24
MONASTERY, ECOHOTEL, BIOTECH LAB Kelley’s Island, OH Construction II Winter 2009 Sophia Chang

Man-Made Naturally

Embed Size (px)

DESCRIPTION

Continuing exploration of the impact of the Michigan Building Code on design for UG3 studio project at TCAUP. Final Construction Documents.

Citation preview

Page 1: Man-Made Naturally

MONASTERY, ECOHOTEL, BIOTECH LABKelley’s Island, OH

Construction IIWinter 2009

Sophia Chang

Page 2: Man-Made Naturally

OCCUPANCY

EGRESS

COST

STRUCTURE

BUILDING SERVICES

HVAC

ENCLOSURE

First Floor OccupancyBasement Occupancy

Lower Basement Occupancy

First Floor EgressBasement Egress

Lower Basement EgressEgress Diagram

Cafeteria Cost AnalysisLaboratory Cost Analysis

Library Cost AnalysisRestaurant Cost Analysis

Suites Cost AnalysisOverall Cost Analysis

Basement Framing PlanStructural Section

Axonometric Force Diagram

SystemsBathroom Plan

HVAC

Detailed SectionDetailed Elevation

Enclosure Diagram

1.011.021.03

2.012.022.032.04

3.013.023.033.043.053.06

4.014.024.03

5.015.02

6.01

7.017.027.03

TABLE OF CONTENTS

Page 3: Man-Made Naturally

01.01

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/10/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Occ

upan

cyCo

mplex

Firs

t Floo

r / 1/

48” =

1’

A1A2A3BR1

R2

100 gross

100 gross200 gross

2. Offices1. Suites

51 ft sq ea.76 ft sq ea.

1 person

4. Storage300 gross(incidental) 194 ft sq ea. 1 person

1 person3. Offices/Suites 51 ft sq ea. 1 person

1 2 3

4 Hour Fire Rating3 Hour Fire Rating2 Hour Fire Rating1 Hour Fire Rating

US2

4

4

Page 4: Man-Made Naturally

A1A2

A3

BR1

R2

200 gross

100 gross100 gross

15 net

100 gross200 gross

(Incidental)

200 gross 4 Hour Fire Rating3 Hour Fire Rating2 Hour Fire Rating1 Hour Fire Rating

4. Kitchen

7. Stacks8. Stacks/Reading Area

5. Restaurant

9. Biotech Laboratory1. Suites

2. Cells

782 ft sq

605 ft sq1601 ft sq

2330 ft sq

10,024 ft sq112 ft sq ea.

112 ft sq ea.

3 people

U

300 gross 10. Laundry Room 351 ft sq 1 person

6 people16 people

155 people6. Cafe 605 ft sq 40 people

100 people1 person

3. Suites/Cells 112 ft sq ea. 1 person

1 person

S2

01.02

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/14/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Occ

upan

cyCo

mplex

Bas

emen

t / 1/4

8” =

1’

1

10

10

2 3

4

9

5 6 7 8

Page 5: Man-Made Naturally

01.03

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/14/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Occ

upan

cyCo

mplex

Sec

ond B

asem

ent /

1/48”

= 1’

A1A2

A3BR1R2

15 net

100 gross

200 gross

100 gross

1. Cafeteria

4. Stacks/Reading Area

2. Kitchen

5. Biotech Laboratory

1311 ft sq

1601 ft sq

782 ft sq

10,024 ft sq

87 people

16 people15 net 3. Restaurant 2330 ft sq 155 people

3 people

100 people

1

2

5

43

4 Hour Fire Rating3 Hour Fire Rating2 Hour Fire Rating1 Hour Fire Rating

US2

Page 6: Man-Made Naturally

02.01

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/10/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Egr

ess

Comp

lex F

irst F

loor /

1/48

” = 1’

A1A2A3BR1

R2

100 gross

100 gross200 gross

2. Offices1. Suites

51 ft sq ea.76 ft sq ea.

1 person

4. Storage300 gross(incidental) 194 ft sq ea. 1 person

1 person3. Offices/Suites 51 ft sq ea. 1 person

1 2 3

US2

4

4

1 exit min.

1 exit min.1 exit min.1 exit min.

1 exit actual

1 exit actual1 exit actual1 exit actual

longest egress route (71 ft)

longest common egress route (71 ft)

Page 7: Man-Made Naturally

A1A2

A3

BR1

R2

200 gross

100 gross100 gross

15 net

100 gross200 gross

(Incidental)

200 gross

4. Kitchen

7. Stacks8. Stacks/Reading Area

5. Restaurant

9. Biotech Laboratory1. Suites

2. Cells

782 ft sq

605 ft sq1601 ft sq

2330 ft sq

10,024 ft sq112 ft sq ea.

112 ft sq ea.

3 people

U

300 gross 10. Laundry Room 351 ft sq 1 person

6 people16 people

155 people6. Cafe 605 ft sq 40 people

100 people1 person

3. Suites/Cells 112 ft sq ea. 1 person

1 person

S2

02.02

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/14/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Egr

ess

Comp

lex B

asem

ent /

1/48”

= 1’

1

10

10

2 3

4

9

5 6 7 8

1 exit min.

1 exit min.

1 exit min.1 exit min.

2 exits min.1 exit min.

2 exits min.1 exit min.1 exit min.

1 exit min.

1 exit actual

1 exit actual

2 exits actual3 exits actual

3 exits actual2 exits actual

3 exits actual1 exit actual1 exit actual

1 exit actual

longest common egress route (40 ft)

longest egress route (71 ft)

Page 8: Man-Made Naturally

02.03

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/14/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Egr

ess

Comp

lex S

econ

d Bas

emen

t / 1/4

8” =

1’

A1A2

A3BR1R2

15 net

100 gross

200 gross

100 gross

1. Cafeteria

4. Stacks/Reading Area

2. Kitchen

5. Biotech Laboratory

1311 ft sq

1601 ft sq

782 ft sq

10,024 ft sq

87 people

16 people15 net 3. Restaurant 2330 ft sq 155 people

3 people

100 people

2 exits min.

