18
Sector WATER SUPPLY & SANITATION Rs.in Million Sr. No. GS. No. Name of Scheme District Approved Cost Exp Upto June 2015 Revised allocation for 2015-16 Funds released till 31.03.16 Funds utilized till 31.03.16 %age utilization on release 31.03.16 Total Accummulati ve exp: till 31.03.16 Physical progress till current month (%age) Remarks (including detailed physical progress) (i) Date of Start of the Project (ii) Date of completion of the Project 1 1014 Bulk Water Supply Project from River Jhelum to Murree Rawalpindi 4254.770 963.049 100.000 100.000 50.000 0.000 0% 963.049 23% PC-I under approval. 2 1016 Installation of Water supply scheme for residents of Fateh Jang Attock Attock 469.913 78.546 50.000 50.000 70.425 70.400 100% 148.946 32% A.A 21.10.2014 T.S 10.11.2014 Date of award 22.01.2015 1) Work is in progress. More Fund are required. (1) Feeding Main (0%), (2) Water Treatment Plant (40%), (3) Staff Quarter Lab (95%), (4) Pumping Machinery (arranged), Clear, GST (0%), (5) Rising Main (60%), (6) OHR 50000 Glns (10%), (7) GST 4000000 Glns (80%), (8) Pump House (0%), (9) Water Distribution Network (52%), (10) Water Meters (0%), (11) O.H Electrification (0%), (12) Aqusition for land (0%). 3 1017 Urban Water Supply Scheme Chakwal Based on Khai Dam, Tehsil Chakwal, District Chakwal Chakwal 547.636 78.085 50.000 50.000 42.500 31.875 75% 109.960 20% Work on filtration plant on Khai Dam is in progress. On the direction of Chief Minister Punjab revise estimate has been submitted for approval in P&D office Lahore. 4 1018 Water Supply Scheme based on Naroomi Dhan Spring Phase-II, Tehsil Pind Dadan Khan, District Jhelum. Jhelum 286.994 224.986 40.994 40.994 40.994 30.500 74% 255.486 89% A.A: 10-04-14 T.S: 16-4-14 Work allotted : Group-I 30-05-2014 Group-II 24-10-2014 Work is in Progress. Scheme is partially operational. 5 1023 Augmentation of Water Supply Scheme, Sargodha based on canal water supply Phase-I Sargodha 268.210 100.127 50.000 50.000 54.000 48.726 90% 148.853 55% Date of A.A 28.02.2014, Date of T.S 30.04.2014, Date of Award 28.06.2014, Scheduled date of Completion is 30.06.2016, Date of Commencement, 28.06.2014, Funds released on 24.08.2015, Funds on-lined on 24.08.2015. 20-No. tube wells completed out of provision 22-No. 09-No. Pump Houses 90% completed out of provision 22-No. 31-Sets of Pumping machinery arranged. R/Main / D-System 59901-Rft laid & 10502- Rft arranged out of provision 124038-Rft. 4-No. GSTs 85% completed out of 05-No. Work in progress. 6 1026 Comprehensive Water Supply & Sewerage Scheme Khushab Khushab 319.000 314.500 50.000 50.000 20.000 8.690 43% 323.190 100% Date of A.A 08.10.2009 Date of T.S 05.11.2009 Date of award 06.01.2010. Scheme Functional. Water is beng supplied to khushab city.Petty works in progress.All Sewer lines are also functional. Funds released on 28.09.2015. Rev.estimate submitted to Secretary HUD & PHED for onward transmission for approval from PDWD.Unless its rev approval further funds can not be utilized. LIST OF MEGA PROJECTS COSTING RS. 200.00 MILLION & ABOVE Provision for 2015- 16 ON-GOING SCHEMES

LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Embed Size (px)

Citation preview

Page 1: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sector WATER SUPPLY & SANITATION Rs.in Million

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

1 1014 Bulk Water Supply Project from River Jhelum to

Murree

Rawalpindi 4254.770 963.049 100.000 100.000 50.000 0.000 0% 963.049 23% PC-I under approval.

2 1016 Installation of Water supply scheme for residents

of Fateh Jang Attock

Attock 469.913 78.546 50.000 50.000 70.425 70.400 100% 148.946 32% A.A 21.10.2014

T.S 10.11.2014

Date of award 22.01.2015

1) Work is in progress. More Fund are required.

(1) Feeding Main (0%), (2) Water Treatment Plant

(40%), (3) Staff Quarter Lab (95%), (4) Pumping

Machinery (arranged), Clear, GST (0%), (5) Rising

Main (60%), (6) OHR 50000 Glns (10%), (7) GST

4000000 Glns (80%), (8) Pump House (0%), (9)

Water Distribution Network (52%), (10) Water Meters

(0%), (11) O.H Electrification (0%), (12) Aqusition for

land (0%).3 1017 Urban Water Supply Scheme Chakwal Based on

Khai Dam, Tehsil Chakwal, District Chakwal

Chakwal 547.636 78.085 50.000 50.000 42.500 31.875 75% 109.960 20% Work on filtration plant on Khai Dam is in progress.

On the direction of Chief Minister Punjab revise

estimate has been submitted for approval in P&D

office Lahore.

4 1018 Water Supply Scheme based on Naroomi Dhan

Spring Phase-II, Tehsil Pind Dadan Khan,

District Jhelum.

Jhelum 286.994 224.986 40.994 40.994 40.994 30.500 74% 255.486 89% A.A: 10-04-14

T.S: 16-4-14

Work allotted :

Group-I 30-05-2014

Group-II 24-10-2014

Work is in Progress. Scheme is partially operational.

5 1023 Augmentation of Water Supply Scheme,

Sargodha based on canal water supply Phase-I

Sargodha 268.210 100.127 50.000 50.000 54.000 48.726 90% 148.853 55% Date of A.A 28.02.2014, Date of T.S 30.04.2014,

Date of Award 28.06.2014, Scheduled date of

Completion is 30.06.2016, Date of Commencement,

28.06.2014, Funds released on 24.08.2015, Funds

on-lined on 24.08.2015.

20-No. tube wells completed out of provision 22-No.

09-No. Pump Houses 90% completed out of

provision 22-No. 31-Sets of Pumping machinery

arranged. R/Main / D-System 59901-Rft laid & 10502-

Rft arranged out of provision 124038-Rft. 4-No.

GSTs 85% completed out of 05-No. Work in

progress. 6 1026 Comprehensive Water Supply & Sewerage

Scheme Khushab

Khushab 319.000 314.500 50.000 50.000 20.000 8.690 43% 323.190 100% Date of A.A 08.10.2009

Date of T.S 05.11.2009

Date of award 06.01.2010.

Scheme Functional. Water is beng supplied to

khushab city.Petty works in progress.All Sewer lines

are also functional. Funds released on 28.09.2015.

Rev.estimate submitted to Secretary HUD & PHED

for onward transmission for approval from

PDWD.Unless its rev approval further funds can not

be utilized.

