Mindalore Project Charter -Project Charter 15.09.2014

Embed Size (px)

DESCRIPTION

Project Charter

Citation preview

  • PREPARED FOR: WATER AND SANITATION, MOGALE CITY LOCAL MUNICIPALITY PO BOX 94 KRUGERSDORP, 1740 TEL: +27 (0)11 668 0724 FAX: +27 (086) 6922903

    PREPARED BY: MORAD CONSULTING (PTY) LTD 274 VOORTREKKER ROAD NOORDHEUWEL, 1739 TEL: +27 (0) 11 954 3835 FAX: +27 (0) 11 954 6565

    MOGALE CITY LOCAL MUNICIPALITY

    MINDALORE WATER PIPELINE REPLACEMENT, 22KM, 75MM, ASBESTOS CEMENT PROJECT

    PROJECT CHARTER/SCOPE BRIEF/BUSINESS PLAN

    SEPTEMBER 2014

    GAUTENG PROVINCE

  • Page 2 of 16

    Contents

    1. EXECUTIVE SUMMARY ........................................................................................................................ 4

    2. BACKGROUND AND PROBLEM STATEMENT .............................................................................. 5

    3. OUTLINE BUSINESS CASE ................................................................................................................. 5

    5. PROJECT SCOPE .................................................................................................................................. 6

    6. REGULATORY REQUIREMENTS ....................................................................................................... 7

    6.1 Environmental Impact Assessment .......................................................................................................... 7

    6.2 Geotechnical Studies ................................................................................................................................ 7

    7. CONSTRAINTS AND ASSUMPTIONS ............................................................................................... 7

    7.1 Physical Constraints .................................................................................................................................. 7

    7.2 Financial Constraints .......................................................................................................................... 7

    8. STAKEHOLDERS AND COMMUNICATION ..................................................................................... 8

    9. PROJECT MANAGEMENT TEAM STRUCTURE ............................................................................. 8

    10. PROJECT FINANCES ...................................................................................................................... 8

    11.1 Professional Fees .................................................................................................................................... 8

    11.2 Cost Estimate and Work Breakdown Structure .................................................................................... 10

    11.3 Cash Flow Projection ............................................................................................................................ 11

    11. PLACES OF WORK ......................................................................................................................... 11

    12. SITE CLEARANCE ........................................................................................................................... 11

    13. DELIVERABLES ............................................................................................................................... 12

    14. MILESTONES .................................................................................................................................... 12

    15. SUCCESS CRITERIA ....................................................................................................................... 12

    16. REPORTING REQUIREMENTS AND MEETING SCHEDULE ................................................. 13

    17. GUIDELINES AND STANDARDS .................................................................................................. 14

    18. QUALITY ASSURANCE AND CODE OF CONDUCT ................................................................ 14

    19. RISK MANAGEMENT ...................................................................................................................... 15

    20.1 Health and Safety Risks ........................................................................................................................ 15

    20.2 Financial Risks ....................................................................................................................................... 15

    20. PROJECT APPROVAL REQUIREMENTS ................................................................................... 15

    21. PROJECT SPONSOR ...................................................................................................................... 15

    22. ACCEPTANCE .................................................................................................................................. 16

  • Page 3 of 16

    Table of Tables

    Table 1: (Source: Extract from Mogale City Local Municipality Strategic Plan 2012-2017) ............................... 5

    Table 2: (Source: Extract from Mogale City Local Municipality Strategic Plan 2014-2018) ............................... 5

    Table 3: Project Management Team Structure .................................................................................................. 8

    Table 5: Professional Fees .................................................................................................................................. 9

    Table 6: Cost Estimate and Work Breakdown Structure .................................................................................. 10

    Table 7: Cash Flow Projection .......................................................................................................................... 11

    Table 8: Reporting Deliverables ....................................................................................................................... 12

    ANNEXURE A: Appointment Letter

    ANNEXURE B: Fee Proposal

    ANNEXURE C: Water Balance Results

    ANNEXURE D: Tables from MCLM Strategic Plan

  • Page 4 of 16

    1. EXECUTIVE SUMMARY

    MORAD Consulting Engineers was appointed by Mogale City Local Municipality for the

    Mindalore Water Pipeline Replacement Project. This Project Charter forms part the

    Consultants appointment and covers the strategy for the planning, designing, tender

    documentation and contract administration of the water pipelines replacement in

    Mindalore, Zone 24 as per the subject project requirements.