1 exit min. 2 exits min.1 exit min.

2 exits min.

2 exits actual

3 exits actual 3 exits actual1 exit actual

3 exits actual

1

2

5

43

US2

longest egress route (175 ft)

longest common egress route (52 ft)

Page 9: Man-Made Naturally

02.04

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/18/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Egr

ess

Comp

lex A

xono

metric

longest egress route (175 ft)

longest common egress route (71 ft)

Page 10: Man-Made Naturally

% of Total

Cost Per S.F. Cost

6.20% $19.20 $22,500 A1010 $5.97 $7,000 A1030 $4.69 $5,500 A2010 $0.00 $0 A2020 $8.53 $10,000

46.00% $34.13 $40,000 $121.59 $142,500

B1010 $4.27 $5,000 B1020 $20.90 $24,500 B2010 $87.46 $102,500B2020 $18.34 $21,500B3010 $8.96 $10,500 B3020 $1.28 $1,500

9.60% $11.52 $13,500 $29.44 $34,500

C1010 $4.27 $5,000 C1020 $5.97 $7,000 C2010 $1.28 $1,500 C3010 $7.25 $8,500C3020 $6.40 $7,500C3030 $4.27 $5,000

38.20% $109.22 $128,000 D1010 $2.99 $3,500D2010 $9.39 $11,000 D2020 $14.08 $16,500 D2040 $5.55 $6,500D3050 $17.92 $21,000 D4010 $2.56 $3,000 D5010 $48.21 $56,500 D5020 $14.93 $17,500 D5030 $2.13 $2,500 D5090 $0.00 $0

100% $174.07 $204,000

25.00% $43.52 $51,000.00

7.00% $12.18 $14,280.00

$229.77 $269,280

$368.87 $432,300

SubTotal

Interior Doors - Door, single leaf, kd steel frame, hollow metal, commercial quality, flush, 3'-0" x 7'-0" x 1-3/8"

(Initial Cost Estimate)

(Initial Cost Estimate)

Stair Construction - Stairs, CIP concrete, w/landing, 20 risers, with nosingWall Finishes - 2 coats paint on masonry with block filler; Painting, interior on plaster and drywall, walls & ceilings, roller work, primer & 2 coats; Vinyl wall covering, fabric back, medium

Communications and Security - Communication and alarm systems, fire detection, non-addressable, 25 detectors; Internet wiring, 8 data/voice outlets per 1000 S.F.

Elevators and Lifts - Hydraulic passenger elevator, 2500 lb., 2 floor, 125 FPM

(Initial Cost Estimate)

Ceiling Finishes - Acoustic ceilings, 3/4" fiberglass board, 24" x 48" tile, tee grid, suspended supportFloor Finishes - Carpet, tufted, nylon, roll goods, 12' wide, 36 oz; Carpet, padding, add to above, maximum; Vinyl, composition tile, maximum

D Services

Architectural Fees

C Interiors

Roof Construction - Floor, composite slab on steel beam, 25'x25' bay, 4.5"slab, 20.5" total depth, 40 PSF superimposed load, 99 PSF total load

Roof Openings - Skylight, plastic domes, insulated curbs, 30 SF to 65 SF, single glazing

Partitions - Metal partition, 5/8"fire rated gypsum board face, 1/4" sound deadening gypsum board, 2-1/2" @ 24", same opposite face, no insulation

Exterior Walls - Stone wall, Indiana limestone, sawn finish, 2" thick, 10' high, 8" CMU back-upExterior Windows - Aluminum flush tube frame, for 1/4"glass,1-3/4"x4", 5'x6' opening, no intermediate horizontals; Glazing panel, plate glass, 1/4" thick, clearRoof Coverings - Asphalt flood coat, gravel, base sheet; Insulation, rigid, roof deck, composite; Roof edges, aluminum; Flashing, aluminum, no backing sides; Gravel stop, aluminum, extruded

Cafeteria, Limestone Face Concrete Block Back-up / Steel Frame

Foundations - Strip footing, concrete, reinforced, load 5.1 KLF, 12" x 24"; Spread footings, 3000 PSI concrete, load 300K, 7' - 6" square x 25" deep / load 400K, 8' - 6" square x 27" deepSlab on Grade - Slab on grade, 4" thick, non industrial, reinforcedBasement Excavation - Excavate and fill, 30,000 SF, 4' deep, sand, gravel, or common earth, on site storageBasement Walls - Foundation wall, CIP, 4' wall height, direct chute, .148 CY/LF, 7.2 PLF, 12" thick

Floor Construction - W12, 400 KIPS, 10' unsupported height, 79 PLF; composite concrete slab on W beam, 5.5" slab, 25'x25' bay, 24.5" total depth, 125 PSF superimposed load, 200 PSF total

B Shell

A Substructure

Floor Area (S.F.): 1172

Story Count: 1Story Height (L.F.): 17.5

Plumbing Fixtures - Water closet; Urinal; Lavatory; Shower ; Kitchen sink w/trim, countertop, stainless steel, 19" x 18"; Service sink w/trim; Water coolerDomestic Water Distribution - Gas fired water heater, commercial, 100< F rise, 200 MBH input, 192 GPHRain Water Drainage - Roof drain, CI, soil,single hub, 5" diam, 10' high; Roof drain, CI, soil,single hub, 5" diam, for each additional foot add

