Monthly Construction Plan Project Status Report Report Date: 7/1/2013 Operating Company Major Updates EAI Two Projects completed EMI One Project completed ELL No major changes to report EGSL No major changes to report ETI No major changes to report EGSL/ELL No major changes to report

Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

  • Upload
    lehanh

  • View
    219

  • Download
    5

Embed Size (px)

Citation preview

Page 1: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Monthly Construction Plan Project Status ReportReport Date: 7/1/2013

Operating Company Major UpdatesEAI Two Projects completedEMI One Project completedELL No major changes to reportEGSL No major changes to reportETI No major changes to reportEGSL/ELL No major changes to report

Page 2: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

11-EAI-003-CP Transmission Reliability - Meeting Planning Criteria

Fordyce: Relocate capacitor bank to 115 kV bus. Install switch on line side of capacitor bank.

EAI Summer 2014 Summer 2013 Construction feasibility Proposed & In Target

Scoping Project scoping underway Summer 2014 Note B N/A

11-EAI-004-1-CP Economic Sheridan South 500 kV FG Upgrade: Mabelvale 500 kV Substation replace 3 breakers, 13 switches, and 2 line traps

EAI Summer 2014 N/A Supplemental

None Approved Construction Outage availability remains the largest challenge.

6/1/14 N/A SHRMAB_KEO, MABSH_WBSH, SHEWHB_MABWR, WHBSHE_MABEL, WHBSHR_KEOWH, SHRELD_HSPET, SHDELD_MCETT, SHEHV_MAGNET

11-EAI-004-2-CP Economic Sheridan South 500 kV FG Upgrade: Sheridan 500 kV Substation replace 11 switches, and 6 line traps

EAI Summer 2014 N/A Supplemental

None Approved Construction Outage availability remains the largest challenge.

6/1/14 N/A SHRMAB_KEO, MABSH_WBSH, SHEWHB_MABWR, WHBSHE_MABEL, WHBSHR_KEOWH, SHRELD_HSPET, SHDELD_MCETT, SHEHV_MAGNET

11-EAI-004-3-CP Economic Sheridan South 500 kV FG Upgrade: White Bluff 500 kV Substation replace 5 switches

EAI Summer 2014 N/A Supplemental

None Approved Construction Outage availability remains as the largest challenge.

6/1/14 N/A WHBSHE_MABEL, WHBSHR_KEOWH

11-EAI-004-4-CP Economic Sheridan South 500 kV FG Upgrade: Eldorado 500 kV Substation replace 1 switch and 2 line traps

EAI Summer 2014 N/A Supplemental

None Approved Construction Outage availability remains as the largest challenge.

6/1/14 N/A SHRELD_HSPET, SHDELD_MCETT, SHEHV_MAGNET

11-EAI-007-CP Transmission Reliability - Meeting Planning Criteria

Hot Springs Hamilton (Albright) - Carpenter Dam: Construct new 115 kV Line and convert Mountain Pine South to ring bus

EAI Summer 2015 Summer 2013 ROW acquisition, construction feasibility.

Approved Scoping CECPN Filing completed. 12/31/15 Note B N/A

11-EAI-008-CP Transmission Reliability - Meeting Planning Criteria

Pine Bluff Voltage Support Project: Phase 2 Woodward: Construct 230 kV ring bus and construct new White Bluff to Woodward 230 kV line

EAI Summer 2015 Summer 2013 Construction feasibility Proposed & In Target

Scoping New line scope under review. Commission Approvals and ROW acquisition 230 kV line may result in ISD slipping to

June 2016.

Summer 2016 Note B N/A

11-EAI-012-CP Transmission Reliability - Meeting Planning Criteria

Stuttgart Ricuskey 115 kV Substation: Expand Capacitor Bank to 39 MVAR

EAI Summer 2013 Summer 2013 None Approved Complete In-Service Summer 2013 6/3/13 N/A Yes N/A

11-EAI-015-CP Transmission Reliability - Meeting Planning Criteria

Jim Hill Area UpgradesDoniphan (AECI New Sub) - Datto 161 construct new line

EAI Summer 2017 Summer 2017 None Proposed & In Target

Scoping Scope under review Summer 2017 N/A N/A

11-EAI-016-CP Transmission Reliability - Meeting Planning Criteria

ISES- Reconfiguration of the 161kV Bus EAI Summer 2018 Summer 2018 None Proposed & In Target

Scoping Summer 2018 NA

11-EAI-017-CP Transmission Reliability - Meeting Planning Criteria

White Bluff: Reconfigure 500 kV Station and construct 230 kV ring bus

EAI Summer 2015 Summer 2013 Construction feasibility Proposed & In Target

Scoping Scope under review. Magnitude of project expected to result in

June 2016 ISD

6/1/16 Note B N/A

11-EAI-024-CP Transmission Reliability - Meeting Planning Criteria

Holland Bottoms to Jacksonville North: Reconductor 115 kV Line

EAI Summer 2018 Summer 2018 None Proposed & In Target

Scoping Summer 2018 NA

11-EAI-025-CP Transmission Reliability - Meeting Planning Criteria

Norfork-Calico Rock : Upgrade 161 kV Line EAI Summer 2016 Summer 2016 None Proposed & In Target

Scoping Scope under review TBD N/A N/A

11-EAI-026-CP Transmission Reliability - Meeting Planning Criteria

NLR Westgate - NLR Levy: Reconductor 115 kV Line EAI Summer 2013 Summer 2013 None Approved Construction Projected ISD changed to 12/31/2013 from 6/1/13 based on outage scheduling. Spring

work completed and approximately 50% of line work

completed and In-Service.

12/31/13 Note B

NLRLVWGLRKS

11-EAI-027-CP Transmission Reliability - Meeting Planning Criteria

AECC L&D 2 to Gillett: Construct new 115 kV Line EAI Summer 2016 Summer 2016 None Proposed & In Target

Scoping Routing of new line in progress. River Crossing presenting

challenges.

6/1/16 Note BN/A

12-EAI-001-CP Transmission Reliability - Meeting Planning Criteria

Calico Rock-Melbourne - Upgrade 161kV Line EAI Winter 2014 Winter 2014 None Approved Design Material requisitions have been submitted by design.

Winter 2014 N/A SAGMEL_ISDEL, MELBCR_ANOFS

12-EAI-002-CP Transmission Reliability - Meeting Planning Criteria

Woodward - Pine Bluff West - Pine Bluff McCamant: Reconductor 115 kV

EAI Summer 2014 Summer 2017 Entergy before ICT Approved Design Attempting to get material in to meet outage scheduling

requirements.

6/1/14 N/AN/A

12-EAI-003-CP Transmission Reliability - Meeting Planning Criteria

Woodward-115 kV Bus Reconfiguration EAI Summer 2016 Summer 2017 Entergy before ICT Proposed & In Target

Scoping Scope under review 6/1/16 N/A N/A

12-EAI-005-CP Transmission Reliability - Meeting Planning Criteria

Camden McGuire - Camden North 115kV Line: Construct New Line

EAI Summer 2014 Summer 2013 ROW acquisition, construction feasibility

Approved Construction River Crossing permit received. APSC CCN approval needed to

continue to meet schedule. ROW procurement activities ongoing. Vegetation clearing scheduled for June/July 2013.

6/1/14 Note B

N/A

12-EAI-006-CP Transmission Reliability - Meeting Planning Criteria

Russellville East-Russellville North: Reconductor 161kV line

EAI Summer 2018 Summer 2018 None Proposed & In Target

Scoping Summer 2018 NA RUSNRE_ANOFS

12-EAI-008-01-CP Transmission Reliability - Meeting Planning Criteria

LV Bagby to Macon Lake: Construct new 230 kV line and operate at 115 kV

EAI Summer 2014 Summer 2013 Construction feasibility Approved Scoping Field visit with APSC completed. CECPN hearing

scheduled for 6/27/13.

6/1/14 Note BN/A

12-EAI-008-02-CP Transmission Reliability - Meeting Planning Criteria

Macon Lake to Reed: Construct new 230 kV line and operate at 115 kV

EAI Summer 2017 Summer 2017 None Approved Scoping Field visit with APSC completed. CECPN hearing scheduled for 6/27/13. Outage scheduling

conflicts with other projects may impact projected ISD.

6/1/17 N/A

N/A

12-EAI-016-CP Transmission Reliability - Meeting Planning Criteria

HS EHV-HS Industrial: Upgrade Terminal Equipment EAI Summer 2015 Summer 2015 None Proposed & In Target

Scoping Under Review Summer 2015 N/A HSEHSI_ARKCP

12-EAI-017-CP Transmission Reliability - Meeting Planning Criteria

HS Industrial-HS Union Carbide: Upgrade Terminal Equipment

EAI Summer 2015 Summer 2015 None Proposed & In Target

Scoping Under Review Summer 2015 N/A N/A

Monthly Construction Plan Project Status Report

Page 2 of 13

Page 3: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

12-EAI-018-CP Transmission Reliability - Meeting Planning Criteria

HS Union Carbide-HS East: Upgrade Terminal Equipment

EAI Summer 2015 Summer 2015 None Proposed & In Target

Scoping Under Review Summer 2015 N/A N/A

12-EAI-019-CP Transmission Reliability - Meeting Planning Criteria

Mabelvale: Replace 500-115 Autos EAI Summer 2016 N/A Supplemental

None Proposed & In Target

Scoping PM&C scoping to begin second half 2013

Summer 2016 N/A MABXF1_MAXF2

12-EAI-021-CP Enhanced Transmission Reliability

Mayflower - Reconfigure 500 kV bus (eliminate breaker failure impact on autos)

EAI Winter 2017 Winter 2017 None Proposed & In Target

Scoping PM&C scoping to begin second half 2013

Winter 2017 N/A MAYXF1_XF2

12-EAI-023-CP Transmission Reliability - Meeting Planning Criteria

Woodward to Pine Bluff Watson Chapel: Rebuild line to 230 kV construction and operate at 115 kV.

EAI Summer 2014 Summer 2013 Construction feasibility Approved Design CECPN application submitted to APSC. Outage scheduling

conflicts with other projects may impact projected ISD.

