MM VITAOILS SDN BHD: SHARING EXPERIENCE ON
CLEANER PRODUCTION PROJECT IMPLEMENTATION
DEPARTMENT OF ENVIRONMENT – UNIVERSITY OF MALAYA – MM VITAOILS
MM VITAOILS SDN BHD. LOT 3, PERSIARAN PERUSAHAAN,SECTION 23, 40300 SHAH ALAM, SELANGOR
CP COLLABORATION CEREMONY – DEMONSTRATION PROJECT
MM VITAOILS SDN BHD IS BEING
SELECTED AS A CLEANER
PRODUCTION IMPLEMENTATION DEMONSTRATION
PREMISE
FEB 22ND 2010
CP INTRODUCTION AND AWARENESS PROGRAMS
MARCH 2010
CLEANER PRODUCTION INTRODUCTION AND AWARENESS PROGRAMME WERE CONDUCTED AT MM VITAOILS PREMISE TO ALL STAFF
CP IMPLEMENTATION - ACTIVITIES
APRIL 2010
• AUDIT ACTIVITIES BY THE CONSULTANT
• BRAINSTORMING SESSION FOR CP PROJECT OPTION
CP AUDIT / PROJECT FINDINGS
TYPE OPTION IMPLEMENTATION TTL %1 ALREADY IMPLEMENTED BY MM VITAOILS 78 30.7
2 TO BE IMPLEMENTED BY MM VITAOILS IN < 3 MONTHS 23 9.1
3 TO BE IMPLEMENTED BY MMVITAOILS WITHIN 1 YEAR 7 2.8
4 TO BE IMPLEMENTED BY MMVITAOILS WITHIN 1 TO 3 YEARS 7 2.8
5 TO BE IMPLEMENTED BY MMVITOAILS IF FINANCE AVAILABLE 27 10.5
6 TO BE IMPLEMENTED BY/ WITH ASSISTANCE OF THE CONSULTANT
65 25.6
7 TO BE CONSIDERED BY THE COMPANY 47 18.5
TOTAL OPTION 254 100
NOTE : CATEGORY OF THE AUDIT WILL BE BASE BY 7 TYPES
MAY 2010
CP AUDIT IMPLEMENTATION
TANKS IS USED TO COLLECT RAIN WATER FOR THE FACTORY FLOOR CLEANING
USING SUFFICIENT LIGHTING DURING
DAY TIME
JUNE 2010
TRANSPARENT ROOFING IS USED
AT THE PRODUCTION AREA
CP PROJECT IMPLEMENTED
CP IMPROVEMENT # 1
TO INSTALL BYPASS PIPING AT THE CHILLING PROCESSBEFORENEED TO SWITCH ON FOR THE CHILLING PROCESS DURING PRODUCTION AFTERTHE NEW PIPING IS BY PASS THE CHILLING PROCESS AND DID NOT NEED TO SWITCH ON CHILLING PROCESS
CP PROJECT IMPLEMENTED
CP IMPROVEMENT NO # 2
TO CHANGE MANUAL TO AUTO PROCESS BY INSTALLATION OF PNUEMATIC CONTROL VALVE EQUIPMENTBEFORE: TIME SPENT FOR WALKING IS 5 MINUTES TO THE WORK PLACEAFTERELIMINATE TIME SPENT TO WALK FROM THE OPERATION ROOM TO THE WORK PLACE
CP PROJECT IMPLEMENTED
CP PROJECT 3 IMPROVE HOMOGENOUS CYCLE BYINCREASE PIPING DIAMETER FROM 1.5 INCH TO 2.0 INCH PER CYLE IS 20 MTBEFORE : 1 HR PER CYCLE FOR 20 MTAFTER : 45 MINUTES PER CYCLE
CP PROJECT IMPLEMENTED
CP PROJECT NO # 4TO IMPROVE PROCESS CYCLE FROM MANUAL HANDLING TO SEMI AUTOMATIC HANDLING
BEFORE PROCESS CYCLE IS TO SEAL CARTON BOX IS 30 SECONDS
AFTERPROCESS CYCLE IS TO SEAL CARTON IS 15 SECONDS
CP PROJECT IMPLEMENTED
CP PROJECT : PROJECT NO # 5
TO IMPROVE MOTOR AND PUMPS EFFICIENCY
BEFOREUSING THE PUMPS AND MOTOR WITH 80% EFFICIENCY
AFTERUSING THE PUMPS AND MOTOR WITH 90 % EFFICIENCY
CP INITIAL NOISE MONITORING
INTIAL NOISE MONITORING PROGRESS WHICH IT IS TO FULLFILL DEPARTMENT OF SAFETY AND HEALTH (DOSH) REQUIREMENT UNDER FACTORY AND MACHINERY ACT ( NOISE EXPOSE) REGULATION AT SEPT 2010
CP AUDIT RESULT
TYPE OPTION IMPLEMENTATIONBEFORE AFTER
TTL % TTL %
1 ALREADY IMPLEMENTED BY MMVITAOILS 78 30.7 95 37.4
2 TO BE IMPLEMENTED BY MMVITAOILS IN < 3 MONTHS 23 9.1 10 3.9
3 TO BE IMPLEMENTED BY MMVITAOILSWITHIN 1 YEAR 7 2.8 4 1.6
4 TO BE IMPLEMENTED BY MMVITAOILS WITHIN 1 – 3 YEARS 7 2.8 6 2.5
5 TO BE IMPLEMENTED BY MMVITAOILS IF FINANCE AVAILABLE 27 10.5 27 10.5
6 TO BE IMPLEMENTED BY ASISSTANT BY / WITH CONSULTANT 65 25.6 65 25.6
7 TO BE CONSIDERED BY THE COMPANY 47 18.5 47 18.5
TOTAL OPTION 254 100 254 100
Note: List of option based on 7 types
CP PROMOTION AT MM VITAOILS
CP TRAINING DEPARTMENT OF ENVIRONMENT CP TEAM OCT 2010
CP CONCLUSION
T H E I M P L E M E N TAT I O N O F T H E C P I S A " M I L E S T O N E " I N M A K I N G M M V I TA O I L S P L A N T I S M O R E E N V I R O N M E N TA L LY F R I E N D LY A N D A S A C O R P O R AT E S O C I A L R E S P O N S I B I L I T Y. W E A R E S AT I S F I E D W I T H T H E C O M M I T M E N T A N D C O O P E R AT I O N S H O W N B Y T H E D E PA R M E N T O F E N V I R O N M E N T A N D U P U M I N T H I S P R O G R A M . M M V I TA O I L S I S C O N V I N C E D T H AT T H E C O N C E P T O F C P I S I D E A L F O R M M V I TA O I L S A N D F O R T H E I N D U S T R A I L A C T I V I T I E S .
CP PRESENTATION
TERIMA KASIHQ & A