Total Building Cost

Terminal & Package Units - Rooftop, multizone, air conditioner, schools and colleges, 25,000 SF, 95.83 tonSprinklers - Wet pipe sprinkler systems, steel, light hazard, 1 floor, 10,000 SF; Wet pipe sprinkler systems, steel, light hazard, each additional floor, 10,000 SFElectrical Service/Distribution - Service installation; Feeder installation; Switchgear installation; 600 ALighting and Branch Wiring - Receptacles; Switches; Miscellaneous power; Central air conditioning; Motor installation; Receptacles; Motor feeder systems; Flourescent fixtures

Other Electrical Systems - Generator sets, w/battery, charger, muffler and transfer switch, gas/gasoline operated, 3 phase, 4 wire, 277/480 V, 11.5 kW

Contractor Fees (General Conditions,Overhead,Profit)

03.01

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/25/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Cost

Estim

ateCa

feter

ia

Page 11: Man-Made Naturally

% of Total Cost Per S.F. Cost9.40% $18.19 $194,000

A1010 $4.55 $48,500 A1030 $4.59 $49,000 A2010 $0.19 $2,000 A2020 $8.86 $94,500

16.20% $20.90 $223,000 $40.87 $436,000

B1010 $2.25 $24,000 B1020 $5.48 $58,500 B2010 $19.97 $213,000B2020 $4.22 $45,000 B2030 $1.87 $20,000 B3010 $5.72 $61,000 B3020 $1.36 $14,500

15.30% $11.99 $128,000 $29.52 $315,000

C1010 $10.87 $116,000 C1020 $1.12 $12,000 C1030 $0.05 $500C3010 $5.81 $62,000C3020 $5.39 $57,500C3030 $6.33 $67,500

58.30% $108.97 $1,162,500 D2010 $60.55 $646,000 D2020 $5.67 $60,500 D2040 $3.56 $38,000D3050 $18.04 $192,500 D4010 $2.30 $24,500 D5010 $8.58 $91,500 D5020 $10.31 $110,000 D5030 $3.00 $32,000 D5090 $0.52 $5,500

0.80% $1.45 $15,500 E1020 $1.45 $15,500

100% $161.50 $1,723,000 25.00% $40.38 $430,750 10.00% $16.15 $172,300

$218.03 $2,326,050 $268.65 $2,866,050

(Initial Cost Estimate)

(Initial Cost Estimate)

SubTotalContractor Fees (General Conditions,Overhead,Profit)Architectural FeesTotal Building Cost

Electrical Service/Distribution - Service installation, 120/208 V, 1000 A; Feeder installation, 600 V, 1000 A; Switchgear installation, 1200 ALighting and Branch Wiring - Receptacles; Wall switches; Miscellaneous power; Central air conditioning power; Flourescent fixtures recess mounted in ceilingCommunications and Security - Communication and alarm systems, fire detection, non-addressable, 50 detectors; Internet wiring, 8 data/voice outlets per 1000 S.F.Other Electrical Systems - Generator sets, w/battery, charger, muffler and transfer switch, 3 phase, 4 wire, 277/480 V, 11.5 kW; ninterruptible power supply with standard battery pack

E Equipment & FurnishingsInstitutional Equipment - Laboratory equipment

D ServicesPlumbing Fixtures - Water closet; Urinal; Lavatory ; Lab sink w/trim, polyethylene, single bowl, double drainboard, 54" x 24" OD; Service sink; Shower; Water coolerDomestic Water Distribution - Gas fired water heater, commercial, 100< F rise, 600 MBH input, 576 GPHRain Water Drainage - Roof drain, DWV PVC, 4" diam, diam, 10' highTerminal & Package Units - Rooftop, multizone, air conditioner, schools and colleges, 25,000 SF, 95.83 tonSprinklers - Wet pipe sprinkler systems, steel, light hazard, 1 floor, 50,000 SF

Partitions - Concrete block (CMU) partition, light weight, hollow, 6" thick, no finish, 8" thick; 8" concrete block partitionInterior Doors - Door, single leaf, kd steel frame, kalamein fire, commercial quality, 3'-0" x 7'-0" x 1-3/4"Fittings - Lockers, steel, single tier, 5' to 6' high, per opening, minimumWall Finishes - 2 coats paint on masonry with block filler; Painting, masonry or concrete, latex, brushwork, primer & 2 coats; Wall coatings, epoxy coatings, maximumFloor Finishes - Carpet tile, nylon, fusion bonded, 18" x 18" or 24" x 24", 35 oz; Composition flooring, epoxy, minimum; Vinyl, composition tile, maximumCeiling Finishes - Acoustic ceilings, 3/4"mineral fiber, 12" x 12" tile, concealed 2" bar & channel grid, suspended support

Exterior Walls - Stone wall, Indiana limestone, sawn finish, 2" thick, 10' high, 8" CMU back-upExterior Windows - Aluminum flush tube frame, for 1/4"glass,1-3/4"x4", 5'x6' opening, no intermediate horizontals; Glazing panel, plate glass, 1/4" thick, clearExterior Doors - aluminum & glass, with transom, narrow stile, double door, hardware, 6'-0" x 10'-0" opening; Aluminum & glass, with transom, non-standard, hardware, 3'-0" x 10'-0" openingRoof Coverings - Roofing, asphalt flood coat, gravel, base sheet; Insulation, rigid, roof deck, composite; Roof edges, aluminum; Flashing, aluminum; Gravel stop, aluminumRoof Openings - Skylight; Roof hatch, with curb; Smoke hatch, unlabeled, galvanized, 2'-6" x 3', not incl hand winch operator