    Mogale City Local Municipality is experiencing unaccounted for water losses in most of

    its areas including Mindalore, zone 24. Morad did a water balance exercise in Mogale

    City to establishing extend of water loses. The results showed losses of up to 28.8%

    for the year 2011. The Municipalitys 2012-2017 and 2014-2018 strategic plans also

    indicate water losses of 31% and 33% respectively. The ultimate goal of Municipality

    strategic plan is to curb water losses to 15% at most.

    To achieve these strategic goals, Mogale City Local Municipality assigned Morad

    Consulting the Mindalore water pipeline replacement project.

    The project comprises of the elimination of the 110mm, 90mm and 75mm diameter

    class 9 asbestos cement lines and the installation of class 12, 420m of 200mm dia

    uPVC pipe, 390m of 160mm dia uPVC pipe, 4450m of 90mm uPVC pipe and

    13700m of 7 5 mm uPVC pipe on the Municipal servitude.

    The allocated budget for the project during this financial year is R7 652 173.00, all

    inclusive. Therefore, we recommend that the project be executed in phases, with the

    first phase having 750m of 90mm Dia uPVC and 2750m of 75mm uPVC pipes to be

    laid for about 200 stands. The total project cost estimate for the construction of this

    phase would be R6 272 681.29 including contingencies and VAT. The professional

    fees would be R1, 377,391.14 including VAT. The duration of the construction will be

    6 months.

  • Page 5 of 16

    2. BACKGROUND AND PROBLEM STATEMENT

    Morad undertook a water balance exercise in Mogale City with the view of establishing

    the extend of water loses in the area. The water balance results showed high water

    loses of up to 28.8% for the year 2011. The Municipalitys 2012-2017 strategic plan

    also showed that for the year 2011/2013, the losses had increased to about 31%.

    Furthermore, the 2014-2018 strategic plan indicates that the losses have further

    increased to 33% at this point in time. The results of the water balance exercise and

    the tables extracted from the Municipality strategic plans are attached in appendix C

    and appendix D respectively.

    Amongst other mitigation measures that could be done, Morad recommended pipe

    replacement of the old class 9 AC pipes with class 12 uPVC pipes.

    3. OUTLINE BUSINESS CASE

    According to the Municipalitys 2014-2018 strategic plan on how to ensure quality

    service delivery, at this point in time, Mogale City water los is sitting at 33%. The

    previous year it was sitting on 31%. This shows a gradual increase in water losses.

    The MCLM Strategic Plan, strategic goals for 2012-2017 and 2014-2018 are as

    follows;

    Strategic Objective

    Performance Indicator

    Requirement

    Baseline/Current

    Target 12/13

    Target 13/14

    Target 14/15

    Target 15/16

    Target 16/17

    Water (Urban and peri-urban)

    Potable water loss(%) (norm 15)

    15 31 25 20 18 15 15

    Table 1: (Source: Extract from Mogale City Local Municipality Strategic Plan 2012-2017)

    Strategic Objective

    Performance

    Indicator

    Requirement

    Baseline/Current

    Target 13/14

    Revised Target 13/14

    Target 14/15

    Target 15/16

    Target 16/17

    Target 17/18

    Water (Urban and peri-urban)

    Potable water loss(%) (norm 15)

    15 33 20 30 25 20 15 15

    Table 2: (Source: Extract from Mogale City Local Municipality Strategic Plan 2014-2018)

  • Page 6 of 16

    To achieve these strategic goals, Mogale City Local Municipality assigned Morad

    Consulting the Kagiso Ext 13 water pipeline replacement project in-order to assist in

    coming up with an engineering sound solution to curbing these water losses.

    4. PROJECT OBJECTIVES AND DESIRED OUTCOME

    The major objective of this project is to reduce the unaccounted for water losses

    in the Municipality. The desire outcome is to have a new distribution network with

    class 12 uPVC pipes replacing the class 9 AC pipes which are rotten and prone

    to bursting.

    The Municipality intends the project to be ready for tender within the current financial

    year ending June 2014.

    5. PROJECT SCOPE

    The project scope with regard to design and tender documentation is as follows;

    Conduct feasibility studies

    Prepare concept design report and drawings for the project.

    Do preliminary design for the water pipeline replacement.

    Preparation of a preliminary cost estimate for the project.

    Provide technical support to the Municipality regarding relevant studies.

    Prepare detail design report and drawings.

    Prepare detail cost estimate

    Prepare tender documents and drawings and assist with procurement.

    The project scope with regard to construction is as follows;

    Lay 750m of 90mm Dia class 12 uPVC and 2750m of 75mm class 12

    uPVC pipes.

