India has states like Maharashtra, Gujarat and Karnataka, which have grown as fast as Asia's tiger economies during the past 10 years. It also has Bihar, with a population size of Germany's and a living standard at par with Burundi's.

While inequalities magnified inter-state competition seemed to have been intensified.

Page 3: Mauritius Ppt

3

CHALLENGES

Development of Bihar has been a matter of concern since independence.

Low Human Development Indices.

Problem areas are:-Stagnant Economic GrowthPersistent PovertyComplex Social StratificationVery poor infrastructure

Page 4: Mauritius Ppt

4

Public investment postulated to go up from Rs21,000 cr in 10th Plan to over Rs 58,000 crores in 11th Plan

Share of private investment in total investment postulated to go up from the present 59 % to 65 % - 10,08,000 cr.

State intends to attract large share of private investment and FDI

Strategy would be through Infrastructure Development as well as Investments in Social Services (Education, Health and Nutrition)

INVESTMENT

Page 5: Mauritius Ppt

5

Utilisation of idle capital assets. Efficient use of existing potential.Direct investment from Central Government.Initiatives in areas of strategic importance e.g., Infrastructure such as Road, Bridges, Power, Increased Agricultural Productivity, Water Management including Flood Control & Interlinking of Rivers. Policy Initiatives for increased Private Investment.

STRATEGY FOR 8.5% GROWTH

Page 6: Mauritius Ppt

6

Study by CRISIL pointed out that-

♦ Sector has grown at 0.38% in past 5 years Vs national avg. of 7.8%

♦ Investment flow is bleak

–Only 0.4% (Rs 7682 Cr) of proposed investments in India are planned in Bihar (Recent IEM Data)

BIHAR INDUSTRY:A RELATIVE ANALYSIS

35.07%

9.14%

55.80%

19.56%27.28%

53.16%

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

Agriculture Industry Services

Bihar India

Sector shares in economy – Bihar / India

70120170220270320370420

Bihar India

Manufacturing growth – Bihar / India2004-05

1993-94

1993

-94

1994

-95

1995

-96

1996

-97

1997

-98

1998

-99

2001

-02

2002

-03

2003

-04

2004

-05

1999

-00

2000

-01

Page 7: Mauritius Ppt

7

Value Addition Potential

Food Processing

Leather

Drugs & Pharmaceuticals

Textile

Downstream petrochemicals engineering.

Access to market.

Out migration of skilled and un-skilled labours.

STRENGTHENING OF INDUSTRY SECTOR

Page 8: Mauritius Ppt

8

Major impediments to investmentAbsence of long term policies, non implementation/ reversal of policy and approach of contract.

Inflexibility of labour laws.

Poor infrastructure – Government has already initiated steps to remove impediments. They are:-

Creation of enabling environment, legislative action, administrative reforms.

Improvement in public delivery system.

INVESTMENT CLIMATE

Page 9: Mauritius Ppt

9

Bihar Single Window Clearance Act-2006

Bihar Infrastructure Development Enabling Act 2006.

New Industrial Policy -2006

Price Preference Policy- 2006

New Policy Initiatives for Entertainment, Tea Processing and Sugar Sectors - 2006.

Amendment of Sugarcane Act 1985 to provide for other products from sugarcane apart from sugar.

Policy for establishing higher Technical Institutions in Private Sector - 2006.

Simplification of VAT Regime - 2006.

RECENT POLICY INITIATIVES

Page 10: Mauritius Ppt

10

BIHAR SINGLE WINDOW CLEARANCE ACT, 2006

Provides for speedy processing of clearance and certificate.For promotion of all-round development of the State and the Industrial Development.Provides for investors’ friendly environmentUnder the Act, Section 5 provides for State Investment Promotion Board as an Empowered Committee.

Page 11: Mauritius Ppt

11

RECENT INITIATIVES

BIHAR FOUNDATION CONSTITUTED AND REGISTERED WITH CM BIHAR AS PATRON

TO ACT AS A FORUM BETWEEN NRBs AND THE STATE

TO FACILITATE DEVELOPMENT OF THE STATE WITH BIHARI DIASPORA’S PARTICIPATION

TO OPEN LOCAL CHAPTERS OUTSIDE AND WITHIN THE COUNTRY

TO PROVIDE INPUTS AND SUGGESTIONS FOR DEVELOPMENT OF THE STATE

Page 12: Mauritius Ppt

12

STATUS OF CLEARANCE GIVEN BY THE BOARD

89Total6Others18Technical Institutions65Industrial Units

Proposals consist of 4.