C Interiors

Slab on Grade - Slab on grade, 4" thick, non industrial, reinforcedBasement Excavation - Excavate and fill, 30,000 SF, 4' deep, sand, gravel, or common earth, on site storageBasement Walls - Foundation wall, CIP, 4' wall height, direct chute, .099 CY/LF, 4.8 PLF, 8" thick; Foundation wall, CIP, 4' wall height, direct chute, .148 CY/LF, 7.2 PLF, 12" thick

B Shell

Floor Construction - Floor, concrete, slab form, open web bar joist @ 2' OC, on bearing wall, 35' span, 20" deep, 125 PSF superimposed load, 172 PSF total loadRoof Construction - Roof, steel joists, 1.5" 22 ga metal deck, on bearing walls, 35' bay, 25.5" deep, 40 PSF superimposed load, 60 PSF total load

(Initial Cost Estimate)

Story Count: 1Story Height (L.F.): 15Floor Area (S.F.): 10668

A SubstructureStandard Foundations - Strip footing, concrete, reinforced, load 5.1 KLF, 12" deep x 24" wide

Laboratory, with Limestone with Concrete Block / R/Conc. Frame

03.02

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/25/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Cost

Estim

ateLa

bora

tory

Page 12: Man-Made Naturally

% of TotalCost Per

S.F. Cost5.90% $7.06 $14,000

A1010 $1.41 $3,500 A1030 $4.64 $11,500 A2010 $0.20 $500 A2020 $0.81 $2,000

32.50% $26.82 $66,500 $57.68 $92,500

B1010 $2.42 $6,000 B1020 $20.37 $50,500 B2010 $10.49 $26,000B2020 $0.81 $2,000B2030 $0.40 $1,000B3010 $4.03 $10,000 B3020 $0.40 $1,000

13.00% $5.25 $13,000 $5.85 $38,500

C1010 $2.62 $6,500 C1020 $1.82 $4,500 C2010 $0.81 $2,000 C3010 $0.61 $1,500C3020 $3.83 $9,500C3030 $5.85 $14,500

48.70% $53.85 $133,500 D1010 $3.23 $8,000D2010 $1.21 $3,000D2020 $7.66 $19,000 D2040 $3.03 $7,500 D3050 $19.77 $49,000 D4010 $2.42 $6,000 D5010 $8.87 $22,000 D5020 $10.69 $26,500 D5030 $1.21 $3,000 D5090 $0.20 $500

100% $92.98 $227,000 25.00% $23.25 $56,750 8.00% $7.44 $18,160.00

$123.66 $301,910.00 $165.51 $370,405.00 (Initial Cost Estimate)

(Initial Cost Estimate)

(Initial Cost Estimate)

Lighting and Branch Wiring - Receptacles; Wall switches; Miscellaneous power; Central air conditioning power; Motor installation, three phase; Flourescent fixtures recess mounted in ceilingCommunications and Security - Communication and alarm systems; Internet wiring, 8 data/voice outlets per 1000 S.F.Other Electrical Systems - Generator sets, w/battery, charger, muffler and transfer switch, gas/gasoline operated, 3 phase, 4 wire; Uninterruptible power supply with standard battery pack

Wall Finishes - Painting, interior on plaster and drywall, walls & ceilings, roller work, primer & 2 coats

Ceiling Finishes - Acoustic ceilings, 3/4"mineral fiber, 12" x 12" tile, concealed 2" bar & channel grid, suspended support

Elevators and LiftsPlumbing Fixtures

Rain Water Drainage - Roof drain, CI, soil,single hub, 5" diam, 10' high; Roof drain, CI, soil,single hub, 5" diam, for each additional foot addTerminal & Package Units - Rooftop, multizone, air conditioner, banks or libraries, 25,000 SF, 104.00 ton

Library, with Limestone with Concrete Block / R/Conc. Frame

Standard Foundations - Strip footing, concrete, reinforced, load 11.1 KLF, 12" deep x 24" wide; Spread footings, 3000 PSI concrete, load 200K, 6' - 0" square x 20" deep, 7' - 6" square x 25" deepSlab on Grade - Slab on grade, 4" thick, non industrial, reinforced

Exterior Doors

Floor Area (S.F.): 2479

Story Count: 1Story Height (L.F.): 15

A Substructure

Roof Construction - Floor, concrete, beam and slab, 25'x25' bay, 40 PSF superimposed load, 12" deep beam, 10" slab, 150 PSF total loadExterior Walls - Stone wall, Indiana limestone, smooth finish, 4" thick, 8' high, 4" CMU back-up

SubTotalContractor Fees (General Conditions,Overhead,Profit)

B Shell

Basement Excavation - Excavate and fill, 10,000 SF, 4' deep, sand gravel, or common earth, on site storageBasement Walls - Foundation wall, CIP, 4' wall height, direct chute, .148 CY/LF, 7.2 PLF, 12" thick

Floor Construction - Cast-in-place column, 16", tied, 300K, 253 lbs/LF, 4000PSI; Waffle slab, cast-in-place, 10" deep rib, 20" column, 25'x25', 200 PSF superimposed load, 310 PSF total load

Exterior Windows

Interior Doors - Single leaf, wood frame, 3'-0" x 7'-0" x 1-3/8", birch, solid coreStair Construction - Stairs, CIP concrete, w/landing, 24 risers, with nosing

Floor Finishes - Carpet tile, nylon, fusion bonded, 18" x 18" or 24" x 24", 35 oz; Vinyl, composition tile, maximum

Architectural FeesTotal Building Cost

Sprinklers - Wet pipe sprinkler systems, steel, light hazard, 1 floor, 10,000 SFElectrical Service/Distribution - Service installation; Feeder installation; Switchgear installation, 400 A

Roof Coverings - Roofing, single ply membrane, EPDM, 60 mils, fully adhered; Insulation, rigid, roof deck, composite with 2" EPS, 1" perlite; Roof edges, aluminum, duranodic, .050" thick, 6" faceRoof Openings

