Upload
lehanh
View
219
Download
5
Embed Size (px)
Citation preview
Monthly Construction Plan Project Status ReportReport Date: 7/1/2013
Operating Company Major UpdatesEAI Two Projects completedEMI One Project completedELL No major changes to reportEGSL No major changes to reportETI No major changes to reportEGSL/ELL No major changes to report
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
11-EAI-003-CP Transmission Reliability - Meeting Planning Criteria
Fordyce: Relocate capacitor bank to 115 kV bus. Install switch on line side of capacitor bank.
EAI Summer 2014 Summer 2013 Construction feasibility Proposed & In Target
Scoping Project scoping underway Summer 2014 Note B N/A
11-EAI-004-1-CP Economic Sheridan South 500 kV FG Upgrade: Mabelvale 500 kV Substation replace 3 breakers, 13 switches, and 2 line traps
EAI Summer 2014 N/A Supplemental
None Approved Construction Outage availability remains the largest challenge.
6/1/14 N/A SHRMAB_KEO, MABSH_WBSH, SHEWHB_MABWR, WHBSHE_MABEL, WHBSHR_KEOWH, SHRELD_HSPET, SHDELD_MCETT, SHEHV_MAGNET
11-EAI-004-2-CP Economic Sheridan South 500 kV FG Upgrade: Sheridan 500 kV Substation replace 11 switches, and 6 line traps
EAI Summer 2014 N/A Supplemental
None Approved Construction Outage availability remains the largest challenge.
6/1/14 N/A SHRMAB_KEO, MABSH_WBSH, SHEWHB_MABWR, WHBSHE_MABEL, WHBSHR_KEOWH, SHRELD_HSPET, SHDELD_MCETT, SHEHV_MAGNET
11-EAI-004-3-CP Economic Sheridan South 500 kV FG Upgrade: White Bluff 500 kV Substation replace 5 switches
EAI Summer 2014 N/A Supplemental
None Approved Construction Outage availability remains as the largest challenge.
6/1/14 N/A WHBSHE_MABEL, WHBSHR_KEOWH
11-EAI-004-4-CP Economic Sheridan South 500 kV FG Upgrade: Eldorado 500 kV Substation replace 1 switch and 2 line traps
EAI Summer 2014 N/A Supplemental
None Approved Construction Outage availability remains as the largest challenge.
6/1/14 N/A SHRELD_HSPET, SHDELD_MCETT, SHEHV_MAGNET
11-EAI-007-CP Transmission Reliability - Meeting Planning Criteria
Hot Springs Hamilton (Albright) - Carpenter Dam: Construct new 115 kV Line and convert Mountain Pine South to ring bus
EAI Summer 2015 Summer 2013 ROW acquisition, construction feasibility.
Approved Scoping CECPN Filing completed. 12/31/15 Note B N/A
11-EAI-008-CP Transmission Reliability - Meeting Planning Criteria
Pine Bluff Voltage Support Project: Phase 2 Woodward: Construct 230 kV ring bus and construct new White Bluff to Woodward 230 kV line
EAI Summer 2015 Summer 2013 Construction feasibility Proposed & In Target
Scoping New line scope under review. Commission Approvals and ROW acquisition 230 kV line may result in ISD slipping to
June 2016.
Summer 2016 Note B N/A
11-EAI-012-CP Transmission Reliability - Meeting Planning Criteria
Stuttgart Ricuskey 115 kV Substation: Expand Capacitor Bank to 39 MVAR
EAI Summer 2013 Summer 2013 None Approved Complete In-Service Summer 2013 6/3/13 N/A Yes N/A
11-EAI-015-CP Transmission Reliability - Meeting Planning Criteria
Jim Hill Area UpgradesDoniphan (AECI New Sub) - Datto 161 construct new line
EAI Summer 2017 Summer 2017 None Proposed & In Target
Scoping Scope under review Summer 2017 N/A N/A
11-EAI-016-CP Transmission Reliability - Meeting Planning Criteria
ISES- Reconfiguration of the 161kV Bus EAI Summer 2018 Summer 2018 None Proposed & In Target
Scoping Summer 2018 NA
11-EAI-017-CP Transmission Reliability - Meeting Planning Criteria
White Bluff: Reconfigure 500 kV Station and construct 230 kV ring bus
EAI Summer 2015 Summer 2013 Construction feasibility Proposed & In Target
Scoping Scope under review. Magnitude of project expected to result in
June 2016 ISD
6/1/16 Note B N/A
11-EAI-024-CP Transmission Reliability - Meeting Planning Criteria
Holland Bottoms to Jacksonville North: Reconductor 115 kV Line
EAI Summer 2018 Summer 2018 None Proposed & In Target
Scoping Summer 2018 NA
11-EAI-025-CP Transmission Reliability - Meeting Planning Criteria
Norfork-Calico Rock : Upgrade 161 kV Line EAI Summer 2016 Summer 2016 None Proposed & In Target
Scoping Scope under review TBD N/A N/A
11-EAI-026-CP Transmission Reliability - Meeting Planning Criteria
NLR Westgate - NLR Levy: Reconductor 115 kV Line EAI Summer 2013 Summer 2013 None Approved Construction Projected ISD changed to 12/31/2013 from 6/1/13 based on outage scheduling. Spring
work completed and approximately 50% of line work
completed and In-Service.
12/31/13 Note B
NLRLVWGLRKS
11-EAI-027-CP Transmission Reliability - Meeting Planning Criteria
AECC L&D 2 to Gillett: Construct new 115 kV Line EAI Summer 2016 Summer 2016 None Proposed & In Target
Scoping Routing of new line in progress. River Crossing presenting
challenges.
6/1/16 Note BN/A
12-EAI-001-CP Transmission Reliability - Meeting Planning Criteria
Calico Rock-Melbourne - Upgrade 161kV Line EAI Winter 2014 Winter 2014 None Approved Design Material requisitions have been submitted by design.
Winter 2014 N/A SAGMEL_ISDEL, MELBCR_ANOFS
12-EAI-002-CP Transmission Reliability - Meeting Planning Criteria
Woodward - Pine Bluff West - Pine Bluff McCamant: Reconductor 115 kV
EAI Summer 2014 Summer 2017 Entergy before ICT Approved Design Attempting to get material in to meet outage scheduling
requirements.
6/1/14 N/AN/A
12-EAI-003-CP Transmission Reliability - Meeting Planning Criteria
Woodward-115 kV Bus Reconfiguration EAI Summer 2016 Summer 2017 Entergy before ICT Proposed & In Target
Scoping Scope under review 6/1/16 N/A N/A
12-EAI-005-CP Transmission Reliability - Meeting Planning Criteria
Camden McGuire - Camden North 115kV Line: Construct New Line
EAI Summer 2014 Summer 2013 ROW acquisition, construction feasibility
Approved Construction River Crossing permit received. APSC CCN approval needed to
continue to meet schedule. ROW procurement activities ongoing. Vegetation clearing scheduled for June/July 2013.
6/1/14 Note B
N/A
12-EAI-006-CP Transmission Reliability - Meeting Planning Criteria
Russellville East-Russellville North: Reconductor 161kV line
EAI Summer 2018 Summer 2018 None Proposed & In Target
Scoping Summer 2018 NA RUSNRE_ANOFS
12-EAI-008-01-CP Transmission Reliability - Meeting Planning Criteria
LV Bagby to Macon Lake: Construct new 230 kV line and operate at 115 kV
EAI Summer 2014 Summer 2013 Construction feasibility Approved Scoping Field visit with APSC completed. CECPN hearing
scheduled for 6/27/13.
6/1/14 Note BN/A
12-EAI-008-02-CP Transmission Reliability - Meeting Planning Criteria
Macon Lake to Reed: Construct new 230 kV line and operate at 115 kV
EAI Summer 2017 Summer 2017 None Approved Scoping Field visit with APSC completed. CECPN hearing scheduled for 6/27/13. Outage scheduling
conflicts with other projects may impact projected ISD.
6/1/17 N/A
N/A
12-EAI-016-CP Transmission Reliability - Meeting Planning Criteria
HS EHV-HS Industrial: Upgrade Terminal Equipment EAI Summer 2015 Summer 2015 None Proposed & In Target
Scoping Under Review Summer 2015 N/A HSEHSI_ARKCP
12-EAI-017-CP Transmission Reliability - Meeting Planning Criteria
HS Industrial-HS Union Carbide: Upgrade Terminal Equipment
EAI Summer 2015 Summer 2015 None Proposed & In Target
Scoping Under Review Summer 2015 N/A N/A
Monthly Construction Plan Project Status Report
Page 2 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
12-EAI-018-CP Transmission Reliability - Meeting Planning Criteria
HS Union Carbide-HS East: Upgrade Terminal Equipment
EAI Summer 2015 Summer 2015 None Proposed & In Target
Scoping Under Review Summer 2015 N/A N/A
12-EAI-019-CP Transmission Reliability - Meeting Planning Criteria
Mabelvale: Replace 500-115 Autos EAI Summer 2016 N/A Supplemental
None Proposed & In Target
Scoping PM&C scoping to begin second half 2013
Summer 2016 N/A MABXF1_MAXF2
12-EAI-021-CP Enhanced Transmission Reliability
Mayflower - Reconfigure 500 kV bus (eliminate breaker failure impact on autos)
EAI Winter 2017 Winter 2017 None Proposed & In Target
Scoping PM&C scoping to begin second half 2013
Winter 2017 N/A MAYXF1_XF2
12-EAI-023-CP Transmission Reliability - Meeting Planning Criteria
Woodward to Pine Bluff Watson Chapel: Rebuild line to 230 kV construction and operate at 115 kV.
EAI Summer 2014 Summer 2013 Construction feasibility Approved Design CECPN application submitted to APSC. Outage scheduling
conflicts with other projects may impact projected ISD.
6/1/14 Note B N/A
12-EAI-027-CP Transmission Reliability - Meeting Planning Criteria
Malvern South: Add 10.2 MVAR Capacitor Bank EAI Summer 2017 Summer 2017 None Proposed & In Target
Scoping Summer 2017 NA N/A
12-EAI-029-CP Transmission Reliability - Meeting Planning Criteria
Upgrade Cheetah to Hot Springs Village 115 kV line EAI Summer 2018 Summer 2018 None Proposed & In Target
Scoping Summer 2018 NA N/A
12-EAI-032-01-CP Transmission Reliability - Meeting Planning Criteria
Construct Gum Springs Switching Station EAI Summer 2018 Summer 2019 Entergy before ICT Proposed & In Target
Scoping PM&C scoping to begin second half 2013
Summer 2018 NA N/A
12-EAI-032-02-CP Transmission Reliability - Meeting Planning Criteria
Gum Springs to Amity construct new line. Add breakers at Amity
EAI Summer 2018 Summer 2019 Entergy before ICT Proposed & In Target
Scoping PM&C scoping to begin second half 2013
Summer 2018 NA N/A
12-EAI-035-CP Transmission Reliability - Meeting Planning Criteria
Ward: Install 21.6 MVAR capacitor bank EAI Summer 2015 Summer 2015 None Proposed & In Target
Scoping PM&C scoping to begin first quarter 2014
Summer 2015 NA N/A
13-EAI-001-CP Transmission Reliability - Meeting Planning Criteria
Pine Bluff McCamant- Pine Bluff East: Reconductor line
EAI Summer 2016 Summer 2016 None Proposed & In Target
Scoping Scope under review Summer 2016 NA N/A
13-EAI-002-CP Transmission Reliability - Meeting Planning Criteria
Pine Bluff Watson Chapel - Pine Bluff South: Rebuild line to 230 kV construction and operate at 115 kV
EAI Summer 2017 Summer 2016 Construction feasibility Proposed & In Target
Scoping Scope under review Summer 2017 NA N/A
13-EAI-003-CP Transmission Reliability - Meeting Planning Criteria
Monticello East to Reed: Construct new 115 kV transmission line. Construct to 230 kV but operate at 115 kV.