LIST OF MEGA PROJECTS COSTING RS. 200.00 MILLION & ABOVE

Provision

for 2015-

16

ON-GOING SCHEMES

Page 2: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

7 1027 Comprehensive Urban Water Supply &

Sewerage / Drainage Scheme Jauharabad

Khushab 479.340 355.519 50.800 50.800 56.800 42.800 75% 398.319 83% Date of A.A 08.10.2009

Date of T.S 05.11.2009

Date of award 11.08.2010

All 10 No. Tubewell with pump house, pumping

machinary and GST 800000 Gln completed. Work of

laying of water supply pipe line is in Progress. 2 out

of 3 disposal works completed and functional. Rev.

rough cost estimate submitted to secretary HUD &

PHED for onward transmission for approval from

PDWD.8 1028 Comprehensive Water Supply & Sewerage

Scheme Mianwali

Mianwali 494.444 421.505 4.980 4.980 8.099 6.595 81% 428.100 87% Date of A.A 16.01.2014

Date of T.S 08.08.2014

Date of 2nd Revised A.A 04.11.2015

Date of Revise T.S 10.12.2015.

Revised date of Completion 30.06.2016

Fund released on 21.09.2015

Tube-Well=8/8, Pump House=8/8, Pumping

Machinery=9/9, Rising Feeding Main=12"i/d A.C=

921/940, 10" i/d A.C= 11959/11960, 8" i/d

PVC=26535/26541, 6"i/d PVC= 30244/30591,4"i/d

PVC=40592/40583, 3"i/d PVC=137262/137106, OHR

= 3/3, Chlorinator = 8/8, T/Line 5/8, RCC

Sewer=42"i/d= 480/475, 36"i/d =8385/8337, 30"i/d

=2159/2235, 27"i/d=8694/8784, 24"i/d=12415/12856,

21"i/d=14020/14473, 18"i/d= 21777/23087,

15"i/d=27821/29188, 12"i/d=131182/137915,

9"i/d=30888/28626, Sullage Carrier= 7850/8500,

Oxidation Pond= 1/2. Work is in progress. Additional

Fund Rs.64.840 M are required to complete the

scheme in C.F.Y

9 1029 Urban Water Supply T.T.Singh (Revised) T.T.Singh 820.700 625.478 40.000 40.000 40.000 32.778 82% 658.256 80% 1-Date of A.A 09.12.2010

2- Date of T.S 07.01.2011

3-Date of Prequalification 15.01.2011

4-Date of invitation of tenders 07.02.2011

5- Date of Receipt of tenders 07.02.2011

6- Date of work oder 14.02.2011

7- Date of A.A 10-04-2014 (Revised)

8- Date of T.S 15-04-2014 (Revised)

9- Anticipated date of completion 30.06.2016 (if full

funds recieved).

10-Funds Released by F.D 10.08.2015 & 17.02.2016

11-Funds online on 20.08.2015 & 22.02.2016

Physical Progress 80%.Tube-Wells 2-Cfs = 9/9,

Pump House /

Transformer Room,At Tube-wells = 12 / 12,

Collector Main 12"i/d AC "B" = 1809 /2000 14"i/dAC

"B" = 1694 / 2000, 16"i/d AC "B" = 1725 / 2000, 18"i/d

AC "B" = 1755 / 2000, Transmission Line 6"i/d AC

"B" = 2582 / 2750 10"i/d AC "B" = 6556 / 6600, 14"i/d

AC "B" = 2200 / 2200, 18"i/d AC "B" = 9850 / 9980 ,

32"i/d GRP "B" = 62105 / 90673, 32"i/d GRP "C" =

15080 / 17000, 32"i/d MS = 825 / 825 , RCC G.S.T At

IPS 5-Lac Glns = 2 / 2 At Wariamwala 1-Lac Glns = 1

/ 1 At Water Works 1 & 2 2-Lac Glns = 2 / 2,Pumping

Machinery For T/Wells 80-BHP = 9 / 9 For IPS 180-

BHP = 4 / 4 For GST 25-BHP = 1/ 1 Central Control

Room = 0 / 1 Electric Transmission Line = 11 / 14

(DN Paid), Railway Road, Suigas & Canal Crossing =

Page 3: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

10 1030 Urban Water Supply Scheme for Pir Mahal

Tehsil Kamalia, District T.T. Singh. (Amended)

T.T.Singh 321.427 314.979 20.827 20.827 20.827 17.911 86% 332.890 100% 1-Date of A.A 14.05.2012

2- Date of T.S 28.01.2013

3-Date of Prequalification 11.09.2012

4-Date of invitation of tenders 16.02.2013

5- Date of Receipt of tenders 16.02.2013

6- Date of work oder 21.02.2013

7- Date of A.A 22.01.2013 (Revised)

8- Date of T.S 28.01.2013 (Revised)

9- Anticipated date of completion 30.06.2016

10-Funds Released by F.D 10.08.2015 & 17.02.2016

11-Funds online on 20.08.2015 & 22.02.2016

Tube-Wells 2-Cfs = 5/5 (100% completed), Pump

House /

Transformer Room At Tube-wells = 6/ 6 ( 100%

completed), Collector Main 12"i/d AC "C" = 1000

/1000 14"i/d AC "C" = 1000 / 1000, 16"i/d AC "C" =

1000 / 1000, 18"i/d AC "C" = 1000 / 1000,

Transmission Line 8"i/d AC "B" = 0 / 500 10"i/d AC

"B" = 800 / 915, 14"i/d AC "B" = 3455 / 3538, 16"i/d

AC "B" = 2065 / 2065 18"i/d AC "B" = 8700 / 8710 ,

20"i/d AC "B" = 21198/ 21200, 20"i/d AC "C" = 3300 /

3300, Distribution System 3"i/d PVC "B" = 257269' /

260540' (laid) 4"i/d PVC "B" = 85848' / 85207' , 6"i/d

PVC "B" = 29210 / 28892, 8"i/d PVC "B" = 12000 /

12371 , 10"i/d PVC "B" = 4736 / 4738, 12"i/d PVC

"B" = 5576/ 5602, 14" i/d AC 2400/2400, 16" i/d AC

1970/1980. RCC G.S.T At IPS 4-Lac Glns = 2 / 2

(100% completed),Pumping Machinery = 8 / 8 set

arranged , OHR 3/3 (100% completed) ,Electric

Transmission Line = 8 / 9 , Railway Road, Suigas 11 1032 Comprehensive Water Supply Scheme Kamalia

City

T.T.Singh 426.211 109.725 30.000 30.000 30.000 30.000 100% 139.725 33% 1- Date of A.A Revised -

8- Date of T.S Revised -

9- Anticipated date of completion 30.12.2017

10-Funds Released by P&D

11-Funds Released by F.D 10.08.2015 & 17.02.2016

12-Funds online on 20.08.2015 & 22.02.2016

14-Project detail:-

Trial Bore= 7/8-Job, T/Well= 2-Cusec=7/8 No.

P/House= 7/8-No., R/Main & D/System,=16" i/d

AC=0/700', 14" i/d PVC= 370/1030', 12" i/d

PVC=580/3010', 10" i/d PVC= 3428/9395', 8" i/d

PVC= 20126/47834', 6" i/d PVC= 45457/115776', 4"

i/d PVC=26920/53600', 3" i/d PVC=164917/523064',

P/machinery,75-BHP=8/8-Set arranged, OHR,

500000-Glns=0/2 Nos, Hypochlorinator=0/8 Nos., Sui

Gas, PTCL line and road crossing=0/3-Job,

Boundary wall=0/8-Job, Staff quarter=0/1 No.,

Electric Transmission line=0/8-Job. Full funds

utilized. Work is in progress.