6/1/14 Note B N/A

12-EAI-027-CP Transmission Reliability - Meeting Planning Criteria

Malvern South: Add 10.2 MVAR Capacitor Bank EAI Summer 2017 Summer 2017 None Proposed & In Target

Scoping Summer 2017 NA N/A

12-EAI-029-CP Transmission Reliability - Meeting Planning Criteria

Upgrade Cheetah to Hot Springs Village 115 kV line EAI Summer 2018 Summer 2018 None Proposed & In Target

Scoping Summer 2018 NA N/A

12-EAI-032-01-CP Transmission Reliability - Meeting Planning Criteria

Construct Gum Springs Switching Station EAI Summer 2018 Summer 2019 Entergy before ICT Proposed & In Target

Scoping PM&C scoping to begin second half 2013

Summer 2018 NA N/A

12-EAI-032-02-CP Transmission Reliability - Meeting Planning Criteria

Gum Springs to Amity construct new line. Add breakers at Amity

EAI Summer 2018 Summer 2019 Entergy before ICT Proposed & In Target

Scoping PM&C scoping to begin second half 2013

Summer 2018 NA N/A

12-EAI-035-CP Transmission Reliability - Meeting Planning Criteria

Ward: Install 21.6 MVAR capacitor bank EAI Summer 2015 Summer 2015 None Proposed & In Target

Scoping PM&C scoping to begin first quarter 2014

Summer 2015 NA N/A

13-EAI-001-CP Transmission Reliability - Meeting Planning Criteria

Pine Bluff McCamant- Pine Bluff East: Reconductor line

EAI Summer 2016 Summer 2016 None Proposed & In Target

Scoping Scope under review Summer 2016 NA N/A

13-EAI-002-CP Transmission Reliability - Meeting Planning Criteria

Pine Bluff Watson Chapel - Pine Bluff South: Rebuild line to 230 kV construction and operate at 115 kV

EAI Summer 2017 Summer 2016 Construction feasibility Proposed & In Target

Scoping Scope under review Summer 2017 NA N/A

13-EAI-003-CP Transmission Reliability - Meeting Planning Criteria

Monticello East to Reed: Construct new 115 kV transmission line. Construct to 230 kV but operate at 115 kV.

EAI Summer 2015 Summer 2017 Entergy before ICT Proposed & In Target

Scoping Route study progressing. CECPN approvals required.

Summer 2015 NA N/A

13-EAI-008-CP Transmission Reliability - Meeting Planning Criteria

Hot Springs EHV Substation: Replace two 115 kV autotransformer breakers

EAI Summer 2013 Summer 2013 None Approved Complete In-Service 6/30/13 6/20/13 NA Yes N/A

13-EAI-009-CP Transmission Service Hot Spring Transmission Service: White Bluff to Pine Bluff Arsenal C - Upgrade terminal equipment at White Bluff

EAI Winter 2013 N/A Supplemental

None Approved Design/Scoping To be worked by T-Grid Winter 2013 NA N/A

14-EAI-002-CP Transmission Service Hot Springs Transmission Service:McCrory-Bailey: Upgrade line to 100C

EAI 2014 Winter N/A Supplemental

None Approved Design/Scoping Being worked in association with NERC Alert Project

2014 Winter N/A N/A

10-EGL-011-CP Transmission Reliability - Meeting Planning Criteria

Mossville - Cut-in line 616 (Nelson to Carlyss 138 kV) into Mossville 138 kV Substation

EGSL Summer 2013 Summer 2013 None Approved Design Material delivery dates will not facilitate current required outage schedule. New outage request

resulting in delay of ISD from 6/30/13 to 11/15 /13.

11/15/13 Generation re-dispatch N/A

11-EGL-002-CP Transmission Reliability - Meeting Planning Criteria

Harelson to Gloria - upgrade 69 kV line EGSL Summer 2018 Summer 2018 None Proposed & In Target

Scoping Summer 2018 NA N/A

11-EGL-016-01-CP Transmission Reliability - Meeting Planning Criteria

Mossville to Canal - Phase 1: Upgrade 69 kV Line EGSL Winter 2013 Winter 2012 Construction feasibility Proposed & In Target

Design/Scoping 12/31/13 NA N/A

11-EGL-016-02-CP Transmission Reliability - Meeting Planning Criteria

Mossville to Canal - Phase 2: Upgrade 69 kV Line EGSL Winter 2014 Winter 2015 Entergy before ICT Proposed & In Target

Design/Scoping Winter 2014 NA N/A

11-EGL-017-CP Transmission Reliability - Meeting Planning Criteria

Five Points to Line 281 Tap to Line 247 Tap- Upgrade 69 kV line

EGSL Winter 2018 Winter 2018 None Proposed & In Target

Planning Winter 2018 N/A N/A

12-EGL-004-CP Transmission Reliability - Meeting Planning Criteria

McManus to Brady Heights - Upgrade 69 kV line EGSL Winter 2017 Winter 2018 Entergy before ICT Proposed & In Target

Planning Winter 2017 N/A N/A

12-EGL-006-CP Transmission Reliability - Meeting Planning Criteria

Bronco - New 230 kV distribution substation (Formerly called Zachery)

EGSL Summer 2017 Summer 2018 Entergy before ICT Proposed & In Target

Planning Summer 2017 Note B N/A

12-EGL-015-CP Economic Willow Glen to Conway - Construct new 230 kV line EGSL Spring 2014 N/A Supplemental

None Approved Design/Construction The project will be split constructed in two phases. The East Phase will be constructed with a planned ISD of July 8,

2013 to energize the new Brittany Substation. ROW

acquisition complete. ROW clearing and construction is well underway. Line work estimated

to complete on July 1, 2013. The West Phase will be

constructed with a planned ISD of June 1, 2014. ROW

acquisition has started on the west phase.

6/1/14 N/A

11-EGL-010-CP Transmission Reliability - Meeting Planning Criteria

Sorrento Upgrade 138/115 kV Auto and upgrade Gonzales - Sorrento 138 kV Line

EGSL/ELL Summer 2014 Summer 2015 Entergy before ICT Approved Design Detailed design has started. Auto transformer has been

ordered.

6/1/14 N/A SREGON_WGWAT

Page 3 of 13

Page 4: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

10-ELL-008-CP Transmission Reliability - Meeting Planning Criteria

Southeast LA Coastal Improvement Plan: Phase 3 Construct Oakville to Alliance 230kV Line Add 230 - 115 kV Autotransformer at Alliance Substation

ELL Summer 2013 Winter 2012 ROW acquisition, construction timing.

Approved Scoping Routing challenges continue to delay start of ROW acquisition. Projected ISD currently moved from 6/1/14 to 6/1/15 to reflect

latest projections. Meetings were held with PSC

Commissioner and DOTD in March. On 3/27/13 LADOTD

requested Entergy to complete design and file a Utility Permit

for soil borings. On May 9, 2013, team concurrence received to order soil borings. Permits will be required from LA DOTD,

COE and possibly Plaquemine Parish for the soil borings.

6/1/15 Note B N/A

10-ELL-009-CP Transmission Reliability - Meeting Planning Criteria

Iron Man to Tezcuco 230 kV line - Construct new line ELL Summer 2015 Summer 2013 Construction feasibility Approved Design/Construction Project Completion date moved to 2015 from 2018 based on expected change in reliability

need date. Iron Man substation placed in service (1/10/12) and included in models. Tezcuco

Substation expansion completed and placed into service 4/24/12.

Permitting complete. ROW acquisition in progress.

5/31/15 Generation re-dispatch N/A

11-ELL-001-CP Enhanced Transmission Reliability

Golden Meadow to Leeville 115 kV - Rebuild/relocate 115 kV transmission line

ELL Spring 2014 N/A Supplemental

None Approved Design Project baselined. On track for current projected ISD. ROW and permitting is resulting in

delay to late spring 2014

5/31/14 N/A N/A

11-ELL-002-CP Transmission Reliability - Meeting Planning Criteria

Mt. Olive: Add Shunt Reactor ELL Winter 2013 Winter 2013 None Approved Construction Site & Foundations complete. Issues with reactor shipment

from manufacturer, working to resolve schedule.

12/13/13 N/A N/A

11-ELL-003-2-CP Transmission Reliability - Meeting Planning Criteria

NE Louisiana Improvement Project - Phase 2 Oak Ridge to new Dunn Substation - Construct new 115 kV Line (1272 ACSS) Add 115 kV breakers at Dunn Add 115 kV, 32.4 MVAR capacitor bank at Dunn

ELL Summer 2014 Summer 2014 None Approved Design Dunn Site work 72%. ROW acquisition nearing completion.

ISD moved from 10/31/14 to 12/19/14 due to outage

scheduling requirements.

12/19/14 N/A N/A

11-ELL-004-CP Transmission Reliability - Meeting Planning Criteria

Northeast LA Improvement Project Phase 3 Upgrade Sterlington to Oakridge to Dunn 115 kV Line

ELL Summer 2015 Summer 2015 None Proposed & In Target

Design/Scoping TBD N/A STOAK_PVBW

11-ELL-009-1-CP Generation Interconnection NM6: Modify Ninemile switchyard for interconnection ELL Winter 2014 N/A Supplemental

None Approved Construction Foundation construction for T- structures 1-10 are completed. Projected ISD for 6A and 6B is

now schedule for 12/1/2013 (from 9/15/13) due to

constraints/coordination with Fossil's EPC contractor.

However, meeting on Thursday, May 9, 2013 revealed Fossil's 115kV BACKFEED Milestone may slide to Dec. 31, 2013.

(Early finish target 12/13/2013; Late Finish 12/31/13) Gen 6C

remains on track for Early finish of April of 2014; Late target

finish of Dec. 01 2014.

12/1/2013 (6A&6B)

12/1/2014 (6C)

N/A N/A

11-ENO-001-CP Generation Interconnection NM6: Upgrade Michoud breaker N9803 ENOI Winter 2014 N/A Supplemental

None Approved Design Design underway. 9/16/13 N/A N/A

11-ELL-010-1-CP Transmission Service NM6: Upgrade Ninemile to Southport 230 kV transmission line No.1

ELL Winter 2014 N/A Supplemental

None Approved Design Design underway. Projected ISD accelerated from 9/30/14.

Project completion date accelerated from 9/30/14 to

9/1/14.

9/1/14 N/A N/A

Page 4 of 13

Page 5: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

11-ELL-010-2-CP Transmission Service NM6: Upgrade Ninemile to Southport 230 kV transmission line No.2

ELL Winter 2014 N/A Supplemental

None Approved Design Design underway. Projected ISD accelerated from 9/30/14.

Project completion date accelerated from 9/30/14 to

9/1/14.

9/1/14 N/A N/A

11-ELL-012-CP Transmission Reliability - Meeting Planning Criteria

Valentine to Clovelly 115 kV upgrade ELL Summer 2015 Winter 2012 Construction feasibility Proposed & In Target

Scoping Developing scope for rebuilding line in existing ROW.

Summer 2015 Note B N/A

13-ELL-002-CP Transmission Reliability - Meeting Planning Criteria

McCall 115 kV Substation: Add 20.4 MVAR Capacitor Bank (Formerly Napoleonville add capacitor bank)

ELL Fall 2013 Summer 2013 Construction feasibility Approved Design Project in design phase. All major materials have been ordered. Site & Foundation

Construction Work has been sent out for Quotes.

9/25/13 Note B N/A

13-ELL-004-CP Transmission Reliability - Meeting Planning Criteria

Minden Improvement Project Ph 1-Place cap bank at Minden REA

ELL Summer 2015 Summer 2016 Entergy before ICT Proposed & In Target

Scoping Summer 2015 NA N/A

10-EMI-017-CP Transmission Reliability - Meeting Planning Criteria

Ray Braswell - Wynndale 115kV Line: Construct New 260 MVAConstruct new 115 kV Switching Station between Byram and Terry. Wynndale SS to be designed for future 230-115 kV auto and distribution facilities

EMI Summer 2013 Summer 2013 None Approved Construction Line construction 27% complete. Wynndale steel construction

80% complete.