85790Direct employment possibilities in the proposals cleared

3.

Rs.36323.496 crore

Investment involved2.89Total proposals cleared1.

Page 13: Mauritius Ppt

13

4- Cement Plants 3

Out of the above:-1- New Sugar Mills 21

2- Mega Projects 143- Expansion of existing Sugar Mills (7 + 2)9

& addition of Ethanol Plant Proposals

5- Power Projects 3

6- Jute Mill 2

7- Handloom Park 1

8- Textile Park 1

9- Tractor Projects 1

10-Mini Steel Plant 1

Page 14: Mauritius Ppt

14

CEMENT PLANTS3 proposals have been cleared.

M/s Century Plywood – Kahalgaon

M/s Ambuja Cements Ltd. – Pandarak

Birla Corporation Ltd., Barh

M/s Century Ply Wood has been allotted land at Kahalgaon

M/s Ambuja Cement has been arranged own land at Pandarak.

M/s Birla Corporation Ltd. Would arrange own land at Barh.

Page 15: Mauritius Ppt

15

POWER PROJECTSProposals received from

1. M/s Vikas Metals & Power Ltd.2 X 250 MW (Begusarai)

2. M/s Century Plywood2 X 250 MW (Kahalgaon)

3. M/s J.A.S. Infrastructure1215 MW (Banka)

The allotment of coal block is yet to be done by Govt. of India.

Page 16: Mauritius Ppt

16

JUTE MILL

M/s Bengali Jute Twine Ltd is establishing unit in Begusarai at an estimated cost of Rs 8.00 crore.

Land has already been allotted.

Civil work has start.

M/s Rameshwar Jute Mill is going to establish a jute mill in Kishanganj.

Land is yet to be identified by the proposers.

Page 17: Mauritius Ppt

17

TEXTILE PARK /HANDLOOM PARK

Handloom Park at an estimated cost of Rs. 25 cr. is being established at Bhagalpur, Biharsharifand 5 other places.

Special Purpose Vehicle has been constituted at Bhagalpur for this purpose.

Land has been identified.

Textile Park at Kahalgaon, Bhagalpur at an est4imated cost of 120 cr. Is under implementation.

Special Purpose Vehicle has been formed. Land has been identified.

Page 18: Mauritius Ppt

18

HIGHER TECHNICAL INSTITUTIONS

18 proposals have been cleared, which

include 3 Medical college cum Super

Speciality Hospital, Engineering

Colleges, Management Institutes.

Communication Institutes and

Entrepreneurs Training Institute.

Page 19: Mauritius Ppt

19

SMALL SCALE & TINY SECTOR

Total registered units in the year 2006-07SSI units 22Tiny units 3419Total Investment Rs. 7243.07

(4697.31)*Total Employment 16578

(15732)*

Page 20: Mauritius Ppt

20

SUGAR MILLS

21 proposals were cleared, but only M/s P & M Infrastructure Pvt. Ltd. have laid the foundation at Guruwalia.Another mill at Saharsa by the same company will come up shortly.Rest have delayed the implementation on account of fall in sugar price.

Page 21: Mauritius Ppt

21

M/s Suprabhatam Sugar Industries Pvt. Ltd. is sanctioning up a sugar mill at Patna, Naubatpur.

Land has been identified and farmers are transferring the land voluntarily.

Civil works likely to start from August.

Page 22: Mauritius Ppt

22

PROJECTS UNDER FOOD PROCESSING

Total project cost - Rs.1,670 crore

Total period - 5 years

IL&FS appointed as Project Management Agency.

In the first phase, Integrated Food Zone, Rural Agri Business Centre/Primary Processing Centre, Air Cargo Complex, Quality Assurance Centre with R & D facilities and development of rice mills cluster will be taken up.

Page 23: Mauritius Ppt

23

HANDLOOM PROJECTS

Total Project cost around Rs.68 crore

Project duration – 2 years

IL&FS appointed as a Project Management Agency.

