    Los Angeles County Project ListingLocal Highway

    (In $000`s)

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLA0G610 Los Angeles SCAB 1AL04 NCRH1 L EXEMPT - 93.127 0

    Description: PTC 1,000 Agency AGOURA HILLS

    The Kanan Road/Agoura Road Ultimate Intersection Improvements Project design consists of designing a signalized intersection that would improve circulation, reduce delays, facilitate large truck movements, reduce conflict points and be located and constructed within an area close in proximity to a freeway interchange and bordered on the north side by built-out and fully improved land. The Kanan Road/Agoura Road Ultimate Intersection Improvements Project was the former Roundabout project.Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalMEASURE R 20H - HIGHWAY CAPITAL

    750 250 1,000 500 500 1,000

    LA0G610 Total 750 250 1,000 500 500 1,000

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLAF7600 Los Angeles SCAB 1O1008 NCR10 L EXEMPT - 93.126 0

    Description: PTC 1,028 Agency ALHAMBRA

    ALHAMBRA PEDESTRIAN IMPROVEMENT/WALKING VIABILITY PROJECT ON VALLEY: (1) Installs ADA curb ramps. (2) Installs bus stop improvements, including pedestrian benches, covered shelters, trash cans, wayfinding/signage, crosswalk enhancements, pedestrian hybrid beacons, pedestrian lighting, pedestrian countdown signals, and removing obstructions from walkways.Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalCITY FUNDS 363 363 33 330 363LOCAL TRANS FUNDS 665 665 60 605 665LAF7600 Total 1,028 1,028 93 935 1,028

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLAF5309 Los Angeles SCAB 1ITS04 ITS02 L TCM Committed 0

    Description: PTC 5,846 Agency AZUSA

    City of Azusa Traffic Management System. This project will upgrade traffic signals at 43 intersections in the City of Azusa. The project will fund the design and construction/implementation of controllers, wiring, detection, conduit, fiber optic, countdown pedestrian heads, signals, video detection, CCTV cameras and traffic control and monitoring upgrades at the 43 intersections.Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalCITY FUNDS 2,338 2,338 2,338 2,338PROP "C25" FUNDS 3,508 3,508 3,508 3,508LAF5309 Total 5,846 5,846 5,846 5,846

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLAE2517 Los Angeles SCAB LAE2517 NCRH4 L EXEMPT - 93.127 0

    Description: PTC 300 Agency BALDWIN PARK

    WIDEN MAINE AVE. IN BALDWIN PARK ADD 1 RIGHT TURN AND 1 LEFT TURN ONLY LANE (SAFETEA-LU Demo ID #2517). Not a capacity enhancement project. Utilizing Toll Credits.

    Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalDEMO-SAFETEA-LU 300 300 300 300LAE2517 Total 300 300 300 300

    Print Date: 6/3/2016 10:25:54 AM Page: 1 of 75

  • Draft 2017 Federal Transportation Improvement Program

    Los Angeles County Project ListingLocal Highway

    (In $000`s)

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLAF3507 Los Angeles SCAB 1NL04 NCN26 L TCM Committed 0

    Description: PTC 820 Agency BALDWIN PARK

    South Baldwin Park Commuter Bikeway Project. Construct 3-mile commuter Class I bike path along San Gabriel River and Walnut Creek connecting to major employment centers on Baldwin Park Blvd.

    Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalCITY FUNDS 100 236 336 113 223 336LOCAL TRANS FUNDS 19 465 484 465 19 484LAF3507 Total 119 701 820 113 688 19 820

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLAF7634 Los Angeles SCAB 7120004 NCR27 L EXEMPT - 93.126 0

    Description: PTC 2,776 Agency BELL

    Design work to improve conditions for pedestrians in order to increase pedestrian safety, and to improve the pedestrian environment in order to promote walking as a viable form of transportation, and encourage the use of public transit.Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalCMAQ 2,159 2,159 2,159 2,159CITY FUNDS 184 371 555 184 371 555ACTIVE TRANSPORTATION PROGRAM

    62 62 62 62

    LAF7634 Total 246 2,530 2,776 246 2,530 2,776

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLAF7120 Los Angeles SCAB 1AL04 NCRH1 L EXEMPT - 93.127 0