12/1/13 Note B N/A

11-EMI-002-CP Transmission Reliability - Meeting Planning Criteria

Baxter Wilson to S.E. Vicksburg - Upgrade 115 kV line EMI Summer 2015 Summer 2015 None Proposed & In Target

Scoping Scoping underway Summer 2015 N/A BWLVKS_VKSW

11-EMI-007-CP Transmission Reliability - Meeting Planning Criteria

Breakers at Hollandale and Belzoni Tap SS (close normally-open point)

EMI Summer 2015 Summer 2015 None Proposed & In Target

Design/Scoping Site acquisition ongoing. Summer 2015 N/A N/A

12-EMI-001-CP Transmission Reliability - Meeting Planning Criteria

Franklin - McComb build new 115 kV line (constructed to 230 kV)

EMI Summer 2017 Summer 2017 None Proposed & In Target

Design/Scoping Summer 2017 N/A N/A

12-EMI-002-1-CP Transmission Reliability - Meeting Planning Criteria

Getwell Area ImprovementsConstruct new Senatobia Industrial substation.Cut in Senatobia to Sardis 115 kV line into new substation and add new 230-115 kV autotransformer

EMI Summer 2016 Summer 2014 Construction feasibility Proposed & In Target

Design/Scoping Summer 2016 Note B N/A

12-EMI-002-2-CP Transmission Reliability - Meeting Planning Criteria

Getwell Area ImprovementsConstruct new 230 kV line from Getwell to new Senatobia Industrial 230-115 kV substation.

EMI Summer 2016 Summer 2014 Construction feasibility Proposed & In Target

Design/Scoping Route and Environmental studies to be completed 2012.

Summer 2016 Note B N/A

13-EMI-001-CP Transmission Reliability - Meeting Planning Criteria

Upgrade CTs at Vicksburg for Vicksburg-B.Wilson ckt 1 (ckt without Spencer Potash on it)

EMI Summer 2013 Summer 2014 Entergy before ICT Approved Complete In-Service Summer 2013 6/13/13 NA Yes N/A

13-EMI-002-CP Transmission Reliability - Meeting Planning Criteria

Durant: Add Capacitor Bank EMI Summer 2017 Summer 2017 None Proposed & In Target

Design/Scoping Summer 2017 NA N/A

14-EMI-001-CP Transmission Reliability - Meeting Planning Criteria

Horn Lake to Greenbrook 115kV line: Upgrade 4 switches

EMI Summer 2013 Summer 2013 Approved Construction Complete pending relay upgrades prior to summer and transfer bus switch scheduled for Fall 2013. Transfer switch

has no impact on rating of circuit

Fall 2013 5/3/13 NA N/A

11-ETI-002-CP Transmission Reliability - Meeting Planning Criteria

Reconductor Sabine to Port Neches Bulk (Line 515) ETI Summer 2017 Summer 2018 Entergy before ICT Proposed & In Target

Design/Scoping Summer 2017 NA SABPN_SABHAM, SABPN_SABLI, SABPNB_LNPNB

11-ETI-003-CP Transmission Reliability - Meeting Planning Criteria

Deweyville (JNEC) - Add 69 kV capacitor bank ETI Spring 2013 Winter 2012 Construction feasibility Proposed & In Target

Design/Scoping Scope under review TBD Note B N/A

11-ETI-018-CP Transmission Reliability - Meeting Planning Criteria

Construct new China to Amelia 230kV line ETI Summer 2016 Summer 2018 Entergy before ICT Approved Design/Scoping CCN process is started for this line. Routing study kickoff

meeting held March 5, 2013. Held Open House for potential affected landowners April 22.

2016 Summer N/A

NA

11-ETI-023-CP Transmission Reliability - Meeting Planning Criteria

Orange County 230kV Project: Construct new Chisholm Road 230 kV substation, Construct new line from Hartburg to Chisholm Road, add 2nd Hartburg 500-230 kV auto

ETI Summer 2017 Summer 2017 None Proposed & In Target

Design/Scoping The CCN process for this line targeted to start in mid - late

summer of 2014.

2017 Summer N/A

N/A

11-ETI-033-CP Transmission Reliability - Meeting Planning Criteria

Toledo Bend to Leach 138 kV - Upgrade line ETI Summer 2017 Summer 2017 None Proposed & In Target

Scoping 2017 Summer N/A LCHTOL_GRICR TBLCH_MTOHTB

11-ETI-034-CP Transmission Reliability - Meeting Planning Criteria

Leach to Newton Bulk 138 kV - Reconductor line ETI Summer 2018 Summer 2018 None Proposed & In Target

Scoping 2018 Summer NA N/A

11-ETI-037-CP Transmission Reliability - Meeting Planning Criteria

Construct new China to Stowell 138 kV line ETI Summer 2018 Summer 2018 None Proposed & In Target

Scoping 2018 Summer NA N/A

11-ETI-038-CP Transmission Reliability - Meeting Planning Criteria

Reconductor Sabine to Port Neches Bulk (via Linde Line 516)

ETI Summer 2018 Summer 2018 None Proposed & In Target

Scoping 2018 Summer NA SABLIN_PNB

11-ETI-039-CP Transmission Reliability - Meeting Planning Criteria

Upgrade Jacinto - Splendora 138 kV Line ETI Summer 2015 Summer 2015 None Proposed & In Target

Scoping 2015 Summer N/A N/A

11-ETI-042-CP Transmission Reliability - Meeting Planning Criteria

Expand Cap Bank at New Caney 138kV ETI Summer 2014 Summer 2015 Entergy before ICT Proposed & In Target

Scoping 2014 Summer NA N/A

12-ETI-004-CP Transmission Reliability - Meeting Planning Criteria

Ponderosa Switching Station: tie lines Longmire to Fish Creek and Conroe to Woodhaven into new switching station (Formerly referred to as Conroe Area SS)

ETI Summer 2013 Summer 2014 Entergy before ICT Approved Design/Construction 138kV site cleared ready for construction to begin. Steel for

project received. Projected ISD moved from 12/16/13 to

12/27/13.

12/27/13 N/A

NA

Page 5 of 13

Page 6: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

12-ETI-007-CP Transmission Reliability - Meeting Planning Criteria

Alden 138 kV Substation: Add Capacitor Bank ETI Summer 2015 Summer 2015 None Proposed & In Target

Scoping 2015 Summer N/A NA

12-ETI-009-CP Transmission Reliability - Meeting Planning Criteria

Sabine: Upgrade terminal equipment (Sabine to Big 3 line)

ETI Summer 2017 Summer 2018 Entergy before ICT Proposed & In Target

Scoping 2017 Summer NA N/A

12-ETI-014-CP Transmission Reliability - Meeting Planning Criteria

Amelia to Helbig: Reconductor Line ETI Summer 2018 Summer 2018 None Proposed & In Target

Scoping 2018 Summer NA AMLHLB_HBCYP

12-ETI-015-CP Enhanced Transmission Reliability

College Station SS: Create emergency tie point with ERCOT (asynchronous)

ETI Fall 2012 N/A Supplemental

None Approved Construction Date moved out to July from May based on City of College

Station work. Entergy has completed all possible work and is waiting on the City of College Station to complete their work. ETI will be able to utilize the

emergency tie if required with City of College Station temporary adjusting configuration. Final

configuration expected to be completed by City is currently

projected to be 7/31/13.

7/31/13 N/A

NA

13-ETI-009-01-CP Transmission Reliability - Meeting Planning Criteria

Ponderosa to Grimes: Construct new 230 kV LineAdd 345-230 kV Auto at GrimesAdd 230-138 kV Auto at Ponderosa

ETI Summer 2016 Summer 2018 Entergy before ICT Approved Scoping The CCN process is underway for this project with a targeted application date of mid June

2013. Open houses were held March 25 and 26. The CCN application period has been extended for three months to

work through some landowner issues; this extension will not

impact the overall targeted ISD.

2016 Summer N/A

GRIMTZ_WDNGRIMZ_GRICRO

13-ETI-009-02-CP Transmission Reliability - Meeting Planning Criteria

Conroe to Ponderosa 138 kV line: Upgrade Line ETI Summer 2016 Summer 2018 Entergy before ICT Approved Scoping 2016 Summer NA N/A

13-ETI-010-01-CP Transmission Reliability - Meeting Planning Criteria

Pansy to Lovells Lake 69 kV line: Upgrade line to 100 deg design

ETI Winter 2013 Summer 2014 Entergy before ICT Proposed & In Target

Design/Scoping LIDAR flown. Data being analyzed to move forward with

project

2013 Winter NAN/A

13-ETI-010-02-CP Transmission Reliability - Meeting Planning Criteria

Lovells Lake to Texas Hillebrandt 69 kV line: Upgrade line to 100 deg design

ETI Winter 2013 Summer 2013 Construction feasibility Proposed & In Target

Design/Scoping LIDAR flown. Data being analyzed to move forward with

project

2013 Winter NAN/A

13-ETI-011-CP Transmission Reliability - Meeting Planning Criteria

Lewis Creek to Egypt 138 kV line: Reconductor ETI Summer 2014 Summer 2014 None Proposed & In Target

Design/Scoping A Contract Project Manager has been assigned to this project

and will begin scoping activities.

2014 Summer NA

N/A

13-ETI-012-CP Transmission Reliability - Meeting Planning Criteria

Construct new Porter to Forest 138 kV transmission line - Construct new line from Porter to Oakridge area and tie into de-energized line 403 - Terminate line 403 into Forest 138 kV substation

ETI Summer 2016 Summer 2018 Entergy before ICT Proposed & In Target

Design/Scoping The site for the Forest station has been identified. The CNN is schedule to start in the next

few months.

