact of the Development on local residents.

Shadow Flicker and Television Reception

37. If, whether through micro-siting or any other reason, the proposed position of

any turbine differs materially from that shown on the application plan (as

amended by the deletion of Turbines 17 – 20) then prior to the erection of that

turbine a study shall be undertaken by a suitably qualified person to assess its

impact in terms of the potential for shadow flicker on any residential and other

properties that would be inhabited by people at such times as any such

problem may occur. The study, which shall also identify any necessary

mitigation measures, shall be submitted to the local planning authority and

approved in writing before the turbine is erected; and any agreed mitigation

measures shall be implemented prior to the first commercial generation of

electricity by the relevant turbine. Subject to condition 38, the mitigation

measures shall remain effective thereafter.

Page 32: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

38. No development shall take place until a scheme detailing the protocol for

communicating, evaluating and responding to (including by mitigation

measures further to or different from those put in place under condition 37)

any complaints of shadow flicker resulting from the development, including

remedial measures, has been submitted to the local planning authority and

has been approved in writing. Operation of the turbines shall take place in

accordance with the requirements of the approved scheme.

39. No development shall take place until a scheme designed to safeguard

existing television reception quality arising from the operation of the wind

turbines has been submitted to the local planning authority and has been

approved in writing. The scheme shall, in particular, provide for a base line

survey of residential properties that might be affected; and a protocol for

dealing with any complaints arising from the operation of any of the wind

turbines and for the identification and implementation of necessary mitigation

measures to be undertaken in accordance with details and a time-table

previously submitted to and approved in writing by the local planning

authority.

Reason: If during the operation of the Development complaints arise because of shadow

flicker or interference to television reception that they are properly dealt with so as to reduce

the impact of the Development on local residents.

Page 33: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

Appendix A - Noise Conditions Guidance Notes

The following paragraphs are based on steps 2 - 6 specified in Section 2 of the Supplementary

Guidance Notes to the Planning Obligation contained within pages 102 et seq of ‘The

Assessment and Rating of Noise from Wind Farms, ETSU-R-97’ published by ETSU for the

Department of Trade and Industry. It has been adapted in the light of experience of actual

compliance measurements.

NOTE 1

Values of the LAF90,10minute noise statistic should be measured at the affected dwelling

using a sound level meter of at least IEC 651 Type 1 quality. This should be fitted with a ½"

diameter microphone and calibrated in accordance with the procedure specified in BS 4142:

1997. The microphone should be mounted on a tripod at 1.2 - 1.5 m above ground level, fitted

with a two layer windshield or suitable equivalent, and placed in the vicinity of, and external to,

the dwelling. The intention is that, as far as possible, the measurements should be made in

‘free-field’ conditions. To achieve this, the microphone should be placed at least 3.5m away

from the building facade or any reflecting surface except the ground.

The LAF90,10minute measurements should be synchronised with measurements of the 10-

minute average wind speed and with operational data from the turbine control systems of the

wind farm or farms.

The wind speed and wind direction and a note of all 10 minute periods when one or more of

the turbines was not operating normally should be provided to the consultant to enable an

analysis to take place.

The precise definition of ‘normal operation’ should be agreed in writing with the local authority

prior to the commencement of the development on the basis of data available but should

generally be taken to mean when the turbine power output is not significantly different from

the reference power curve, which may be a noise optimised power curve if appropriate, using

the nacelle anemometer.

In the interests of commercial confidentiality no information is required to be provided for

individual turbines or on the nature of any abnormality or for any period during which noise

monitoring is not taking place.

NOTE 2

The noise measurements should be made over a period of time sufficient to provide not less

than 100 valid data points. Measurements should also be made over a sufficient period to

provide valid data points throughout the range of wind speeds considered by the local authority

to be most critical. Valid data points are those that remain after the following data have been

excluded:-

all periods during rainfall;

all periods during which wind direction is more than 45 degrees from every line from each

of the turbines and the measurement position;

all periods during which turbine operation was not normal.

A least squares, ‘best fit’ curve should be fitted to the data points.

NOTE 3

Where, following a complaint to and in the reasonable opinion of the local planning authority,

the noise emission contains a tonal component, the following rating procedure should be used.

This is based on the repeated application of a tonal assessment methodology.

For each 10-minute interval for which LAF90,10minute data have been obtained, a tonal

assessment is performed on noise emission during 2-minutes of the 10-minute period. The 2-

Page 34: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December

minute periods should be regularly spaced at 10-minute intervals provided that uninterrupted

clean data are obtained.

For each of the 2-minute samples the margin above or below the audibility criterion of the tone

level difference, Ltm, is calculated by comparison with the audibility criterion given in Section

2.1 on page 104 et seq of ETSU-R-97.

The margin above audibility is plotted against wind speed for each of the 2-minute samples.

For samples for which the tones were inaudible or no tone was identified, substitute a value of

zero audibility.

A linear regression is then performed to establish the margin above audibility at the assessed

wind speed. If there is no apparent trend with wind speed then a simple arithmetic average

will suffice.

The tonal penalty is derived from the margin above audibility of the tone according to the figure

below.

0

1

2

3

4

5

6

0 1 2 3 4 5 6 7 8

Tone Level above Audibility (dB)

Pe

na

lty

(d

B)

The rating level at each wind speed is the arithmetic sum of the wind farm noise level, as

determined from the best fit curve described in Note 2, and the penalty for tonal noise.

The rating level shall be determined for each wind speed. If the values lie below the maximum

values of turbine noise indicated by the table in the annex to these conditions then no further

action is necessary.

NOTE 4

If the rating level is above the limit, a correction for the influence of background noise should be

made. This may be achieved by repeating the steps in Note 2, with the wind farm switched

off, and determining the background noise at the assessed wind speed, Lb. The wind farm

noise at this speed, Lw, is then calculated as follows where La is the measured level with

turbines running but without the addition of any tonal penalty:

Lw = 10log 10

La

10 -10

Lb

10

The Rating level is re-calculated by adding the tonal penalty (if any) to the wind farm noise. If

the rating level lies below the values indicated from the table in the annex then no further

action is required.

If the rating level exceeds any of the turbine noise levels in the table in the Annex then the

development fails to comply with the relevant Planning Condition.

Page 35: Mr David Hodkinson Vattenfall Wind Power Ltd Bridge End Hexham€¦ · 2.3 The public inquiry was held at The Britannia Hotel, Newcastle Airport, between 15 January 2008 and 18 December