Page 4: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

12 1033 Construction of Urban Water Supply Scheme

Gujrat

Gujrat 684.050 381.192 70.000 70.000 70.000 39.000 56% 420.192 61% *Start Date 30.06.2009

*Completion date 30.06.2016. A.A Date =10.02.2009

T.S date=6.5.2009

PVC Pipe of 12" 6979 Rft Laid PVC Pipe of 10" 76367 Rft

Laid PVC Pipe of 8" 140882 Rft Laid PVC Pipe of 6"

88305 Rft Laid PVC Pipe of 4" 219397 Rft Laid Work in

progress of laying of pipe line. 12 Nos Tube wells out of 17

Nos are functional and 12 Nos T/W Handed over to TMA

Gujrat and 2 Nos OHR's are functional. Work is in

progress.Funds (2nd half) received on 29.02.2016.

13 1041 Water Supply Scheme for Shah Kot Town ,

District Nankana Sahib

Nankana Sahib 214.373 198.264 23.498 23.498 23.498 20.600 88% 218.864 100% A.A 05.12.2014

T.S 09.01.2015

Date of award of work18.06.2008

Tubewell boring 10/10. No

Pumping Chamber 12'x12' 10/10 No

Pumping Machinery 0.5 Cusec BHP 30 Head 370

10/10 set

Electric Connection Demand notice paid

3"i/d PVC Class B 123520/127919 Rft

4"i/d PVC Class B 32737/38340 Rft

6"i/d AC Class B 36349/35660 Rft

8"i/d AC Class B 3656/3810 Rft

10"i/d AC Class B 3883/3850 Rft

12"i/d AC Class B 2445/2583 Rft

16"i/d AC Class B 1330/1142 Rft

Rising main 6"i/d AC Class D 1011/1000 Rft

8"i/d AC Class D 993/1000 Rft

10"i/d AC Class D 1487/1000 Rft

12"i/d AC Class D 2350/1700 Rft

12"i/d AC Class B 6329/5800 Rft

18"i/d AC Class C 24960/24960 Rft

18"i/d AC Class B 23950/23950 Rft

GST/ 275,000 & 60,000 Glns 90/100%

Pumping Machinery for GST Q=2.5 Cusec BHP 50

Head 100 2/2 Set

O.H.R 100,000 Glns 1/1. No

The Scheme is under test operation .

Page 5: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

14 1042 Urban Extension Water Supply & Sewerage

Scheme Nankana Sahib

Nankana Sahib 236.068 169.186 40.954 40.954 35.954 30.500 85% 199.686 85% A.A 10.04.2013

T.S 13.05.2014

Date of award of work 29.03.2010

Aquifer test Electric Survey and Trial Boring 1/1

Installation of Tube Wells. 13/14

Pump House 12x12. 10/14

Pumping Machinery 14/14

(V.T) Dis 0.5 Cusec Head 300’.

External Electrification 0/16 Paid to WAPDA.

20”i/d AC/GRP B Class Pipe 31439 / 32270

A.C 20”i/d AC/GRPC-Class Pipe 5063 /5100

A.C 16”i/d B-Class Pipe 959 /5100

A.C 14”i/d B-Class Pipe 4912 /5900

A.C 14”i/d C-Class Pipe 1477 /1500 RFt

A.C 12”i/d B-Class Pipe 3026/5350

A.C 12”i/d C-Class Pipe 1000 /1000 Rft

A.C 10”i/d B -Class Pipe 6692/6850

A.C 10”i/d C - Class Pipe 1758/2000

A.C 8”i/d B-Class Pipe 3790 /4250

A.C 8”i/d C-Class Pipe 1000/1000

A.C 6”i/d C-Class Pipe 844/1000

PVC 3” I/d Pipe 0/6000 arranged

PVC 4” I/d Pipe 0/8900 arranged

Staff Quarter 3/6

Generating Set 200 KVA. 0/3

Const: of G.S.Tank.

400000 Glns Capacity 1/1

200000 Glns Capacity 0/1

Hypochlorinator 0/6

Pumping Machinery for G.S.T (V.T) Dis 2.0 Cusec

Head 120’. 6/6

Renovation of Existing OHR 0/115 1043 Urban Water Supply & Sewerage/ Drainage

Scheme Phool Nagar

Kasur 444.328 444.348 5.617 5.617 10.617 8.494 80% 452.842 100% Date of A.A :14-04-2009

Revised Date of A.A : Nil

Date of T.S :18-04-2009

Date of Award :28-05-2009

Scheduled date of Completion on :04/12/2010

Revised date of Completion :30/06/2016

Date of Commencement :28-05-2009

Funds released on :02/08/2014

Work in Progress16 1047 Extension / Improvement of Water Supply

Scheme Southern City, Okara.

Okara 864.000 391.239 104.238 104.238 112.238 100.756 90% 491.995 57% (1) Date of AA-21.04.2014

(2) Date of TS-28.04.2014

(3) Date of Pre-qualification.23.04.2014

(4) Date of Invitation of Tender.13.05.2014

(5) Date of Receipt of Tenders.13.05.2014

(6) Date of work Order.27.05.2014

(7) Date of completion As per PC-I. 30.06.2017

(8) Anticipated date of completion. 30.06.2017

(9) Re-appropriation of funds (+/-) (+) 8.00 dt:

20.01.2016,

(10) Project Details.

Physical progress 62%

(1)Tubewell 26/26, (2) Pump House 26/26 (3)

Rising Main & Distribution System 3" to 24“ i/d

43491/440615, (4) OHR 100000 Glns 4/5,( 80 %) (5)

GST 4/4, (85%) (6) Pumping Machinery 0/45,(7) Staff

Quarter 2/4 (8) External Electrification Demand

Notices Paid to WAPDA (9) Boundary Wall 991/2660

. Work in Progress.

Page 6: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

17 1051 Urban Water Supply & Sewerage Scheme

Pakpattan & Arifwala District Pakpattan

Pakpattan 727.216 662.396 50.722 50.722 18.082 18.082 100% 680.478 94% Date of AA = 17.01.2009

Date of T.S = 07.02.2009

Work Award = 20.03.2009

Scope of Work

Sewerage

(1) RCC Sewer

(i) 9" i/d = 9744/81965 Rft. (ii) 12" i/d = 86467/80387

(iii) 15" i/d = 31788/30115 Rft. (iv) 18" i/d =

13495/13835 Rft

(v) 21" i/d =3793/3735 Rft. (vi) 24" i/d = 11749/4215

Rft.

(vii) 27" i/d = 1260/1260 Rft. (viii) 30" i/d = 4040/6218

Rft.

(ix) 33" i/d = 5167/6675 Rft. (x) 36" i/d = 9252/12354

Rft.

(xi) 42" i/d = 17397/10365 Rft.

(2) Disposal works

(i) Screening Chamber = 4/4 No. (ii) Collecting tank =

8/8 No.

(iii) Control panel = 9/10 No. (iv) P/ Machinery =

16/16 Set.

(v) GRP Forcemain = 5044/4900 Rft. (vi) Over Head

Transmission line = 5/5 Job. (vii) Inter connection =

4/4 Job.

(viii) Pacca Sullage Carrier=13608/18600 Rft.

(ix) Boundary wall = 3833/4233 Rft. (x) Staff Quarter

= 11/14 No.

(xi) Diesel Oil Generator= 6/6 No.

Water Supply

(i) Tubewell = 24/24 No. (ii)Pump House =24/24 No.