2016 Summer NA

N/A

13-ETI-013-CP Transmission Reliability - Meeting Planning Criteria

Egypt to Panorama 138 kV Line: Reconductor line ETI Summer 2018 Summer 2018 None Proposed & In Target

Design/Scoping 2018 Summer NA N/A

PREVIOUSLY COMPLETED PROJECTS10CP-EAI-001 Transmission Reliability -

Meeting Planning CriteriaHamlet 161 kV Substation: Install 161 kV Breaker on Conway Industrial Line

EAI Summer 2009 Summer 2009 None Approved Complete In-service 12/4/09 12/4/09 Complete Yes

10CP-EAI-002 Transmission Reliability - Meeting Planning Criteria

Gillette 115 kV Substation: Install 10.8 MVAR Capacitor Bank

EAI Summer 2009 Summer 2009 None Approved Complete In-service 7/1/09 5/16/09 Complete Yes

10CP-EAI-003 Transmission Reliability - Meeting Planning Criteria

Conway West - Donaghey 161 kV Line: Reconductor with 666 ACSS

EAI Summer 2009 Summer 2009 None Approved Complete In-service 3/24/09 Complete Yes

10CP-EAI-004 Transmission Reliability - Meeting Planning Criteria

Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Add 10.8 MVAR capacitor bank at Emerson 115 kV substation

EAI Summer 2009 Summer 2009 None Approved Complete In-service 12/31/09 10/8/09 Complete Yes

10CP-EAI-005 Transmission Reliability - Meeting Planning Criteria

Danville 161 kV Substation: Upgrade Terminal Equipment to match or exceed Magazine line ratings

EAI Fall 2009 Fall 2009 None Approved Complete In-service 8/14/09 8/14/09 Complete Yes

10CP-EAI-006 Transmission Reliability - Meeting Planning Criteria

Donaghey - Conway South 161 kV Line: Reconductor with 666 ACSS

EAI Spring 2010 Summer 2009 Project in service Approved Complete In-service 4/21/10 Complete Yes

Page 6 of 13

Page 7: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

10CP-EAI-007-1 Transmission Service SMEPA (Plum Point): * Dell - Manilla 161kV Line: Upgrade to at least 247MVA

EAI Spring 2010 Spring 2010 None Approved Complete In-service 4/5/10 4/2/10 Complete Yes

10CP-EAI-007-2 Transmission Service SMEPA (Plum Point): * Manilla - Monette 161kV Line: Upgrade to at least 247MVA

EAI Spring 2010 Spring 2010 None Approved Complete In-service 12/26/08 12/22/08 Complete Yes

10CP-EAI-007-3 Transmission Service SMEPA (Plum Point): * Jonesboro North - Paragould South 161kV Line: Upgrade to at least 247MVA

EAI Spring 2010 Spring 2010 None Approved Complete In-service 5/29/09 5/14/09 Complete Yes

10CP-EAI-007-4 Transmission Service SMEPA (Plum Point): * Jonesboro North - Jonesboro 161kV Line: Upgrade to at least 247MVA

EAI Spring 2010 Spring 2010 None Approved Complete In-service 1/8/10 1/9/10 Complete Yes

10CP-EAI-008 Transmission Reliability - Meeting Planning Criteria

Beebe 115 kV Substation: Install 21.6 MVAR Capacitor Bank

EAI Summer 2010 Summer 2010 None Approved Complete In-service 6/1/10 4/21/10 Complete Yes

10CP-EAI-009 Transmission Reliability - Meeting Planning Criteria

Melbourne - Sage 161 kV Line: Upgrade line to at least 1200 A

EAI Summer 2010 Summer 2009 First identified by ICT in early 2009. Construction not feasible by summer 2009 due to material acquisition and outage coordination

Approved Complete In-service 6/1/10 6/19/10 Complete Yes

10CP-EAI-010 Transmission Reliability - Meeting Planning Criteria

Warren East 115 kV Substation: Install 10.8 MVAR Capacitor Bank

EAI Summer 2010 Summer 2010 None Approved Complete In-service 8/6/10 7/18/10 Complete Yes

10CP-EAI-011 Transmission Reliability - Meeting Planning Criteria

Parkin to Twist 161 kV - Replace line trap at Parkin (increase rating of line segment)

EAI Winter 2010 Winter 2010 None Approved Complete In-Service 12/31/10 12/22/10 Complete Yes

10CP-EAI-012-1 Transmission Service Transmission Service (OG&E) Upgrade ANO - Russelville North 161 kV Line to 546 MVA

EAI Summer 2010 2012 None Approved Complete In-service 6/1/10 5/18/10 Complete Yes

10CP-EAI-012-2 Transmission Service Transmission Service (OG&E) Upgrade Russelville East - Russelville South 161 kV Line to 448 MVA

EAI Summer 2010 Summer 2010 None Approved Complete In-service 9/30/10 8/12/10 Complete Yes

10-EAI-013-CP Transmission Reliability - Meeting Planning Criteria

Osage Creek-Grandview New Line Build new 161 kV (At Least 1200 A) line from Grandview (Planned SPA 161 kV Substation tapped on the Eureka - Table Rock 161 kV Line) to Osage Creek

EAI Summer 2011 Summer 2012 Entergy before ICT Approved Complete In-Service 12/15/11 11/28/11 Complete Yes N/A

10CP-EAI-014 Transmission Reliability - Meeting Planning Criteria

Harrison East to Everton Road 161 kV Line: Upgrade Harrison East Terminal Equipment to 1200 A

EAI Winter 2009 Winter 2009 None Approved Complete In-service 12/15/09 12/15/09 Complete Yes

10CP-EAI-016-1 Transmission Service Transmission Service (Aquila) Upgrade Hot Springs - Bismark 115 kV Line to 176 MVA

EAI Winter 2011 Summer 2012 None Approved Complete In-service 6/1/11 10/20/10 Complete Yes

10-EAI-015-1-CP Transmission Reliability - Meeting Planning Criteria

Holland Bottoms (Cabot EHV): Construct new 500/161/115 kV substation Phase 1 Projects Tap the Keo - ISES 500 kV Line Tap the Cabot - Jacksonville North 115 kV Line Install 500 kV and 115 kV Busses and a 600 MVA 500 kV / 115 kV Autotransformer

EAI Summer 2011 Summer 2012 Entergy before ICT Approved Complete In-service 12/31/11 1/6/12 Complete Yes N/A

10-EAI-015-2-CP Transmission Reliability - Meeting Planning Criteria

Holland Bottoms (Cabot EHV): Construct new 500/161/115 kV substation Phase 2 Projects Install 161 kV Bus and a 600 MVA 500 kV / 161 kV Autotransformer

EAI Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 5/23/12 N/A Yes N/A

10CP-EAI-016-2 Transmission Service Transmission Service (Aquila) Upgrade Bismark - Alpine 115 kV Line to 176 MVA

EAI Winter 2011 Winter 2011 None Approved Complete In-Service 2/28/11 3/2/11 Complete Yes

10CP-EAI-016-3 Transmission Service Transmission Service (Aquila) Upgrade Alpine - Amity 115 kV Line to 176 MVA

EAI Winter 2011 Winter 2011 None Approved Complete In-Service 3/31/11 3/22/11 Complete Yes

10-EAI-017-CP Transmission Reliability - Meeting Planning Criteria

Holland Bottoms - Hamlet 161 kV Line: Construct new 161 kV Line Convert Hamlet SS to a breaker station (Single Bus Single Breaker Scheme) Move the Quitman line from Gold Creek to Hamlet SS Move the Gravel Ridge line from Gold Creek to Hamlet SS Construct a line rated at least 1200 A from Hamlet SS to Holland Bottoms

EAI Summer 2012 Summer 2013 Entergy before ICT Approved Complete In-Service 6/1/12 5/23/12 N/A Yes N/A

Page 7 of 13

Page 8: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

10-EAI-018-CP Transmission Reliability - Meeting Planning Criteria

Ebony 161 kV Switching Station: Install 5 Breaker Ring Bus Lines Terminating Into New Ebony Substation (ratings unchanged): Ebony - Kuhn Road 161 kV Line Ebony - WM Lehi - WM Polk - WM EHV 161 kV Line Ebony - WM Dover - WM Gateway 161 kV Line Ebony - Marked Tree 161 kV Line Ebony - WM Lehi - WM EHV 161 kV Line

EAI Summer 2012 Summer 2012 None Approved Complete In-service 12/31/12 11/16/12 N/A Yes N/A

10-EAI-019-CP Transmission Reliability - Meeting Planning Criteria

Jonesboro to Hergett 161 kV Line: Upgrade 161 kV Line to at least 240 MVA

EAI Summer 2012 Summer 2012 None Approved Complete In-Service 5/1/12 5/3/12 N/A Yes JONHE_JONJOS

10-EAI-020-CP Transmission Reliability - Meeting Planning Criteria

Benton North to Benton South: Construct New 115 kV Line Rated at least 170 MVA Install Switching Stations at Benton North and Benton South

EAI Winter 2012 Winter 2012 None Approved Complete In-Service 6/30/13 4/22/13 Complete Yes N/A

10-EAI-022-1-CP Transmission Service Westar Transmission Service Monette - Paragould 161kV Line: Upgrade to at least 246 MVA

EAI Summer 2012 Summer 2013 Entergy before ICT Approved Complete In-service 12/30/11 1/10/12 Complete Yes MONJPA_SANSH

10-EAI-022-2-CP Transmission Service Westar Transmission Service Paragould Substation: Upgrade the switch B6673 from 600A to 2000A

EAI Summer 2012 Summer 2013 Entergy before ICT Approved Complete In-Service 10/16/11 9/29/11 Complete Yes MONJPA_SANSH

10-EAI-022-3-CP Transmission Service Westar Transmission Service Russellville South - Dardanelle Dam (SPA) 161kV Line: Replace switch

EAI Summer 2012 N/A Supplemental

None Approved Complete In-Service 12/31/11 10/31/11 Complete Yes

10CP-EAI-023 Transmission Reliability - Meeting Planning Criteria

Couch to McNeil 115kV Line: Upgrade jumpers at Couch

EAI Summer 2011 Summer 2011 None Approved Complete In-Service Winter 2010 1/20/11 Complete Yes

10CP-EAI-024 Transmission Reliability - Meeting Planning Criteria

Lake Catherine 4 to Arklahoma 115 kV line: Upgrade risers at Arklahoma

EAI Summer 2011 Summer 2011 None Approved Complete In-Service Spring 2011 1/24/11 Complete Yes

10CP-EAI-026 Transmission Reliability - Meeting Planning Criteria

Mablevale to LR Alexander 115 kV line: Replace switches and risers at Mablevale and upgrade bus at LR Mann Road

EAI Winter 2010 Winter 2010 None Approved Complete In-Service 4/6/11 4/13/11 Complete Yes

10CP-EAI-027 Transmission Reliability - Meeting Planning Criteria

Russelville North to Russelville East 115 kV line: Replace jumpers at Russellville East

EAI Spring 2011 Spring 2011 None Approved Complete In-Service Winter 2010 1/17/10 Complete Yes

10CP-EAI-028 Transmission Reliability - Meeting Planning Criteria

Morgan to Mayflower 115 kV line: Replace jumpers and bus at Mayflower

EAI Summer 2011 Summer 2011 None Approved Complete In-Service 2/4/11 2/8/11 Complete Yes

10CP-EAI-029 Transmission Reliability - Meeting Planning Criteria

Maumelle East SS to Morgan 115 kV line: Replace switch and bus at Maumelle East SS

EAI Summer 2011 Summer 2011 None Approved Complete In-Service Spring 2011 4/12/11 Complete Yes

10CP-EAI-030 Transmission Reliability - Meeting Planning Criteria

Heber Springs South to Heber Springs Industrial 161 kV line: Replace bus at Heber Springs South

EAI Summer 2011 Summer 2011 None Approved Complete In-Service 4/7/11 4/25/11 Complete Yes

10-EAI-031-CP Economic West Memphis to Birmingham Steel 500 kV line flowgate: Replace 500 kV breaker, six line traps, and 2 switches at West Memphis 500 kV substation

EAI Winter 2011 N/A Supplemental

None Approved Complete In-service 3/5/12 2/28/12 Complete Yes IWMPBIR_SANSH

11-EAI-001-CP Transmission Reliability - Meeting Planning Criteria

Pine Bluff Voltage Support Project - Phase 1 Poyen 115 kV Substation: Add 21.6 MVAR Capacitor Bank

EAI Summer 2012 Summer 2012 None Approved Complete In-Service 6/15/12 5/31/12 N/A Yes N/A

11-EAI-006-CP Transmission Reliability - Meeting Planning Criteria

Ebony 161 kV Switching Station: Add 36 MVAR Capacitor Bank

EAI Winter 2012 Summer 2013 Entergy before ICT Approved Complete In-service 12/31/12 11/30/12 Complete Yes N/A