Partitions - Metal partition, 5/8"fire rated gypsum board face, 1/4" sound deadening gypsum board, 2-1/2" @ 24", same opposite face, no insulation

D Services

C Interiors

Domestic Water Distribution - Gas fired water heater, commercial, 100< F rise, 500 MBH input, 480 GPH

03.03

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/25/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Cost

Estim

ateLib

rary

Page 13: Man-Made Naturally

% of Total

Cost Per S.F. Cost

4.90% $6.17 $26,500 A1010 $0.58 $2,500 A1030 $4.54 $19,500 A2010 $0.47 $2,000 A2020 $0.58 $2,500

18.10% $23.99 $103,000 $28.65 $123,000

B1010 $4.89 $21,000 B1020 $14.21 $61,000 B2010 $4.66 $20,000B2020 $1.28 $5,500B2030 $4.66 $20,000B3010 $4.77 $20,500 B3020 $0.12 $500

16.50% $5.12 $22,000 $21.54 $92,500

C1010 $1.98 $8,500 C1020 $1.86 $8,000 C2010 $1.28 $5,500 C3010 $1.86 $8,000C3020 $8.27 $35,500C3030 $6.29 $27,000

58.40% $73.93 $317,500 D2010 $8.38 $36,000 D2020 $6.17 $26,500 D2040 $1.40 $6,000 D3050 $33.19 $142,500 D4010 $6.05 $26,000 D4020 $1.51 $6,500 D5010 $5.01 $21,500 D5020 $9.43 $40,500 D5030 $2.79 $12,000

2.20% $2.79 $12,000 E1090 $2.79 $12,000

100% $112.00 $481,000 25.00% $28.00 $120,250.00 7.00% $7.84 $33,670.00

$147.84 $634,920 $175.67 $754,380 (Initial Cost Estimate)

(Initial Cost Estimate)

(Initial Cost Estimate)B Shell

Floor Construction - Cast-in-place conc column, 24", tied, 900K load, 567 lbs/LF, 4000PSI; Flat plate, concrete, 10" slab, 24" column, 25'x25', 125 PSF superimposed load, 250 PSF total loadRoof Construction - Floor, concrete, beam and slab, 25'x25' bay, 40 PSF superimposed load, 20" deep beam, 9" slab, 152 PSF total load

A Substructure

Sprinklers - Wet pipe sprinkler systems, steel, light hazard, 1 floor, 2000 SF; Wet pipe sprinkler systems, steel, ordinary hazard, 1 floor, 1000 SFStandpipes - Wet standpipe risers, class III, steel, black, sch 40, 4" diam pipe, 1 floor

Exterior Walls - Stone wall, Indiana limestone, sawn finish, 2" thick, 10' high, 8" CMU back-upExterior WindowsExterior DoorsRoof Coverings - Roofing, asphalt flood coat, gravel, base sheet; Insulation, rigid roof deck, composite; Roof Edges, aluminum; Flashing, aluminum; Gravel stop, aluminum

Electrical Service/Distribution - Service installation; Feeder installation; Switchgear installation, 400 A

D Services

Interior Doors - Door, single leaf, wood frame, 3'-0" x 7'-0" x 1-3/8", birch, hollow core

Wall Finishes - Painting, interior on plaster and drywall, walls & ceilings, roller work, primer & 2 coats; Ceramic tile, thin set, 4-1/4" x 4-1/4"Stair Construction - Stairs, CIP concrete, w/landing, 20 risers, with nosing

Domestic Water Distribution - Gas fired water heater, commercial, 100< F rise, 500 MBH input, 480 GPHRain Water Drainage - Roof drain, CI, soil,single hub, 3" diam, 10' high; Roof drain, CI, soil,single hub, 4" diam, 10' highTerminal & Package Units - Rooftop, multizone, air conditioner, restaurants, 3,000 SF, 15.00 ton; Commercial kitchen exhaust/make-up air system, rooftop, gas, 2000 CFM

Contractor Fees (General Conditions,Overhead,Profit)Architectural Fees

E Equipment & FurnishingsOther Equipment - 1 - Range, restaurant type, 6 burners & 1 standard oven; 1 - Reach-in Freezer; 1 - Food warmer, counter; 1 - Dishwasher, 10-12 racks per hour

Lighting and Branch Wiring - Receptacles; Miscellaneous power; Central air conditioning power; Flourescent fixtures recess mounted in ceilingCommunications and Security - Communication and alarm systems, fire detection, addressable, 12 detectors, includes outlets, boxes, conduit and wire; Fire alarm command center

Total Building Cost

Floor Area (S.F.): 4294

Story Count: 1Story Height (L.F.): 15

Restaurant, with Limestone with Concrete Block / R/Conc. Frame

Standard Foundations - Strip footing, concrete, reinforced, load 11.1 KLF, 12" x 24"; spread footings, 3000 PSI concrete, load 25K, 3' - 0" square x 12" deepSlab on Grade - Slab on grade, 4" thick, non industrial, reinforcedBasement Excavation - Excavate and fill, 4000 SF, 4' deep, sand, gravel, or common earth, on site storageBasement Walls - Foundation wall, CIP, 4' wall height, direct chute, .148 CY/LF, 7.2 PLF, 12" thick

SubTotal

Roof Openings - Skylight, plastic domes, insulated curbs, nominal size to 10 SF, double glazing

Partitions - Wood, 5/8"fire rated gypsum board face, none base,2 x 4,@ 16" OC framing,same opposite face, 0 insul; 5/8" gypsum board, taped & finished, painted on metal furring