(iii) P. Machinery = 24/24 Set. (iv) E/Electrification =

24/24 Job. 18 1054 Rehabilitaion of Urban Water Supply Scheme

Fort Minroe

D.G.Khan 257.064 9.998 50.384 50.384 70.384 70.384 100% 80.382 31% • Date of A.A =01.04.2015

• Date of TS =04.05.2015

• Date of Prequalification = 07.01.2015

• Date of invitation of tenders = 05.05.2015

• Date of receipt of tenders = 20.05.2015

• Date of work order = 12.06.2015

• Date of completion as per PC-I = 31.03.2017

• Anticipated date of completion = 30.06.2017

• Funds released by P&D = ADP Allocation

• Funds released by FD = 10.08.2015 (I) &

17.02.2016 (II)

• Re-appropriation of funds = + 20.00 Million

(25.11.2015).

Scope of Work

WSB ON RAKHNI STREAM

Invest: of Source = 2/2 job, T/W =2/2, P/H for T/W

2/2, New P/H for T/W = 5/5 Set, Const: of RCC GST

100000 Gln 1/1, P/M for B.S/IPS = 0/(3+3=6), P/M

for GST W/W FM = 0/2 Set,

DISTRIBUTION SYSTEM FOR F.MUNROE

4" i/d G.I = 4200/4560,

3" i/d G.I = 3500/9165,

2" i/d G.I = 4050/10920,

1-1/2" i/d G.I = 2800/18810,

E/Connection for T/W = 0/1,

Diesel / Generator 400 KVA = 0/3,

Generating Room 20x12 = 3/3,

Repair of Construction of Staff Quarter Rakni field =

2/2, Const: of Store Room at Fort Munroe = 0/1,

Page 7: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

19 1057 Urban Water Supply Scheme,Muzaffargarh

(Ammended) (PSDP)

Muzaffargarh 419.689 362.833 20.221 20.221 24.721 18.170 74% 381.003 91% • Date of A.A 10.11.2008

• Date of TS 04.02.2009

• Date of Prequalification NIL

• Dated of invitation of tenders 18.2.2009

• Dated of receipt of tenders 07.3.2009

• Dated of work order 27.03.2009

• Dated of completion as per PC-I = 09.11.2011

• Anticipated date of completion 30.06.2017

• Funds released by P&D = ADP Allocation

• Funds released by FD = 10.08.15 (I) & 17.02.2016

• Re-appropriation of funds = (-) 4.00 M (25.11.2015)

& (+) 4.500 M (25.11.2015)

• Project Details

TW-24/24, PH-22/24 Nos.PM-(TW) 7/24 17

arranged, (GST) 11/20 9 arranged, RM-8" to 24" i/d

27386 / 51326 Rft Dist. Sys.3" to 22" laid. 633200 Rft.

/674002. Elect.2/6.SQ-3/6

BW-15680/4296 Rft. OHR-3/6, D-Gen-2 sets 2/4

Sets, GST-6/9 No.

• Zone 6 is already completed and tested. TMA M.

Garh is not ready to take over due to financial

constraints. Zone-1 is also complete.

• Work is in progress

20 1059 Rehabilitation and Agumentation of Water Supply

Scheme, Bahawalpur

Bahawalpur 282.533 250.240 10.060 10.060 2.510 1.950 78% 252.190 89% Date of AA :29-11-2006

Date of TS :08-01-2007

Date of RAA: 17-04-2014.

Date of RTS. 17-04-2014

Date of invitation of tenders.06-02-2007.

Date of receipt of tender.14-02-2007.

Date of work order:17-03-2007.

Date of completion as per PC-1=28-11-2007

Date of completion as per agreement=16-03-2008.

Anticipated date of completion 30-06-2017.

Funds released by FD on 10-08-2015 & 17-02-2016.

Funds onlined on 20-08-2015 & 22-02-2016.

Re-appropriation of funds=(-Rs.4.00 +3.550=7.550

Million )vide C.E(S), PHED office letter No.Re-app-

2015-16/3758-71/B(4) dated 25-11-2015 & No.2402-

06/B(4) dated 29-03-2016.

Reason for slow progress=Water supply at Maqbool

Colony, Islami Colony, Model Town C completed,

functional and handed over to TMA city Bahawalpur

w.e.f 30-04.2014. Balance portion of the scheme

(Model Town-B, Karana Basti, Kousar Colony & Trust

Colony) is under test operation. Balance work for

laying of 3” GI pipe 22680 Rft is pending by the

contractor.

During the inspection of Chief Engineer(S), PHED

Lahore on 06-03-2016 the narrow streets in which 3"

dia GI pipe has to be laid was visited and laying of

pipe inside narrow street is not feasible at this stage.

However testing of old distribution is in progress and

shell take long time to complete because the

distribution has laid 08 years ago and damaged due

to laying of sui gass pipe line in the same streets.

Page 8: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

21 1062 Water Supply Scheme Sadiqabad, Tehsil

Sadiqabad, District R.Y. Khan.

R.Y.Khan 692.527 141.067 100.000 100.000 119.000 97.192 82% 238.259 34% A.A issued on 12-05-2014.

Date of T.S. 26-05-2014.

Stay order granted by M/S Jam Brothers against

prequalification of the contractor. Stay vacated on 03-

12-2014.

Date of prequalification=21-07-2014

Date of invitation of tenders=04-12-2014

Date of receipt of tenders = 22-12-2014.

Date of work order= 03-01-2015.

Date of completion as per PC-1=11-11-2016

Date of completion as per agreement= 30.06.2017.

Funds released by FD on 10-08-2015 & 17-02-2016.

Funds onlined on 20-08-2015 & 22-02-2016.

Re-appropriation of funds(+ Rs.19.00 M) vide Chief

Engineer(S), PHED Lahore office letter No.2402-

06/B(4) dated 29-03-2016.

Consultans engaged by Govt. on 8-1-2015. Team of

consultant joined duty on 13-2-2015. Work is in

progress.

Physical Progress: 43%

1.Tube well = 10 Nos./10 No.(100%)

2. Pump House = 10 Nos.(50%)

3. Pumping Machinery = 10 Sets

4. Rising Main / Distribution System 14" to 20"=87186

Rft/41006 Rft laid. Balance Work is in progress.

5. IPS 450000 Gallians G.S.T. = 3 Nos.

6. G.S.T. 200000 Gallians = 1 No.

7. G.S.T. 100000 Gallians = 2 Nos.

8. G.S.T. 50000 Gallians = 1 No.

9. Boundary Walls = 1 Job

10. Pumping Machinery for IPS = 5 Nos.

11. Pumping Machinery 30 BHP for G.S.T = 2 Nos.22 1066 Urban Sewerage Scheme Jhelum with Treatment

Plant

Jhelum 434.800 300.921 50.914 50.914 45.614 0.180 0% 301.101 69% orignal A.A= 434.800

Revise A.A= 539.592

T.S Under process

Scheme has been revised and Adminitratively

approved vide.

No.SO(PH-S)9-16/2015 (Jhelum)

dt:.29.03.2016.

Fundes will be utilized after Technical Sanction

& award of work.

23 1067 Comprehensive Sewerage Scheme Bhalwal

Colonies

Sargodha 206.000 180.000 20.100 20.100 9.000 5.209 58% 185.209 90% Date of A.A 25.06.2009, Revised Date of A.A

31.01.2014, Date of T.S 29.06.2009, Date of Award

24.11.2009 & 04.12.2009, Scheduled date of

Completion on 12.2010, Revised date of Completion

30.06.2016, Date of Commencement, 24.11.2009 &

04.12.2009, Funds released on 24.08.2015, Funds

on-lined on 24.08.2015.