EAI Summer 2015 Summer 2017 Entergy before ICT Proposed & In Target
Scoping Route study progressing. CECPN approvals required.
Summer 2015 NA N/A
13-EAI-008-CP Transmission Reliability - Meeting Planning Criteria
Hot Springs EHV Substation: Replace two 115 kV autotransformer breakers
EAI Summer 2013 Summer 2013 None Approved Complete In-Service 6/30/13 6/20/13 NA Yes N/A
13-EAI-009-CP Transmission Service Hot Spring Transmission Service: White Bluff to Pine Bluff Arsenal C - Upgrade terminal equipment at White Bluff
EAI Winter 2013 N/A Supplemental
None Approved Design/Scoping To be worked by T-Grid Winter 2013 NA N/A
14-EAI-002-CP Transmission Service Hot Springs Transmission Service:McCrory-Bailey: Upgrade line to 100C
EAI 2014 Winter N/A Supplemental
None Approved Design/Scoping Being worked in association with NERC Alert Project
2014 Winter N/A N/A
10-EGL-011-CP Transmission Reliability - Meeting Planning Criteria
Mossville - Cut-in line 616 (Nelson to Carlyss 138 kV) into Mossville 138 kV Substation
EGSL Summer 2013 Summer 2013 None Approved Design Material delivery dates will not facilitate current required outage schedule. New outage request
resulting in delay of ISD from 6/30/13 to 11/15 /13.
11/15/13 Generation re-dispatch N/A
11-EGL-002-CP Transmission Reliability - Meeting Planning Criteria
Harelson to Gloria - upgrade 69 kV line EGSL Summer 2018 Summer 2018 None Proposed & In Target
Scoping Summer 2018 NA N/A
11-EGL-016-01-CP Transmission Reliability - Meeting Planning Criteria
Mossville to Canal - Phase 1: Upgrade 69 kV Line EGSL Winter 2013 Winter 2012 Construction feasibility Proposed & In Target
Design/Scoping 12/31/13 NA N/A
11-EGL-016-02-CP Transmission Reliability - Meeting Planning Criteria
Mossville to Canal - Phase 2: Upgrade 69 kV Line EGSL Winter 2014 Winter 2015 Entergy before ICT Proposed & In Target
Design/Scoping Winter 2014 NA N/A
11-EGL-017-CP Transmission Reliability - Meeting Planning Criteria
Five Points to Line 281 Tap to Line 247 Tap- Upgrade 69 kV line
EGSL Winter 2018 Winter 2018 None Proposed & In Target
Planning Winter 2018 N/A N/A
12-EGL-004-CP Transmission Reliability - Meeting Planning Criteria
McManus to Brady Heights - Upgrade 69 kV line EGSL Winter 2017 Winter 2018 Entergy before ICT Proposed & In Target
Planning Winter 2017 N/A N/A
12-EGL-006-CP Transmission Reliability - Meeting Planning Criteria
Bronco - New 230 kV distribution substation (Formerly called Zachery)
EGSL Summer 2017 Summer 2018 Entergy before ICT Proposed & In Target
Planning Summer 2017 Note B N/A
12-EGL-015-CP Economic Willow Glen to Conway - Construct new 230 kV line EGSL Spring 2014 N/A Supplemental
None Approved Design/Construction The project will be split constructed in two phases. The East Phase will be constructed with a planned ISD of July 8,
2013 to energize the new Brittany Substation. ROW
acquisition complete. ROW clearing and construction is well underway. Line work estimated
to complete on July 1, 2013. The West Phase will be
constructed with a planned ISD of June 1, 2014. ROW
acquisition has started on the west phase.
6/1/14 N/A
11-EGL-010-CP Transmission Reliability - Meeting Planning Criteria
Sorrento Upgrade 138/115 kV Auto and upgrade Gonzales - Sorrento 138 kV Line
EGSL/ELL Summer 2014 Summer 2015 Entergy before ICT Approved Design Detailed design has started. Auto transformer has been
ordered.
6/1/14 N/A SREGON_WGWAT
Page 3 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
10-ELL-008-CP Transmission Reliability - Meeting Planning Criteria
Southeast LA Coastal Improvement Plan: Phase 3 Construct Oakville to Alliance 230kV Line Add 230 - 115 kV Autotransformer at Alliance Substation
ELL Summer 2013 Winter 2012 ROW acquisition, construction timing.
Approved Scoping Routing challenges continue to delay start of ROW acquisition. Projected ISD currently moved from 6/1/14 to 6/1/15 to reflect
latest projections. Meetings were held with PSC
Commissioner and DOTD in March. On 3/27/13 LADOTD
requested Entergy to complete design and file a Utility Permit
for soil borings. On May 9, 2013, team concurrence received to order soil borings. Permits will be required from LA DOTD,
COE and possibly Plaquemine Parish for the soil borings.
6/1/15 Note B N/A
10-ELL-009-CP Transmission Reliability - Meeting Planning Criteria
Iron Man to Tezcuco 230 kV line - Construct new line ELL Summer 2015 Summer 2013 Construction feasibility Approved Design/Construction Project Completion date moved to 2015 from 2018 based on expected change in reliability
need date. Iron Man substation placed in service (1/10/12) and included in models. Tezcuco
Substation expansion completed and placed into service 4/24/12.
Permitting complete. ROW acquisition in progress.
5/31/15 Generation re-dispatch N/A
11-ELL-001-CP Enhanced Transmission Reliability
Golden Meadow to Leeville 115 kV - Rebuild/relocate 115 kV transmission line
ELL Spring 2014 N/A Supplemental
None Approved Design Project baselined. On track for current projected ISD. ROW and permitting is resulting in
delay to late spring 2014
5/31/14 N/A N/A
11-ELL-002-CP Transmission Reliability - Meeting Planning Criteria
Mt. Olive: Add Shunt Reactor ELL Winter 2013 Winter 2013 None Approved Construction Site & Foundations complete. Issues with reactor shipment
from manufacturer, working to resolve schedule.
12/13/13 N/A N/A
11-ELL-003-2-CP Transmission Reliability - Meeting Planning Criteria
NE Louisiana Improvement Project - Phase 2 Oak Ridge to new Dunn Substation - Construct new 115 kV Line (1272 ACSS) Add 115 kV breakers at Dunn Add 115 kV, 32.4 MVAR capacitor bank at Dunn
ELL Summer 2014 Summer 2014 None Approved Design Dunn Site work 72%. ROW acquisition nearing completion.
ISD moved from 10/31/14 to 12/19/14 due to outage
scheduling requirements.
12/19/14 N/A N/A
11-ELL-004-CP Transmission Reliability - Meeting Planning Criteria
Northeast LA Improvement Project Phase 3 Upgrade Sterlington to Oakridge to Dunn 115 kV Line
ELL Summer 2015 Summer 2015 None Proposed & In Target
Design/Scoping TBD N/A STOAK_PVBW
11-ELL-009-1-CP Generation Interconnection NM6: Modify Ninemile switchyard for interconnection ELL Winter 2014 N/A Supplemental
None Approved Construction Foundation construction for T- structures 1-10 are completed. Projected ISD for 6A and 6B is
now schedule for 12/1/2013 (from 9/15/13) due to
constraints/coordination with Fossil's EPC contractor.
However, meeting on Thursday, May 9, 2013 revealed Fossil's 115kV BACKFEED Milestone may slide to Dec. 31, 2013.
(Early finish target 12/13/2013; Late Finish 12/31/13) Gen 6C
remains on track for Early finish of April of 2014; Late target
finish of Dec. 01 2014.
12/1/2013 (6A&6B)
12/1/2014 (6C)
N/A N/A
11-ENO-001-CP Generation Interconnection NM6: Upgrade Michoud breaker N9803 ENOI Winter 2014 N/A Supplemental
None Approved Design Design underway. 9/16/13 N/A N/A
11-ELL-010-1-CP Transmission Service NM6: Upgrade Ninemile to Southport 230 kV transmission line No.1
ELL Winter 2014 N/A Supplemental
None Approved Design Design underway. Projected ISD accelerated from 9/30/14.
Project completion date accelerated from 9/30/14 to
9/1/14.
9/1/14 N/A N/A
Page 4 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
11-ELL-010-2-CP Transmission Service NM6: Upgrade Ninemile to Southport 230 kV transmission line No.2
ELL Winter 2014 N/A Supplemental
None Approved Design Design underway. Projected ISD accelerated from 9/30/14.
Project completion date accelerated from 9/30/14 to
9/1/14.
9/1/14 N/A N/A
11-ELL-012-CP Transmission Reliability - Meeting Planning Criteria
Valentine to Clovelly 115 kV upgrade ELL Summer 2015 Winter 2012 Construction feasibility Proposed & In Target
Scoping Developing scope for rebuilding line in existing ROW.
Summer 2015 Note B N/A
13-ELL-002-CP Transmission Reliability - Meeting Planning Criteria
McCall 115 kV Substation: Add 20.4 MVAR Capacitor Bank (Formerly Napoleonville add capacitor bank)
ELL Fall 2013 Summer 2013 Construction feasibility Approved Design Project in design phase. All major materials have been ordered. Site & Foundation
Construction Work has been sent out for Quotes.
9/25/13 Note B N/A
13-ELL-004-CP Transmission Reliability - Meeting Planning Criteria
Minden Improvement Project Ph 1-Place cap bank at Minden REA
ELL Summer 2015 Summer 2016 Entergy before ICT Proposed & In Target
Scoping Summer 2015 NA N/A
10-EMI-017-CP Transmission Reliability - Meeting Planning Criteria
Ray Braswell - Wynndale 115kV Line: Construct New 260 MVAConstruct new 115 kV Switching Station between Byram and Terry. Wynndale SS to be designed for future 230-115 kV auto and distribution facilities
EMI Summer 2013 Summer 2013 None Approved Construction Line construction 27% complete. Wynndale steel construction
80% complete.
