  • 1Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    1 July 9, 2013

    Lancaster Station Capstone Project 

    Overview

    Presented to  Lancaster Traffic Commission

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 2Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    2

    STATION FACTS

    Opened in 1929 by the  Pennsylvania Railroad

    3rd busiest station on  the Keystone Corridor  (559,364 passengers for  FY12)

    Provides access to  Keystone Service and  the Pennsylvanian

    Lancaster Train Station

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 3Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    3

    The Challenge

     Aging facility

     Deterioration

     Not compliant with ADA requirements

     Public perception

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 4Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    The Solution

    The Capstone Project 

    –Addresses both  interior and exterior renovations

    –Restores the station to its historic significance

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 5Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    The Capstone Project

    Consists of two phases

    –Phase 1‐ Amtrak Short‐Term work

    –Phase 2‐ Contracted Long‐Term work 

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 6Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    Phase 1‐ Short‐Term Work

    Before After

    Restoration of benches in Main Waiting Room and  Concourse Bridge

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 7Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    Phase 1: Short‐Term Work

    Ceiling Repairs Completed Ceiling Repairs

    Plaster and Paint repairs in the station foyer

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 8Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    Phase 1: Short‐Term Work

    Before After

    Concourse Bridge Paint and Plaster Repairs

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 9Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    Phase 1: Short‐Term Work

    Exterior Sidewalk Repairs

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 10Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    Phase 1: Short‐Term Work

    Before After

    Donation of (6) Clocks from Brent Miller Jewelers

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 11Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    Phase 2: Contracted Long‐Term work

    Peeling Paint and Plaster Ceiling deterioration

    LoBar Construction currently making paint and plaster repairs  to main waiting room

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 12Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    Phase 2: Long‐Term Contracted Work

     Concourse HVAC Replacement Contract awarded to Fluidics of Philadelphia Estimated completion by end of summer 2013

     ASDP‐ ADA Project Design phase

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 13Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    The Capstone Project

    Completion date: Fall 2013

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission

  • 14Amtrak and the Future of the Northeast Corridor Proprietary – Not for distribution without Amtrak permission

    14

    Thank You!

    Lancaster Station Capstone Project Overview: July 9, 2013, Amtrak presentation to Lancaster Traffic Commission