1
Kilovar Planning for Southern California Edison J. H. DRAKE MEMBER AIEE G. A. DAVIS MEMBER AIEE E FFECTIVE KILOVAR PLANNING, which is be- coming capacitor planning for many electrical systems, requires detailed knowledge of system reactive power characteristics and operating requirements. Plan- ning kilovar generating capacity then becomes analogous to planning kilowatt generating capacity. In both in- stances, load is forecast and generating capacity for the load plus appropriate reserve for system contingencies is planned. The reactive demand and supply for the Southern California Edison Company system is shown in Fig. 1. Maximum over-all system reactive demand of 1.93 million kvar occurred in July 1954 at which time the real power demand was 1.83 million kilowatts. Charging kilovars were about equal to the reactive losses of the 1,900-mile, 220-kv system. Synchronous condensers supplied 63 per cent of 1.43 million kvar of reactive demand existing at the 66-kilovolt level and below, while static capacitors supplied 25 per cent. The reactive generating margin for system contingencies was available in synchronous con- densers and in steam plants near the load center. Fixed capacitors on 4-kilovolt circuits corrected circuit power factor to unity at light loads. Most capacitors on higher voltage distribution circuits were switched, either seasonally or by voltage control. Capacitors at substations were usually switched, either manually by supervisory control, or automatically with current biased voltage control predominating. Growth in reactive demand at the 66-kilovolt level has been 125,000 kvar each year. In addition to planning for this load, kilovar generating margin has been planned to provide for contingencies such as transmitting large amounts of interchange power, outage of a major trans- Fig. 1. Reactive supply and demand at time of summer reactive peak, 3 pm, July 30, 1954 I RESERVE I GENERATOR | CAPABILITY J 2000 1800 1600 1400 RS 1200 < AV 1000 CD UJ 800 800 600 400 200 0 220 KV BANKS AND LINES GENERATION AND INTER- CONNECTIONS 220 KV BANKS AND LINES 220 KV LINE CHARGING 220 KV LINE CHARGING 66 KV LINES, TRANSFORMERS BELOW 220 KV, DISTRIBUTION LINES AND CUSTOMER LOAD SYNCHRONOUS CONDENSERS STATIC CAPACITORS 220 KV LINE CHARGING SYNCHRONOUS CONDENSERS STATIC CAPACITORS Q < < >- - < rr < > 1930 1935 1945 1955 INSTALLED CAPACITY Fig. 2. Relationship between megavar capacity and megawatt demand mission line or synchronous condenser, or unusually heavy air-conditioning load. Static capacitors will supply the majority of this annual growth of reactive demand in the future, as shown in Fig. 2. Synchronous condensers, which for many years provided for the reactive load growth and margin, are decreasing in relative importance. This decrease is due in part to changing cost relationship between synchronous con- densers and capacitors, and to the fact that fewer long transmission lines which require kilovar absorbing capa- bilities of condensers will be added to the system. Capacitors will be apportioned to the various 220/66- kilovolt operating areas in accordance with the reactive load and reserve requirements. Unswitched circuit in- stallations will be determined by minimum load power factor on circuits, and switched circuit installations will be determined by local voltage conditions. Specific substation installations will depend mainly upon available transformer taps, upon desired voltage correction, and upon required correction of 66-kilovolt subtransmission voltage level. Capacitors will be programmed for installa- tion on 66-kilovolt busses at substations after optimum capacitor installations have been completed on the dis- tribution voltage busses. Digest of paper 56-2, "Planning Kilovars and Capacitors for the Southern California Edison System," recommended by the AIEE Committee on Transmission and Dis- tribution and approved by the AIEE Committee on Technical Operations for presenta- tion at the AIEE Winter General Meeting, New York, . Y., January 30-February 3, 1956. Scheduled for publication in AIEE Power Apparatus and Systems, 1956. J. H. Drake and G. A. Davis are with the Southern California Edison Company, Los Angeles, Calif. APRIL 1956 Drake, Davis—Kilovar Planning 355