12/1/13 Note B N/A
11-EMI-002-CP Transmission Reliability - Meeting Planning Criteria
Baxter Wilson to S.E. Vicksburg - Upgrade 115 kV line EMI Summer 2015 Summer 2015 None Proposed & In Target
Scoping Scoping underway Summer 2015 N/A BWLVKS_VKSW
11-EMI-007-CP Transmission Reliability - Meeting Planning Criteria
Breakers at Hollandale and Belzoni Tap SS (close normally-open point)
EMI Summer 2015 Summer 2015 None Proposed & In Target
Design/Scoping Site acquisition ongoing. Summer 2015 N/A N/A
12-EMI-001-CP Transmission Reliability - Meeting Planning Criteria
Franklin - McComb build new 115 kV line (constructed to 230 kV)
EMI Summer 2017 Summer 2017 None Proposed & In Target
Design/Scoping Summer 2017 N/A N/A
12-EMI-002-1-CP Transmission Reliability - Meeting Planning Criteria
Getwell Area ImprovementsConstruct new Senatobia Industrial substation.Cut in Senatobia to Sardis 115 kV line into new substation and add new 230-115 kV autotransformer
EMI Summer 2016 Summer 2014 Construction feasibility Proposed & In Target
Design/Scoping Summer 2016 Note B N/A
12-EMI-002-2-CP Transmission Reliability - Meeting Planning Criteria
Getwell Area ImprovementsConstruct new 230 kV line from Getwell to new Senatobia Industrial 230-115 kV substation.
EMI Summer 2016 Summer 2014 Construction feasibility Proposed & In Target
Design/Scoping Route and Environmental studies to be completed 2012.
Summer 2016 Note B N/A
13-EMI-001-CP Transmission Reliability - Meeting Planning Criteria
Upgrade CTs at Vicksburg for Vicksburg-B.Wilson ckt 1 (ckt without Spencer Potash on it)
EMI Summer 2013 Summer 2014 Entergy before ICT Approved Complete In-Service Summer 2013 6/13/13 NA Yes N/A
13-EMI-002-CP Transmission Reliability - Meeting Planning Criteria
Durant: Add Capacitor Bank EMI Summer 2017 Summer 2017 None Proposed & In Target
Design/Scoping Summer 2017 NA N/A
14-EMI-001-CP Transmission Reliability - Meeting Planning Criteria
Horn Lake to Greenbrook 115kV line: Upgrade 4 switches
EMI Summer 2013 Summer 2013 Approved Construction Complete pending relay upgrades prior to summer and transfer bus switch scheduled for Fall 2013. Transfer switch
has no impact on rating of circuit
Fall 2013 5/3/13 NA N/A
11-ETI-002-CP Transmission Reliability - Meeting Planning Criteria
Reconductor Sabine to Port Neches Bulk (Line 515) ETI Summer 2017 Summer 2018 Entergy before ICT Proposed & In Target
Design/Scoping Summer 2017 NA SABPN_SABHAM, SABPN_SABLI, SABPNB_LNPNB
11-ETI-003-CP Transmission Reliability - Meeting Planning Criteria
Deweyville (JNEC) - Add 69 kV capacitor bank ETI Spring 2013 Winter 2012 Construction feasibility Proposed & In Target
Design/Scoping Scope under review TBD Note B N/A
11-ETI-018-CP Transmission Reliability - Meeting Planning Criteria
Construct new China to Amelia 230kV line ETI Summer 2016 Summer 2018 Entergy before ICT Approved Design/Scoping CCN process is started for this line. Routing study kickoff
meeting held March 5, 2013. Held Open House for potential affected landowners April 22.
2016 Summer N/A
NA
11-ETI-023-CP Transmission Reliability - Meeting Planning Criteria
Orange County 230kV Project: Construct new Chisholm Road 230 kV substation, Construct new line from Hartburg to Chisholm Road, add 2nd Hartburg 500-230 kV auto
ETI Summer 2017 Summer 2017 None Proposed & In Target
Design/Scoping The CCN process for this line targeted to start in mid - late
summer of 2014.
2017 Summer N/A
N/A
11-ETI-033-CP Transmission Reliability - Meeting Planning Criteria
Toledo Bend to Leach 138 kV - Upgrade line ETI Summer 2017 Summer 2017 None Proposed & In Target
Scoping 2017 Summer N/A LCHTOL_GRICR TBLCH_MTOHTB
11-ETI-034-CP Transmission Reliability - Meeting Planning Criteria
Leach to Newton Bulk 138 kV - Reconductor line ETI Summer 2018 Summer 2018 None Proposed & In Target
Scoping 2018 Summer NA N/A
11-ETI-037-CP Transmission Reliability - Meeting Planning Criteria
Construct new China to Stowell 138 kV line ETI Summer 2018 Summer 2018 None Proposed & In Target
Scoping 2018 Summer NA N/A
11-ETI-038-CP Transmission Reliability - Meeting Planning Criteria
Reconductor Sabine to Port Neches Bulk (via Linde Line 516)
ETI Summer 2018 Summer 2018 None Proposed & In Target
Scoping 2018 Summer NA SABLIN_PNB
11-ETI-039-CP Transmission Reliability - Meeting Planning Criteria
Upgrade Jacinto - Splendora 138 kV Line ETI Summer 2015 Summer 2015 None Proposed & In Target
Scoping 2015 Summer N/A N/A
11-ETI-042-CP Transmission Reliability - Meeting Planning Criteria
Expand Cap Bank at New Caney 138kV ETI Summer 2014 Summer 2015 Entergy before ICT Proposed & In Target
Scoping 2014 Summer NA N/A
12-ETI-004-CP Transmission Reliability - Meeting Planning Criteria
Ponderosa Switching Station: tie lines Longmire to Fish Creek and Conroe to Woodhaven into new switching station (Formerly referred to as Conroe Area SS)
ETI Summer 2013 Summer 2014 Entergy before ICT Approved Design/Construction 138kV site cleared ready for construction to begin. Steel for
project received. Projected ISD moved from 12/16/13 to
12/27/13.
12/27/13 N/A
NA
Page 5 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
12-ETI-007-CP Transmission Reliability - Meeting Planning Criteria
Alden 138 kV Substation: Add Capacitor Bank ETI Summer 2015 Summer 2015 None Proposed & In Target
Scoping 2015 Summer N/A NA
12-ETI-009-CP Transmission Reliability - Meeting Planning Criteria
Sabine: Upgrade terminal equipment (Sabine to Big 3 line)
ETI Summer 2017 Summer 2018 Entergy before ICT Proposed & In Target
Scoping 2017 Summer NA N/A
12-ETI-014-CP Transmission Reliability - Meeting Planning Criteria
Amelia to Helbig: Reconductor Line ETI Summer 2018 Summer 2018 None Proposed & In Target
Scoping 2018 Summer NA AMLHLB_HBCYP
12-ETI-015-CP Enhanced Transmission Reliability
College Station SS: Create emergency tie point with ERCOT (asynchronous)
ETI Fall 2012 N/A Supplemental
None Approved Construction Date moved out to July from May based on City of College
Station work. Entergy has completed all possible work and is waiting on the City of College Station to complete their work. ETI will be able to utilize the
emergency tie if required with City of College Station temporary adjusting configuration. Final
configuration expected to be completed by City is currently
projected to be 7/31/13.
7/31/13 N/A
NA
13-ETI-009-01-CP Transmission Reliability - Meeting Planning Criteria
Ponderosa to Grimes: Construct new 230 kV LineAdd 345-230 kV Auto at GrimesAdd 230-138 kV Auto at Ponderosa
ETI Summer 2016 Summer 2018 Entergy before ICT Approved Scoping The CCN process is underway for this project with a targeted application date of mid June
2013. Open houses were held March 25 and 26. The CCN application period has been extended for three months to
work through some landowner issues; this extension will not
impact the overall targeted ISD.
2016 Summer N/A
GRIMTZ_WDNGRIMZ_GRICRO
13-ETI-009-02-CP Transmission Reliability - Meeting Planning Criteria
Conroe to Ponderosa 138 kV line: Upgrade Line ETI Summer 2016 Summer 2018 Entergy before ICT Approved Scoping 2016 Summer NA N/A
13-ETI-010-01-CP Transmission Reliability - Meeting Planning Criteria
Pansy to Lovells Lake 69 kV line: Upgrade line to 100 deg design
ETI Winter 2013 Summer 2014 Entergy before ICT Proposed & In Target
Design/Scoping LIDAR flown. Data being analyzed to move forward with
project
2013 Winter NAN/A
13-ETI-010-02-CP Transmission Reliability - Meeting Planning Criteria
Lovells Lake to Texas Hillebrandt 69 kV line: Upgrade line to 100 deg design
ETI Winter 2013 Summer 2013 Construction feasibility Proposed & In Target
Design/Scoping LIDAR flown. Data being analyzed to move forward with
project
2013 Winter NAN/A
13-ETI-011-CP Transmission Reliability - Meeting Planning Criteria
Lewis Creek to Egypt 138 kV line: Reconductor ETI Summer 2014 Summer 2014 None Proposed & In Target
Design/Scoping A Contract Project Manager has been assigned to this project
and will begin scoping activities.
2014 Summer NA
N/A
13-ETI-012-CP Transmission Reliability - Meeting Planning Criteria
Construct new Porter to Forest 138 kV transmission line - Construct new line from Porter to Oakridge area and tie into de-energized line 403 - Terminate line 403 into Forest 138 kV substation
ETI Summer 2016 Summer 2018 Entergy before ICT Proposed & In Target
Design/Scoping The site for the Forest station has been identified. The CNN is schedule to start in the next
few months.
