MANAGEMENT PLANNING AND
CONTROL SYSTEM (MPCS)
L & T CONSTRUCTION
MMH - ICDelhi Cluster
OBJECTIVE OF THE SESSION… What is Planning
Why is it required
Planning process
Resource schedules
Planning – Frame work
Schedules for Planning & Monitoring
WHAT IS PLANNING….
A process to answer basic questions like
Why?
What?
When?
Who?
Where?
How?
MANAGEMENT PLANNING
To systematically plan events
within certain time frame
with limited resources
in most economical manner , and
with total safety and quality in place
STAGES OF PLANNING
At tendering stage
On award of contract at macro and micro level
While executing
Monthly planning
Weekly planning at sectional level
Day to day planning at individual level
PLANNING – TYPES
Time planning
Material planning
Work planning
Cost planning
SCHEDULES
To manage Resources …. (5M)
Manpower
Machinery
Materials
Money
Minute (Time)
CONTROL SYSTEM
It helps to monitor
Deployment of various resources
Effective utilization of various resources
Progress of works w.r.t plan
Monitor Project Cost
Enables to take corrective action in time
MPCS in
L&T
SCHEDULING SYSTEM
TENDERING SYSTEM
MONITORING SYSTEM
MANAGEMENT INFORMATION SYSTEM
TENDERING SYSTEM
For preparation of Tenders
Identical to Scheduling system
Not used for monitoring directly.
Why ?
Execution In-charge not involved. So no commitment
available
Resource commitments might be different at scheduling
stage
Worked out details may not be sufficient for monitoring
TENDERING SYSTEM
Main objective is…
To assist in proper estimation of unit
rates & Pricing of tender
To provide a framework for scheduling
TENDERING SYSTEM – SCHEDULES T-0 – Construction Programme T-1 – Schedule of Invoicing T-2 – Schedule of Milestone eventsT-3 – Schedule of P&MT-4 – Schedule of Staff T-5 – Schedule of Labour T-6 – Schedule of Bulk material T-7 – Schedule of Specialized agencies T-8 – Schedule of Direct CostsT-9 – Schedule of Over heads T-10 –Cash gap statement