Kilovar planning for Southern California edison

  • Upload
    g-a

  • View
    213

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Kilovar planning for Southern California edison

Kilovar Planning for Southern California Edison

J. H . D R A K E M E M B E R A I E E

G. A . D A V I S M E M B E R A I E E

EF F E C T I V E K I L O V A R P L A N N I N G , w h i c h is be ­c o m i n g c a p a c i t o r p l a n n i n g for m a n y e lec t r ica l

systems, r equ i r e s d e t a i l e d k n o w l e d g e of sys tem r e a c t i v e p o w e r charac te r i s t i c s a n d o p e r a t i n g r e q u i r e m e n t s . P l a n ­n i n g k i lovar g e n e r a t i n g c a p a c i t y t h e n b e c o m e s a n a l o g o u s to p l a n n i n g k i l o w a t t g e n e r a t i n g c a p a c i t y . I n b o t h in­s tances , l o a d is forecast a n d g e n e r a t i n g c a p a c i t y for t h e load p lus a p p r o p r i a t e r e se rve for sys tem con t ingenc i e s is p l a n n e d .

T h e r eac t i ve d e m a n d a n d s u p p l y for t h e S o u t h e r n Cal i forn ia E d i s o n C o m p a n y sys tem is s h o w n in F ig . 1. M a x i m u m over -a l l sys tem r e a c t i v e d e m a n d of 1.93 mi l l ion k v a r o c c u r r e d in J u l y 1954 a t w h i c h t i m e t h e r e a l p o w e r d e m a n d w a s 1.83 mi l l ion k i lowa t t s . C h a r g i n g k i lovars w e r e a b o u t e q u a l to t h e r e a c t i v e losses of t h e 1,900-mile, 220-kv sys tem. S y n c h r o n o u s c o n d e n s e r s s u p p l i e d 63 p e r c e n t of 1.43 mi l l ion k v a r of r e a c t i v e d e m a n d exis t ing a t t h e 66-ki lovol t level a n d be low, w h i l e s ta t ic c a p a c i t o r s supp l i ed 25 p e r c e n t . T h e r e a c t i v e g e n e r a t i n g m a r g i n for system con t ingenc ies w a s a v a i l a b l e in s y n c h r o n o u s con ­densers a n d i n s t e a m p l a n t s n e a r t h e l o a d c e n t e r .

F ixed c a p a c i t o r s o n 4-ki lovol t c i rcu i t s c o r r e c t e d c i rcu i t p o w e r fac tor t o u n i t y a t l igh t l oads . M o s t c a p a c i t o r s on h i g h e r v o l t a g e d i s t r i b u t i o n c i rcui t s w e r e swi t ched , e i the r seasonal ly o r b y v o l t a g e c o n t r o l . C a p a c i t o r s a t subs ta t ions w e r e u sua l l y swi t ched , e i t he r m a n u a l l y b y superv isory con t ro l , o r a u t o m a t i c a l l y w i t h c u r r e n t b i a sed vo l t age c o n t r o l p r e d o m i n a t i n g .

G r o w t h in r e a c t i v e d e m a n d a t t h e 66-ki lovol t level has b e e n 125,000 k v a r e a c h y e a r . I n a d d i t i o n t o p l a n n i n g for this load , k i lovar g e n e r a t i n g m a r g i n h a s b e e n p l a n n e d to p r o v i d e for con t ingenc ie s s u c h as t r a n s m i t t i n g l a r g e a m o u n t s of i n t e r c h a n g e p o w e r , o u t a g e of a m a j o r t r a n s -

Fig. 1. Reactive supply and demand at time of summer reactive peak, 3 pm, July 30, 1954