11-EAI-010-CP Transmission Reliability - Meeting Planning Criteria

Wilmar Substation: Add 21.6 MVAR Capacitor Bank (Formerly Hilo Substation)

EAI Winter 2012 Summer 2013 Entergy before ICT Approved Complete In-service 2/15/13 1/21/13 N/A Yes N/A

11CP-EAI-011 Transmission Reliability - Meeting Planning Criteria

Pangburn 161 kV Substation: Relocate Rutherford 161 kV Cap Bank to Pangburn

EAI Summer 2011 Summer 2014 Entergy before ICT Approved Complete In-service 8/22/11 8/31/11 Complete Yes

11CP-EAI-013 Transmission Reliability - Meeting Planning Criteria

Woodward to Pine Bluff Watson Chapel: Upgrade bus at PB Watson Chapel

EAI Summer 2011 N/A Project recently added Approved Complete In-Service 5/1/11 4/26/11 Complete Yes

12-EAI-020-CP Transmission Reliability - Meeting Planning Criteria

Mabelvale: Change 500-115 NLTC from 487.5kV tap to 512.5kV tap

EAI Summer 2013 Summer 2013 None Approved Complete In-Service 5/10/12 5/10/12 N/A Yes MABXF1_MAXF2

12-EAI-028-CP Transmission Reliability - Meeting Planning Criteria

Quitman to Bee Branch: Replace 600A switch(Formerly upgrade line project)

EAI Winter 2012 Winter 2017 Entergy before ICT Approved Complete In-service 12/31/12 10/23/12 N/A Yes QUTBEB_FTSAR

13-EAI-004-CP Transmission Reliability - Meeting Planning Criteria

Monticello East - Add 21.6 MVAR capacitor bank EAI Summer 2013 Summer 2015 Entergy before ICT Approved Complete In-Service Summer 2013 5/29/13 Complete Yes N/A

13-EAI-007-CP Transmission Reliability - Meeting Planning Criteria

Jim Hill to St. Francis 161 kV line: Upgrade terminal equiment at Jim Hill

EAI Fall 2012 Fall 2012 Project added per request of AECI Approved Complete In-service 12/1/12 10/23/12 N/A Yes

10CP-EGL-001 Transmission Reliability - Meeting Planning Criteria

Acadia 138 kV Substation: Install 36 MVAR Capacitor Bank

EGSL Summer 2009 Summer 2009 None Approved Complete In-service 6/19/09 Complete Yes

10CP-EGL-002 Transmission Reliability - Meeting Planning Criteria

Addis to Cajun 230 kV line - Upgrade Limiting Section With Double-Bundled 649.5 ACAR (654 MVA)

EGSL Winter 2010 Winter 2012 Entergy before ICT Approved Complete In-Service 12/31/10 12/15/10 Complete Yes

10CP-EGL-003 Transmission Reliability - Meeting Planning Criteria

Carter and Elton Capacitor Banks: Upgrade 69 kV capacitor bank at Elton to 14 MVAR, Add 69 kV, 14 MVAR capacitor bank at Carter

EGSL Fall 2010 Fall 2010 None Approved Complete In-service 12/3/10 10/27/10 Complete Yes

10-EGL-004-CP Transmission Reliability - Meeting Planning Criteria

Construct New Youngsville 138 kV Distribution Substation

EGSL Winter 2011 Summer 2012 Entergy before ICT Approved Complete In-service 12/31/11 11/21/11 Complete Yes

10CP-EGL-005 Transmission Reliability - Meeting Planning Criteria

Alchem - Monochem 138 kV Line: Upgrade 138 kV line to 275 MVA

EGSL Summer 2011 Summer 2011 None Approved Complete In-Service 5/1/11 5/24/11 Complete Yes MONALC_SGAAC

Page 8 of 13

Page 9: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

10CP-EGL-006-1 Transmission Reliability - Meeting Planning Criteria

Acadiana Area Improvement Project Phase 1 Projects Construct new Sellers Road to Meaux 230 kV Line

EGSL Summer 2011 Winter 2010 ROW acquisition, material lead times, construction coordination. Jointly agreed to by parties.

Approved Complete In-Service 5/6/11 5/6/11 Complete Yes

10CP-EGL-006-2 Transmission Reliability - Meeting Planning Criteria

Acadiana Area Improvement Project Phase 1 Projects Add 450 MVA, 230-138 kV auto at Meaux

EGSL Summer 2011 Winter 2010 ROW acquisition, material lead times, construction coordination. Jointly agreed to by parties.

Approved Complete In-Service 5/2/11 5/6/11 Complete Yes

10CP-EGL-006-3 Transmission Reliability - Meeting Planning Criteria

Acadiana Area Improvement Project Phase 1 Projects Add new 138 kV line bay at Moril (Segura Line)

EGSL Summer 2011 Summer 2011 None Approved Complete In-service 5/5/10 Complete Yes

10CP-EGL-006-4 Transmission Reliability - Meeting Planning Criteria

Acadiana Area Improvement Project Phase 1 Projects Add new 500 kV position for Cleco autotransformer at Richard

EGSL Summer 2011 Winter 2010 ROW acquisition, material lead times, construction coordination. Jointly agreed to by parties.

Approved Complete In-Service 11/22/10 5/6/11 Complete Yes RICXF1_XF2

10-EGL-007-1-CP Transmission Reliability - Meeting Planning Criteria

Acadiana Area Improvement Project Phase 2 Projects Construct new Labbe to Sellers Road 230 kV Line

EGSL Summer 2012 Summer 2012 None Approved Complete In-Service 6/29/12 6/28/12 N/A YesN/A

10-EGL-007-2-CP Transmission Reliability - Meeting Planning Criteria

Acadiana Area Improvement Project Phase 2 Projects Add new 500 kV position for Cleco autotransformer at Wells

EGSL Summer 2012 Summer 2012 None Approved Complete In-Service. Entergy completed work to allow CLECO connection of new auto.

3/19/12 3/16/12 N/A Yes

BONXF_FLNHPK

10-EGL-008-CP Transmission Reliability - Meeting Planning Criteria

Construct new Nelson to Moss Bluff 230 kV line Disconnect existing Nelson to Moss Bluff 230 kV line Will be used in the future to create a Nelson to new Lake Charles 230 kV line

EGSL Summer 2012 Summer 2012 None Approved Complete In-Service 5/31/12 5/12/12 N/A Yes NELMB_CARBOU

10-EGL-009-CP Transmission Reliability - Meeting Planning Criteria

Tejac to Marydale: Upgrade 69 kV transmission line EGSL Summer 2012 Summer 2013 Entergy before ICT Approved Complete In-service 1/31/12 2/15/12 Complete Yes N/A

10-EGL-010-CP Transmission Reliability - Meeting Planning Criteria

Loblolly-Hammond Build 230 kV Line EGSL/ELL Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 12/16/11 Complete Yes

10CP-EGL-013 Transmission Reliability - Meeting Planning Criteria

Krotz Springs to Line 642 Tap 138 kV line: Upgrade bus at Colonial Springs Tap

EGSL Summer 2013 Summer 2013 None Approved Complete In-Service Spring 2011 3/14/11 Complete Yes

10CP-EGL-014 Transmission Reliability - Meeting Planning Criteria

Livonia to Line 643 Tap 138 kV line: Upgrade riser at Livonia

EGSL Winter 2010 Winter 2010 None Approved Complete In-Service Spring 2011 3/16/11 Complete Yes

10CP-EGL-015 Transmission Reliability - Meeting Planning Criteria

Wilbert to Livonia 138 kV line: Upgrade risers at Wilbert and Livonia

EGSL Summer 2011 Summer 2011 None Approved Complete In-Service Spring 2011 1/25/11 Complete Yes

10CP-EGL-016 Transmission Reliability - Meeting Planning Criteria

Big Three to Carlyss 230 kV line: Upgrade bus, switch, and jumpers at Carlyss 230 kV substation

EGSL Summer 2011 Summer 2011 None Approved Complete In-service 5/6/11 6/9/11 Complete Yes

10-EGL-017-CP Transmission Reliability - Meeting Planning Criteria

Richard to Habetz 138 kV line: Upgrade bus at Richard EGSL Winter 2010 Winter 2010 None Approved Complete In-Service 11/30/11 10/10/11 Complete Yes RICHAB_BONAM RICHAB_PDMLA RICHAB_RICWE

10-EGL-018-CP Transmission Reliability - Meeting Planning Criteria

Willow Glen to Bayou LaButte 500 kV line: Replace/change line relay CT and ratio at Willow Glen (Formerly Willow Glen to Webre)

EGSL Summer 2011 Summer 2012 Entergy before ICT Approved Complete In-service 3/31/12 2/27/12 Complete Yes WEBWG_CJFAN

10CP-EGL-019 Transmission Reliability - Meeting Planning Criteria

Willow Glen to Geismar 138 kV line: Upgrade risers at Willow Glen and Geismar

EGSL Summer 2011 Summer 2011 None Approved Complete In-Service Summer 2011 1/20/11 Complete Yes

10CP-EGL-020 Transmission Reliability - Meeting Planning Criteria

Port Hudson to Fancy Point 230 kV line: Upgrade bus at Fancy Point

EGSL Winter 2010 Winter 2010 None Approved Complete In-Service Winter 2010 12/20/10 Complete Yes

10CP-EGL-021 Transmission Reliability - Meeting Planning Criteria

Richard to Scott 1 138kV segment: Replace/change CT ratio at Richard and upgrade bus at Scott

EGSL Winter 2010 Winter 2010 None Approved Complete In-Service Winter 2010 1/7/11 Complete Yes

10CP-EGL-022 Transmission Reliability - Meeting Planning Criteria

Carlyss to Rose Bluff 230 kV line: Upgrade bus, switch, and jumpers at Carlyss 230 kV substation

EGSL Winter 2010 Winter 2010 None Approved Complete In-Service Spring 2011 5/23/11 Complete Yes ROSCAR_NELMO

11-EGL-004-CP Transmission Reliability - Meeting Planning Criteria

Bloomfield to Bosco 138 kV line (formerly Vatican project) Construct new Bloomfield 138 kV SS north of Vatican Construct new Bosco 138 kV SS on Scott to Scanlan 138 kV line Construct new Bloomfield to Bosco 138 kV line Install 5 ohm reactor at Bosco substation

EGSL Summer 2013 Winter 2012 Construction feasibility Approved Complete In-service 12/31/12 12/20/12 N/A Yes

NCRSCB_RICHR, NRCSCB_WLPNT, NCRSC_RICWEL

11-EGL-005-CP Transmission Reliability - Meeting Planning Criteria

Jackson to Tejac: Upgrade 69 kV transmission line EGSL Summer 2012 Summer 2012 None Approved Complete In-service 6/15/12 6/5/12 N/A Yes N/A

11-EGL-008-CP Transmission Reliability - Meeting Planning Criteria

Francis 69 kV substation - Add 14.4 MVAR, 69 kV capacitor bank (Previously considered Marydale as alternate location)

EGSL Summer 2013 Summer 2013 None Approved Complete In-Service 3/29/13 3/25/13 N/A YesN/A

11CP-EGL-011 Transmission Reliability - Meeting Planning Criteria

Carlyss to Citcon West 138 kV: Upgrade station equipment

EGSL Winter 2011 Winter 2010 Construction scheduling in conjunction with work on Carlyss 230 kV bus results in a more probable date of after summer 2011.