The scheme was divided in to three zones. Zone III

handed over to TMA and Zone I & II are under test

operation. Revised Rough Cost Estimate submitted

to Govt: for seeking revised approval from P&D

Department to clear the liability of price variation and

demand notice for restoration of roads by TMA

Bhalwal.

Page 9: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

24 1070 Urban Sewerage Scheme for (Islam Pura, Zafar

Colony, Qartaba Town, Jauhar Colony, Sultan

Town, Shirazi park, Mujhid Colony, Ali Town,

Gilwala Including Adjacent Colonies) & Abadies

of (Yousaf park, Aziz Colony, Bashir Colony,

Nawab Colony, Ch

Sargodha 389.887 0.000 70.000 70.000 70.000 57.402 82% 57.402 15% Date of A.A 09.06.2015, Date of T.S 17.06.2015,

Date of Award 31.07.2015, Scheduled date of

Completion is 30.07.2017, Date of Commencement,

31.07.2015, Funds released on 24.08.2015, Funds

on-lined on 24.08.2015.

Work on screening chamber, collecting tank,

pumping chamber is in progress.

25 1075 Urban Sewerage & Drainage Scheme Pir Mehal. T.T.Singh 290.460 40.000 30.000 30.000 30.000 30.000 100% 70.000 24% 1-Date of A.A 16.10.2014

2- Date of T.S 03.12.2014

3-Date of Prequalification 08.12.2014

4-Date of invitation of tenders 23.12.2014

5- Date of Receipt of tenders 23.12.2014

6- Date of work oder 31.12.2014

7- Anticipated date of completion 30.12.2016

8-Funds Released by F.D 10.08.2015 & 17.02.2016

9-Funds online on 20.08.2015 & 22.02.2016

10-Project detail:-.

Survey investigation & design services= 0/1-Job,

RCC Sewer 12" i/d =5573/53220 Rft (12000-

arrainged), 15" i/d =1124/1526 Ft (1000-

Arrainged), 18" i/d =1900/5759 Ft, 21" i/d

=1870/6838 Ft (2000-arraneged), 24" i/d

=1697/3245 Ft (1000-arranged), 27" i/d =0/5880 Ft

(2000-arrainged), 36" i/d =500/932 Ft (450-

arrainged), Force main & sullage carrier, a, Force

main zone A, 24" i/d =0/4200, zone B, 24" i/d=0/3000,

zone C 32" i/d=0/1100-Ft, b, Sullage carrier, zone

A,=0/2000', zone B,=0/2000', zone C=0/3000', Sump

well=0/2 No. Pumping chamber 25 dia=0/1 No 65%.

screening chamber zone A=0/1 No. 10% zone C=0/1

No 90%. Collecting tank, zone A, 25' dia=0/160% No.

zone C 25' dia=0/2 No.90%, P/Machinery= 0/7-Set

(arranged), Inter connection, Zone A & B=0/2-Job.

Zone C=0/1-Job, Surface drain=0/130552', Brick 26 1076 Urban Sewerage Drainage Scheme Kamoke,

District Gujranwala. (under revision)

Gujranwala 327.115 303.983 40.000 40.000 20.000 8.500 43% 312.483 96% *Start Date 14.04.2009.

*Completion date 30.06.2016.

The scheme completed as per approved scope.

Claim of contractor Rs. 5.5 Million is pending,. The

scheme is sent for approval. If it is approved, the

payment to the contractor will be made otherwise the

funds which received in excess are proposed to be re-

appropriated to other fast moving schemes.

27 1107 Kasur Environmental Improvement Project,

Disrtict Kasur

Kasur 2272.769 1492.890 36.000 36.000 3.000 2.802 93% 1495.692 66% Date of A.A :04/02/2009

Revised Date of A.A :Nil

Date of T.S :20/05/2009

Date of Award :29/06/2009

Scheduled date of Completion on :28-06-2011

Revised date of Completion :30/06/2017

Date of Commencement :29/06/2009

Funds released on :02-08-2014

Funds on-lined on :

Funds Re-appropriated

Page 10: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

28 1108 Urban Sewerage Drainage Scheme, Pattoki Kasur 650.734 473.794 50.180 75.180 90.180 83.549 93% 557.343 86% Date of A.A :14/09/2009

Revised Date of A.A :Nil

Date of T.S :29/10/2009

Date of Award :30-12-2009

Scheduled date of Completion on :29-06-2011

Revised date of Completion :30/06/2016

Date of Commencement :29/10/2009

Funds released on :02-08-2014

Work in Progress. 29 1115 Urban Drainage PCC & Brick Pavement Scheme

Kasur City

Kasur 457.681 29.999 50.000 60.000 59.999 59.130 99% 89.129 19% Date of A.A :09.02.2015

Revised Date of A.A :Nil

Date of T.S :10.03.2015

Date of Award :

Scheduled date of Completion on :

Revised date of Completion :

Date of Commencement :

Funds released on : 03.04.2015

Work in Progress30 1119 Construction of Sewerage Scheme Renala Khurd

City, District Okara Ammended.

Okara 314.972 199.941 20.000 20.000 22.000 17.600 80% 217.541 69% (1) Date of AA-02.04.2014

(2) Date of TS-14.04.2014

(3) Date of Pre-qualification.10.04.2014

(4) Date of Invitation of Tender,05.05.2014

(5) Date of Receipt of Tenders,05.05.2014

(6) Date of work Order.13.05.2014

(7) Date of completion As per PC-I. 30.06.2016.

(8) Anticipated date of completion,30.06.2017

(9) Project Details.

Physical progress-66% ,

(1)R.C.C Sewer 48"i/d (Trunk) 32850/3100 (ii) R.C.C

Sewer 9"to 42"i/d= 1492/39825 , (2) Sullage Carrier

105/800 (3) Protection Wall for Seepage Drain

250/250, Work in Progress31 1121 Complete Repair and renovation of Sewerage

system including pcc, drains, water channels,

solling, tough tiles in Basir Pur District Okara

Okara 211.905 67.424 30.000 30.000 43.500 35.151 81% 102.575 48% (1) Date of AA-11.04.2014

(2) Date of TS-20.06.2014

(3) Date of Pre-qualification,05.05.2014

(4) Date of Invitation of Tender,28.06.2014

(5) Date of Receipt of Tenders,30.06.2014

(6) Date of work Order.17.07.2014

(7) Date of completion As per PC-I. 30.06.2017

(8) Anticipated date of completion,30.06.2017

(9) Re-appropriation of funds (+) Rs. 8.300

dt; 31.03.2016

(10) Project Details.

Physical progress- 48%

(1)Screening Chamber 1/1, (2)Collecting Tank 20'

dia 2/2, (3)Pumping Chamber 25'dia 1/1, (4)Pumping

Machinery 3 & 2 cusec 4/4 (5) R.C.C Sewer 9"& 30“

i/d 31683/44024, (6)External Electrification 1/1,

(Payment made to WAPDA)(7)Sullage Carrier

3200/3400, (8)Boundary wall 400/400, (9)Staff

Quarter 1/1, (10)Tuff Tile 0/517814Sft, (11) Surface

Drain 1200/2615 (12) Brick Pavement 0/12999 Cft

(13) P.C.C 4307/6197 Cft (14) Storm Water Channal

13365/15372 Work in Progress

Page 11: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

32 1122 Sewerage Scheme DepalPur City District Okara Okara 300.355 24.894 40.000 40.000 50.000 39.433 79% 64.327 21% (1) Date of AA-09.04.2010

(2) Date of TS-18.08.2010

(3) Date of Pre-qualification,20.03.2015

(4) Date of Invitation of Tender,09.05.2015

(5) Date of Receipt of Tenders,10.05.2015

(6) Date of work Order.24.11.2010 & 03.09.2015

(7) Date of completion As per PC-I. 30.06.2017

(8) Anticipated date of completion,30.06.2018

(9) Re-appropriation of funds (+) Rs. 10.00

dt; 31.03.2016

(10) Project Details.