SCHEDULING SYSTEM To be done jointly by
Regional Planning Office
Site In charge
Site Planning In-charge
To be completed before 30 days
Updated every month
Unit costs & financial commitments shall not be modified
during execution
Performance to be evaluated against the parameters accepted
S0 : CONSTRUCTION PROGRAM
MPCS SCHEDULES
CONTD……
S1 : SCHEDULE OF INVOICING
S2 : SCHEDULE OF MILESTONE
S3 : SCHEDULE OF P & M
S4 : SCHEDULE OF STAFF
S5 : SCHEDULE OF LABOUR
MPCS SCHEDULES
S6 : SCHEDULE OF MATERIALS
S7 : SCHEDULE OF SPECIALISED AGENCY
S8 : SCHEDULE OF DIRECT COST
S9 : SCHEDULE OF INDIRECT COST
S10 : SCHEDULE OF LIQUIDITY FORECAST
S0 :CONSTRUCTION PROGRAM
Most important schedule
Runs through the execution process of the project
Provides inputs for all other schedules
Forms the basis for micro planning at site
To be updated every month to reflect the progress
achieved & corrective actions
Study Scope of work
Decide sequence of construction and method
Prepare WBS for the Project
Study time schedule as per Contract Agreement
Prepare bar chart assuming Most likely time period
PROCEDURE STEPS
MASTER SCHEDULE SL NO Description 2008 2009
Feb Mar Apr May Jun July Aug Sep Oct Nov Dec Jan Feb Mar April May
1 Design & Drg Appr.
2 Supply of MS Pipes
3 Coating Works
4 Pipe laying & Testing
5 Bridge at River Crossing
6 Intake-well construction
7
Sump & Pump House at IPS
8 Sump at BPT
9 Supply of Electrical items
10 Surge Vessel
11 Commissioning
S0: BASED ON MASTER SCHEDULE
S1 : SCHEDULE OF INVOICINGProjects month wise invoicing amount Used as basis for monitoring progress invoicing For Lump-sum contracts, amount to be arrived based on stage payment terms of contractAmounts to include projected escalation alsoSmall value items can be clubbed into single item
SCHEDULE OF INVOICING Schedule : S1 Job No:
Client: Job Description:
Contractual Date of completion: ( All Figs in Rs. 000's)
Sl NO Item description Unit Scope Sales
RateMonth 1 Month 2 Month .. Month .. Month 12
Qty Value Qty Value Qty Value Qty Value Qty Value
Other Items
Total FTM
CUM
S2 : SCHEDULE OF MILESTONE EVENTS
Indicates important contractual milestones
To include important events requiring external
agency interface
Helps in understanding & monitoring the project
progress at a glance
SCHEDULE OF MILESTONE ENENTS Schedule :S0 Job No:
Client: Job Description:
Contractual Date of completion: Date:
SL NO Description of Milestone Events
Estimated Date of Completion
Projected Slippage in event of completion
Description & impact of
Problems
Action to be taken
Person Responsible
Latest estimated
completion date
Projected Slippages ( in weeks)
1
2
3
4
5
6
7
S3 : SCHEDULE OF PLANT & MACHINERIESTo ensure mobilization of right P&M at right time
Compiled S-3 schedule at cluster helps management in
deciding
Inter-site mobilization
External hiring
New procurement
Forms the basis for de-mobilization plan
To be updated fortnightly during mobilization / de-
mobilization & monthly afterwards
SCHEDULE OF PLANT & MACINERY Schedule :S3 Job No:
Client: Job Description:
Contractual Date of completion: Date:
Sl no. Asset code A/R/S Description of item Total Qty
Required
RequirementRecd date
Exp. Release
dateReleased
date Remarks From To
S4 : SCHEDULE OF STAFF REQUIREMENTHelps in timely mobilization of required staff
Compiled S-4 schedule at Cluster helps management in
deciding
Inter-site transfers
Short term recruitment (Incase it is required)
Permanent recruitment
Forms the basis for de-mobilization plan
To be updated fortnightly during mobilization / de-mobilization
& monthly afterwards
SCHEDULE OF STAFF
SCHEDULE : S4 JOB NO : CLIENT : JOB DESCRIPTION :
CONTRACTUAL DATE OF COMPLETION: DATE :
SL. NO.
P.S. NO. NAME A/
R/S DIS. CADRE FUNCTION REQUIRED DATE
REPORTING DATE
EXP REL DATE
ACT RELEASE
DATEACTUAL RELEASE REMARKS
S-3 & S-4 – PROBLEMS FACED Not received in time Not adhering to schedule
dates All details not filled Requirement exaggerated Model & capacity not
described properly Different formats used
Send every month in time Analyse & inform in advance
any change in dates in unavoidable cases
Fill in all details Give actual requirement
Check the details before sending to Cluster
Use standard formats
S5 : SCHEDULE OF LABOUR
Helps in stage wise mobilization of labour
To ensure that there are no abnormally high peaks /
troughs in the requirement
To plan the housing & temp. infrastructure
For large projects, category wise histogram may be
required
Can be updated quarterly
SCHEDULE OF LABOUR REQUIREMENT
SCHEDULE : S5 JOB NO : CLIENT : JOB DESCRIPTION : CONTRACTUAL DATE OF COMPLETION: DATE :
SL. NO. DESCRIPTION
TOTAL MAN-
MONTH1st
MONTH2nd
MONTH3RD
MONTH4th
MONTH5th
MONTH6th
MONTH7th
MONTH REMARKS
S-6 : SCHEDULE OF BULK MATERIALS
To ensure availability of essential materials to suit S-0
Shall include all A & B category materials in ABC
analysis
To include critical items like imported / specially
manufactured items
Best possible rates & terms from right source
Surplus materials from other sites
S-6 : SCHEDULE OF BULK MATERIALS
Optimum stock levels
Separate list for Formwork, Structural steel for giving
item wise break-up
Factors like monsoon, union budget and other local
factors shall be considered
Separate list for Client supply
Qty. to include wastage, rolling margin etc..
Can be updated quarterly
SCHEDULE OF MATERIALS REQUIREMENT
SCHEDULE : S6 JOB NO : CLIENT : JOB DESCRIPTION :
CONTRACTUAL DATE OF COMPLETION: DATE :
SL. NO. DESCRIPTION UOM QTY 1st
MONTH2nd
MONTH3RD
MONTH4th
MONTH5th
MONTH6th
MONTH7th
MONTH REMARKS
S7: SCHEDULE OF SPECIALISED AGENCIES
This schedule lists the activities which are to be carried
out by specialist agencies.
Specialist work includes water proofing, insulation,
false ceiling, testing works etc.