C Interiors

Floor Finishes - Carpet tile, nylon, fusion bonded, 18" x 18" or 24" x 24", 35 oz; Tile, quarry tile, mud set, minimum; Tile, quarry tile, mud set, maximumCeiling Finishes - Acoustic ceilings, 3/4"mineral fiber, 12" x 12" tile, concealed 2" bar & channel grid, suspended support

Plumbing Fixtures - Water closet; Urinal; Lavatory ; Kitchen sink w/trim, countertop, stainless steel, 44" x 22" triple bowl; Service sink w/trim; Shower; Water cooler

03.04

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/25/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Cost

Estim

ateRe

staur

ant

Page 14: Man-Made Naturally

% of Total Cost Per S.F. Cost7.60% $16.54 $447,000

A1010 $6.22 $168,000 A1030 $2.29 $62,000 A2010 $0.09 $2,500 A2020 $7.94 $214,500

45.20% $109.57 $2,960,750 $185.50 $5,013,000

B1010 $10.64 $287,500 B1020 $5.37 $145,000 B2010 $75.94 $2,052,250 B2020 $12.10 $327,000 B2030 $0.30 $8,000 B3010 $5.22 $141,000

16.90% $26.00 $702,500 $36.72 $992,500

C1010 $13.97 $377,500 C1020 $6.11 $165,000 C1030 $2.53 $68,500 C2010 $3.39 $91,500 C3010 $2.29 $62,000C3020 $4.90 $132,500C3030 $3.53 $95,500

30.30% $66.02 $1,784,000 D1010 $23.24 $628,000 D2010 $10.23 $276,500 D2020 $2.83 $76,500 D2040 $0.28 $7,500 D3010 $7.77 $210,000 D3030 $8.45 $228,500 D4010 $2.70 $73,000 D5010 $2.20 $59,500 D5020 $6.83 $184,500 D5030 $1.30 $35,000 D5090 $0.19 $5,000

0.10% $0.15 $4,000 E1090 $0.15 $4,000

100% $218.28 $5,898,250 25.00% $54.57 $1,474,562.50

8.00% $17.46 $471,860.00 $290.31 $7,844,672.50 $405.56 $10,959,865.00 (Initial Cost Estimate)

(Initial Cost Estimate)

(Initial Cost Estimate)

Roof Construction - Floor, steel joists, beams, 1.5" 22 ga metal deck, on columns, 25'x25' bay, 20" deep, 40 PSF superimposed load, 60 PSF total loadExterior Walls - Stone wall, Ohio limestone, smooth finish, 4" thick, 8' high, 8" CMU back-upExterior Windows - Windows, aluminum, sliding, standard glass, 5' x 3'

B Shell

Basement Excavation - Excavate and fill, 30,000 SF, 4' deep, sand, gravel, or common earth, on site storageBasement Walls - Foundation wall, CIP, 4' wall height, direct chute, .099 CY/LF, 4.8 PLF, 8" thick; 148 CY/LF, 7.2 PLF, 12" thick

Floor Construction - Floor, conc, slab form, open web bar joist @ 2' OC, on W beam and column, 25'x25', 29" deep, 65 PSF superimposed, 110 PSF total; Fireproofing

Slab on Grade - Slab on grade, 4" thick, non industrial, reinforced

A Substructure

SubTotalContractor Fees (General Conditions,Overhead,Profit)Architectural FeesTotal Building Cost

E Equipment & Furnishings

Rain Water Drainage - Roof drain, DWV PVC, 4" diam, diam, 10' highEnergy Supply - Apartment building heating system, fin tube radiation, forced hot water, 20,000 SF area,200,000 CF volCooling Generating Systems - Packaged chiller, air cooled, with fan coil unit, medical centers, 20,000 SF, 46.66 ton

Suites, 2-3 Story with Limestone with Concrete Block Back-up / Steel Frame/ Steel Joists

Exterior Doors - Door, steel 18 gauge, hollow metal, 1 door with frame, no label, 3'-6" x 7'-0" openingRoof Coverings - Roofing, asphalt flood coat, gravel, base sheet; Insulation, rigid, roof deck, composite; Roof edges, aluminum; Flashing, aluminum

Partitions - Metal partition, 5/8"fire rated gypsum board face, no base, same opposite face, no insul; 1/2" fire rated gypsum board, taped & finishedInterior Doors - Door, single leaf, wood frame, 3'-0" x 7'-0" x 1-3/8", birch, solid core, hollow coreFittings - Cabinets, residential, wall, two doors x 48" wide

Story Height (L.F.): 15Story Count: 2

Floor Area (S.F.): 27026

Standard Foundations - Strip footing, conc, reinforced, load 5.1 KLF, 12" x 24", load 18.4 KLF, 12" x 40"; Spread footings, 3000 PSI conc, load 150K, 5' - 6" square x 18" deep

Stair Construction - Stairs, steel, cement filled metal pan & picket rail, 16 risers

C Interiors

Wall Finishes - Painting, interior on plaster and drywall, walls & ceilings, roller work, primer & 2 coats; Vinyl wall covering, fabric back, medium weight; Ceramic tileFloor Finishes - Carpet tile, nylon, fusion bonded, 18" x 18" or 24" x 24", 24 oz, 35 oz; Carpet padding; Vinly, composition tile; Tile, ceramic natural clayCeiling Finishes - Gypsum board ceilings, 5/8" fire rated gypsum board, painted and textured finish,1-5/8" metal stud furring, 24" OC support

Elevators and Lifts - 8 - Hydraulic, passenger elevator, 2000 lb, 2 floors, 100 FPM

Other Equipment - 2 - Laundry equipment, washer, residential, 4 cycle, average; 2 - Laundry equipment, dryers, gas-fired residential, 16 lb capacity, average