Approved Complete In-service 9/29/11 9/28/11 Complete Yes

11CP-EGL-012 Transmission Reliability - Meeting Planning Criteria

Carlyss to Nelson 230 kV: Upgrade station equipment at Carlyss

EGSL Winter 2013 Winter 2013 None Approved Complete In-service Spring 2011 6/9/11 Complete Yes

11-EGL-013-CP Transmission Reliability - Meeting Planning Criteria

Fireco to Copol 69 kV line: Upgrade switches and line trap

EGSL Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 5/21/12 N/A Yes N/A

Page 9 of 13

Page 10: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

11-EGL-013-1-CP Transmission Reliability - Meeting Planning Criteria

Fireco to Copol 69 kV line: Upgrade line conductor EGSL Winter 2012 Summer 2013 Entergy before ICT Approved Complete In-service 12/31/12 12/17/12 N/A Yes N/A

11-EGL-014-CP Transmission Reliability - Meeting Planning Criteria

Addis 69 kV Substation: Upgrade 69 kV switches and line trap

EGSL Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 5/21/12 N/A Yes N/A

11-EGL-015-1-CP Transmission Service Acadia Generation - Reconfigure Richard 138 kV substation (Upgrade ckts 3 and 4 and Richard relaying work)

EGSL Summer 2013 N/A Supplemental

None Approved Complete In-service 6/15/12 5/15/12 N/A Yes RICXF1_XF2, BONCEC_RICCO, RICCOL_FANCJ, RICCOL_NCRIC,

RICCOL_SCOTT11-EGL-015-3-CP Transmission Service Acadia Generation - Upgrade Moril to Hopkins 138 kV

lineEGSL Summer 2013 N/A

SupplementalNone Approved Complete In-service 11/15/12 10/30/12 N/A Yes N/A

11-EGL-015-4-CP Transmission Service Acadia Generation - Upgrade 69 kV breaker at Scott 18220

EGSL Summer 2013 N/A Supplemental

None Approved Complete In-Service 10/28/12 10/11/12 N/A NA N/A

12-EGL-003-CP Transmission Reliability - Meeting Planning Criteria

Champagne to Plaisance 138 kV line - Modify/Replace CTs at Champagne

EGSL Summer 2013 Summer 2013 None Approved Complete In-service 6/1/13 12/26/12 N/A Yes PLACHM_COCVP

12-EGL-008-CP Transmission Reliability - Meeting Planning Criteria

Copol to Bourbeaux: Upgrade 69 kV line EGSL Winter 2014 Summer 2017 Entergy before ICT Approved Complete In-Service 4/3/13 4/18/13 Complete Yes N/A

12-EGL-014-CP Transmission Reliability - Meeting Planning Criteria

Lake Charles Bulk Substation: Replace four 69 kV, 600 A switches on transformers and bus section breaker with 1200 A switches

EGSL Fall 2012 Summer 2013 Entergy before ICT Approved Complete In-service 12/1/12 1/28/13 N/A YesN/A

10CP-ELL-001 Transmission Reliability - Meeting Planning Criteria

Snakefarm to Kenner 115 kV line: Upgrade to 359 MVA ELL Spring 2010 Spring 2010 None Approved Complete In-service 3/25/10 Complete Yes

10CP-ELL-002 Transmission Reliability - Meeting Planning Criteria

Bogalusa to Adams Creek 230 kV No. 2 - Upgrade terminal equipment at Bogalusa

ELL Winter 2009 Winter 2009 None Approved Complete In-service 1/18/10 Complete Yes

10CP-ELL-003 Transmission Reliability - Meeting Planning Criteria

Delhi 115 kV Substation - Add 30.5 MVAR Capacitor Bank

ELL Winter 2009 Winter 2009 None Approved Complete In-service 10/21/09 Complete Yes

10CP-ELL-004 Economic Delhi 115 kV Substation - Add 10 Ohm series reactor ELL Spring 2010 Spring 2010 None Approved Complete In-service 5/28/10 5/20/10 Complete Yes

10CP-ELL-005-1 Transmission Reliability - Meeting Planning Criteria

Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Construct a new 345-115 kV substation consisting of a 500 MVA auto. Cut station into EL Dorado to Longwood 345 kV line.

ELL Summer 2011 Summer 2013 Entergy before ICT Approved Complete In-Service 6/1/11 6/15/11 Complete Yes

10CP-ELL-005-2 Transmission Reliability - Meeting Planning Criteria

Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Add 32.4 MVAR capacitor bank at Lucky 115 kV substation

ELL Summer 2011 Summer 2011 None Approved Complete In-service 3/1/09 Complete Yes

10CP-ELL-005-3 Transmission Reliability - Meeting Planning Criteria

Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Add 32.4 MVAR capacitor bank at Vienna 115 kV substation

ELL Summer 2011 Summer 2011 None Approved Complete In-service 10/1/09 Complete Yes

10-ELL-006-CP Transmission Reliability - Meeting Planning Criteria

Bayou LaButte: Construct new 500-230 kV Substation Install 800 MVA, 500-230 kV autotransformer Cut in Webre to Willow Glen 500 kV line Construct new 230 kV line from Bayou LaBoutte to Iberville 230 kV substation

ELL Winter 2011 Winter 2012 Entergy before ICT Approved Complete In-Service 12/15/11 11/22/11 Complete Yes WEBWG_CJFAN

10-ELL-007-CP Transmission Reliability - Meeting Planning Criteria

Southeast LA Coastal Improvement Plan: Phase 2 Build Peters Road-Oakville 230kV Line and Substation

ELL Summer 2012 Winter 2011 ROW acquisition, construction timing.

Approved Complete In-service 9/20/12 9/6/12 Complete Yes N/A

10-ELL-010-1-CP Transmission Service Ouachita Transmission Service Split Sterlington 115 kV bus and replace 500-115 auto #2 with 750 MVA

ELL Summer 2012 N/A Supplemental

None Approved Complete In-Service. Auto placed in-service 2/14/12. Bus split completed 3/12/12.

3/9/12 3/12/12 Complete Yes N/A

10-ELL-010-2-CP Transmission Service Ouachita Transmission Service Upgrade Walnut Grove to Swartz 115 kV line

ELL Spring 2013 N/A Supplemental

None Approved Complete In-service 5/18/12 4/17/12 Complete Yes N/A

10CP-ELL-010-3 Transmission Service Ouachita Transmission Service Upgrade Frostkraft to Rilla 115 kV line

ELL Summer 2012 N/A Supplemental

None Approved Complete In-service 6/4/10 6/14/10 Complete Yes

10-ELL-010-4-CP Transmission Service Ouachita Transmission Service Upgrade Sterlington to Log Cabin 115 kV line

ELL Summer 2012 N/A Supplemental

None Approved Complete In-Service 6/1/12 12/20/11 Complete Yes N/A

10CP-ELL-010-5 Transmission Reliability - Meeting Planning Criteria

Ouachita Transmission Service Loop Sterlington to North Crossett into North Bastrop

ELL Summer 2012 Summer 2012 None Approved Complete In-service 6/1/11 6/15/11 Complete Yes

10CP-ELL-010-6 Transmission Service Ouachita Transmission Service Add 43 MVAR, 115 kV capacitor bank at Riser

ELL Summer 2012 N/A Supplemental

None Approved Complete In-service 11/1/10 11/23/10 Complete Yes

10CP-ELL-011 Transmission Reliability - Meeting Planning Criteria

Barataria to Ninemile 115 kV line: Replace line Trap ELL Winter 2010 Winter 2010 None Approved Complete In-Service 3/31/11 4/11/11 Complete Yes

10CP-ELL-012 Transmission Reliability - Meeting Planning Criteria

Waterford to Ninemile 230 kV line: Replace line trap, switches, and jumpers at Ninemile

ELL Summer 2011 Summer 2011 None Approved Complete In-Service 5/31/11 5/31/11 Complete Yes WATNM_GYPSN

10CP-ELL-013 Transmission Reliability - Meeting Planning Criteria

Raceland to Couteau 115 kV line: Replace switch, jumpers and line trap

ELL Winter 2010 TBD None Approved Complete In-service Winter 2010 10/25/10 Complete Yes

11-ELL-003-1-CP Transmission Reliability - Meeting Planning Criteria

NE Louisiana Improvement Project - Phase 1 Swartz to Oak Ridge - Construct new 115 kV Line (1272 ACSS) Operate Sterlington to Oak Ridge normally open

ELL Summer 2013 Summer 2013 None Approved Complete In-Service 5/24/13 3/22/13 N/A Yes STOAK_PVBW

11CP-ELL-006 Transmission Reliability - Meeting Planning Criteria

Hooker to Waterford 230 kV line - Upgrade station equipment

ELL Spring 2011 Spring 2011 None Approved Complete In-Service Spring 2011 5/17/11 Complete Yes HOWATR_UCWAT

11CP-ELL-007 Transmission Reliability - Meeting Planning Criteria

Waterford to Union Carbide 230 kV line - Upgrade station equipment

ELL Spring 2011 Spring 2011 None Approved Complete In-Service Spring 2011 5/26/11 Complete Yes UCWAT_HOWATR

Page 10 of 13

Page 11: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

11CP-ELL-008 Transmission Reliability - Meeting Planning Criteria

Union Carbide to Hooker 230 kV line - Upgrade station equipment

ELL Spring 2011 Spring 2011 None Approved Complete In-Service Spring 2011 4/12/11 Complete Yes

12-ELL-001-CP Transmission Reliability - Meeting Planning Criteria

Gypsy to Luling: Upgrade line bay bus and jumpers at Luling

ELL Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 12/22/11 Complete Yes LULGYP_GYPXF

13-ELL-001-CP Transmission Reliability - Meeting Planning Criteria

Golden Meadow to Barataria: Upgrade switch ELL Summer 2013 Summer 2013 None Approved Complete In-Service 4/30/13 4/25/13 Complete Yes N/A

10CP-EMI-001 Transmission Reliability - Meeting Planning Criteria

Liberty-Gloster: Upgrade 115 kV Line For Natchez De-listing

EMI Summer 2009 Summer 2009 None Approved Complete In-service 4/25/09 Complete Yes

10CP-EMI-002 Transmission Reliability - Meeting Planning Criteria

Indianola-Greenwood 115 kV Line: Upgrade line to 161 MVA Upgrade Terminal Equipment at Morehead, Itta Bena, and Greenwood

EMI Summer 2010 2009 First identified by ICT in 2009 Base Plan. Construction of this project could not be completed in short time frame.