2016 Summer NA
N/A
13-ETI-013-CP Transmission Reliability - Meeting Planning Criteria
Egypt to Panorama 138 kV Line: Reconductor line ETI Summer 2018 Summer 2018 None Proposed & In Target
Design/Scoping 2018 Summer NA N/A
PREVIOUSLY COMPLETED PROJECTS10CP-EAI-001 Transmission Reliability -
Meeting Planning CriteriaHamlet 161 kV Substation: Install 161 kV Breaker on Conway Industrial Line
EAI Summer 2009 Summer 2009 None Approved Complete In-service 12/4/09 12/4/09 Complete Yes
10CP-EAI-002 Transmission Reliability - Meeting Planning Criteria
Gillette 115 kV Substation: Install 10.8 MVAR Capacitor Bank
EAI Summer 2009 Summer 2009 None Approved Complete In-service 7/1/09 5/16/09 Complete Yes
10CP-EAI-003 Transmission Reliability - Meeting Planning Criteria
Conway West - Donaghey 161 kV Line: Reconductor with 666 ACSS
EAI Summer 2009 Summer 2009 None Approved Complete In-service 3/24/09 Complete Yes
10CP-EAI-004 Transmission Reliability - Meeting Planning Criteria
Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Add 10.8 MVAR capacitor bank at Emerson 115 kV substation
EAI Summer 2009 Summer 2009 None Approved Complete In-service 12/31/09 10/8/09 Complete Yes
10CP-EAI-005 Transmission Reliability - Meeting Planning Criteria
Danville 161 kV Substation: Upgrade Terminal Equipment to match or exceed Magazine line ratings
EAI Fall 2009 Fall 2009 None Approved Complete In-service 8/14/09 8/14/09 Complete Yes
10CP-EAI-006 Transmission Reliability - Meeting Planning Criteria
Donaghey - Conway South 161 kV Line: Reconductor with 666 ACSS
EAI Spring 2010 Summer 2009 Project in service Approved Complete In-service 4/21/10 Complete Yes
Page 6 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
10CP-EAI-007-1 Transmission Service SMEPA (Plum Point): * Dell - Manilla 161kV Line: Upgrade to at least 247MVA
EAI Spring 2010 Spring 2010 None Approved Complete In-service 4/5/10 4/2/10 Complete Yes
10CP-EAI-007-2 Transmission Service SMEPA (Plum Point): * Manilla - Monette 161kV Line: Upgrade to at least 247MVA
EAI Spring 2010 Spring 2010 None Approved Complete In-service 12/26/08 12/22/08 Complete Yes
10CP-EAI-007-3 Transmission Service SMEPA (Plum Point): * Jonesboro North - Paragould South 161kV Line: Upgrade to at least 247MVA
EAI Spring 2010 Spring 2010 None Approved Complete In-service 5/29/09 5/14/09 Complete Yes
10CP-EAI-007-4 Transmission Service SMEPA (Plum Point): * Jonesboro North - Jonesboro 161kV Line: Upgrade to at least 247MVA
EAI Spring 2010 Spring 2010 None Approved Complete In-service 1/8/10 1/9/10 Complete Yes
10CP-EAI-008 Transmission Reliability - Meeting Planning Criteria
Beebe 115 kV Substation: Install 21.6 MVAR Capacitor Bank
EAI Summer 2010 Summer 2010 None Approved Complete In-service 6/1/10 4/21/10 Complete Yes
10CP-EAI-009 Transmission Reliability - Meeting Planning Criteria
Melbourne - Sage 161 kV Line: Upgrade line to at least 1200 A
EAI Summer 2010 Summer 2009 First identified by ICT in early 2009. Construction not feasible by summer 2009 due to material acquisition and outage coordination
Approved Complete In-service 6/1/10 6/19/10 Complete Yes
10CP-EAI-010 Transmission Reliability - Meeting Planning Criteria
Warren East 115 kV Substation: Install 10.8 MVAR Capacitor Bank
EAI Summer 2010 Summer 2010 None Approved Complete In-service 8/6/10 7/18/10 Complete Yes
10CP-EAI-011 Transmission Reliability - Meeting Planning Criteria
Parkin to Twist 161 kV - Replace line trap at Parkin (increase rating of line segment)
EAI Winter 2010 Winter 2010 None Approved Complete In-Service 12/31/10 12/22/10 Complete Yes
10CP-EAI-012-1 Transmission Service Transmission Service (OG&E) Upgrade ANO - Russelville North 161 kV Line to 546 MVA
EAI Summer 2010 2012 None Approved Complete In-service 6/1/10 5/18/10 Complete Yes
10CP-EAI-012-2 Transmission Service Transmission Service (OG&E) Upgrade Russelville East - Russelville South 161 kV Line to 448 MVA
EAI Summer 2010 Summer 2010 None Approved Complete In-service 9/30/10 8/12/10 Complete Yes
10-EAI-013-CP Transmission Reliability - Meeting Planning Criteria
Osage Creek-Grandview New Line Build new 161 kV (At Least 1200 A) line from Grandview (Planned SPA 161 kV Substation tapped on the Eureka - Table Rock 161 kV Line) to Osage Creek
EAI Summer 2011 Summer 2012 Entergy before ICT Approved Complete In-Service 12/15/11 11/28/11 Complete Yes N/A
10CP-EAI-014 Transmission Reliability - Meeting Planning Criteria
Harrison East to Everton Road 161 kV Line: Upgrade Harrison East Terminal Equipment to 1200 A
EAI Winter 2009 Winter 2009 None Approved Complete In-service 12/15/09 12/15/09 Complete Yes
10CP-EAI-016-1 Transmission Service Transmission Service (Aquila) Upgrade Hot Springs - Bismark 115 kV Line to 176 MVA
EAI Winter 2011 Summer 2012 None Approved Complete In-service 6/1/11 10/20/10 Complete Yes
10-EAI-015-1-CP Transmission Reliability - Meeting Planning Criteria
Holland Bottoms (Cabot EHV): Construct new 500/161/115 kV substation Phase 1 Projects Tap the Keo - ISES 500 kV Line Tap the Cabot - Jacksonville North 115 kV Line Install 500 kV and 115 kV Busses and a 600 MVA 500 kV / 115 kV Autotransformer
EAI Summer 2011 Summer 2012 Entergy before ICT Approved Complete In-service 12/31/11 1/6/12 Complete Yes N/A
10-EAI-015-2-CP Transmission Reliability - Meeting Planning Criteria
Holland Bottoms (Cabot EHV): Construct new 500/161/115 kV substation Phase 2 Projects Install 161 kV Bus and a 600 MVA 500 kV / 161 kV Autotransformer
EAI Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 5/23/12 N/A Yes N/A
10CP-EAI-016-2 Transmission Service Transmission Service (Aquila) Upgrade Bismark - Alpine 115 kV Line to 176 MVA
EAI Winter 2011 Winter 2011 None Approved Complete In-Service 2/28/11 3/2/11 Complete Yes
10CP-EAI-016-3 Transmission Service Transmission Service (Aquila) Upgrade Alpine - Amity 115 kV Line to 176 MVA
EAI Winter 2011 Winter 2011 None Approved Complete In-Service 3/31/11 3/22/11 Complete Yes
10-EAI-017-CP Transmission Reliability - Meeting Planning Criteria
Holland Bottoms - Hamlet 161 kV Line: Construct new 161 kV Line Convert Hamlet SS to a breaker station (Single Bus Single Breaker Scheme) Move the Quitman line from Gold Creek to Hamlet SS Move the Gravel Ridge line from Gold Creek to Hamlet SS Construct a line rated at least 1200 A from Hamlet SS to Holland Bottoms
EAI Summer 2012 Summer 2013 Entergy before ICT Approved Complete In-Service 6/1/12 5/23/12 N/A Yes N/A
Page 7 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
10-EAI-018-CP Transmission Reliability - Meeting Planning Criteria
Ebony 161 kV Switching Station: Install 5 Breaker Ring Bus Lines Terminating Into New Ebony Substation (ratings unchanged): Ebony - Kuhn Road 161 kV Line Ebony - WM Lehi - WM Polk - WM EHV 161 kV Line Ebony - WM Dover - WM Gateway 161 kV Line Ebony - Marked Tree 161 kV Line Ebony - WM Lehi - WM EHV 161 kV Line
EAI Summer 2012 Summer 2012 None Approved Complete In-service 12/31/12 11/16/12 N/A Yes N/A
10-EAI-019-CP Transmission Reliability - Meeting Planning Criteria
Jonesboro to Hergett 161 kV Line: Upgrade 161 kV Line to at least 240 MVA
EAI Summer 2012 Summer 2012 None Approved Complete In-Service 5/1/12 5/3/12 N/A Yes JONHE_JONJOS
10-EAI-020-CP Transmission Reliability - Meeting Planning Criteria
Benton North to Benton South: Construct New 115 kV Line Rated at least 170 MVA Install Switching Stations at Benton North and Benton South
EAI Winter 2012 Winter 2012 None Approved Complete In-Service 6/30/13 4/22/13 Complete Yes N/A
10-EAI-022-1-CP Transmission Service Westar Transmission Service Monette - Paragould 161kV Line: Upgrade to at least 246 MVA
EAI Summer 2012 Summer 2013 Entergy before ICT Approved Complete In-service 12/30/11 1/10/12 Complete Yes MONJPA_SANSH
10-EAI-022-2-CP Transmission Service Westar Transmission Service Paragould Substation: Upgrade the switch B6673 from 600A to 2000A
EAI Summer 2012 Summer 2013 Entergy before ICT Approved Complete In-Service 10/16/11 9/29/11 Complete Yes MONJPA_SANSH
10-EAI-022-3-CP Transmission Service Westar Transmission Service Russellville South - Dardanelle Dam (SPA) 161kV Line: Replace switch
EAI Summer 2012 N/A Supplemental
None Approved Complete In-Service 12/31/11 10/31/11 Complete Yes
10CP-EAI-023 Transmission Reliability - Meeting Planning Criteria
Couch to McNeil 115kV Line: Upgrade jumpers at Couch
EAI Summer 2011 Summer 2011 None Approved Complete In-Service Winter 2010 1/20/11 Complete Yes
10CP-EAI-024 Transmission Reliability - Meeting Planning Criteria
Lake Catherine 4 to Arklahoma 115 kV line: Upgrade risers at Arklahoma
EAI Summer 2011 Summer 2011 None Approved Complete In-Service Spring 2011 1/24/11 Complete Yes
10CP-EAI-026 Transmission Reliability - Meeting Planning Criteria
Mablevale to LR Alexander 115 kV line: Replace switches and risers at Mablevale and upgrade bus at LR Mann Road
EAI Winter 2010 Winter 2010 None Approved Complete In-Service 4/6/11 4/13/11 Complete Yes
10CP-EAI-027 Transmission Reliability - Meeting Planning Criteria
Russelville North to Russelville East 115 kV line: Replace jumpers at Russellville East
EAI Spring 2011 Spring 2011 None Approved Complete In-Service Winter 2010 1/17/10 Complete Yes
10CP-EAI-028 Transmission Reliability - Meeting Planning Criteria
Morgan to Mayflower 115 kV line: Replace jumpers and bus at Mayflower
EAI Summer 2011 Summer 2011 None Approved Complete In-Service 2/4/11 2/8/11 Complete Yes
10CP-EAI-029 Transmission Reliability - Meeting Planning Criteria
Maumelle East SS to Morgan 115 kV line: Replace switch and bus at Maumelle East SS
EAI Summer 2011 Summer 2011 None Approved Complete In-Service Spring 2011 4/12/11 Complete Yes
10CP-EAI-030 Transmission Reliability - Meeting Planning Criteria
Heber Springs South to Heber Springs Industrial 161 kV line: Replace bus at Heber Springs South
EAI Summer 2011 Summer 2011 None Approved Complete In-Service 4/7/11 4/25/11 Complete Yes