Helps in
Mobilisation of special agencies on time
Finalisation of specifications, scope etc. in time
SCHEDULE OF SPECIALISED AGENCIES
SCHEDULE : S7JOB NO :
CLIENT : JOB DESCRIPTION :
CONTRACTUAL DATE OF COMPLETION: DATE :
SL. NO. DESCRIPTION UOM QTY DATE OF START DATE OF COMPLETION REMARKS
S-8 : SCHEDULE OF DIRECT COST & S-9 : SCHEDULE OF OVERHEADS
Projects the total cost of project at the scheduling stage
Break-up of Accepted Cost Estimate
Temporary / Enabling structure cost can be deferred in
proportion to invoicing
Cost of items shall include projected escalation based on
past / expected trends
On client supply materials no escalation to be considered
Cost of P&M used specifically for particular item of work
to be considered in direct cost & not in overheads
S-8 & S-9 is the basis for original estimates column in JCR
S-8 : SCHEDULE OF DIRECT COST & S-9 : SCHEDULE OF OVERHEADS
SCHEDULE OF DIRECT COST Schedule : S8 Job No:
Client: Job Description:
Contractual Date of completion: ( All Figs in Rs. 000's)
Sl NO Item description Uom Scope Unit
RateMonth 1 Month 2 Month .. Month .. Month 12
Qty Cost Qty Cost Qty Cost Qty Cost Qty Cost
Other Items
Total FTM
CUM
SCHEDULE OF OVERHEADS Schedule : S9 Job No:
Client: Job Description:
Contractual Date of completion: ( All Figs in Rs. 000's)
Sl. NO Description Total Amount Month 1 Month 2 Month .. Month .. Month 12
Other Items
Total FTM
CUM
S-10 : CASH GAP STATEMENT
Aids in analyzing the cash flow / Working capital
requirements
Outflow should include payments made at HQ /
Cluster also
Can be updated quarterly
S10 : SCHEDULE OF LIQUIDITY DESCRIPTION
MONTHS
MTH1 MTH2 MTH3 MTH4 MTH5 MTH6 MTH7 MTH8 MTH9 MTH10 MTH11 MTH12
I.INVOICING - 5 5 10 20 20 15 10 8 8 6 3
DIRECT COST
5 5 7 7 10 10 8 8 5 5 4 3
INDIRECT COST
0.5 0.5 1 1 2 2 2 2 1 1 0.5 0.5
II. TOTAL COST
5.5 5.5 8 8 12 12 10 10 6 6 4.5 3.5
CASH FLOW ( I –II)
(5.5) (0.5) (3) 2 8 8 5 0 2 2 1.5 (0.5)
MONITORING SYSTEM
Objectives
Monitor projects progress in terms of
Cost
Physical progress
Contribution against targets
Initiate corrective action when required
To provide data for MIS
MONITORING SYSTEM
To be prepared every month
Cluster to review & give feedback
Weekly review meeting at site
Quarterly review meeting at Cluster
MONTHLYREPORTS
JOB COST REPORT
MONTHLY PROGRESS REPORT
PERFORMANCE REPORT
ANNEXURE V-A
RECONCILIATION
MONTHLY PROGRESS REPORTHighlights of progress of works achieved during the month and cumulative.
The report includes
Monthly Highlights
Physical Progress
Financial Progress
Progress Photographs
Safety & Quality Statistics
Constraints
JOB COST REPORT
What do we Infer from JCR ? Cost incurred till date for various project activities
Estimated cost for the balance works
Revised overall cost estimate for the project
Revised Profit Margin from the Project
Variance of cost w.r.t ACE
PURPOSE OF JCR It’s a tool to monitor financial performance of the job and highlights the areas of concern.
Timely implementation of remedial measures on area of concern.
It’s a Mid course correction : Initiate necessary proactive steps
It Identifies items which are making loss / profit
It’s a Reference document for Tendering / Contracts / Operations
JOB COST REPORT
NAME OF THE JOB :SITE CODE JOB NO. MONTH
Contractual Date of Commencement Original Contract Value Actual Date of Commencement
Contractual Date of Completion Revised Contract Value
Expected Date of Completion
RECON CODE
DESCRIPTION UNIT
JOB STATUS TO DATE ESTIMATE TO COMPLETE REVISED ESTIMATE ORIGINAL ESTIMATE FOR
REVISED QTYVARIANCE
COSTREVISED SALES
REMARKS
UNITSACTUAL
COSTUNIT COST UNITS COST
UNIT COST
UNITS COSTUNIT COST
UNIT COST UNIT COST
TOTAL COST FOR WORKS
OVERHEADS
TOTAL COST OF PROJECT
Estimated Site Contribution on Completion (Rev. Cont. Value - Rev. Cost. Estimate )
Rs.