Approved Complete In-service 5/26/10 6/10/10 Complete Yes

10-EMI-003-CP Transmission Reliability - Meeting Planning Criteria

Magee 115 kV Substation: Replace Switches EMI Winter 2011 Winter 2011 None Approved Complete In-Service 12/15/11 11/30/11 Complete Yes

10CP-EMI-004-1 Transmission Service TVA Affected System Upgrades Morton 115 kV Substation: Upgrade 600 A Switches to 1200A

EMI Spring 2010 N/A Supplemental

None Approved Complete In-service 11/6/09 Complete Yes

10CP-EMI-004-2 Transmission Service TVA Affected System Upgrades South Jackson - Florence 115 kV Line: Upgrade to at least 240 MVA

EMI Spring 2010 N/A Supplemental

None Approved Complete In-service 4/23/10 Complete Yes

10CP-EMI-005 Transmission Service Grand Gulf Uprate Project Baxter Wilson - Ray Braswell 500 kV Line: Upgrade Breakers and Switches to 3000 A

EMI Summer 2010 N/A Supplemental

None Approved Complete In-service 4/9/10 Complete Yes

10CP-EMI-006-1 Transmission Reliability - Meeting Planning Criteria

Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 1 Projects Winona 115 kV Substation: Install 21.6 MVAR Capacitor Bank

EMI Winter 2009 Winter 2009 None Approved Complete In-service 12/15/09 11/30/09 Complete Yes

10CP-EMI-006-2 Transmission Reliability - Meeting Planning Criteria

Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 1 Projects Greenwood 115 kV Substation: Upgrade 21.6 MVAR Capacitor Bank to 32.4 MVAR

EMI Winter 2009 Winter 2009 None Approved Complete In-service 12/15/09 10/28/09 Complete Yes

10CP-EMI-006-3 Transmission Reliability - Meeting Planning Criteria

Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 1 Projects Schlater 115 kV substation: Install 21.6 MVAR Capacitor Bank

EMI Winter 2009 Winter 2009 None Approved Complete In-service 12/15/09 10/21/09 Complete Yes

10-EMI-007-01-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Rolling Fork

EMI Spring 2011 N/A Supplemental

None Approved Complete In-service 2/17/12 1/9/12 Complete Yes N/A

10-EMI-007-02-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Yazoo City Municipal

EMI Spring 2011 N/A Supplemental

None Approved Complete In-service 2/1/12 1/26/12 Complete Yes N/A

10-EMI-007-03-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Carthage

EMI Spring 2011 N/A Supplemental

None Approved Complete In-Service 1/11/12 12/8/11 Complete Yes

10-EMI-007-04-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Tylertown

EMI Spring 2011 N/A Supplemental

None Approved Complete In-Service 10/24/11 12/8/11 Complete Yes

10CP-EMI-007-05 Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Senatobia

EMI Spring 2011 N/A Supplemental

None Approved Complete In-Service 6/1/11 6/6/11 Complete Yes

10CP-EMI-007-06 Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Plum Point

EMI Spring 2011 N/A Supplemental

None Approved Complete In-Service 6/1/11 6/6/11 Complete Yes

10-EMI-007-07-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Upgrade 21.6 MVAR capacitor bank at McComb to 32.4 MVAR.

EMI Spring 2011 N/A Supplemental

None Approved Complete In-service 12/19/11 1/30/12 Complete Yes N/A

10CP-EMI-007-08 Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Hernando into (2) 21 MVAR cap banks.\

EMI Spring 2011 N/A Supplemental

None Approved Complete In-Service 6/1/11 6/6/11 Complete Yes

10-EMI-007-09-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Hollandale into (2) 21 MVAR cap banks.

EMI Spring 2011 N/A Supplemental

None Approved Complete In-Service 10/28/11 11/30/11 Complete Yes

10-EMI-007-10-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Port Gibson into (2) 21 MVAR cap banks.

EMI Spring 2011 N/A Supplemental

None Approved Complete In-service 2/17/12 1/24/12 Complete Yes N/A

10-EMI-007-11-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Fayette into (2) 21 MVAR cap banks.

EMI Spring 2011 N/A Supplemental

None Approved Complete In-Service 2/17/12 12/16/11 Complete Yes

10-EMI-007-12-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install 115 kV, 32.4 MVAR capacitor bank at Magee.

EMI Spring 2011 N/A Supplemental

None Approved Complete In-Service 3/1/12 3/2/12 Complete Yes N/A

10CP-EMI-008 Transmission Reliability - Meeting Planning Criteria

Florence - Florence SS - Star 115 kV Line: Upgrade to at least 240 MVA

EMI Spring 2011 Spring 2011 None Approved Complete In-Service 1/31/11 4/7/11 Complete Yes

Page 11 of 13

Page 12: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

10CP-EMI-009 Transmission Reliability - Meeting Planning Criteria

Waterways - Vicksburg East 115 kV Line: Upgrade to at least 240 MVA

EMI Summer 2011 Summer 2011 None Approved Complete In-Service 6/1/11 4/27/11 Complete Yes WTVICE_BAXXFWTVICE_GGFRAWAWVIC_RABBA

10CP-EMI-011-1 Transmission Reliability - Meeting Planning Criteria

McAdams Area Upgrades McAdams Substation: Add 2nd 560 MVA 500 kV / 230 kV Autotransformer (Hartburg Spare single phase units)

EMI Summer 2011 Summer 2013 Entergy before ICT Approved Complete In-Service 6/1/11 6/2/11 Complete Yes MCAD_LAKOV_D

10CP-EMI-011-2 Transmission Reliability - Meeting Planning Criteria

McAdams Area Upgrades McAdams - Pickens 230 kV line: Upgrade to Double-Bundled 954 ACSR (880 MVA)

EMI Summer 2011 Summer 2013 Entergy before ICT Approved Complete In-Service 6/1/11 5/18/11 Complete Yes MCAPIC_MCALA

10-EMI-012-1-CP Transmission Reliability - Meeting Planning Criteria

Ridgeland-Madison Reliability Improvement Rebuild Lakeover - Ridgeland Line

EMI Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 5/30/12 N/A Yes N/A

10-EMI-012-2-CP Transmission Reliability - Meeting Planning Criteria

Ridgeland-Madison Reliability Improvement Build Lakeover - Sunnybrook - Northpark 115 kV Line

EMI Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 5/30/12 N/A Yes N/A

10-EMI-013-CP Transmission Service Ouachita Transmission Service Move Sterlington 600 MVA auto to Baxter Wilson 500 (Second 500-115 kV auto)

EMI Summer 2012 N/A Supplemental

None Approved Complete In-Service 6/15/12 6/26/12 N/A Yes N/A

10-EMI-014-1-CP Transmission Reliability - Meeting Planning Criteria

Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 2 Projects Tillatoba to South Grenada 230 kV Line: Construct New 520 MVA Line

EMI Summer 2012 Summer 2012 None Approved Complete In-service 6/15/12 6/11/12 N/A Yes N/A

10-EMI-014-2-CP Transmission Reliability - Meeting Planning Criteria

Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 2 Projects South Grenada 115 kV Substation: Install 230 kV Bus and a 400 MVA 230-115 kV Autotransformer

EMI Summer 2012 Summer 2012 None Approved Complete In-service 6/15/12 6/11/12 N/A Yes N/A

10-EMI-017-01-CP Transmission Reliability - Meeting Planning Criteria

Ray Braswell to Spring Ridge Road 115kV line upgrade EMI Summer 2013 Summer 2013 Project identified as part of 10-EMI-017-CP requirements due to swapping of line bays

Approved Complete In-Service 6/1/13 5/16/13 Complete Yes

10-EMI-018-CP Transmission Reliability - Meeting Planning Criteria

Getwell to Church Road 230 kV construct new 230 kV Transmission Line

EMI Summer 2013 Summer 2013 None Approved Complete In-Service 6/1/13 5/10/13 Complete Yes N/A

10CP-EMI-020 Transmission Reliability - Meeting Planning Criteria

Ray Braswell to Clinton 115 kV line: Upgrade switch at Clinton and riser at Ray Braswell

EMI Summer 2011 Summer 2011 None Approved Complete In-Service Spring 2011 2/10/11 Complete Yes

10CP-EMI-021 Transmission Reliability - Meeting Planning Criteria

Clinton to Jackson NW 115 kV line: Upgrade switch at Clinton

EMI Summer 2011 Summer 2011 None Approved Complete In-Service Spring 2011 2/10/11 Complete Yes

11-EMI-001-CP Transmission Reliability - Meeting Planning Criteria

Rankin Industrial - Airport: Reconductor to bring complete line up to 1272 ACSR

EMI Winter 2011 Summer 2012 Entergy before ICT Approved Complete In-service 12/22/11 1/10/12 Complete Yes N/A

11CP-EMI-003 Transmission Reliability - Meeting Planning Criteria

Upgrade Terminal Equipment on Vicksburg - Waterway 115kV

EMI Summer 2011 Summer 2011 None Approved Complete In-service Summer 2011 1/24/11 Complete Yes

11-EMI-004-CP Transmission Reliability - Meeting Planning Criteria

Ray Braswell to West Jackson 115 kV line: Reconductor line

EMI Summer 2012 Summer 2013 Entergy before ICT Approved Complete In-Service 11/21/12. Final relay settings completed and installed March 2013. Line now up to full conductor rating.

Winter 2012 11/21/12 N/A Yes N/A

11CP-EMI-005 Transmission Reliability - Meeting Planning Criteria

Miami to Monument Street: Upgrade line trap at Monument Street

EMI Summer 2012 N/A Project recently added Approved Complete In-Service 6/1/11 5/26/11 Complete Yes

12-EMI-003-CP Transmission Reliability - Meeting Planning Criteria

Northeast Jackson to Klean Steel - Upgrade CT and Jumpers/Risers at NE Jackson

EMI Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 12/7/11 Complete Yes N/A

13-EMI-004-CP Transmission Service SMEPA Plum Point Transmission Service: Horn Lake to Greenbrook 115 kV line: Upgrade station equipment at Horn Lake

EMI Summer 2013 N/A Supplemental

None Approved Complete In-Service Summer 2013 4/19/13 Complete Yes N/A

13-EMI-006-CP Enhanced Transmission Reliability

Bolton 115 kV Substation: Add 115 kV breakers EMI Summer 2013 N/A Supplemental

None Approved Complete In-Service Summer 2014 3/28/13 NA N/A (No model effect)

RBBOLT_BWXFM

10CP-ENO-001 Transmission Reliability - Meeting Planning Criteria

Paterson 115kV: Restore 4 breakers ENOI Summer 2009 Summer 2009 None Approved Complete In-service 1/29/09 Complete Yes

10CP-ETI-001 Transmission Reliability - Meeting Planning Criteria

Newton Bulk: Replace/Re-tap CT to increase rating on Holly Springs line

ETI Summer 2009 Summer 2009 None Approved Complete In-service Winter 2009 Complete Yes

10CP-ETI-002 Transmission Reliability - Meeting Planning Criteria

Beaumont 69 kV Improvement Plan: Option 2 ETI Summer 2009 Summer 2009 None Approved Complete In-service 6/19/09 Complete Yes

10CP-ETI-003 Generation Interconnection Sheco Jacinto - Generator Interconnection ETI Summer 2009 N/A Supplemental