    Install 45 isolation valves

    Install 22 pipe bends

    Install 1 reducer

  • Page 7 of 16

    Install 25 fire hydrants

    Provide about 123 house connection and accessories

    6. REGULATORY REQUIREMENTS

    6.1 Environmental Impact Assessment

    The project comprises of the replacement of the Asbestos cement pipelines with

    uPVC pipelines of the same diameter on the Municipal servitude.

    Since this project is not listed under the Environmental Impact Assessment

    Regulations Listing Notice 1 of 2010, there is no need to conduct an EIA.

    6.2 Geotechnical Studies

    No Geotechnical studies will be required for this pipe replacement project.

    7. CONSTRAINTS AND ASSUMPTIONS

    7.1 Physical Constraints

    The constraints and assumptions pertaining to this project area;

    It is assumed that the roads that will be crossed during laying of the pipes

    are municipal roads and that permission to cross will be obtained.

    7.2 Financial Constraints

    The allocated budget for the project during this financial year is R7 652

    1736.00, all inclusive. With this budget, only 750m of 90mm Dia uPVC and

    2750m of 75mm uPVC pipes can be laid for about 200 stands, instead of the

    required 2700m of 110mm uPVC pipe, 7780m of 90mm uPVC pipe and

    9120m of 75mm uPVC pipe. This means the project has to be done in phases

    with the first phase being funded by the R7, 652 173.00 available.

  • Page 8 of 16

    8. STAKEHOLDERS AND COMMUNICATION

    The distribution network will be owned by Mogale City Local Municipality

    (MCLM) and will be used to supply potable water to the consumers in the

    Mindalore zone 24 area. The reservoirs are owned by MCLM as well.

    Hence the stakeholders are the following:

    The community in the Mindalore zone 24 area, represented by the Ward

    Counsellors of the wards that fall wholly or partially within the supply zone

    of the reservoir.

    Mogale City Local Municipality, represented by the Municipal Manager,

    Mr Dan Mashitisho.

    9. PROJECT MANAGEMENT TEAM STRUCTURE

    Project Team Role Project Team

    Member(s) Organization Email

    Executive Manager: Infrastructure Services

    Mpako Dennis Mokotedi

    Mogale City Local Municipality

    Manager: Water & Sanitation

    Sandile Mbanjwa

    Mogale City Local Municipality

    [email protected]

    Project Executive Collin Radebe Morad Consulting [email protected]

    Project Engineer Michael Benhura

    Morad Consulting [email protected]

    Table 3: Project Management Team Structure

    Additional team members will be introduced as required for the successful completion

    of the project. Only skilled and experienced staff, professionally registered where

    appropriate, will be assigned to the project.

    10. PROJECT FINANCES

    11.1 Professional Fees

    As per Mogale City Local Municipality appointment letter to Morad Consulting

    Engineers, the appointment is in line with Morads existing Contract

    COO(PMU)01/2011 with Mogale City Local Municipality.

  • Page 9 of 16

    Fees will be calculated according to the fee scales agreed in the above contract, for

    the following stages as defined in the Engineering Professions Act (Act 46 of 2000):