Page 24: Mauritius Ppt

24

Salient features of the project

Textile Park

Handloom Park

Privatisation of 3 cooperative spinning mills and dyeing and processing plants.

Up gradation of training institutions.

Designing and product development.

HANDLOOM PROJECTS

Page 25: Mauritius Ppt

25

ETHANOL PLANTS

4 Ethanol plants from Maize at Hajipur, Begusarai, Khagaria and Bhagalpur.

10 plants for Ethanol from Sugarcane juice at Araria, Katihar, Bhagalpur, Jamui, Munger, Nalanda Aurangabad, Rohtas and Buxor.

The total investment is around 4.00 billion USD.

The firms has signed up the non disclosure and other legal agreements.

Page 26: Mauritius Ppt

26

Financial closure with Malaysian and other investors has been achieved. Mukherjee & Associates, Pune has been appointed as Engineering Consultant.ICAR would give consultancy for sugarcane cultivation.M/s Fleck from Austria is the coordinator for supply of Plant & Machinery from Europe Commitment charges to suppliers of plant & machinery already sent.The team would be positioned at the end of August and civil work likely to start in September.

Page 27: Mauritius Ppt

27

INITIATIVES IN LEATHER SECTOR

Bihar is a major producer of good quality hides and skins.

Bihar ranks 3rd in production of hides and skins in the country. Produces 2.64 million bovine hides per annum.

Square shaped goat hide is world famous for its quality.

Acute shortage of trained manpower in footwear industry.

Page 28: Mauritius Ppt

28

INITIAVES IN LEATHER SECTOR

State Govt. approached Ministry of Commerce, Govt. of India for establishment of Footwear Design & Dev. Institute in Bihar.

Report on potential of leather industry in Bihar has been prepared by CLRI.

CLRI is also making project report for establishment of CETP at Muzaffarpur.

A meeting is fixed on 21.07.2007 at Kanpur with leather industry Association.

Page 29: Mauritius Ppt

29

REVIVAL OF THE CLOSED UNITS OF THE SUGAR CORPORATION LTD.

SBI Caps have submitted the diagnostic study report.

Only 8 out of 17 units are viable for revival.

In other cases, sale of assets for other industrial purposes is to be suggested.

Cabinet approval is being taken.

Page 30: Mauritius Ppt

30

CEMENT PLANTSThere are three proposals cleared by the State Investment Promotion Board.(i) M/s Century Plywood at Kahalgaon

1 M.T.

(ii) M/s Ambuja Cements at Pandarak near Barh 1 M.T.

(iii) M/s Birla Cement Plant at Barh 1 M.T.

Agreement for supply of fly ash on long term basis to the proposed cement units are yet to be signed by NTPC with the Investors.

Page 31: Mauritius Ppt

31

PRIVATISATION OF THE BIHAR SUGAR CORPORATION

15 Sugar Mills and 2 Distilleries closed for more than 10 years.

Diagnostic Study Report by SBI Capital Market has been submitted.

Revival of 8 units for setting up sugar complex and disposal of the remaining for other industrial purposes are being taken up.

Page 32: Mauritius Ppt

32

INVESTMENT SCOPE

MAURITIAN INVESTORS CAN FOCUS ON

- SUGAR & ETHANOL

- FOOD-PROCESSING SECTOR

- HANDLOOM & TEXTILES

- PHARMA

- LEATHER

- TOURISM

- PPP PROJECTS ON INFRASTRUCTURE

Page 33: Mauritius Ppt

33

ROAD CONSTRUCTION

DEPARTMENT

Page 34: Mauritius Ppt

34

INFRASTRUCTURE - ROADS

The State has

3629 Kms of National Highways

3232 Kms of State Highways

7714 Kms of Major District Roads

In three years the State will have Road Infrastructure which will rival the best in the country

Page 35: Mauritius Ppt

35

National Highways

2123 Kms being 4- laned - 1608 Kmsunder NHDP, 245 Kms under Buddhist Circuit Project & 270 Kms on BOT basis

(MAP)

INFRASTRUCTURE – ROADS

Page 36: Mauritius Ppt

36

State HighwaysAll State Highways being 2-laned– 2035 Km under RSVY & 927 Km with assistance from ADB.162 Kms being 4-laned on BOT basis.