    Description: PTC 3,384 Agency BELL GARDENS

    EASTERN AVENUE AND FLORENCE AVENUE RSTI PROJECT : (1) Widen Florence Ave at intersection of Florence Ave and Eastern Ave to accommodate 2 westbound left-turn lanes and a westbound dedicated right-turn lane. (2) Widens sidewalks from 5 ft to 8 ft on Florence Av and includes high visibility crosswalks, pedestrian-level lighting, landscaping, and upgraded traffic signal timing.Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalCITY FUNDS 116 210 858 1,184 10 141 1,033 1,184PROP "C25" FUNDS 246 390 1,564 2,200 31 1,126 1,043 2,200LAF7120 Total 362 600 2,422 3,384 41 1,267 2,076 3,384

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLA0G948 Los Angeles SCAB 1AL04 NCRH1 L EXEMPT - 93.127 0

    Description: PTC 1,600 Agency BURBANK

    Intersection improvement - improve traffic signal operation and timing, reduce traffic congestion at the intersection, and improve pedestrian safety through the modification of median islands, installation of new median islands, the modification of existing pedestrian crosswalks and modification of traffic signal phasing and timing.Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalMEASURE R 20H - HIGHWAY CAPITAL

    180 1,420 1,600 400 1,200 1,600

    LA0G948 Total 180 1,420 1,600 400 1,200 1,600

    Print Date: 6/3/2016 10:25:54 AM Page: 2 of 75

  • Draft 2017 Federal Transportation Improvement Program

    Los Angeles County Project ListingLocal Highway

    (In $000`s)

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLAF3313 Los Angeles SCAB 1AL04 ITS02 L TCM Committed 0

    Description: PTC 1,274 Agency BURBANK

    Burbank-Glendale Traffic System Coordination. Replace Type 170 traffic signal controllers with Type 2070 & associated communications equipment in Burbank & Glendale & install system detection on Glenoaks Bl & San Fernando Bl. City of Burbank and City of Glendale along Glenoaks Boulevard between Buena Vista Street in Burbank and Geneva Street in Glendale, and along San Fernandom Boulevard between Olive Avenue in Burbank and Glendale Avenue in Glendale (Sig Syn - aprox. 65 signals).Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalCITY FUNDS 255 255 255 255PROP "C25" FUNDS 1,019 1,019 1,019 1,019LAF3313 Total 1,274 1,274 255 1,019 1,274

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLAF3509 Los Angeles SCAB 7120004 NCN25 L NON-REPORTABLE TCM

    COMMITTED0

    Description: PTC 4,384 Agency BURBANK

    Burbank Channel Bikeway Regional Gap Closure - Design and construct a Class 1 bicycle and pedestrian path along the Burbank Western Flood Control Channel. The project includes bikeway treatments at three controlled local street crossings (1) Flower St/ Olive Ave, 2) Verdugo/bike path, 3) Providencia/ Lake St.), and a grade separated crossing at Alameda Av. The project limits on the Burbank Western Flood Control Channel are from Olive Ave/Flower St to Alameda Ave for approximately 0.79 miles.Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalCMAQ 400 46 2,275 2,721 446 2,275 2,721AGENCY 100 11 570 681 111 570 681STATE PARK FUNDS 982 982 982 982LAF3509 Total 500 57 3,827 4,384 557 3,827 4,384

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLAF5306 Los Angeles SCAB 1ITS04 ITS02 L TCM Committed 0

    Description: PTC 743 Agency BURBANK

    Burbank Traffic Responsive Signal System; upgrade 20 signals on Hollywood Way and 18 on Buena Vista St., connect 38 signals to the fiber-optic cable-trunk line, and purchase fiber-optic modems. Includes a demand-responsive traffic signal system along Hollywood Way and Buena Vista St., license, system integration and testing of the Quick Track Adaptive Control Software.Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 TotalCITY FUNDS 20 179 199 199 199PROP "C25" FUNDS 544 544 544 544LAF5306 Total 20 723 743 743 743

    ProjectID County Air Basin Model RTP ID Program Route Begin End System Conformity Category AmendmentLAF5701 Los Angeles SCAB 1ITS04 ITS14 L EXEMPT - 93.126 0

    Description: PTC 889 Agency BURBANK

    Burbank Traveler Information and Wayfinding System -This static and dynamic wayfinding signage project for providing drivers information about parking options and destinations in downtown Burbank and near Bob Hope Airport and providing transit users arrival of the next bus. Additional signage will be installed at the two rail stations in Burbank and bicycle signage will be included to help identify destination and travel distance for this mode.Fund ENG R/W CON Total Prior 2016/2017 2017/2018 2018/2019 2019/202