Revise A.A Costing Rs. 300.355 M dated 31.10.2014.

(1)Screening Chamber 2/2,(75%) (2)Collecting Tank

4/4 (75%) ,(3)Pumping Chamber 1/2, (4)Pumping

Machinery 8/8 (arranged),(5) R.C.C Sewer 9" to 42"

i/d 12160/ 99899 (6)External Electrification 1/2

(Payment made to WAPDA, (7)Sullage Carrier

3000/14975 Rft, (8) staff Quarter 1/1 (80%).(9) Drain

0/7000 Rft (10) Bricks Pavement.0/64681 Rft. (11)

Complaint Cell 0/1. (12) Force Main 24" i/d

1500/1500 Rft (Arranged) . Work in Progress

33 1126 Rehabilitation / extension of sewerage / drainage

system of Mian Channu City

Khanewal 299.976 40.000 69.525 69.525 69.525 69.525 100% 109.525 37% 1. Date of AA: 12-02-2015.

2. Date of TS: 05-03-2015.

3. Date of Pre-qualification 19-03-2015

4. Date of invitation of tender. 11-04-2015

5. Date of Receipt of tender. 23-04-2015

6. Date of Work order. 11-05-2015

7. Date of Completion as per PC-I. 11.02.2017

8. Anticipated date of Completion. 30-06-2017

9.. Funds released by FD. 17-02-2016

110. Funds onlined on. 20.02.2016

11. Projects details.

1. R. C. C. Sewer

9" i/d 13611 Rft 12" i/d 11553 Rft

15" i/d 3891 Rft 18" i/d 2731 Rft

21" i/d 3226 Rft 24" i/d 2064 Rft

27" i/d 1980/850 Rft 30" i/d 980 /400 Rft

33" i/d 1915/1673 Rft 36"i/d 983/1500 Rft

42" i/d 2777/400 Rft.

2. S. Chamber 12.125'x 25.375' = 1 No/80%.

3. C/T 25' i/d = 2 Nos/80%.

4. P.Chmber 25' i/d = 1 No/80%

5. P/M 4 = Nos. 6. G/Room 25'x15' = 2 Nos.

7. D/G 2 = Nos. 8.O/F Chamber 6'x4'= 1 No.

9. Staff Quarter 4 Nos/75 %. 10. B. Wall 1050/1050

ft

11. I/C 1 Job 12. EC= 1 Job

13. B/P 2566 Cft 14. F/Main GRP 17800 Rft

15. Acquisition of Lank Zone A =1 Job/Under

Process.

16. Reh: of Treatment Plants = 1 Job.

Page 12: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

34 1127 Provision of drainage / sewerage, soling & water

supply in Municipal Area of Burewala City.

Vehari 358.775 50.000 50.000 50.000 49.600 32.500 66% 82.500 23% 1. Date of A.A: 29.12.2014.

2. Date of T.S: 12.03.2015

3. Date of Pre-Qualification: 13.03.2015

4. Date of Invitation of Tender: 10.04.2015

5. Date of receipt of Tender: 11.04.2015

6. Date of Award: 20.04.2015

7. Date of Completion as per PC-I: 28.12.2016

8. Anticipated Date of Completion: 30.06.2017

9. Funds released by F.D: 17.02.2016

10. Funds online on: 22.02.2016

11. Project Detail.

Trial Bore = 2/2, T/W= 1/2, PH=0/2, PM= 0/2,

RM 8" i/d PVC = 0/1800 Rft, Hypochlorinator =0/2,

Ex. Elect = 0/2, Staff Quarter 2 Room = 0/3, Survey

Investigation and Design Service = 1/1 Job, R.C.C.

Sewer 9" i/d= 11500/50586 Rft,

12" i/d= 8000/19541 Rft, 15" i/d= 0/6482 Rft,

18" i/d= 1524/6289 Rft, 21" i/d= 0/1160 Rft 24" i/d=

0/3789,

27" i/d= 0/7315, 30" i/d= 0/6415, 33"i/d= 0/10343,

36"i/d= 0/956, 42"i/d= 0/9839, 48"i/d = 0/93 Rft,

Control Room12'x12'= 0/1, Screening Chamber

14'x28'= 0/1, Collecting Tank 26' Dia = 0/2 No.,

Pumping Machinery 6 Cusec =0/2 Set, Pumping

Machinery 4 Cusec =0/2 Set,

Forcemain= 0/9275 Rft, Sullage Carrier = 0/100 Rft,

Inter Connection = 0/1 No, Discharge Sump = 0/1

No.,

Generator 200 KVA = 0/1 No., Boundary wall =

0/453 Rft,

Ext Electrification = 0/2 Job,

Surface Drian Type-I = 0/1000 Rft, Brick Pavement = 35 1129 Comprehensive Sewerage / Drainage Scheme

Taunsa Sharif including Tuff Tilling of Streets

D.G.Khan 485.406 19.986 50.000 50.000 50.000 40.000 80% 59.986 12% • Date of A.A = 12.02.2015

• Date of TS = 29.04.2015

• Date of Prequalification = 07.01.2015

• Date of invitation of tenders = 03.04.2015

• Date of receipt of tenders = 20.05.2015

• Date of work order = 27.05.2015

• Date of completion as per PC-I = 11.02.2017

• Anticipated date of completion = 30.06.2017

• Funds released by FD = 17.02.2016 (II).

• Re-appropriation of funds = + 25 M (18.09.2015)

Scope of Work

RCC SEWER

9" RCC = 28416/200217,

12" RCC = 12416/15492,

15" RCC = 3894/5310,

18" RCC = 3237/4120,

21" RCC = 1284/4425,

24" RCC = 872/1000,

Sullage Carrier = 0/2400,

Tuff Tile = 45078/3273647

Work in progress.

Page 13: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

36 1131 Urban drinage/sewerage/tuff tile scheme in

Jampur City (replacement of outlived sewer and

new sewer system in Faisal Colony, Shah Jamal

Colony and Tattar Wala)

Rajanpur 365.753 50.000 70.000 70.000 60.000 46.200 77% 96.200 26% 1. Date of A.A = 23.12.2014

2. Date of T.S = 26.02.2015

3. Date of pre-qualification = 18-2-2015

4. Date of reciept of Tenders 11.03.2015

5. Date of work order = 26.03.2015

6. Date of completion as per PC-I = 17.02.2016

7. Anticipated date of completion 30.06.2017

8. Funds released by FD = 10.08.2015 (I)

& 17.02.2016 (II)

9.. Re-Appropration of funds = (-) 10 (M)

(24.03.2016)

13. Project Details

RCC Sewer

9" to 54" i/d = 14572/57815 & 7014 arranged

Forcemain 32" dia GRP = 0/1000'

Tuff TIle = 172055 Sft/1271680' Sft

Sub Base Course 29275/231600 Cft

Surface Drain Type-I = 11700/54412

Disposal Works = 80%/1,

Pumping Machinery = 0/4

Staff Quarter = 0/2,

OHT = 0/1, Ext: Elec.= 0/1,

Work is in Progress.