    MOGALE CITY LOCAL MUNICIPALITY

    (B) PROFESSIONAL SERVICES PROVISION FEES MINDALORE ZONE 24

    1.0 PROFESSIONAL FEES

    ITEM DESCRIPTION % AMOUNT

    1.1 Inception 5 R 43,157.27

    1.2 Concept and Viability 25 R 215,786.34

    1.3 Design Development 25 R 215,786.34

    1.4 Documentation and Procurement 15 R 129,471.80

    1.5 Contract Administration and Inspection 25 R 215,786.34

    1.6 Close Out Report 5 R 43,157.27

    Sub-Total Excl. VAT (Professional Fees) 100 R 863,145.34

    2.0 ADDITIONAL FEES

    ITEM DESCRIPTION RATE QTY AMOUNT

    2.1 Survey R - 1 R -

    2.2 Geotechnical Investigation R - 1 R -

    2.2 Full Time Resident Engineer R 15,000.00 6 R 90,000.00

    Sub-Total Excl. VAT (Additional Fees) R 90,000.00

    3.0 DISBURSEMENTS

    ITEM DESCRIPTION RATE QTY AMOUNT

    3.1 Travelling R 5.72 3000 R 17,160.00

    3.2 Reporting R 1,500.00 8 R 12,000.00

    3.3 Health and Safety R 30,000.00 6 R 180,000.00

    3.4 Copies and Printing

    3.4.1. A4 Black and White R 0.93 8000 R 7,440.00

    3.4.2 A4 Colour Pages R 12.71 500 R 6,355.00

    3.4.3 A4 Typing R 47.67 500 R 23,835.00

    3.4.4 A3 Black and White R 1.79 20 R 35.80

    3.4.5 A3 Colour R 16.46 20 R 329.20

    3.4.6 A3 Typing R 47.67 10 R 476.70

    3.4.7. A4 Binding R 27.32 20 R 546.40

    3.4.8 A1 Printing R 86.43 80 R 6,914.40

    Sub-Total Excl. VAT (Disbursements) R 255,092.50

    TOTAL (Excl. 14% VAT) R 1,208,237.84

    Add 14% VAT R 169,153.30

    TOTAL (Incl. 14% VAT) R 1,377,391.14

    Table 4: Professional Fees

  • Page 10 of 16

    11.2 Cost Estimate and Work Breakdown Structure

    Description Cost

    Site Clearance R 283 500.00 Trench excavation

    R 2 306 560,00

    Provision for Pipe Bedding R 716 800.00 Supply and construction of 2750 meters long 75 mm uPVC pipelines and accessories.

    R 275 000.00

    Supply and construction of 750 meters long 90 mm uPVC pipelines and accessories.

    R 97 500.00

    Installation of 45 isolation valves R 96 000.00

    Installation of 22 bends R 7 890.00

    Installation of 15 tees R 16 850.00

    Installation of 1 reducer

    R 560.00

    Installation of 25 fire hydrants within the town, Installation of 39 thrust blocks

    R 191 700.00

    R1 305.00

    Provide approximately 122 house connections and accessories, R 286 955.00 Provision of connection to existing network, R 20 000.00

    Provisional amounts. R 543 5230.70

    Preliminary & Generals R 616 368.00

    Sub-Total 1 Cost Estimate for Construction Works R 5 268 718.70

    Allow for Contract Price Escalation to be claimed in accordance with the GCC 2010 (2nd Edition) Including Contingencies @5%

    R 263,435.94

    Total Cost Estimate for Construction Works (Excl. VAT) R 5 532 154.64

    Professional Fees Estimate, including Survey, Geo-tech, etc. R 1,208,237.84

    Total Project Cost Estimate (Excl. VAT) R6,740,392,48

    VAT R 906,773.92

    Total Project Cost Estimate (Incl. VAT) R 7,383,730.46

    Table 5: Cost Estimate and Work Breakdown Structure

  • Page 11 of 16

    11.3 Cash Flow Projection

    Period Payment Cumulative Total

    1ST Month 2014 R 172,197.50 R 172,197.50

    2nd Month 2014 R 319,795.35 R 491,992.85

    3rd Month 2014 R 196,797.14 R 688,789.98

    4th Month 2014 R 734,045.16 R 1,422,835.15

    5th Month 2014 R 756,845.16 R 2,179,680.31

    6th Month 2014 R 1,132,566.98 R 3,312,247.29

    7th Month 2014 R 1,171,070.65 R 4,483,317.94

    8th Month 2014 R 1,018,566.98 R 5,501,884.92

    9th Month 2014 R 1,189,088.79 R 6,690,973.71

    10th Month 2014 R 961,199.28 R 7,652,173.00

    Table 6: Cash Flow Projection

    11. PLACES OF WORK

    The planning, designing, tender document and preparation for the new business

    plan will be primarily carried out at the Morad Consulting Offices, at 274

    Voortrekker Road, Noordheuwel. Site visits will be done to the existing

    distribution network sites in Kagiso as necessary. Attendance of scheduled

    meetings will be done at the offices of MCLM. Meetings with relevant

    stakeholders like Rand Water and Johannesburg Water will be held at their

    respective offices.

    12. SITE CLEARANCE

    Clearance to proceed with construction will only be given when all required approvals

    and authorization have been obtained and all applicable environmental requirements

    have been satisfied. Land ownership and Surveyor-General boundaries will be

    confirmed where necessary.

    .

  • Page 12 of 16

    13. DELIVERABLES

    The project deliverables for this pipe replacement project are as follows;

    Laying of 750m of 90mm Dia class 12 uPVC and 2750m of 75mm class 12

    uPVC pipes.