Major District Roads: - 7714 Kms

4500 Kms taken up in 06-07 for widening and strengthening – in various stages of completion.

2000 Kms being taken up this year.

INFRASTRUCTURE – ROADS

Page 37: Mauritius Ppt

37

Quantum Jump

As against an average outlay of 40-50 Crores per year for roads under Plan outlay for 06-07 was 600 Crores. This financial year outlay is 922 Crores for roads alone. This does not include the allocation for State Highways under which the expected expenditure during this year is approx. 1000 Crores.

INFRASTRUCTURE – ROADS

Page 38: Mauritius Ppt

38

Page 39: Mauritius Ppt

39

HEALTH

Page 40: Mauritius Ppt

40

To Raise the Infrastructure and

Services in Health Sector to Indian

Public Health Standard

GOAL

Page 41: Mauritius Ppt

41

STRENGTHENING HEALTH INFRASTRUCTURE

1553 per year for 3

years7517765881516580HSC5

331 per year for 3

years30812361544APHC4

201533533PHC to be

converted inCHC

3

207922101Sub DivisionalHospital2

11112538District Hospital1

Plan

Work Already taken

up

No. to be

created Existing No. as per

the IPHS

Name of theHealth

Facilities

Sl.No.

Page 42: Mauritius Ppt

42

Healthcare Services in the District Hospitals

Ancillary and Support Services:Medico-legal/postmortemAmbulance servicesDietary servicesLaundry servicesSecurity servicesWaste managementCounseling Services Warehousing/Central StoreMaintenance and repairElectric & Water Supply AC &Heating TransportCommunicationMedical Social WorkNursing ServicesSterilization DisinfectionHorticulture Lift and vertical transportRefrigeration

Diagnostic and Para Clinical Services:Laboratory servicesImaging servicesCT Scan servicesSonographyECGEEGEchocardiogramPathologyBlood BankPhysiotherapyDental Technology Drugs and Pharmacy

OPD ServicesIndoor Services, Emergency services

General MedicineGeneral SurgeryO&G servicesPaediatrics &NeonatologyCasualtyCritical Care (ICU)AnesthesiaOphthalmologyENTSkin & VD/ RTI/STIOrthopaedicsRadiology & UltrasonographyRadiotherapyDental carePublic Health Management

Page 43: Mauritius Ppt

43

No. of Patients Visited per Govt. Hospital per Month

39

653

1018 11

01 1306 15

47

2758

3063

2685

2454 26

38

2565

2243

2224

2257

2120

2784

3508

0

500

1000

1500

2000

2500

3000

3500

4000

Jan.

, 06

Feb.

, 06

Mar

ch, 0

6

April

, 06

May

, 06

June

, 06

July

, 06

Augu

st, 0

6

Sep.

, 06

Oct

., 06

Nov.

, 06

Dec.

, 06

Jan.

, 07

Feb.

, 07

Mar

ch, 0

7

April

, 07

May

, 07

June

, 07

Months

Num

bers

Page 44: Mauritius Ppt

44

EDUCATION

Page 45: Mauritius Ppt

45

New teacher recruitment policy and rules: no contract or para-teachers – over 1,20,000 school teachers appointed through Panchayati RajInstituions (PRI)15 000 New Schools: learning centers abolished and 15000 new schools established – building const going on.Mukhyamantri Samgra Vidyalaya VikashKarykram : Not add a classroom, make a school-Integrated development of school: provision of boundary walls, major renovations, kitchen shed etc, games including children’s educational excursion and other facilities

RECENT MAJOR INITIATIVES

Page 46: Mauritius Ppt

46

Free uniform and bicycles: All girls of 6-8 to get free uniform and of class 9-10 bicycles-enhance girls’ participation and reduce gender gaps Mid-day Meals: State share for cooking meals increased from Rs. 0.64 to Rs. 1.00, being given to mothers’ committees and SHG under overall VSS supervisionTeachers grievances and disengagement from non-teaching activities: A series of steps to enhance teacher’s morale and enhance teaching time

RECENT MAJOR INITIATIVES

Page 47: Mauritius Ppt

47

Establishment of new Institutions in HE: Chankya National Law University, BIT Extn. Campus established.