None Approved Complete In-service 7/3/09 Complete Yes

10CP-ETI-004 Transmission Reliability - Meeting Planning Criteria

Gulfway 230 kV Substation Construct new Gulfway 230 kV Substation Cut new Substation into existing VFW to Kolbs 230 kV Line Construct new Sabine to Gulfway 230 kV line

ETI Fall 2009 Fall 2009 None Approved Complete In-service 10/13/09 Complete Yes

10CP-ETI-005 Transmission Reliability - Meeting Planning Criteria

Fawil: Upgrade 138/69 kV Auto ETI Winter 2009 Winter 2009 None Approved Complete In-service 1/23/10 Complete Yes

10CP-ETI-006 Transmission Reliability - Meeting Planning Criteria

Porter - Tamina: Replace Breaker/Switches ETI Summer 2009 Summer 2009 None Approved Complete In-service 10/22/09 Complete Yes

10CP-ETI-007 Enhanced Transmission Reliability

Warren Substation - Add two breakers ETI Winter 2009 N/A Supplemental

None Approved Complete In-service 1/2/08 Complete N/A (No model effect)

Page 12 of 13

Page 13: Monthly Construction Plan Project Status · PDF fileMonthly Construction Plan Project Status ... feasibility Approved Scoping Field visit with ... Construction Plan Project Status

Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan

Construction Plan ID Project Driver Project Name Operating

CompanyProposed ISD

(Planning)ICT Identified Need By Date Need by date difference

Project Funding Status

Project Status Project Status CommentsCurrent

Projected ISD

Actual ISD Mitigation Plan if requiredIncluded in AFC

Model? (Yes/No)

Flowgate(s) impacted

Monthly Construction Plan Project Status Report

10CP-ETI-008-1 Transmission Reliability - Meeting Planning Criteria

Temco and Shepherd 138 kV Substations - Upgrade CTs at Temco

ETI Summer 2010 Summer 2010 None Approved Complete In-service 9/30/10 10/26/10 Complete Yes

10CP-ETI-008-2 Transmission Reliability - Meeting Planning Criteria

Temco and Shepherd 138 kV Substations - Upgrade CTs at Shepherd

ETI Summer 2010 Summer 2010 None Approved Complete In-service 9/30/10 10/26/10 Complete Yes

10CP-ETI-009 Transmission Reliability - Meeting Planning Criteria

Western Region Reliability Improvement Plan Phase 3 Interim (Part 1) Relocate Sheco's Caney Creek 138 kV Substation

ETI Summer 2010 Summer 2010 None Approved Complete In-service 10/10/10 1/21/10 Complete Yes

10CP-ETI-010 Transmission Reliability - Meeting Planning Criteria

College Station 138kV Switching Station Construct new 3 terminal 138 kV Switching Station Close normally open switch at Speedway

ETI Spring 2011 2009 Requires installation of circuit breakers resulting in additional design and material lead time

Approved Complete In-service 12/31/10 11/29/10 Complete Yes

10CP-ETI-011 Transmission Reliability - Meeting Planning Criteria

Western Region Reliability Improvement Plan Phase 3 Interim (Part 3). Upgrade South Beaumont to Fontenot Corner 138 kV line

ETI Winter 2010 Winter 2010 None Approved Complete In-Service 4/21/11 5/24/11 Complete Yes

10CP-ETI-012 Transmission Reliability - Meeting Planning Criteria

Western Region Reliability Improvement Plan Phase 3 Interim (Part 2) Jacinto-Lewis Creek: Convert to 230 kV operation. Add 450 MVA 230-138 Auto at Lewis Creek

ETI Summer 2011 Summer 2011 None Approved Complete In-Service 2/25/11 3/2/11 Complete Yes

10-ETI-013-CP Transmission Service Grand Gulf Uprate Project Upgrade Hartburg to Inland Orange to McLewis 230 kV line

ETI Winter 2011 N/A Supplemental

None Approved Complete In-Service 12/16/11 12/28/11 Complete Yes HBIN_HBCYP

10-ETI-017-CP Transmission Reliability - Meeting Planning Criteria

Jasper to Rayburn 138 kV line: Upgrade ETI Summer 2013 Summer 2013 None Approved Complete In-Service 5/31/13 5/14/13 Complete Yes N/A

10CP-ETI-020 Transmission Reliability - Meeting Planning Criteria

Inland Orange to McLewis 230 kV line: Upgrade risers at Inland Orange and switch 22628 at McLewis

ETI Winter 2010 Winter 2010 None Approved Complete In-Service 4/23/11 5/11/11 Complete Yes

10CP-ETI-021 Transmission Reliability - Meeting Planning Criteria

Hartburg to Inland Orange 230 kV line: Upgrade risers at Inland Orange

ETI Winter 2010 Winter 2010 None Approved Complete In-service 12/16/11 2/18/11 Complete Yes

10-ETI-022-CP Transmission Reliability - Meeting Planning Criteria

McLewis to Helbig 230 kV line: Upgrade bus and switches 22627 & 22628 at McLewis

ETI Winter 2011 Summer 2012 Entergy before ICT Approved Complete In-service 12/16/11 1/4/12 Complete Yes N/A

10CP-ETI-023 Transmission Reliability - Meeting Planning Criteria

Sabine to Linde 138 kV line: Upgrade bus and risers at Sabine and Linde

ETI Winter 2010 Winter 2010 None Approved Complete In-Service Winter 2010 2/1/11 Complete Yes

10CP-ETI-024 Transmission Reliability - Meeting Planning Criteria

Sabine to Mid County 230 kV line: Upgrade bus and jumpers at Mid County

ETI Winter 2010 Winter 2010 None Approved Complete In-Service Winter 2010 11/22/10 Complete Yes

10CP-ETI-025 Transmission Reliability - Meeting Planning Criteria

Chem Rd to Dupont Sabine 3 138 kV line: Upgrade metering CT at Dupont Sabine

ETI Summer 2011 Summer 2011 None Approved Complete In-Service Summer 2011 3/7/11 Complete Yes

10CP-ETI-026 Transmission Reliability - Meeting Planning Criteria

Orange to Bunch Gully 138 kV line: Upgrade bus and risers at Orange

ETI Winter 2010 Winter 2010 None Approved Complete In-Service 5/20/11 5/25/11 Complete Yes

10-ETI-027-CP Transmission Reliability - Meeting Planning Criteria

Toledo Bend to Leesville 138 kV line: Upgrade CT at Toledo Bend

ETI Summer 2011 Summer 2011 None Approved Complete In-Service 12/15/11 12/1/11 Complete Yes

10-ETI-028-CP Transmission Reliability - Meeting Planning Criteria

Toledo Bend to Van Ply 138 kV line: Upgrade CT at Toledo Bend

ETI Summer 2011 Summer 2011 None Approved Complete In-Service 12/15/11 12/14/11 Complete Yes TBDVPL_MOHBG TOLVP_RODCOL

10CP-ETI-029 Transmission Reliability - Meeting Planning Criteria

Cypress to Lumberton 138 kV line: Upgrade bus at Lumberton and Cypress

ETI Summer 2011 Summer 2011 None Approved Complete In-Service 3/1/11 3/21/11 Complete Yes

10CP-ETI-030 Transmission Reliability - Meeting Planning Criteria

Goslin to Conroe Bulk 138 kV line: Upgrade bus differential at Conroe.

ETI Summer 2011 Summer 2011 None Approved Complete In-Service 5/13/11 5/26/11 Complete Yes

11CP-ETI-001 Transmission Reliability - Meeting Planning Criteria

Hearne to Calvert - Uprate 69 kV line ETI Summer 2011 Summer 2011 None Approved Complete In-Service 6/24/11 6/28/11 Complete Yes

11CP-ETI-004 Transmission Reliability - Meeting Planning Criteria

Elizabeth to Gallier - Uprate 69 kV line 2.5 miles ETI Summer 2012 Winter 2010 Construction feasibility. Approved Complete In-Service TBD 9/14/11 Complete Yes

11-ETI-006-CP Transmission Reliability - Meeting Planning Criteria

Somerville 69 kV: Expand capacitor bank ETI Summer 2012 Summer 2012 None Approved Complete In-Service 5/3/12 5/15/12 N/A Yes N/A

11CP-ETI-007 Transmission Reliability - Meeting Planning Criteria

Navasota to Magnolia Anderson 138kV: Upgrade relay CT

ETI Summer 2011 Summer 2011 None Approved Complete In-service 7/14/11 7/18/11 Complete Yes

11-ETI-008-CP Transmission Reliability - Meeting Planning Criteria

Cedar Hill to Plantation 138 kV line: Upgrade line conductor and station equipment at Plantation

ETI Summer 2013 Summer 2013 None Approved Complete In-Service 4/12/13 2/21/13 N/A Yes N/A

11-ETI-008-01-CP Transmission Reliability - Meeting Planning Criteria

Plantation to Conroe 138 kV line: Upgrade station equipment at Plantation

ETI Summer 2013 Summer 2013 None Approved Complete In-Service 4/12/13 4/4/13 Complete Yes N/A

11-ETI-009-CP Transmission Reliability - Meeting Planning Criteria

Toledo Bend to Leach 138 kV line: Upgrade station equipment at Toledo Bend

ETI Winter 2013 Winter 2013 None Approved Complete In-Service 12/15/11 11/28/11 Complete Yes LCHTOL_GRICR

11-ETI-010-CP Transmission Reliability - Meeting Planning Criteria

Leach to Newton Bulk 138 kV line: Upgrade terminal equipment at Newton Bulk

ETI Winter 2013 Summer 2014 Entergy before ICT Approved Complete In-Service 3/18/13 3/18/13 Complete Yes N/A

11CP-ETI-011 Transmission Reliability - Meeting Planning Criteria

Port Neches to Linde: Upgrade station equipment at Port Neches

ETI Summer 2011 Summer 2011 None Approved Complete In-Service 5/5/11 5/2/11 Complete Yes

11-ETI-020-CP Transmission Reliability - Meeting Planning Criteria

Hickory Ridge-Eastgate 138kV: Upgrade terminal equipment at Eastgate

ETI Summer 2016 Summer 2016 None Approved Complete In-Service 5/1/13 4/5/13 Complete Yes NA

11-ETI-036-CP Transmission Reliability - Meeting Planning Criteria

Plantation to Conroe 138 kV line: Reconductor Line ETI Summer 2013 Summer 2013 None Approved Complete In-Service 4/12/13 4/4/13 Complete Yes NA

11-ETI-041-CP Transmission Reliability - Meeting Planning Criteria

Eastgate to Dayton Bulk 138kV: Upgrade terminal equipment at Eastgate (formerly reconductor).

ETI Summer 2013 Summer 2016 Entergy before ICT Approved Complete In-Service 5/1/13 4/19/13 Complete Yes NA

11-ETI-043-CP Transmission Reliability - Meeting Planning Criteria

Expand Cap Bank at Calvert 69kV ETI Summer 2013 Summer 2013 None Approved Complete In-Service 6/1/13 5/8/13 Complete Yes NA

12-ETI-003-CP Transmission Reliability - Meeting Planning Criteria

Bentwater Substation: Add 138 kV Capacitor Bank ETI Summer 2013 Summer 2013 None Approved Complete In-Service 2013 Summer 5/1/13 Complete Yes NA

Page 13 of 13