PLANNING MANAGER SITE ACCOUNTANT PROJECT MANAGER
Gross Margin
Gross Margin in %
JCR FORMAT
JCR INTERPRETATION
A ) Revised Estimate ( revised qty)Cost Incurred + Cost estimate for balance
qty
B) Original Estimate ( revised qty) Revised Qty X ACE Unit Rate
C) Variance ( B-A) Original Estimate – Revised Estimate
D) Profit = RCV – Revised Estimate
Performance Report Information provided by this statement includes
Monthly & Cumulative Invoicing ( Budget Vs. Act)
Work in Progress
Collection
Age wise outstanding Break-up
Funds Requirement by Site
Working Capital Details
Monthly and Cumulative Cost details
Staff & workmen Strength
Staff Productivity
Financial Parameters
Annexure VA- Outstanding StatementInformation provided by this statement includes
Month wise billing details
Cumulative Billing
Deductions break-up
Payment Collected
Net Receivables
TDS Certificate
Age wise outstanding detail
ANNEXURE VA
JOB NO:
PROJECT : DATE:
SL NO MonthInvoice No
/ Date
Invoice Amount (Rs.)
RecoveriesNet
Amount Payable
(Rs.)
Payment Received
(Rs.)
Net Receivable
(Rs.)Remarks
Certificate receipt
SUB. CER.MOB
ADV + Int.
RET IT WCT OTH TOT IT WCT
TOTAL
Bulk Material Reconciliation
Consumption of materials is checked with respect to
Norms or Design
Ensures that desired quantity of material is consumed
into the product to get required quality
Control on wastages ,excess consumption and theft
Rolling Margin to be accounted in case of Steel.
Quantity Reconciliation
Reconciles the work done quantity paid to various
agencies w.r.t quantities certified by Client or w.r.t
approved drawings.
Assists in taking corrective action for any variations.
?
REMEMBER
Prepare look ahead plan w.r.t front availability
Anticipate resource requirement in advance
Study Drawing
Workout material requirement
Make redirection and catch-up plan
Concentrate of Productivity
THANK YOU
MPCS
It defines total work content of the project
It ensures that the work undertaken is desired and necessary
All undesired and unnecessary work is eliminated.
Scope management
It ensures that only the optimum amount of work is undertaken in order to deliver the project successfully.
SCOPE
MPCS
OPTIMISTIC TIME
The minimum time for completion of an activity
PESSIMISTIC TIME
The maximum time for completion of an activity
MOST LIKELY TIME
The probable time for completion of an activity thatWould most reasonable be expected to occur.
WBS represents systematic and logical breakdown of Project
WBS is a task oriented family tree
Lowest level of WBS is Work Package. At this level work is assigned ; time duration & cost is estimated
WORK BREAK DOWN SCHEDULE
WBS reflects true Project Completion Status
MPCS
Level 1 The top-most level of WBS is single task which is the project
Level 2 This depends on the type of the project
Number of WBS Levels Too many levels make the control and execution of project difficult Too few levels will not allow proper assignments and control. Decompose the task upto Work Package level
WBS: STRUCTURE
WBS ILLUSTRATION
WATER TREATMENT PLANT
CIVIL WORKS
AREATOR FLASH MIXER CLARIFLOCULATOR
MECHANICAL WORKS E&I WORKS
FILTER HOUSE
DESIGN & DRG
SUMP & PH
ACTIVITY 1 ACTIVITY 2 ACTIVITY 3
LEVEL 1
LEVEL 2
LEVEL 3
LEVEL 4
100
10 10 25 25 30
10 50 30 10
25 40 35
LEVEL 1
LEVEL 2
LEVEL3
LEVEL 4
DESCRIPTIONLEVEL 1 LEVEL 2 LEVEL 3 LEVEL 4
WTG ACH WTG ACH WTG ACH WTG ACH
A WTP 100 5
A1.0 AREATOR 10
A2.0 FLASH MIXER 10
A3.0CLARIFLOCULATOR 25 5
A3.1 Design & Drawing 10
A3.2 Civil works 50 20
A3.1.1 Activity 1 25
A3.1.2 Activity 2 40 40
A3.1.3 Activity 3 35
Sub-Total A3.2 100 40
A3.3 Mechanical Works 30
A3.4 E&I Works 10
Sub-total A3.0 100 20
A4.0 FILTER HOUSE 25
A5.0 SUMP & PH 30
TOTAL A 100 5
JCR INPUTS Recon Code wise activity details Cost Statement
Quantities paid to Sub-contractors
MIB Details
ETC Quantity and unit rate
ACE Details
ACE : Accepted Cost Estimate
It’s a detailed estimate of the expected cost to be spent for successful completion of a project
It’s a yard stick for measuring the profitability of a project.
Consists of two parts: Direct Cost & Indirect Cost
It enables site management to monitor the profitability of the project by comparing it with JCR.
ACE has to be prepared within 1 month from the date
of receipt of LOI / Work Order from the Client
SITE ENGINEER'S REPORT TO THE OFFICE: Sub: High Priority Sir,
"Steel roof and column already erected at site, kindly send us the foundation drawings urgently."
Regards, Site Engineer