Thermal Generation KENITRA ONE Kenitra - Thermal Power Plant 315 MW Construction of the 315 MW power plant of Kenitra as EPC contractor, in a consortium with General Electric. The scope of works included: . the mechanical and electrical balance of plant, . the control system, . the civil works, . the turbines supplied by General Electric, . the local transportation, . the customs clearance, . the erection of equipment. SOLUTION IMPLEMENTED DESIGN ENGINEERING, IMPLEMENTATION Activity Mechanics, Electricity, Automation monitoring and control, Civil Works, Structures Technologies Used GE 9E Gas turbine Customer Benefits . The consortium delivered the complete power plant in advance on the planning for the client’s satisfaction. Business Units Involved Omexom Power Plants - Thermal Philippe LENTZ - [email protected] Xavier DUCLOS - [email protected] Country: Morocco Site: Kenitra Budget (k€): 101,000 Start Date: 05/2010 End Date: 11/2012 Contacts SCAN WITH UBLEAM APPLICATION

KENITRA ONE Kenitra - Thermal Power Plant 315 MW · PDF fileKENITRA ONE Kenitra - Thermal Power Plant 315 MW Construction of the 315 MW power plant of Kenitra as EPC ... Start 0Date:

  • Upload
    dodung

  • View
    264

  • Download
    1

Embed Size (px)

Citation preview

Page 1: KENITRA ONE Kenitra - Thermal Power Plant 315 MW · PDF fileKENITRA ONE Kenitra - Thermal Power Plant 315 MW Construction of the 315 MW power plant of Kenitra as EPC ... Start 0Date:

Thermal Generation

KENITRA ONE

Kenitra - Thermal Power Plant 315 MW

Construction of the 315 MW power plant of Kenitra as EPC contractor, in a consortium with General Electric. The scope of works included: . the mechanical and electrical balance of plant, . the control system, . the civil works, . the turbines supplied by General Electric, . the local transportation, . the customs clearance, . the erection of equipment.

SOLUTION IMPLEMENTED

DESIGN ENGINEERING, IMPLEMENTATION Activity

Mechanics, Electricity, Automation & monitoring and control, Civil Works, Structures

Technologies Used GE 9E Gas turbine

Customer Benefits . The consortium delivered the complete power plant in advance on the planning for the client’s satisfaction.

Business Units Involved Omexom Power Plants - Thermal

Philippe LENTZ - [email protected] DUCLOS - [email protected]

Country: Morocco Site: Kenitra Budget (k€): 101,000 Start Date: 05/2010 End Date: 11/2012

Contacts

SCAN WITH UBLEAM APPLICATION