Plumbing Fixtures - Laundry sink w/trim, PE on CI, black iron frame, 24" x 20", single compt; Bathroom, three fixture, 2 wall plumbing, lavatory, water closet & bathtubDomestic Water Distribution - Gas fired water heater, residential, 100< F rise, 30 gal tank, 32 GPH

D Services

Sprinklers - Wet pipe sprinkler systems, steel, light hazard, 1 floor, 5000 SFElectrical Service/Distribution - Service installation; Feeder installation; Switchgear installation, 600 ALighting and Branch Wiring - Receptacles; Wall switches; Miscellaneous power; Central air conditioning power; Motor installation; Incandescent fixturesCommunications and Security - Communication and alarm systems, fire detection, non-addressable, 25 detectors; Internet wiring, 2 data/voice outlets per 1000 S.F.Other Electrical Systems - Generator sets, w/battery, charger, muffler and transfer switch, gas/gasoline operated, 3 phase, 4 wire, 277/480 V, 7.5 kW

03.05

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/25/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Cost

Estim

ateSu

ites

Page 15: Man-Made Naturally

Cost Per S.F. CostContractor

FeesArchitectural

Fees

Cafeteria A Substructure $19.20 $22,500 $51,000 $14,280 B Shell $34.13 $40,000 C Interiors $11.52 $13,500 D Services $109.22 $128,000

Project Cost, Kelley's Island, OH; Year 2009

Complex

A Substructure, $704 000

Architect, $1 301 013$ $ ,

Laboratory A Substructure $18.19 $194,000 $430,750 $172,300 B Shell $20.90 $223,000 C Interiors $11.99 $128,000 D Services $108.97 $1,162,500 E Equipment & Furnishings $1.45 $15,500

Library A Substructure $7.06 $14,000 $56,750 $18,160 B Shell $26.82 $66,500 C Interiors $5.25 $13,000 D Services $53.85 $133,500

Restaurant A Substructure $6.17 $26,500 $120,250 $33,670 B Shell $23.99 $103,000 C Interiors $5.12 $22,000 D Services $73.93 $317,500

$ $

$704,000

B Shell,$5,807,000

C Interiors, D Services, $3 525 500

E Equipment & Furnishings,

$31,500

Contractor, $3,876,875

$1,301,013

E Equipment & Furnishings $2.79 $12,000 Suites A Substructure $16.54 $447,000 $1,474,563 $471,860

B Shell $109.57 $2,960,750 C Interiors $36.72 $992,500 D Services $66.02 $1,784,000 E Equipment & Furnishings $0.15 $4,000

$769.55 $8,823,250 $2,133,313 $710,270 $1,527.65 $15,507,500 $3,876,875 $1,301,013

Total Cost % of Total

SubTotal(Initial Cost Estimate)

Originally the cost of this building was $20,685,388. Later, two major changes were

$1,473,000$3,525,500

Total Cost % of TotalA Substructure $704,000 6.03%B Shell $3,393,250 29.08%C Interiors $1,169,000 10.02%D Services $3,525,500 30.22%E Equipment & Furnishings $31,500 0.27%Contractor $2,133,313 18.29%Architect $710,270 6.09%Total Project Cost $11,666,833(Initial Cost Estimate) $20,685,388

Originally the cost of this building was $20,685,388. Later, two major changes weremade. The limestone originally used on the exterior of all the buildings was removed from those buildings which are submerged under the ground. Concrete was substituted for the bearing walls which had been constituted by limestone blocks. This saved on the labor and manufacturing costs of quarrying limestone. For the suites, the limestone block was maintained. However, instead of transporting limestone from Indiana, limestone from Kelley's Island will be used instead. This was a major savings on transportation costs. Going along with the spirit of ecotourism and the idea of experiencing nature rather than buffering oneself from it, the finishing for the interiors was also removed. All of these changes amounted to a $9,018,555 [as notated in blue on the previous cost sheets], a 43% drop in the overall cost.

03.06

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/25/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Cost

Estim

ateOv

erall

Page 16: Man-Made Naturally

Bearing wall

Open web steel joist. 22” deep, 3” slab, 1/2”

deck, 3’ o.c.

Custom structural steel truss. 8’ deep, 3”

decking, 6” slab, 12’ o.c.

Clear-span rigid steel frame. 81” crown depth,

11’ shoulder, 21” base

Open web steel joist. 32” deep, 3’ o.c.

Open web steel joist. 26” deep, 3’ o.c.Structural steel girder. 30 “ deep

Structural steel girder. 19 “ deep

Pros:-Rigid frame system is less complex-Rigid frame minimizes need for columns-Permits construction under adverse weather conditions.-Minimizes on-site erection and construction time-Avoids the need for diagonal bracing and shear walls

Cons:-The rigid frame takes up much of the window area and blocks the natural light from getting into the lab.-Steel does not have a high fire-resistance rating-Does not minimize the number of separate trades needed to complete a building 04.01

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

1/30/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Fra

ming

Plan

Comp

lex B

asem

ent /

1/48”

= 1’

Open-web steel joist. 6” deep, 3’ o.c.

Structural steel girder.

6” deep

Bearing Wall

Page 17: Man-Made Naturally

04.02

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

2/17/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Stru

ctura

l Sec

tion

Comp

lex / 3

/32” =

1’

Footing tie grouted into

limestone

Foundation footing with rebar

reinforcement

Concrete bearing wall. 2’ thick with limestone facing

Hollow partition

wall. 1’ thick

Custom structural steel truss. 8’ deep, 3” decking, 12’ o.c.

Clear-span rigid steel frame. 81”

crown depth, 11’ shoulder, 21” base

Concrete bearing wall. 2’ thick

Open-web steel joist. 22” deep, 3” slab, 1/2”

deck, 3’ o.c.