10-EAI-031-CP Economic West Memphis to Birmingham Steel 500 kV line flowgate: Replace 500 kV breaker, six line traps, and 2 switches at West Memphis 500 kV substation
EAI Winter 2011 N/A Supplemental
None Approved Complete In-service 3/5/12 2/28/12 Complete Yes IWMPBIR_SANSH
11-EAI-001-CP Transmission Reliability - Meeting Planning Criteria
Pine Bluff Voltage Support Project - Phase 1 Poyen 115 kV Substation: Add 21.6 MVAR Capacitor Bank
EAI Summer 2012 Summer 2012 None Approved Complete In-Service 6/15/12 5/31/12 N/A Yes N/A
11-EAI-006-CP Transmission Reliability - Meeting Planning Criteria
Ebony 161 kV Switching Station: Add 36 MVAR Capacitor Bank
EAI Winter 2012 Summer 2013 Entergy before ICT Approved Complete In-service 12/31/12 11/30/12 Complete Yes N/A
11-EAI-010-CP Transmission Reliability - Meeting Planning Criteria
Wilmar Substation: Add 21.6 MVAR Capacitor Bank (Formerly Hilo Substation)
EAI Winter 2012 Summer 2013 Entergy before ICT Approved Complete In-service 2/15/13 1/21/13 N/A Yes N/A
11CP-EAI-011 Transmission Reliability - Meeting Planning Criteria
Pangburn 161 kV Substation: Relocate Rutherford 161 kV Cap Bank to Pangburn
EAI Summer 2011 Summer 2014 Entergy before ICT Approved Complete In-service 8/22/11 8/31/11 Complete Yes
11CP-EAI-013 Transmission Reliability - Meeting Planning Criteria
Woodward to Pine Bluff Watson Chapel: Upgrade bus at PB Watson Chapel
EAI Summer 2011 N/A Project recently added Approved Complete In-Service 5/1/11 4/26/11 Complete Yes
12-EAI-020-CP Transmission Reliability - Meeting Planning Criteria
Mabelvale: Change 500-115 NLTC from 487.5kV tap to 512.5kV tap
EAI Summer 2013 Summer 2013 None Approved Complete In-Service 5/10/12 5/10/12 N/A Yes MABXF1_MAXF2
12-EAI-028-CP Transmission Reliability - Meeting Planning Criteria
Quitman to Bee Branch: Replace 600A switch(Formerly upgrade line project)
EAI Winter 2012 Winter 2017 Entergy before ICT Approved Complete In-service 12/31/12 10/23/12 N/A Yes QUTBEB_FTSAR
13-EAI-004-CP Transmission Reliability - Meeting Planning Criteria
Monticello East - Add 21.6 MVAR capacitor bank EAI Summer 2013 Summer 2015 Entergy before ICT Approved Complete In-Service Summer 2013 5/29/13 Complete Yes N/A
13-EAI-007-CP Transmission Reliability - Meeting Planning Criteria
Jim Hill to St. Francis 161 kV line: Upgrade terminal equiment at Jim Hill
EAI Fall 2012 Fall 2012 Project added per request of AECI Approved Complete In-service 12/1/12 10/23/12 N/A Yes
10CP-EGL-001 Transmission Reliability - Meeting Planning Criteria
Acadia 138 kV Substation: Install 36 MVAR Capacitor Bank
EGSL Summer 2009 Summer 2009 None Approved Complete In-service 6/19/09 Complete Yes
10CP-EGL-002 Transmission Reliability - Meeting Planning Criteria
Addis to Cajun 230 kV line - Upgrade Limiting Section With Double-Bundled 649.5 ACAR (654 MVA)
EGSL Winter 2010 Winter 2012 Entergy before ICT Approved Complete In-Service 12/31/10 12/15/10 Complete Yes
10CP-EGL-003 Transmission Reliability - Meeting Planning Criteria
Carter and Elton Capacitor Banks: Upgrade 69 kV capacitor bank at Elton to 14 MVAR, Add 69 kV, 14 MVAR capacitor bank at Carter
EGSL Fall 2010 Fall 2010 None Approved Complete In-service 12/3/10 10/27/10 Complete Yes
10-EGL-004-CP Transmission Reliability - Meeting Planning Criteria
Construct New Youngsville 138 kV Distribution Substation
EGSL Winter 2011 Summer 2012 Entergy before ICT Approved Complete In-service 12/31/11 11/21/11 Complete Yes
10CP-EGL-005 Transmission Reliability - Meeting Planning Criteria
Alchem - Monochem 138 kV Line: Upgrade 138 kV line to 275 MVA
EGSL Summer 2011 Summer 2011 None Approved Complete In-Service 5/1/11 5/24/11 Complete Yes MONALC_SGAAC
Page 8 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
10CP-EGL-006-1 Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 1 Projects Construct new Sellers Road to Meaux 230 kV Line
EGSL Summer 2011 Winter 2010 ROW acquisition, material lead times, construction coordination. Jointly agreed to by parties.
Approved Complete In-Service 5/6/11 5/6/11 Complete Yes
10CP-EGL-006-2 Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 1 Projects Add 450 MVA, 230-138 kV auto at Meaux
EGSL Summer 2011 Winter 2010 ROW acquisition, material lead times, construction coordination. Jointly agreed to by parties.
Approved Complete In-Service 5/2/11 5/6/11 Complete Yes
10CP-EGL-006-3 Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 1 Projects Add new 138 kV line bay at Moril (Segura Line)
EGSL Summer 2011 Summer 2011 None Approved Complete In-service 5/5/10 Complete Yes
10CP-EGL-006-4 Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 1 Projects Add new 500 kV position for Cleco autotransformer at Richard
EGSL Summer 2011 Winter 2010 ROW acquisition, material lead times, construction coordination. Jointly agreed to by parties.
Approved Complete In-Service 11/22/10 5/6/11 Complete Yes RICXF1_XF2
10-EGL-007-1-CP Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 2 Projects Construct new Labbe to Sellers Road 230 kV Line
EGSL Summer 2012 Summer 2012 None Approved Complete In-Service 6/29/12 6/28/12 N/A YesN/A
10-EGL-007-2-CP Transmission Reliability - Meeting Planning Criteria
Acadiana Area Improvement Project Phase 2 Projects Add new 500 kV position for Cleco autotransformer at Wells
EGSL Summer 2012 Summer 2012 None Approved Complete In-Service. Entergy completed work to allow CLECO connection of new auto.
3/19/12 3/16/12 N/A Yes
BONXF_FLNHPK
10-EGL-008-CP Transmission Reliability - Meeting Planning Criteria
Construct new Nelson to Moss Bluff 230 kV line Disconnect existing Nelson to Moss Bluff 230 kV line Will be used in the future to create a Nelson to new Lake Charles 230 kV line
EGSL Summer 2012 Summer 2012 None Approved Complete In-Service 5/31/12 5/12/12 N/A Yes NELMB_CARBOU
10-EGL-009-CP Transmission Reliability - Meeting Planning Criteria
Tejac to Marydale: Upgrade 69 kV transmission line EGSL Summer 2012 Summer 2013 Entergy before ICT Approved Complete In-service 1/31/12 2/15/12 Complete Yes N/A
10-EGL-010-CP Transmission Reliability - Meeting Planning Criteria
Loblolly-Hammond Build 230 kV Line EGSL/ELL Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 12/16/11 Complete Yes
10CP-EGL-013 Transmission Reliability - Meeting Planning Criteria
Krotz Springs to Line 642 Tap 138 kV line: Upgrade bus at Colonial Springs Tap
EGSL Summer 2013 Summer 2013 None Approved Complete In-Service Spring 2011 3/14/11 Complete Yes
10CP-EGL-014 Transmission Reliability - Meeting Planning Criteria
Livonia to Line 643 Tap 138 kV line: Upgrade riser at Livonia
EGSL Winter 2010 Winter 2010 None Approved Complete In-Service Spring 2011 3/16/11 Complete Yes
10CP-EGL-015 Transmission Reliability - Meeting Planning Criteria
Wilbert to Livonia 138 kV line: Upgrade risers at Wilbert and Livonia
EGSL Summer 2011 Summer 2011 None Approved Complete In-Service Spring 2011 1/25/11 Complete Yes
10CP-EGL-016 Transmission Reliability - Meeting Planning Criteria
Big Three to Carlyss 230 kV line: Upgrade bus, switch, and jumpers at Carlyss 230 kV substation
EGSL Summer 2011 Summer 2011 None Approved Complete In-service 5/6/11 6/9/11 Complete Yes
10-EGL-017-CP Transmission Reliability - Meeting Planning Criteria
Richard to Habetz 138 kV line: Upgrade bus at Richard EGSL Winter 2010 Winter 2010 None Approved Complete In-Service 11/30/11 10/10/11 Complete Yes RICHAB_BONAM RICHAB_PDMLA RICHAB_RICWE
10-EGL-018-CP Transmission Reliability - Meeting Planning Criteria
Willow Glen to Bayou LaButte 500 kV line: Replace/change line relay CT and ratio at Willow Glen (Formerly Willow Glen to Webre)
EGSL Summer 2011 Summer 2012 Entergy before ICT Approved Complete In-service 3/31/12 2/27/12 Complete Yes WEBWG_CJFAN
10CP-EGL-019 Transmission Reliability - Meeting Planning Criteria
Willow Glen to Geismar 138 kV line: Upgrade risers at Willow Glen and Geismar
EGSL Summer 2011 Summer 2011 None Approved Complete In-Service Summer 2011 1/20/11 Complete Yes
10CP-EGL-020 Transmission Reliability - Meeting Planning Criteria
Port Hudson to Fancy Point 230 kV line: Upgrade bus at Fancy Point
EGSL Winter 2010 Winter 2010 None Approved Complete In-Service Winter 2010 12/20/10 Complete Yes
10CP-EGL-021 Transmission Reliability - Meeting Planning Criteria
Richard to Scott 1 138kV segment: Replace/change CT ratio at Richard and upgrade bus at Scott
EGSL Winter 2010 Winter 2010 None Approved Complete In-Service Winter 2010 1/7/11 Complete Yes
10CP-EGL-022 Transmission Reliability - Meeting Planning Criteria
Carlyss to Rose Bluff 230 kV line: Upgrade bus, switch, and jumpers at Carlyss 230 kV substation
EGSL Winter 2010 Winter 2010 None Approved Complete In-Service Spring 2011 5/23/11 Complete Yes ROSCAR_NELMO
11-EGL-004-CP Transmission Reliability - Meeting Planning Criteria
Bloomfield to Bosco 138 kV line (formerly Vatican project) Construct new Bloomfield 138 kV SS north of Vatican Construct new Bosco 138 kV SS on Scott to Scanlan 138 kV line Construct new Bloomfield to Bosco 138 kV line Install 5 ohm reactor at Bosco substation
EGSL Summer 2013 Winter 2012 Construction feasibility Approved Complete In-service 12/31/12 12/20/12 N/A Yes
NCRSCB_RICHR, NRCSCB_WLPNT, NCRSC_RICWEL
11-EGL-005-CP Transmission Reliability - Meeting Planning Criteria
Jackson to Tejac: Upgrade 69 kV transmission line EGSL Summer 2012 Summer 2012 None Approved Complete In-service 6/15/12 6/5/12 N/A Yes N/A
11-EGL-008-CP Transmission Reliability - Meeting Planning Criteria
Francis 69 kV substation - Add 14.4 MVAR, 69 kV capacitor bank (Previously considered Marydale as alternate location)
EGSL Summer 2013 Summer 2013 None Approved Complete In-Service 3/29/13 3/25/13 N/A YesN/A
11CP-EGL-011 Transmission Reliability - Meeting Planning Criteria
Carlyss to Citcon West 138 kV: Upgrade station equipment
EGSL Winter 2011 Winter 2010 Construction scheduling in conjunction with work on Carlyss 230 kV bus results in a more probable date of after summer 2011.