New Institutions coming up: National level management institute on the IIM pattern, Aryabahtta Professional University, University of Nalanda

Page 48: Mauritius Ppt

48

PANCHAYATI

RAJ

Page 49: Mauritius Ppt

49

Empowerment of women and other disadvantaged sections of the society through affirmative action.Promotion of participation of the general masses through a mandatory quorum system for Gram Sabha meetings.Ppromotion of accountability and supervision in the functioning of the PRIs through ‘Social Audit’ and formation of Vigilance Committees.Grant of ‘Public Servant’ status to enhance the accountability of the elected PRI representatives.Gram Katchhary – Speedy, cheap and accessible, justice delivery system at door steps to function with the help of Nyayamitras

Enactment of Bihar Panchayat Raj Act, 2006ACHIEVEMENTS

Page 50: Mauritius Ppt

50

Of the 2,53,260 elected representatives of PRIs, 1,30,031 are women.

Incident free General Panchyat Election,06 held by SEC

50% reservation for women and nomination of members of SC, ST & OBC (in case of non-representation) in DPCs

Successful conduct of election to DPCs by SEC

Achievements……..

Activity Mapping; 29 subjects, 20 line departments have been completed.

Devolution and Decentralization

Page 51: Mauritius Ppt

51

A number of rules have been framed since the enactment of Bihar PanchayatRaj Act, 2006 for the smooth functioning of the PRIs.

Framing of Rules

Achievements……..

Page 52: Mauritius Ppt

52

To enable service delivery through CSC kiosks; creation of Panchayat Portal for easy transfer and access to data; creation of MIS & application of Plan plus for Planning

A project based on ‘PRIYASOFT’ for accounting has been submitted to GOI for approval.

Installation of E-governance, new Financial Management System and MIS

Linkage of bank accounts of PRIs through core banking system.

Simple, easy, transparent and equalising transfer system of funds

Page 53: Mauritius Ppt

53

ENERGY

Page 54: Mauritius Ppt

54

Negotiations on with NTPC to hand over distribution of Patna and Bhagalpur towns. NTPC to start due diligence soon.

Revenue based franchise system already introduced in 158 feeders in rural and urban areas. Revenue increased upto 200% in many feeders.

Improved resource mobilization. Revenue collection increased from Rs. 65 crores per month (2005-06) to Rs. 85 crores (2006-07). Rs. > 100 crores in last 3 months.

Bring down AT&C by 3% p.a. in the next five years.

POWER REFORMS

Page 55: Mauritius Ppt

55

Current installed capacity of 587 MW insufficient Expansion of Barauni and Kanti Thermal Power Stations by adding 500 MW each.Setting up of new power plant under joint venture with NTPC at Nabinagar (3x660 MW). New Hydro Power plant proposed at Dagmara(126MW)Shell company under joint venture with IL&FS to develop new sites at Katihar and Pirpainti (to be handed over through competitive bidding).Nuclear Power Corporation team visited Rajauli for setting up of a Nuclear Power Plant of 1000 MW. NPC to expedite the workCoal blocks/linkages needed for the new projects

CAPACITY ADDITION IN GENERATION

Page 56: Mauritius Ppt

56

Rural Works Department

Page 57: Mauritius Ppt

57

VisionTo provide all weather rural road connectivity to all habitations by construction of remaining 33525 km of link routes and upgradation of 4227 km of through routes requiring about 15000 cr and maintenance of total constructed roads requiring 400 Crore per Year (on average basis for routine maintenance).

Achievement during 2006-07Completed 1251.35 km under State Plan and 1256 km under PMGSY (including NEAs part) with total expenditure of 152294 lac.

Rural Works Department

Page 58: Mauritius Ppt

58

Initiatives undertaken

Mukhya Mantri Gram Sadak Yojana for providing connectivity to 500-999 population.

Strengthening of BRRDA .

Dedicated PIUs for implementation of Bharat Nirman Yojana.

Strengthening of Quality Control Mechanism

Updation of Core Network.

Outsourcing of Process Management with DPR Preparation to IL&FS.