Limestone tiling

Exterior bearing wall. limestone, maintain 6” continuous vertical bearing wall

Structural steel roof joist. 6” deep, 1/2” decking, roofing membrane

Exterior bearing wall. limestone

Open-web steel joist. 6” deep, 3’ o.c.

Concrete bearing wall beyond section cut

Footing beyond section cut

Structural steel girder. 2’ deep

Page 18: Man-Made Naturally

04.03

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

2/08/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

3D S

tructu

re D

iagra

mCo

mplex

Labo

rator

y-Res

taura

nt

Page 19: Man-Made Naturally

05.01

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

2/28/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Buil

ding S

ervic

esCo

mplex

/ 1/64

” = 1’

A2

A3

B

R1R2

Lab

Suites/Offices

Stacks + Reading Area

Cafeteria + Kitchen

Unisex BathroomMen’s BathroomWoman’s Bathroom

Switchgear and transformer room

Restaurant + Cafe

Cells

100 people

1 person

22 people

87 people

195 people

1 person

1 per 25, first 50; 1 per 50, remainder1 per unit

1 female per 65

1 per 75

1 per 75

1 per unit

1 male per 1252 female wc.

1 wc. per unit

1 female wc.

1 female wc.

2 female wc.

1 wc. per unit

2 male wc.

1 male wc.

1 male wc.

2 male wc.

2 female lavatory

1 lavatory per unit

1 female lavatory

1 female lavatory

1 female lavatory

1 lavatory per unit

2 male lavatory

1 male lavatory

1 male lavatory

1 male lavatory

1 per 100

1 per 500

1 per 500

1 per 500

1 drinking fountain

1 drinking fountain

1 drinking fountain

1 drinking fountain

1 per 40, first 50; 1 per 80, remainder1 per unit

1 per 200

1 per 200

1 per 200

1 per unit

Floor Area of Commercial Building: 19,273 ft^2 totalSize of Combined Room for Transformers and Switch gear: 30’ x 30’ x 11’

Page 20: Man-Made Naturally

05.02

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

2/28/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Barri

er F

ree B

athro

om P

lanCo

mplex

/ 1/4”

= 1’

Plumbing Wall 60”

30”

35”

18”

12”

33”

48”

42”

56”

32”

32”

60”

Page 21: Man-Made Naturally

boiler room and chilled

water plant (3775 ft sq.)

cooling tower

(612 ft sq.)

boiler rooms(344 ft sq.)

hot water runs through floor slab.

fan room(1191 ft sq.)

raised floorsupply ductworkreturn ductwork

hollow wallBecause of the size and variety of programs in this complex, two different systems were chosen. The Hydronic Convector was chosen for the suites and offices because of it’s small size and capability for providing comfortable heating. While it is a system meant for heating only, the suites and offices already benefit from the natural cooling systems of the building in the summer. This combination of systems saves on energy, costs, and maintenance. Because of the narrow width of the building, the smaller size of the boiler and absence of the need for any other HVAC rooms is also ideal.

In the lab, restaurant, and library space there is no natural cooling system in effect. A Variable Air Volume system is applied for both heating and cooling. This system is good for minimizing system noise, which is key in spaces like the library where a quiet atmosphere for reading is required.

Variable Air VolumePros:-Minimize operating cost-Maximize control of air velocity and air quality-Maximize individual control over temperature-Minimize system noise-Minimize visual obtrusiveness-Minimize system maintenance-Self Balancing

Cons:-Limited in the range of heating or cooling demand that may be accommodated within a single system. When one area needs heating while another needs cooling, a VAV system cannot serve both areas without help from a secondary system.

Hydronic ConvectorPros:-Minimize operating cost-Minimize system noise-Minimize visual obtrusiveness-Maximize flexibility of rental space-Minimize fllor space used for the heating and cooling systems-Minimize floor-to-floor height-Minimize system maintenance-Excellent comfort

Cons:-System used for heating only. -Cooling, humidity control, and ventilation must be provided by separate means.

06.01

Stud

ent:

Soph

ia Ch

ang

Uniqu

e Nam

e: x

iaofan

Origi

nal D

ate:

3/15/2

009

Date

Revis

ed: 3

/31/20

09LA

B Ins

tructo

r: M

ichae

l Ezb

an

Code

Hea

ting a

nd C

oolin

gCo

mplex

Bas

emen

t / 1/4

8” =

1’

Page 22: Man-Made Naturally

07.01

Student: Sophia ChangUnique Name: xiaofanOriginal Date: 3/28/2009 Date Revised: 3/31/2009LAB Instructor: Michael Ezban

Enclosure SystemComplex / 1/4” = 1’

rigid insulation

roof decking

boltsrigid steel frame

custom steel truss

double paned window

soil

grass

waterproofing membrane

coping

limestone block

ties

concrete foundation wall

drainage mat

angle

raised floor tile

supporting beam

bolts

gravel

drainage pipe

gravel

footing

footing ties

cant strip

premolded filler and sealant

waterproofing membrane

rigid insulation

limestone shale

Page 23: Man-Made Naturally

07.02

Student: Sophia ChangUnique Name: xiaofanOriginal Date: 3/19/2009 Date Revised: 3/31/2009LAB Instructor: Michael Ezban

Enclosure System - ElevationComplex / 1/4” = 1’

rigid steel frame

double paned window

structural silicone sealant

limestone block

grass

soil

limestone rock

grass

coping

Page 24: Man-Made Naturally

07.03

Student: Sophia ChangUnique Name: xiaofanOriginal Date: 3/28/2009 Date Revised: 4/08/2009LAB Instructor: Michael Ezban

Enclosure System DiagramsComplex / 1/4” = 1’