Approved Complete In-service 9/29/11 9/28/11 Complete Yes
11CP-EGL-012 Transmission Reliability - Meeting Planning Criteria
Carlyss to Nelson 230 kV: Upgrade station equipment at Carlyss
EGSL Winter 2013 Winter 2013 None Approved Complete In-service Spring 2011 6/9/11 Complete Yes
11-EGL-013-CP Transmission Reliability - Meeting Planning Criteria
Fireco to Copol 69 kV line: Upgrade switches and line trap
EGSL Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 5/21/12 N/A Yes N/A
Page 9 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
11-EGL-013-1-CP Transmission Reliability - Meeting Planning Criteria
Fireco to Copol 69 kV line: Upgrade line conductor EGSL Winter 2012 Summer 2013 Entergy before ICT Approved Complete In-service 12/31/12 12/17/12 N/A Yes N/A
11-EGL-014-CP Transmission Reliability - Meeting Planning Criteria
Addis 69 kV Substation: Upgrade 69 kV switches and line trap
EGSL Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 5/21/12 N/A Yes N/A
11-EGL-015-1-CP Transmission Service Acadia Generation - Reconfigure Richard 138 kV substation (Upgrade ckts 3 and 4 and Richard relaying work)
EGSL Summer 2013 N/A Supplemental
None Approved Complete In-service 6/15/12 5/15/12 N/A Yes RICXF1_XF2, BONCEC_RICCO, RICCOL_FANCJ, RICCOL_NCRIC,
RICCOL_SCOTT11-EGL-015-3-CP Transmission Service Acadia Generation - Upgrade Moril to Hopkins 138 kV
lineEGSL Summer 2013 N/A
SupplementalNone Approved Complete In-service 11/15/12 10/30/12 N/A Yes N/A
11-EGL-015-4-CP Transmission Service Acadia Generation - Upgrade 69 kV breaker at Scott 18220
EGSL Summer 2013 N/A Supplemental
None Approved Complete In-Service 10/28/12 10/11/12 N/A NA N/A
12-EGL-003-CP Transmission Reliability - Meeting Planning Criteria
Champagne to Plaisance 138 kV line - Modify/Replace CTs at Champagne
EGSL Summer 2013 Summer 2013 None Approved Complete In-service 6/1/13 12/26/12 N/A Yes PLACHM_COCVP
12-EGL-008-CP Transmission Reliability - Meeting Planning Criteria
Copol to Bourbeaux: Upgrade 69 kV line EGSL Winter 2014 Summer 2017 Entergy before ICT Approved Complete In-Service 4/3/13 4/18/13 Complete Yes N/A
12-EGL-014-CP Transmission Reliability - Meeting Planning Criteria
Lake Charles Bulk Substation: Replace four 69 kV, 600 A switches on transformers and bus section breaker with 1200 A switches
EGSL Fall 2012 Summer 2013 Entergy before ICT Approved Complete In-service 12/1/12 1/28/13 N/A YesN/A
10CP-ELL-001 Transmission Reliability - Meeting Planning Criteria
Snakefarm to Kenner 115 kV line: Upgrade to 359 MVA ELL Spring 2010 Spring 2010 None Approved Complete In-service 3/25/10 Complete Yes
10CP-ELL-002 Transmission Reliability - Meeting Planning Criteria
Bogalusa to Adams Creek 230 kV No. 2 - Upgrade terminal equipment at Bogalusa
ELL Winter 2009 Winter 2009 None Approved Complete In-service 1/18/10 Complete Yes
10CP-ELL-003 Transmission Reliability - Meeting Planning Criteria
Delhi 115 kV Substation - Add 30.5 MVAR Capacitor Bank
ELL Winter 2009 Winter 2009 None Approved Complete In-service 10/21/09 Complete Yes
10CP-ELL-004 Economic Delhi 115 kV Substation - Add 10 Ohm series reactor ELL Spring 2010 Spring 2010 None Approved Complete In-service 5/28/10 5/20/10 Complete Yes
10CP-ELL-005-1 Transmission Reliability - Meeting Planning Criteria
Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Construct a new 345-115 kV substation consisting of a 500 MVA auto. Cut station into EL Dorado to Longwood 345 kV line.
ELL Summer 2011 Summer 2013 Entergy before ICT Approved Complete In-Service 6/1/11 6/15/11 Complete Yes
10CP-ELL-005-2 Transmission Reliability - Meeting Planning Criteria
Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Add 32.4 MVAR capacitor bank at Lucky 115 kV substation
ELL Summer 2011 Summer 2011 None Approved Complete In-service 3/1/09 Complete Yes
10CP-ELL-005-3 Transmission Reliability - Meeting Planning Criteria
Sarepta Project (NW Louisiana/South Arkansas Voltage Support Plan) Add 32.4 MVAR capacitor bank at Vienna 115 kV substation
ELL Summer 2011 Summer 2011 None Approved Complete In-service 10/1/09 Complete Yes
10-ELL-006-CP Transmission Reliability - Meeting Planning Criteria
Bayou LaButte: Construct new 500-230 kV Substation Install 800 MVA, 500-230 kV autotransformer Cut in Webre to Willow Glen 500 kV line Construct new 230 kV line from Bayou LaBoutte to Iberville 230 kV substation
ELL Winter 2011 Winter 2012 Entergy before ICT Approved Complete In-Service 12/15/11 11/22/11 Complete Yes WEBWG_CJFAN
10-ELL-007-CP Transmission Reliability - Meeting Planning Criteria
Southeast LA Coastal Improvement Plan: Phase 2 Build Peters Road-Oakville 230kV Line and Substation
ELL Summer 2012 Winter 2011 ROW acquisition, construction timing.
Approved Complete In-service 9/20/12 9/6/12 Complete Yes N/A
10-ELL-010-1-CP Transmission Service Ouachita Transmission Service Split Sterlington 115 kV bus and replace 500-115 auto #2 with 750 MVA
ELL Summer 2012 N/A Supplemental
None Approved Complete In-Service. Auto placed in-service 2/14/12. Bus split completed 3/12/12.
3/9/12 3/12/12 Complete Yes N/A
10-ELL-010-2-CP Transmission Service Ouachita Transmission Service Upgrade Walnut Grove to Swartz 115 kV line
ELL Spring 2013 N/A Supplemental
None Approved Complete In-service 5/18/12 4/17/12 Complete Yes N/A
10CP-ELL-010-3 Transmission Service Ouachita Transmission Service Upgrade Frostkraft to Rilla 115 kV line
ELL Summer 2012 N/A Supplemental
None Approved Complete In-service 6/4/10 6/14/10 Complete Yes
10-ELL-010-4-CP Transmission Service Ouachita Transmission Service Upgrade Sterlington to Log Cabin 115 kV line
ELL Summer 2012 N/A Supplemental
None Approved Complete In-Service 6/1/12 12/20/11 Complete Yes N/A
10CP-ELL-010-5 Transmission Reliability - Meeting Planning Criteria
Ouachita Transmission Service Loop Sterlington to North Crossett into North Bastrop
ELL Summer 2012 Summer 2012 None Approved Complete In-service 6/1/11 6/15/11 Complete Yes
10CP-ELL-010-6 Transmission Service Ouachita Transmission Service Add 43 MVAR, 115 kV capacitor bank at Riser
ELL Summer 2012 N/A Supplemental
None Approved Complete In-service 11/1/10 11/23/10 Complete Yes
10CP-ELL-011 Transmission Reliability - Meeting Planning Criteria
Barataria to Ninemile 115 kV line: Replace line Trap ELL Winter 2010 Winter 2010 None Approved Complete In-Service 3/31/11 4/11/11 Complete Yes
10CP-ELL-012 Transmission Reliability - Meeting Planning Criteria
Waterford to Ninemile 230 kV line: Replace line trap, switches, and jumpers at Ninemile
ELL Summer 2011 Summer 2011 None Approved Complete In-Service 5/31/11 5/31/11 Complete Yes WATNM_GYPSN
10CP-ELL-013 Transmission Reliability - Meeting Planning Criteria
Raceland to Couteau 115 kV line: Replace switch, jumpers and line trap
ELL Winter 2010 TBD None Approved Complete In-service Winter 2010 10/25/10 Complete Yes
11-ELL-003-1-CP Transmission Reliability - Meeting Planning Criteria
NE Louisiana Improvement Project - Phase 1 Swartz to Oak Ridge - Construct new 115 kV Line (1272 ACSS) Operate Sterlington to Oak Ridge normally open
ELL Summer 2013 Summer 2013 None Approved Complete In-Service 5/24/13 3/22/13 N/A Yes STOAK_PVBW
11CP-ELL-006 Transmission Reliability - Meeting Planning Criteria
Hooker to Waterford 230 kV line - Upgrade station equipment
ELL Spring 2011 Spring 2011 None Approved Complete In-Service Spring 2011 5/17/11 Complete Yes HOWATR_UCWAT
11CP-ELL-007 Transmission Reliability - Meeting Planning Criteria
Waterford to Union Carbide 230 kV line - Upgrade station equipment
ELL Spring 2011 Spring 2011 None Approved Complete In-Service Spring 2011 5/26/11 Complete Yes UCWAT_HOWATR
Page 10 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
11CP-ELL-008 Transmission Reliability - Meeting Planning Criteria
Union Carbide to Hooker 230 kV line - Upgrade station equipment
ELL Spring 2011 Spring 2011 None Approved Complete In-Service Spring 2011 4/12/11 Complete Yes
12-ELL-001-CP Transmission Reliability - Meeting Planning Criteria
Gypsy to Luling: Upgrade line bay bus and jumpers at Luling
ELL Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 12/22/11 Complete Yes LULGYP_GYPXF
13-ELL-001-CP Transmission Reliability - Meeting Planning Criteria
Golden Meadow to Barataria: Upgrade switch ELL Summer 2013 Summer 2013 None Approved Complete In-Service 4/30/13 4/25/13 Complete Yes N/A
10CP-EMI-001 Transmission Reliability - Meeting Planning Criteria
Liberty-Gloster: Upgrade 115 kV Line For Natchez De-listing
EMI Summer 2009 Summer 2009 None Approved Complete In-service 4/25/09 Complete Yes
10CP-EMI-002 Transmission Reliability - Meeting Planning Criteria
Indianola-Greenwood 115 kV Line: Upgrade line to 161 MVA Upgrade Terminal Equipment at Morehead, Itta Bena, and Greenwood
EMI Summer 2010 2009 First identified by ICT in 2009 Base Plan. Construction of this project could not be completed in short time frame.