37 1140 Sewerage Scheme Chishtian (City Uplift

Package Chishtian)

Bahawalnagar 916.110 172.859 50.000 50.000 75.119 56.800 76% 229.659 25% Date of A.A 25.05.2014 .

Date of T.S. 21-07-2014.

Date of Prequalification. 21-07-2014

DAte of invitation of tenders=25-07-2014

Date of receipt of tenders =12-08-2014

Date of work order= 16-09-2014.

Date of completion as per PC-1=24-05-2017

Date of completion as per agreement= 15.09.2017.

Funds released by FD on 10-08-2015 & 17-02-2016.

Funds onlined on 20-08-2015 & 22-02-2016.

Re-appropriation of funds( + Rs.25.119 million)vide

Chief Engineer(S), PHED Lahore office letter

No.2429/B(4) dated 30-03-2016.

Scheme is fast moving. Work is in progress. Rs.400

M is required to complete the disposal work Zone-A &

B. and under water sewer line 66" dia.

Physical Progress: 32%

ZONE-A

R.C.C. Sewer 9" dia=36500 Rft/-

12" dia= 121754 Rft/6573 Rft,

15" dia=12832Rft/4420 Rft

18" dia=9318Rft/4018Rft

21"dia=5088Rft/6044Rft

24"dia=2364Rft/2391Rft

27" ida=4156Rft/2740 1Rft

30" dia=1162Rft/1903Rft

33" dia=3471Rft/1478 Rft

36" dia=5344Rft/ 837 Rft

42" dia=3674Rft/(-)

48" dia=4140Rft(-)

66" dia=2632Rft(-)

DISPOSAL WORK

Page 14: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

38 1141 Reh: & Aug: of Sewrage Scheme Khanpur City,

Phase-II.

R.Y.Khan 432.980 169.991 50.000 50.000 50.000 48.835 98% 218.826 51% Date of AA :05.03.2014.

Date of TS :05.03.2014

Date of pre-qualification: 05.03.2014

Date of invitation of tenders:08-03-2014

Date of receipt of tenders =25-03-2014

Date of work order=14.04.2014.

Date of completion as per PC-1=04-03-2016

Date of completion as per agreement= 13.04.2016.

Anticipated date of completion=30-06-2017

Funds released by FD on 10-08-2015 & 17-02-2016.

Funds onlined on 20-08-2015 & 22-02-2016.

Laying of sewer pipe 15" to 54" dia is in progress.

Cost of land paid to Revenue Department.

Notification for section 17 (4), (6) is issued by

Commissioner Bahawalpur dated 19.11.2014. Work

is in progress. Physical Progress:58%

1. R.C.C. Trunk Sewer 15" to 54" i/d =32984/84742

Rft(38%)

2. Screening Chamber =1 No. (80%-)

3. Pump House =1 No. (70%)

4. Pumping Machinery =5 Sets (Arranged)

5. Out Fall Chamber =1 No. (-)

6. Boundary Wall=620 Rft(-)

7. Sullage Carrier=3000 Rft(-)

8. Force main(24"/d)=7400/7600(97%)

9. Diesel Generator with Generator Room=1 Set

(Arranged)

10. Staff Quarter=2 No. (-)

11. Land Acquisition=1 Job. (100%)

39 1145 Construction of sullage carrier/Storm Water

channelfrom village Durhata and other allied

abadies UC No. 21 to seepage drain tehsil

bhowana district chiniot

Chiniot 251.746 224.761 20.723 20.723 0.540 0.540 100% 225.301 89% 1. Date of AA =06.06.2014

2. Date of TS =(Revised)20.04.2015

3. Date of Pre-qualification =13.06.2014

4. Date of inviting Tenders=19.06.2014

5. Date receipt of Tende.19.06.2014

6. Date of work order=23.07.2014

7. Date of Completion as per PC-I = 1 Year

8. Anticipated Date of Completion = 30.06.2016

9. Funds released by FD=10.08.2015, 17.02.2016

10. Funds onlined on=20.08.2015, 22.02.2016

11. Re-appropriation of Funds (+/-)= (-) Rs.20.183M

12. Project details=Sullage carrier (RCC) =

39760/39682. Sullage carrier (Brick Masonry) =

3524/3030.

Work is completed as per scope of the work and

operational. Efforts are being made to hand over the

scheme to TMA Chiniot for future operation and

Page 15: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

40 1276 Improvement of Rural Water Supply Scheme,

Dajal.

Rajanpur 217.875 80.000 30.000 30.000 90.000 70.500 78% 150.500 69% 1. Date of A.A = 23.12.2014

2. Date of T.S = 26.02.2015

3. Date of pre-qualification = 18.02.2015

4. Date of invitation of Tendering = 23.02.2015

5. Date of Reiept of Tenders .11.03.2015

6. Date of Work Order = 26.03.2015

7. Date of completion as per PC-I = 22.12.2016

8. Anticipated date of completion 30.06.2017

9. Funds released by FD = 10.08.2015 (I)

& 17.02.2016 (II)

11. Re-Appropration of funds = (+) 40 (M) (20 M

07.10.2015 & 20 M 24.03.2016)

12. Project Details

Trial Bore = 1/1, T/W = 5/5,

P.H = 5/5

R. Main 6" to 12" i/d =59400/74250 Rft.

D.Sys. 3" to 16" i/d = 7106/35530

OHT Line =0/1, GST = 70%/1

P.M for GST = 2/2 arranged,

OHR = 0/1

Steel arranged 20 tone.

Work is in progress.

41 1520 Scaling up Pakistan Approach for Total

Sanitation (PATS) in Punjab (ODF)

Punjab 400.000 67.702 200.705 200.705 200.705 43.300 22% 111.002 28% Work in progress.

NEW SCHEMES1 1521 Water supply scheme Fazaiya Housing Colony,

Turnol, Tehsil & District Rawalpindi.

Rawalpindi 373.073 0.000 50.000 50.000 50.000 0.000 0% 0.000 0% A.A dt:01-01-2016

T.S dt:04-02-2016 Tender invited on

07-04-2016..

2 1526 Augmentation of Sewerage Scheme Sargodha Sargodha 1200.000 0.000 100.000 100.000 0.000 0.000 0% 0.000 0% M/s G3 Engineering Consultants (Pvt.) Ltd Lahore

have been appointed for designing / planning &

committed that estimate / PC-I presented to P&D

Department for approval.

3 1528 Ext./ Rehabilitation of Urban Sewerage Scheme

Gojra, T.T.Singh - ADP 2015-16

T.T.Singh 400.000 0.000 30.000 30.000 15.000 0.661 4% 0.661 0% 1-Date of A.A 12.11.2015

2- Date of T.S 26.02.2016

3-Date of Prequalification -08.03.2015

4-Date of invitation of tenders 24.03.2016

5- Date of Receipt of tenders 26.03.2016

6-Funds Released by F.D 05.01.2016

7-Funds online on 20..01.2016

8-Project detail:-

Tender Received on 26.03.2016 & under

process in E.E office.

4 1531 Improvement / Extension Urban Water Supply

Sewerage & Drainage Scheme M.B.Din City

M.B.Din 300.000 0.000 40.000 40.000 0.000 0.000 0% 0.000 0% The scheme has been approved in the DDWP

Meeting held on 10.03.16. A.A issued on

25.03.2016. Tenders under process.

5 1587 Urban Water Supply Scheme Muridkey Sheikhupura 450.000 0.000 20.000 20.000 0.000 0.000 0% 0.000 0% Funds not released so for

6 1589 Comprehensive Water Supply & Sewerage

Scheme for vehari city.