    Installation of 45 isolation valves

    Installation of 22 pipe bends

    Installation of 1 reducer

    Installation of 25 fire hydrants

    Providing about 123 house connection and accessories

    Reporting as follows;

    Deliverable Status Importance

    Project Charter Finished Required

    Concept Design Report and Drawings Finished Required

    Preliminary Design Report and Drawings Finished Required

    Detail Design Report and Drawings Started Required

    Tender Documents and Drawings Started Required

    Table 7: Reporting Deliverables

    14. MILESTONES

    The main project milestone is the to complete the pipe replacement of the

    existing AC pipes with 750m of 90mm Dia class 12 uPVC and 2750m of 75mm

    class 12 uPVC pipes by the end of this current financial year with the allocated

    budget of R7 652 1736.00.

    15. SUCCESS CRITERIA

    The success of the project will be measured in terms of the following criteria:

  • Page 13 of 16

    Submission of a complete design, including design report, tender drawings and

    cost estimate.

    Submission of complete tender documents and drawings, based on a draft

    submitted to MCLM for comment.

    Submission of a Close Out Report

    16. REPORTING REQUIREMENTS AND MEETING SCHEDULE

    During the execution of the project, regular progress meetings shall be held between

    MCLM and Morad, to discuss progress and to ensure that the development of options

    and solutions remains aligned with the ultimate vision of MCLM for the water supply

    system as a whole.

    The provisional meeting schedule allows for the following meetings:

    One monthly meeting with the Executive Manager: Infrastructure Services and

    the Manager: Water & Sanitation.

    A biweekly meeting with the Manager: Water & Sanitation.

    Other staff shall attend the meeting when required by the Manager: Water & Sanitation.

    During the execution of the project, the following reports will be prepared and submitted

    Concept Design Report

    Preliminary Design Report

    Detail Design Report

    Monthly Technical Project Report

    Close-out Report

  • Page 14 of 16

    17. GUIDELINES AND STANDARDS

    The design criteria, materials and methods of shall be based on the following

    guidelines and standards:

    The National Housing Board's: "GUIDELINES FOR THE PROVISION OF

    ENGINEERING SERVICES FOR RESIDENTIAL TOWNSHIPS" Redbook

    All materials and methods of not specifically listed in these guidelines shall

    be in accordance with general methods of building as set out in the "SABS

    STANDARD SPECIFICATIONS, STANDARDISED SPECIFICATIONS and

    CODES OF PRACTICE" as applicable.

    The criteria and guidelines will be from GUIDELINES FOR HUMAN AND

    SETTLEMENT PLANNING AND DESIGN and DWAF GUIDELINES. The

    discussions will be based on actual field investigations, review of criteria

    related to the project and current design and technical manuals.

    Department of Water Affairs and Forestrys: TECHNICAL GUIDELINES FOR THE

    DEVELOPMENT OF WATER AND SANITATION INFRASTRUCTURE

    Gauteng Department of Agriculture and Rural Development GDARD

    GUIDELINES.

    Additional guidelines and standards will be consulted where required. In such cases

    Morad will ensure that only recognized local and international documents are used as

    the basis for any analysis or design.

    18. QUALITY ASSURANCE AND CODE OF CONDUCT

    Morads ISO 9001-accredited Quality Assurance procedures will be adhered to during

    the execution of the project.

    Morad project team members will at all times conduct themselves in a professional

    manner and act in accordance with the provisions of the Engineering Services Act (Act

    46 of 2000).

  • Page 15 of 16

    19. RISK MANAGEMENT

    20.1 Health and Safety Risks

    Since the construction will be taking place in a built up residential area, there are

    safety risks due to the presents of plant and other equipment. The contract needs to

    take serious safety measures so as to avoid causing any damage to property or

    people in the neighborhood.

    20.2 Financial Risks

    There is risk that the project might not get sufficient funding in the next financial year

    and this can prohibit the completion of the next phases after phase 1.

    20. PROJECT APPROVAL REQUIREMENTS

    All deliverables under this appointment will be submitted to the Manager: Water &

    Sanitation for approval.

    Each stage of the project shall be approved by the Manager: Water & Sanitation

    before the next stage is commenced.

    21. PROJECT SPONSOR

    The project sponsor is the Mogale City Municipality, represented by the Executive

    Manager: Infrastructure Services, Mr Mpako Dennis Mokotedi.

  • Page 16 of 16

    22. ACCEPTANCE

    This Project Charter prepared by Morad Consulting is based on the content of the

    appointment letter dated 19 November 2013.

    Prepared by: Approved and accepted by:

    Collin Radebe, Pr. Eng. Mr Sandile Mbanjwa

    Project Manager Manager: Water & Sanitation

    Morad Consulting Mogale City Local Municipality