Approved Complete In-service 5/26/10 6/10/10 Complete Yes
10-EMI-003-CP Transmission Reliability - Meeting Planning Criteria
Magee 115 kV Substation: Replace Switches EMI Winter 2011 Winter 2011 None Approved Complete In-Service 12/15/11 11/30/11 Complete Yes
10CP-EMI-004-1 Transmission Service TVA Affected System Upgrades Morton 115 kV Substation: Upgrade 600 A Switches to 1200A
EMI Spring 2010 N/A Supplemental
None Approved Complete In-service 11/6/09 Complete Yes
10CP-EMI-004-2 Transmission Service TVA Affected System Upgrades South Jackson - Florence 115 kV Line: Upgrade to at least 240 MVA
EMI Spring 2010 N/A Supplemental
None Approved Complete In-service 4/23/10 Complete Yes
10CP-EMI-005 Transmission Service Grand Gulf Uprate Project Baxter Wilson - Ray Braswell 500 kV Line: Upgrade Breakers and Switches to 3000 A
EMI Summer 2010 N/A Supplemental
None Approved Complete In-service 4/9/10 Complete Yes
10CP-EMI-006-1 Transmission Reliability - Meeting Planning Criteria
Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 1 Projects Winona 115 kV Substation: Install 21.6 MVAR Capacitor Bank
EMI Winter 2009 Winter 2009 None Approved Complete In-service 12/15/09 11/30/09 Complete Yes
10CP-EMI-006-2 Transmission Reliability - Meeting Planning Criteria
Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 1 Projects Greenwood 115 kV Substation: Upgrade 21.6 MVAR Capacitor Bank to 32.4 MVAR
EMI Winter 2009 Winter 2009 None Approved Complete In-service 12/15/09 10/28/09 Complete Yes
10CP-EMI-006-3 Transmission Reliability - Meeting Planning Criteria
Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 1 Projects Schlater 115 kV substation: Install 21.6 MVAR Capacitor Bank
EMI Winter 2009 Winter 2009 None Approved Complete In-service 12/15/09 10/21/09 Complete Yes
10-EMI-007-01-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Rolling Fork
EMI Spring 2011 N/A Supplemental
None Approved Complete In-service 2/17/12 1/9/12 Complete Yes N/A
10-EMI-007-02-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Yazoo City Municipal
EMI Spring 2011 N/A Supplemental
None Approved Complete In-service 2/1/12 1/26/12 Complete Yes N/A
10-EMI-007-03-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Carthage
EMI Spring 2011 N/A Supplemental
None Approved Complete In-Service 1/11/12 12/8/11 Complete Yes
10-EMI-007-04-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Tylertown
EMI Spring 2011 N/A Supplemental
None Approved Complete In-Service 10/24/11 12/8/11 Complete Yes
10CP-EMI-007-05 Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Senatobia
EMI Spring 2011 N/A Supplemental
None Approved Complete In-Service 6/1/11 6/6/11 Complete Yes
10CP-EMI-007-06 Transmission Service Grand Gulf Uprate Project: Add vars to system Install a 115 kV, 21.6 MVAR capacitor bank at Plum Point
EMI Spring 2011 N/A Supplemental
None Approved Complete In-Service 6/1/11 6/6/11 Complete Yes
10-EMI-007-07-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Upgrade 21.6 MVAR capacitor bank at McComb to 32.4 MVAR.
EMI Spring 2011 N/A Supplemental
None Approved Complete In-service 12/19/11 1/30/12 Complete Yes N/A
10CP-EMI-007-08 Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Hernando into (2) 21 MVAR cap banks.\
EMI Spring 2011 N/A Supplemental
None Approved Complete In-Service 6/1/11 6/6/11 Complete Yes
10-EMI-007-09-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Hollandale into (2) 21 MVAR cap banks.
EMI Spring 2011 N/A Supplemental
None Approved Complete In-Service 10/28/11 11/30/11 Complete Yes
10-EMI-007-10-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Port Gibson into (2) 21 MVAR cap banks.
EMI Spring 2011 N/A Supplemental
None Approved Complete In-service 2/17/12 1/24/12 Complete Yes N/A
10-EMI-007-11-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Split existing 32.4 MVAR capacitor banks at Fayette into (2) 21 MVAR cap banks.
EMI Spring 2011 N/A Supplemental
None Approved Complete In-Service 2/17/12 12/16/11 Complete Yes
10-EMI-007-12-CP Transmission Service Grand Gulf Uprate Project: Add vars to system Install 115 kV, 32.4 MVAR capacitor bank at Magee.
EMI Spring 2011 N/A Supplemental
None Approved Complete In-Service 3/1/12 3/2/12 Complete Yes N/A
10CP-EMI-008 Transmission Reliability - Meeting Planning Criteria
Florence - Florence SS - Star 115 kV Line: Upgrade to at least 240 MVA
EMI Spring 2011 Spring 2011 None Approved Complete In-Service 1/31/11 4/7/11 Complete Yes
Page 11 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
10CP-EMI-009 Transmission Reliability - Meeting Planning Criteria
Waterways - Vicksburg East 115 kV Line: Upgrade to at least 240 MVA
EMI Summer 2011 Summer 2011 None Approved Complete In-Service 6/1/11 4/27/11 Complete Yes WTVICE_BAXXFWTVICE_GGFRAWAWVIC_RABBA
10CP-EMI-011-1 Transmission Reliability - Meeting Planning Criteria
McAdams Area Upgrades McAdams Substation: Add 2nd 560 MVA 500 kV / 230 kV Autotransformer (Hartburg Spare single phase units)
EMI Summer 2011 Summer 2013 Entergy before ICT Approved Complete In-Service 6/1/11 6/2/11 Complete Yes MCAD_LAKOV_D
10CP-EMI-011-2 Transmission Reliability - Meeting Planning Criteria
McAdams Area Upgrades McAdams - Pickens 230 kV line: Upgrade to Double-Bundled 954 ACSR (880 MVA)
EMI Summer 2011 Summer 2013 Entergy before ICT Approved Complete In-Service 6/1/11 5/18/11 Complete Yes MCAPIC_MCALA
10-EMI-012-1-CP Transmission Reliability - Meeting Planning Criteria
Ridgeland-Madison Reliability Improvement Rebuild Lakeover - Ridgeland Line
EMI Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 5/30/12 N/A Yes N/A
10-EMI-012-2-CP Transmission Reliability - Meeting Planning Criteria
Ridgeland-Madison Reliability Improvement Build Lakeover - Sunnybrook - Northpark 115 kV Line
EMI Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 5/30/12 N/A Yes N/A
10-EMI-013-CP Transmission Service Ouachita Transmission Service Move Sterlington 600 MVA auto to Baxter Wilson 500 (Second 500-115 kV auto)
EMI Summer 2012 N/A Supplemental
None Approved Complete In-Service 6/15/12 6/26/12 N/A Yes N/A
10-EMI-014-1-CP Transmission Reliability - Meeting Planning Criteria
Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 2 Projects Tillatoba to South Grenada 230 kV Line: Construct New 520 MVA Line
EMI Summer 2012 Summer 2012 None Approved Complete In-service 6/15/12 6/11/12 N/A Yes N/A
10-EMI-014-2-CP Transmission Reliability - Meeting Planning Criteria
Grenada/Winona/Greenwood Area Improvement (Tillatoba auto alternative): Phase 2 Projects South Grenada 115 kV Substation: Install 230 kV Bus and a 400 MVA 230-115 kV Autotransformer
EMI Summer 2012 Summer 2012 None Approved Complete In-service 6/15/12 6/11/12 N/A Yes N/A
10-EMI-017-01-CP Transmission Reliability - Meeting Planning Criteria
Ray Braswell to Spring Ridge Road 115kV line upgrade EMI Summer 2013 Summer 2013 Project identified as part of 10-EMI-017-CP requirements due to swapping of line bays
Approved Complete In-Service 6/1/13 5/16/13 Complete Yes
10-EMI-018-CP Transmission Reliability - Meeting Planning Criteria
Getwell to Church Road 230 kV construct new 230 kV Transmission Line
EMI Summer 2013 Summer 2013 None Approved Complete In-Service 6/1/13 5/10/13 Complete Yes N/A
10CP-EMI-020 Transmission Reliability - Meeting Planning Criteria
Ray Braswell to Clinton 115 kV line: Upgrade switch at Clinton and riser at Ray Braswell
EMI Summer 2011 Summer 2011 None Approved Complete In-Service Spring 2011 2/10/11 Complete Yes
10CP-EMI-021 Transmission Reliability - Meeting Planning Criteria
Clinton to Jackson NW 115 kV line: Upgrade switch at Clinton
EMI Summer 2011 Summer 2011 None Approved Complete In-Service Spring 2011 2/10/11 Complete Yes
11-EMI-001-CP Transmission Reliability - Meeting Planning Criteria
Rankin Industrial - Airport: Reconductor to bring complete line up to 1272 ACSR
EMI Winter 2011 Summer 2012 Entergy before ICT Approved Complete In-service 12/22/11 1/10/12 Complete Yes N/A
11CP-EMI-003 Transmission Reliability - Meeting Planning Criteria
Upgrade Terminal Equipment on Vicksburg - Waterway 115kV
EMI Summer 2011 Summer 2011 None Approved Complete In-service Summer 2011 1/24/11 Complete Yes
11-EMI-004-CP Transmission Reliability - Meeting Planning Criteria
Ray Braswell to West Jackson 115 kV line: Reconductor line
EMI Summer 2012 Summer 2013 Entergy before ICT Approved Complete In-Service 11/21/12. Final relay settings completed and installed March 2013. Line now up to full conductor rating.