ι I R E S E R V E I

GENERATOR | CAPABILITY

J ι

2 0 0 0

1 8 0 0

1 6 0 0

1400

RS

1200

<

AV

1 0 0 0 CD UJ 8 0 0 8 0 0

6 0 0

4 0 0

2 0 0

0

2 2 0 KV B A N K S

AND L I N E S

G E N E R A T I O N A N D I N T E R ­

C O N N E C T I O N S 2 2 0 KV B A N K S

AND L I N E S 2 2 0 KV

L I N E CHARGING

2 2 0 KV L I N E

CHARGING

6 6 KV LINES, TRANSFORMERS BELOW 220 KV, DISTRIBUTION LINES AND CUSTOMER

L O A D

SYNCHRONOUS CONDENSERS

STATIC CAPACITORS

2° 2 2 0 KV

LINE CHARGING

SYNCHRONOUS CONDENSERS

STATIC CAPACITORS

Q

<

ο <

>-Ι ­ο

< ο rr < >

1930 1935 1945 1955

INSTALLED C A P A C I T Y

Fig. 2. Relationship between megavar capacity and megawatt demand

mission l ine o r s y n c h r o n o u s c o n d e n s e r , o r u n u s u a l l y h e a v y a i r - c o n d i t i o n i n g l o a d .

S t a t i c c a p a c i t o r s will s u p p l y t h e m a j o r i t y of this a n n u a l g r o w t h of r e a c t i v e d e m a n d in t h e fu tu re , as s h o w n in F ig . 2. S y n c h r o n o u s condense r s , w h i c h for m a n y yea r s p r o v i d e d for t h e r e a c t i v e l o a d g r o w t h a n d m a r g i n , a r e dec reas ing in r e l a t ive i m p o r t a n c e . T h i s d e c r e a s e is d u e in p a r t to c h a n g i n g cost r e l a t i o n s h i p b e t w e e n s y n c h r o n o u s con­densers a n d c a p a c i t o r s , a n d to t h e fact t h a t fewer long t r ansmiss ion l ines w h i c h r e q u i r e k i lova r a b s o r b i n g c a p a ­bili t ies of c o n d e n s e r s wil l b e a d d e d to t h e sys tem.

C a p a c i t o r s wil l b e a p p o r t i o n e d to t h e va r ious 2 2 0 / 6 6 -ki lovol t o p e r a t i n g a r e a s in a c c o r d a n c e w i t h t h e r eac t ive l o a d a n d rese rve r e q u i r e m e n t s . U n s w i t c h e d c i rcu i t in­s ta l la t ions will b e d e t e r m i n e d b y m i n i m u m load p o w e r fac tor o n c i rcui t s , a n d swi t ched c i rcu i t ins ta l la t ions will b e d e t e r m i n e d b y loca l v o l t a g e cond i t i ons . Specific s u b s t a t i o n ins ta l l a t ions will d e p e n d m a i n l y u p o n ava i l ab l e t r a n s f o r m e r t a p s , u p o n des i red v o l t a g e co r rec t ion , a n d u p o n r e q u i r e d c o r r e c t i o n of 66-ki lovol t sub t ransmiss ion vo l t age level . C a p a c i t o r s will b e p r o g r a m m e d for ins ta l la­t ion on 66-ki lovol t busses a t subs t a t ions after o p t i m u m c a p a c i t o r ins ta l l a t ions h a v e b e e n c o m p l e t e d on t h e dis­t r i b u t i o n v o l t a g e busses.

Digest of paper 56-2, "Planning Kilovars and Capacitors for the Southern California Edison System," recommended by the AIEE Committee on Transmission and Dis­tribution and approved by the AIEE Committee on Technical Operations for presenta­tion at the AIEE Winter General Meeting, New York, Ν. Y., January 30-February 3, 1956. Scheduled for publication in AIEE Power Apparatus and Systems, 1956.

J. H. Drake and G. A. Davis are with the Southern California Edison Company, Los Angeles, Calif.

APRIL 1956 Drake, Davis—Kilovar Planning 355