The Missing Links: Project Goals The goal of The Missing Links project was to reduce the amount of mis-sorted bags, track mis- sorts from tote audit forms, and add preventative measures to aid in the process such as wooden dividers between totes.

Missing Links QBR Slides

Embed Size (px)

Citation preview

Page 1: Missing Links QBR Slides

The Missing Links: Project Goals

The goal of The Missing Links project was to reduce the amount of mis-sorted bags, track mis-sorts from tote audit forms, and add preventative measures to aid in the process such as wooden dividers between totes.

Page 2: Missing Links QBR Slides

The Missing Links : Status

05/02/20232 McKesson Corporation Confidential and Proprietary

Team UpdateStatus: We are currently at a sort accuracy percentage of 99.7

Road Blocks: We noticed bags overlapping onto the next tray. We also have seen a large amount of side by side mis-sorts and bags coming from UU5/6.

Plan Implementation:We have added tray extensions or “flights” to every tray. We are also fabricating top divider pieces for each chute to prevent side by side drops. Lastly, we are tracking mis-sorts from UU5/6 and sending to GBI for analysis.

Page 3: Missing Links QBR Slides

•At the end of FY16, our sort accuracy was 99.77%. We will need to reduce the mis-sorts from UU5/6 and side by side drops to increase our accuracy percentage further.

99.7% Sort Accuracy

•Continue to keep a log of mis-sorts versus the total script volume daily and track mis-sorts to determine root cause.

Team Members

05/02/2023 McKesson Corporation Confidential and Proprietary3

The Missing Links: Bottom LineCurrent Results

Description

Tray “Flights”

Page 4: Missing Links QBR Slides

05/02/20234 McKesson Corporation Confidential and Proprietary

UpgradesAddition of Top Dividers and Install of Sensors on Closeout Chutes

Plans & Goals Results & Savings

Installing Top Dividers to Chutes in Closeout

GBI installing sensors to chutes and beacon lights to indicate sorting issues, eliminate unnecessary audits

Achieve sorting aaccuracy of 99.9%

Reduce staff from 8 associates to 3 working closeout on the night shift, potential savings of $260,000 (based on a “fully loaded” associate with beneifts at $25 per hour)

Dividers at top of chutes in tote closeout

Page 5: Missing Links QBR Slides

5

The Missing Links: Continued Success

Top Dividers •Being Installed December 2016

GBI Upgrades •Add beacon lights above each chute to

indicate sorting issues in early 2017