VMI 1 1/16/2004 Presented by: Suryanarayana Murthy Teegela

Min Max Planning DEMO

Embed Size (px)

Citation preview

Page 1: Min Max Planning DEMO

 

VMI 11/16/2004Presented by: Suryanarayana Murthy Teegela

Page 2: Min Max Planning DEMO

Min-Max Planning 2

What is Min Max Planning?

specify minimum and maximum inventory levels for your items.

Minimum = “order point”.

Maximum = "order up to" .

When the inventory level for an item drops below the minimum, Oracle Inventory suggests a new purchase requisition or internal requisition to bring the balance back up to the maximum.

Page 3: Min Max Planning DEMO

Min-Max Planning 3

Purchase Requisition:- for Buy Items Item=Buy Source =Supplier Internal Requisition:- for Items Internal movements Item=Buy Source =Org/Subinventory

Inventory Level = (on-hand quantity) + (quantity on-order)

Where:On-Order Qty = open PO + Approved Requisitions

Page 4: Min Max Planning DEMO

Min-Max Planning 4

TIMING OF ORDERSInventory Level < minimum quantity

QUANTITY OF ORDERSOrder quantity = Maximum Qty – Inventory Level

Performed by running the Min-Max Planning report.Can perform at 2 levels:

Org Level : Uses item attribute planning modifiers

Subinventory Level : Uses values and parameters set at theitem/subinventory level.

Page 5: Min Max Planning DEMO

Min-Max Planning 5

SET UP

Item Attributes:Inventory ItemStockableTransactablePurchasedPurchasableList Price (if Buy item)Inventory Planning Method: Min-MaxMake or Buy: BuyMin-Max QuantityOrder QuantitySource: Supplier

Page 6: Min Max Planning DEMO

Min-Max Planning 6

Page 7: Min Max Planning DEMO

Min-Max Planning 7

Page 8: Min Max Planning DEMO

Min-Max Planning 8

Page 9: Min Max Planning DEMO

Min-Max Planning 9

Org Level Setup:In Item General Tab : EnterInventory Planning Method: Min-Max, Make or Buy: BuyMin-Max Quantity & Order QuantitySource Type : Supplier

Page 10: Min Max Planning DEMO

Min-Max Planning 10

Sub-Inventory Level Setup:

Values can be set using either the Subinventory Items or the Item/Subinventories windows:In Item General Tab : EnterInventory Planning Method: Min-Max, Make or Buy: BuyMin-Max Quantity & Order QuantitySource Type : Supplier

Go to Org Attributes in Organization AssignementGo to Tools: Item SubinventoriesMin Max Quantity set at Subinventory levelSourcing : Supplier

Note: Sub-Inventory Level setup overrides Org level controls of the item.

Page 11: Min Max Planning DEMO

Min-Max Planning 11

Page 12: Min Max Planning DEMO

Min-Max Planning 12

Page 13: Min Max Planning DEMO

Min-Max Planning 13

Page 14: Min Max Planning DEMO

Min-Max Planning 14

Min-Max Report:

Run Min-Max Report with following parameters:

Planning Level: Organization / SubinventorySubinventory: Select subinventory if planning level is subinventory

Item Selection: Items under min quantityItems: Select range of itemsDemand & Supply cut-off dates: default (system date) Restock: YES (creates purchase requisition)

Leave other parameters as their defaults

Page 15: Min Max Planning DEMO

Min-Max Planning 15

Page 16: Min Max Planning DEMO

Min-Max Planning 16

Page 17: Min Max Planning DEMO

Min-Max Planning 17

See the out put after report completed with normal

As parameter RESTOCK is set to ‘YES’ inventory creates Purchase Requisition in interface tables.

Open the view output of the completed report to see the details of replenishment of the item.

Minimum QuantityMaximum QuantityOn Hand QuantitySupply Quantity (Approved PRs + Purchased Orders)Available Quantity (On Hand quantity + Supply Quantity)Min Max Order QuantityReorder Quantity: Max Order quantity – Available Quantity

Page 18: Min Max Planning DEMO

Min-Max Planning 18

Page 19: Min Max Planning DEMO

Min-Max Planning 19

After PR is created and interfaced in Inventory, Go to Purchasing responsibility run request “REQUISITION IMPORT” with the following parameters:

Import Source: INV (Default)Group By: All (Default)Initiate Approval after ReqImport: Yes / NoYes indicates initiate approval process of sending PR for next level of approval.No Indicates won’t initiate approval process – User need to send it for approval manually.

Note: Request must run from purchasing user responsibility

Page 20: Min Max Planning DEMO

Min-Max Planning 20

Page 21: Min Max Planning DEMO

Min-Max Planning 21

After completion of request open the view output window to see the status of the Purchase Requisition.

Can see 2 kinds of messages1)Number of unapproved requisitions created = 1 2)Number of approved requisitions created = 1

Unapproved requisitions will be created if the user who imported requistion does not have sufficient approval limits.

Approved requisitions will be created if the user who imported requision does have sufficient approval limits.

These approval process will be initiated when ‘Initiate Approval after ReqImport’ Is set to ‘YES’ in parameter of ‘Requisition Import’ request.

Page 22: Min Max Planning DEMO

Min-Max Planning 22

Page 23: Min Max Planning DEMO

Min-Max Planning 23

After Requisition import is completed go to Requisition summary window to see the imported requisition.

Page 24: Min Max Planning DEMO

Min-Max Planning 24

Page 25: Min Max Planning DEMO

Min-Max Planning 25

“Purchase Requistions for re-orders are automatically created by the system on daily basis” can be achieved by using Concurrent Request scheduling process.

Schedule to run “Min-Max Report” on daily basis.

Submit Min-Max Report from SRS window and go to “Schedule” and select Run the job ‘Periodically’ to rerun every ‘1’ ‘day’ and enable check box of “increment date parameter each run” and submit the request.

Request will be scheduled to run every day with incremental data parameter, subsequently PRs will be created for reorder quantities of items under minimum quantity level.

Page 26: Min Max Planning DEMO

Min-Max Planning 26

Page 27: Min Max Planning DEMO

Min-Max Planning 27

After completion of scheduled Min-Max Report, schedule to run “Requisition Import” concurrent report.

Schedule to run “Requisition Import” on daily basis.

Submit Requisition Import Report from SRS window and go to “Schedule” and select Run the job ‘Periodically’ to rerun every ‘1’ ‘day’ and enable check box of “increment date parameter each run” and submit the request.

Request will be scheduled to run every day with incremental data parameter, subsequently PRs will be imported which are created against Min Max Report.

Page 28: Min Max Planning DEMO

Min-Max Planning 28

While scheduling the above reports optionally choose notification option to see the view outputs of the completed requests and their status.

Go to Options and select people under “Notify the following people”, it allows you to select N number of people for those you want to send the view outputs of these completed requests.

After completion of the request system will send a notification with URL to see the output of the completed request.

Page 29: Min Max Planning DEMO

Min-Max Planning 29

Page 30: Min Max Planning DEMO

Min-Max Planning 30

Page 31: Min Max Planning DEMO

Min-Max Planning 31

People under the ‘Notify the following people’ will receive a notification in their ‘Notification Summary’ after completion of every request.

Page 32: Min Max Planning DEMO

Min-Max Planning 32