Vehari 308.201 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% Scheme approved by PDWP on 24.03.2016

A.A awaited.7 1605 Urban Sewerage/Drainage scheme, PCC Slab &

Brick Pavement in Bhakkar City

Bhakkar 619.218 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% The work for survey, planning, designing, estimating

and submission of P.C-I awarded to M/s E.S.C by the

Chief Engineer (North), PHED Lahore on 03.11.2015

and work is in progress.

Page 16: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

8 1606 Urban Water Supply Scheme Gojra (Phase-II) -

ADP 2015-16

T.T.Singh 532.942 0.000 30.000 30.000 30.000 0.022 0% 0.022 0% Scheme approved in DDWP meeting held

on 10.12.2016.Pre-Qualification of

contractors and T.S under process.9 1607 Extension / Rehabilitation of Urban Sewerage

Scheme Karnalia City (Phase-II)

T.T.Singh 360.000 0.000 30.000 30.000 15.000 0.022 0% 0.022 0% 1-Date of A.A 12.11.2015

2- Date of T.S 25.02.2016

3-Date of Prequalification -08.03.2016

4-Date of invitation of tenders 24.03.2016

5- Date of Receipt of tenders 26.03.2016

6- Anticipated date of completion

7-Funds Released by F.D 05.01.2016

8-Funds online on 20..01.2016

9-Project detail:-

Tender Received on 26.03.2016 & under

process in E.E office.

10 1611 Sewerage / Drainage Scheme Malikwal City,

Distt.M.B.Din

M.B.Din 237.200 0.000 50.000 50.000 50.000 0.000 0% 0.000 0% The scheme has been approved in the DDWP

Meeting held on 10.12.15. A.A issued on 06.01.2016.

Work alloted.

11 1683 Mega Sewerage Scheme Liaqatpur City R.Y.Khan 500.000 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% Rough Cost Estimate an amount to

Rs.500.000 M re-submitted to Chief

Engineer(S), PHED Lahore vide this office

letter No.6665 dated 13-10-2015 & sent to

Secretary HUD & PHED Lahore by the CE

(S) on 17.11.2015 and same has been

submitted to P&D Department by the

Government on 25.11.2015 for approval.

The scheme was deffered by P&D during

January, 2016.

SCOPE OF WORK.

RCC Sewer 9" to 60" i/d=73389 Rft.

(Zone-A).

Screening chamber=1 No.

Collecting Tank=2 No.

Pump House = 2 No.

Pumping machinery=4 set.

Disposal Works (Zone-C).

Screening chamber=1 No.

Collecting Tank=1 No.

Pump House=1 No.

Pumping machinery=2 set.

Disposal Works (Zone-B).

Screening chamber=1 No.

Collecting Tank=1 No.

Pump House=1 No.

Pumping machinery=2 set.

Page 17: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

12 1684 SEWERAGE SYSTEM AND REHABILITATION

OF ROADS, MUNICIPAL COMMITTEE ZAHIR

PIR, TEHSIL KHAN PUR, DISTRICT RAHIM

YAR KHAN

R.Y.Khan 315.801 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% Rough Cost Estimate an amount to

Rs.315.800 M resubmitted to Chief

Engineer(S), PHED Lahore vide this office

letter No.8883 dated 11.12.2015 after

attending the observations for approval from

competent authority. PC-II has been

submitted to P&D Department by

Government vide letter No.SO(PH-S)6-

3/2015(RYK) dated 22-03-2016

SCOPE OF WORK.

A. Servey and investigation services=1 Job.

B.RCC Sewers 9",to 36",dia 51275 Rft

C. Disposal Works 2. No.

D. External Electrification 1.Job

E. Acqusation of Land 1.Job

13 1689 Comprehensive sewerage scheme, Chenab

Nagar, Chiniot

Chiniot 730.000 0.000 25.000 25.000 0.000 0.000 0% 0.000 0% 1.Date of Completion as per PC-I = 3 Year.

2.Anticipated Date of Completion =

31.06.2019 .

3.Project details

The Rough Cost Estimate / PC-I was

discussed in PDWP on 11.11.2015 and

scheme was deferred for vetting by the

Consultant.

Moreover soil samples have also been

taken from 3-points and Laboratory test was

conducted to ascertain the availability of

Sulfate Salt. Estimate has been reframed

accordingly for Rs. 719.752 Million and

submitted to P & D Department Lahore on

14.01.2016 for placing before PDWP for

approval. Date of PDWP meeting awaited.

14 1729 Water supply scheme Lalamusa and Rural Areas Gujrat 469.504 0.000 40.000 40.000 0.000 0.000 0% 0.000 0% Rough Cost estimate has been submitted to quarter

concerned for arranging its Administrative Approval.

A.A awaited.

15 1736 Construction of PCC / Tuff Tiles / Sewerage &

Drainage Scheme in PP-163, District

Sheikhupura

Sheikhupura 373.950 0.000 30.000 30.000 0.000 0.000 0% 0.000 0% Funds not released so far

16 1833 Sewerage / Drainage Scheme Malikwal City,

Distt.M.B.Din

M.B.Din 237.200 0.000 50.000 50.000 0.000 0.000 0% 0.000 0% Funds have not yet been released by the F.D

17 1847 Const. of Nullah from Sublime Chowk to Uggoki

More to Sahowala Bridge to Syphonof Nullah

Aik, Sialkot

Sialkot 302.048 0.000 70.000 70.000 0.000 0.000 0% 0.000 0% *A.A Date =28.01.2016

*T.S date=14.02.2016

Work awarded on 20.02.2016 . Contractor

mobilize to start the work. Funds awaited.

18 1894 PCC and drainage scheme Thieng More / Illah

abad, Tehsil Chunian, District Kasur

Kasur 256.672 0.000 20.000 20.000 10.000 2.325 0% 2.325 1% Work recently allotted.

Page 18: LIST OF MEGA PROJECTS COSTING RS. 200.00 … PHED March,16.pdfOn the direction of Chief Minister Punjab revise ... khushab city.Petty works in progress.All Sewer lines ... Date of

Sr.

No.

GS.

No.

Name of Scheme District Approved

Cost

Exp Upto

June 2015

Revised

allocation

for 2015-16

Funds

released till

31.03.16

Funds

utilized

till

31.03.16

%age

utilization

on release

31.03.16

Total

Accummulati

ve exp: till

31.03.16

Physical

progress

till current

month

(%age)

Remarks (including detailed physical

progress)

(i) Date of Start of the Project

(ii) Date of completion of the Project

Provision

for 2015-

16

19 1942 Multi Sectoral Nutrition Strategy for WASH

Including Water Supply, Sanitation, Hygiene,

Waste Water Treatment, Disposal of Solid

Waste

9 Villages of Brackish / Barani Districts one from

each Civil Division having population > 10,000)

Punjab 700.000 0.000 75.000 75.000 0.000 0.000 0% 0.000 0% PC-I submitted by Sargodha & Rawalpindi Circles to

CE where as PC-I of Lahore & Gujranwala Circle are

still awaited.

20 1947 Upgradation / Strengthening of Existing

Laboratories at District Head Quarter

Punjab 200.000 0.000 35.000 35.000 0.000 0.000 0% 0.000 0% Scheme deferred by DDSC