Winter 2012 11/21/12 N/A Yes N/A
11CP-EMI-005 Transmission Reliability - Meeting Planning Criteria
Miami to Monument Street: Upgrade line trap at Monument Street
EMI Summer 2012 N/A Project recently added Approved Complete In-Service 6/1/11 5/26/11 Complete Yes
12-EMI-003-CP Transmission Reliability - Meeting Planning Criteria
Northeast Jackson to Klean Steel - Upgrade CT and Jumpers/Risers at NE Jackson
EMI Summer 2012 Summer 2012 None Approved Complete In-Service 6/1/12 12/7/11 Complete Yes N/A
13-EMI-004-CP Transmission Service SMEPA Plum Point Transmission Service: Horn Lake to Greenbrook 115 kV line: Upgrade station equipment at Horn Lake
EMI Summer 2013 N/A Supplemental
None Approved Complete In-Service Summer 2013 4/19/13 Complete Yes N/A
13-EMI-006-CP Enhanced Transmission Reliability
Bolton 115 kV Substation: Add 115 kV breakers EMI Summer 2013 N/A Supplemental
None Approved Complete In-Service Summer 2014 3/28/13 NA N/A (No model effect)
RBBOLT_BWXFM
10CP-ENO-001 Transmission Reliability - Meeting Planning Criteria
Paterson 115kV: Restore 4 breakers ENOI Summer 2009 Summer 2009 None Approved Complete In-service 1/29/09 Complete Yes
10CP-ETI-001 Transmission Reliability - Meeting Planning Criteria
Newton Bulk: Replace/Re-tap CT to increase rating on Holly Springs line
ETI Summer 2009 Summer 2009 None Approved Complete In-service Winter 2009 Complete Yes
10CP-ETI-002 Transmission Reliability - Meeting Planning Criteria
Beaumont 69 kV Improvement Plan: Option 2 ETI Summer 2009 Summer 2009 None Approved Complete In-service 6/19/09 Complete Yes
10CP-ETI-003 Generation Interconnection Sheco Jacinto - Generator Interconnection ETI Summer 2009 N/A Supplemental
None Approved Complete In-service 7/3/09 Complete Yes
10CP-ETI-004 Transmission Reliability - Meeting Planning Criteria
Gulfway 230 kV Substation Construct new Gulfway 230 kV Substation Cut new Substation into existing VFW to Kolbs 230 kV Line Construct new Sabine to Gulfway 230 kV line
ETI Fall 2009 Fall 2009 None Approved Complete In-service 10/13/09 Complete Yes
10CP-ETI-005 Transmission Reliability - Meeting Planning Criteria
Fawil: Upgrade 138/69 kV Auto ETI Winter 2009 Winter 2009 None Approved Complete In-service 1/23/10 Complete Yes
10CP-ETI-006 Transmission Reliability - Meeting Planning Criteria
Porter - Tamina: Replace Breaker/Switches ETI Summer 2009 Summer 2009 None Approved Complete In-service 10/22/09 Complete Yes
10CP-ETI-007 Enhanced Transmission Reliability
Warren Substation - Add two breakers ETI Winter 2009 N/A Supplemental
None Approved Complete In-service 1/2/08 Complete N/A (No model effect)
Page 12 of 13
Active Projects Based On:Report Date: July 1, 2013 Entergy 2013 - 2017 Final Construction Plan
Construction Plan ID Project Driver Project Name Operating
CompanyProposed ISD
(Planning)ICT Identified Need By Date Need by date difference
Project Funding Status
Project Status Project Status CommentsCurrent
Projected ISD
Actual ISD Mitigation Plan if requiredIncluded in AFC
Model? (Yes/No)
Flowgate(s) impacted
Monthly Construction Plan Project Status Report
10CP-ETI-008-1 Transmission Reliability - Meeting Planning Criteria
Temco and Shepherd 138 kV Substations - Upgrade CTs at Temco
ETI Summer 2010 Summer 2010 None Approved Complete In-service 9/30/10 10/26/10 Complete Yes
10CP-ETI-008-2 Transmission Reliability - Meeting Planning Criteria
Temco and Shepherd 138 kV Substations - Upgrade CTs at Shepherd
ETI Summer 2010 Summer 2010 None Approved Complete In-service 9/30/10 10/26/10 Complete Yes
10CP-ETI-009 Transmission Reliability - Meeting Planning Criteria
Western Region Reliability Improvement Plan Phase 3 Interim (Part 1) Relocate Sheco's Caney Creek 138 kV Substation
ETI Summer 2010 Summer 2010 None Approved Complete In-service 10/10/10 1/21/10 Complete Yes
10CP-ETI-010 Transmission Reliability - Meeting Planning Criteria
College Station 138kV Switching Station Construct new 3 terminal 138 kV Switching Station Close normally open switch at Speedway
ETI Spring 2011 2009 Requires installation of circuit breakers resulting in additional design and material lead time
Approved Complete In-service 12/31/10 11/29/10 Complete Yes
10CP-ETI-011 Transmission Reliability - Meeting Planning Criteria
Western Region Reliability Improvement Plan Phase 3 Interim (Part 3). Upgrade South Beaumont to Fontenot Corner 138 kV line
ETI Winter 2010 Winter 2010 None Approved Complete In-Service 4/21/11 5/24/11 Complete Yes
10CP-ETI-012 Transmission Reliability - Meeting Planning Criteria
Western Region Reliability Improvement Plan Phase 3 Interim (Part 2) Jacinto-Lewis Creek: Convert to 230 kV operation. Add 450 MVA 230-138 Auto at Lewis Creek
ETI Summer 2011 Summer 2011 None Approved Complete In-Service 2/25/11 3/2/11 Complete Yes
10-ETI-013-CP Transmission Service Grand Gulf Uprate Project Upgrade Hartburg to Inland Orange to McLewis 230 kV line
ETI Winter 2011 N/A Supplemental
None Approved Complete In-Service 12/16/11 12/28/11 Complete Yes HBIN_HBCYP
10-ETI-017-CP Transmission Reliability - Meeting Planning Criteria
Jasper to Rayburn 138 kV line: Upgrade ETI Summer 2013 Summer 2013 None Approved Complete In-Service 5/31/13 5/14/13 Complete Yes N/A
10CP-ETI-020 Transmission Reliability - Meeting Planning Criteria
Inland Orange to McLewis 230 kV line: Upgrade risers at Inland Orange and switch 22628 at McLewis
ETI Winter 2010 Winter 2010 None Approved Complete In-Service 4/23/11 5/11/11 Complete Yes
10CP-ETI-021 Transmission Reliability - Meeting Planning Criteria
Hartburg to Inland Orange 230 kV line: Upgrade risers at Inland Orange
ETI Winter 2010 Winter 2010 None Approved Complete In-service 12/16/11 2/18/11 Complete Yes
10-ETI-022-CP Transmission Reliability - Meeting Planning Criteria
McLewis to Helbig 230 kV line: Upgrade bus and switches 22627 & 22628 at McLewis
ETI Winter 2011 Summer 2012 Entergy before ICT Approved Complete In-service 12/16/11 1/4/12 Complete Yes N/A
10CP-ETI-023 Transmission Reliability - Meeting Planning Criteria
Sabine to Linde 138 kV line: Upgrade bus and risers at Sabine and Linde
ETI Winter 2010 Winter 2010 None Approved Complete In-Service Winter 2010 2/1/11 Complete Yes
10CP-ETI-024 Transmission Reliability - Meeting Planning Criteria
Sabine to Mid County 230 kV line: Upgrade bus and jumpers at Mid County
ETI Winter 2010 Winter 2010 None Approved Complete In-Service Winter 2010 11/22/10 Complete Yes
10CP-ETI-025 Transmission Reliability - Meeting Planning Criteria
Chem Rd to Dupont Sabine 3 138 kV line: Upgrade metering CT at Dupont Sabine
ETI Summer 2011 Summer 2011 None Approved Complete In-Service Summer 2011 3/7/11 Complete Yes
10CP-ETI-026 Transmission Reliability - Meeting Planning Criteria
Orange to Bunch Gully 138 kV line: Upgrade bus and risers at Orange
ETI Winter 2010 Winter 2010 None Approved Complete In-Service 5/20/11 5/25/11 Complete Yes
10-ETI-027-CP Transmission Reliability - Meeting Planning Criteria
Toledo Bend to Leesville 138 kV line: Upgrade CT at Toledo Bend
ETI Summer 2011 Summer 2011 None Approved Complete In-Service 12/15/11 12/1/11 Complete Yes
10-ETI-028-CP Transmission Reliability - Meeting Planning Criteria
Toledo Bend to Van Ply 138 kV line: Upgrade CT at Toledo Bend
ETI Summer 2011 Summer 2011 None Approved Complete In-Service 12/15/11 12/14/11 Complete Yes TBDVPL_MOHBG TOLVP_RODCOL
10CP-ETI-029 Transmission Reliability - Meeting Planning Criteria
Cypress to Lumberton 138 kV line: Upgrade bus at Lumberton and Cypress
ETI Summer 2011 Summer 2011 None Approved Complete In-Service 3/1/11 3/21/11 Complete Yes
10CP-ETI-030 Transmission Reliability - Meeting Planning Criteria
Goslin to Conroe Bulk 138 kV line: Upgrade bus differential at Conroe.
ETI Summer 2011 Summer 2011 None Approved Complete In-Service 5/13/11 5/26/11 Complete Yes
11CP-ETI-001 Transmission Reliability - Meeting Planning Criteria
Hearne to Calvert - Uprate 69 kV line ETI Summer 2011 Summer 2011 None Approved Complete In-Service 6/24/11 6/28/11 Complete Yes
11CP-ETI-004 Transmission Reliability - Meeting Planning Criteria
Elizabeth to Gallier - Uprate 69 kV line 2.5 miles ETI Summer 2012 Winter 2010 Construction feasibility. Approved Complete In-Service TBD 9/14/11 Complete Yes
11-ETI-006-CP Transmission Reliability - Meeting Planning Criteria
Somerville 69 kV: Expand capacitor bank ETI Summer 2012 Summer 2012 None Approved Complete In-Service 5/3/12 5/15/12 N/A Yes N/A
11CP-ETI-007 Transmission Reliability - Meeting Planning Criteria
Navasota to Magnolia Anderson 138kV: Upgrade relay CT
ETI Summer 2011 Summer 2011 None Approved Complete In-service 7/14/11 7/18/11 Complete Yes
11-ETI-008-CP Transmission Reliability - Meeting Planning Criteria
Cedar Hill to Plantation 138 kV line: Upgrade line conductor and station equipment at Plantation
ETI Summer 2013 Summer 2013 None Approved Complete In-Service 4/12/13 2/21/13 N/A Yes N/A
11-ETI-008-01-CP Transmission Reliability - Meeting Planning Criteria
Plantation to Conroe 138 kV line: Upgrade station equipment at Plantation
ETI Summer 2013 Summer 2013 None Approved Complete In-Service 4/12/13 4/4/13 Complete Yes N/A
11-ETI-009-CP Transmission Reliability - Meeting Planning Criteria
Toledo Bend to Leach 138 kV line: Upgrade station equipment at Toledo Bend
ETI Winter 2013 Winter 2013 None Approved Complete In-Service 12/15/11 11/28/11 Complete Yes LCHTOL_GRICR
11-ETI-010-CP Transmission Reliability - Meeting Planning Criteria
Leach to Newton Bulk 138 kV line: Upgrade terminal equipment at Newton Bulk
ETI Winter 2013 Summer 2014 Entergy before ICT Approved Complete In-Service 3/18/13 3/18/13 Complete Yes N/A
11CP-ETI-011 Transmission Reliability - Meeting Planning Criteria
Port Neches to Linde: Upgrade station equipment at Port Neches
ETI Summer 2011 Summer 2011 None Approved Complete In-Service 5/5/11 5/2/11 Complete Yes
11-ETI-020-CP Transmission Reliability - Meeting Planning Criteria
Hickory Ridge-Eastgate 138kV: Upgrade terminal equipment at Eastgate
ETI Summer 2016 Summer 2016 None Approved Complete In-Service 5/1/13 4/5/13 Complete Yes NA
11-ETI-036-CP Transmission Reliability - Meeting Planning Criteria
Plantation to Conroe 138 kV line: Reconductor Line ETI Summer 2013 Summer 2013 None Approved Complete In-Service 4/12/13 4/4/13 Complete Yes NA
11-ETI-041-CP Transmission Reliability - Meeting Planning Criteria
Eastgate to Dayton Bulk 138kV: Upgrade terminal equipment at Eastgate (formerly reconductor).
ETI Summer 2013 Summer 2016 Entergy before ICT Approved Complete In-Service 5/1/13 4/19/13 Complete Yes NA
11-ETI-043-CP Transmission Reliability - Meeting Planning Criteria
Expand Cap Bank at Calvert 69kV ETI Summer 2013 Summer 2013 None Approved Complete In-Service 6/1/13 5/8/13 Complete Yes NA
12-ETI-003-CP Transmission Reliability - Meeting Planning Criteria
Bentwater Substation: Add 138 kV Capacitor Bank ETI Summer 2013 Summer 2013 None Approved Complete In-Service 2013 Summer 5/1/13 Complete Yes NA
Page 13 of 13