Upload
junaid-tajudeen
View
231
Download
0
Embed Size (px)
Citation preview
8/8/2019 Junaid Nse Project
1/32
1
8/8/2019 Junaid Nse Project
2/32
DEDICATION
This project is dedicated to the memory of my late father Mr
Junaid Adesanya Ishola Kareem and my late sisters, Mrs Kudirat
Amope Coker and Mrs. Adiyat Atoke Fasasi.
2
8/8/2019 Junaid Nse Project
3/32
TABLE OF CONTENTS
Dedication.
2
Table of contents
3
Acknowledgement..
5
CHAPTER 1:Introduction.6
CHAPTER 2:Details of Professional Training and
Experience.....12
2.1 Construction of Housing Unit at Abesan
5..12
2.2 Rehabilitation of Rural Roads in Odeda LocalGovernment..14
2.3 Underground Water Development (Borehole) in
Aigbede Odeda Local Government
Council.15
2.4 Rehabilitation of Building Project in Abeokuta South
Local Government Council..16
2.5 Construction of College Clinic Phase I & II at F.C.E Abeokuta..17
2.6 Report of Professional Experience on Construction
of 1500 Seating Capacity Lecture Theatre Phase 1
at Federal College of Education Osilele
Abeokuta................18
2.6.1 Introduction18
2.6.2 Preliminary Planning.18
2.6.3 The Architectural Design..19
2.6.4 Problems 19
2.6.5 Prospect ....22
2.6.6 Design Analysis..243
8/8/2019 Junaid Nse Project
4/32
2.7 Report of Professional Experience on Reconstruction of
ALG School 1 & 2 Oke Ago-Owu.27
2.7.1 Reconstruction of ALG School 1..272.7.2 Reconstruction of ALG School 228
LIST OF TABLE
Table 1: Method Statement for poultry building construction7
Table 2: Programme probability Distribution for Construction of
Poultry Building project at Gracib Farm Site 9
Table 3: Spot height survey of phase A
.21
Table 4: Spot height survey of phase B
..22
4
3a
8/8/2019 Junaid Nse Project
5/32
LIST OF FIGURE
Figure 1: The critical path Network schedule for construction
of poultry building project at Gracib farm site.
7b
Figure 2: Program of work for rehabilitation of Gbongon
-Iwo Iseyin Road contract No:
5952.11b
Figure 3: Critical path method scheduling for Rehabilitation of
Gbongon -Iwo Iseyin Road
............11c
Figure 4: Spot height survey for construction of 150 Seating
capacity lecture theatre at FCE Osiele
Abeokuta..22b
5
3b
8/8/2019 Junaid Nse Project
6/32
Figure 5: Schematic diagram for proposed Ground floor level of
1500 seating capacity lecture theare at FCE Osile
Abeokuta.......................................................22c
Figure 6: Progamme of work for Renovation of school in Owu
Gbagura community Abeokuta - a world Assisted Project
of Ogun State Community Based urban Development
Project ...................................................................28b
LIST OF PLATES
Plate 1a: Preliminary survey and Excavation of
Foundation and column Bases.19b
Plate 1b: Determination of DPC and oversite concrete
Floor level .19b
Plate 2a: Consultants and Director of works and service Dept.
Inspecting the casting of oversite Concrete floor
..20b
Plate 2b: Consultants and Director of works and services Dept.
Inspecting the final completion of sub-Structure
work.20b
6
4a
8/8/2019 Junaid Nse Project
7/32
Plate 3a: Super structure works commence from the
Stage Area
..25b
Plate 3b: Consultant Engineer (Engr. Sogbetun) checking
The column height with leveling instrument.25b
Plate 4a: Casting of level + 2250 and level +
3600..25c
Plate 4b: completion of Block work and concrete
work to roof
level..25c
Plate 5a & 5b: Bar arrangement of Doubly reinforcement concrete
Deep Beam of the stage area before
casting.25d
Plate 6a & 6b: Steel Roof formation
..25e
7
4b
8/8/2019 Junaid Nse Project
8/32
ACKNOWLEDGMENT
I give praises, glory and honour to the Almighty Allah the
most high God, the most beneficent and the most merciful to
mankind.
I will continually appreciate the tremendous support and
encouragement of my humble mentor, Engr. R.A. Kumolu, may
the Lord continue to grant him and his family immense love,
shower his abundant and infinite mercy on them.
I also thank my employers and all that have contributed to
my exposure in the last seventeen years. To just mentioned few,
Engr. Emmanuel Ibok Essien (Ritman Nig Ltd), Engr. Sogbetun
(Tropaed Groups), Engr. Odedoyin (FCE Abeokuta), Mr Oyetunji,
W.B. (Fatnuroye Ltd), Chief Daodu, A. (OASIS/Cardinal), Arc R.
Ayegbajeje (Ren Consult) and Arc Olamilekan Adegbile (Adkon
Engineering Ltd).
The project would not have been completed if not for the
cooperation and assistance of Mrs. Junaid Abosede Olubukola,
Oluwafeyisayo,Oluwafayokemi,Oluwaferanmi,Balikis,Famakinwa
Brown, Alhaja Junaid Abeni Murilat and Mrs Toyin Aderogba. May
Allah grant everyone his infinite mercy.
8
8/8/2019 Junaid Nse Project
9/32
1.0 INTRODUCTION
This report is presented to Nigerian Society of Engineers in
partial fulfillment for my election as a corporate member of the
Nigerian Society of Engineers. It covers a period of seventeen
years of active engineering service.
On graduating with Bachelor of Science in Civil Engineering
from Obafemi Awolowo University, Ile-Ife in March 1991 I was
deployed to Akwa-Ibom State for National Youth Service Corps
where I was posted to Ritman Nigerian Limited, Ikot-Ekpene for
my primary assignment -an indigenous engineering firm
specialized in rural development projects.
During the service year I joined the company as a Site
Engineer under the supervision of Engr. Emmanuel Ibok Essien
and I supervised the construction of the following projects at
Cracib Investment Limited farm site in Ikot-Otu between May and
November 1991.
The projects includes:
(i) Administrative office block
(ii) Twins flat of 3 bedrooms for staff accommodation
(iii) 4 blocks of multipurpose livestock building
9
8/8/2019 Junaid Nse Project
10/32
The major problem encountered at Gracib farm site was
during the foundation excavation. This poultry building project
was sited on a loose soil. This problem was overcome by
providing earthwork support to the sides of excavation to enable
the excavation reach the suitable Stratum of required bearing
capacity. I prepared my method statement and programme of
work for the construction of poultry buidings and other jobs, at
the same time make a weekly site report for Engr. Essien.
In January 1992 I was assigned to road rehabilitation
projects within Ikot-Ekpene. The job includes asphalt overlay and
design of open channel flow for the lined drains.
The roads in Ikot-Ekpene are:
(i) Ibong Road - 2.727km
(ii) Dibue Road - 0.744km(iii) Child Maternal Health Road - 0.302km
(iv) Oko Eto Road - 0.602km
(v) Etok Akpan Amond Road - 0.782km
(vi) Old Itu Road - 3.5km
These roads was awarded to Ritman Nigeria Limited by Ikot-
Ekpene Local Government Council via job order from Council
Chairman and supervised by the Council Engineer -Engr. E.
Umeh.
10
8/8/2019 Junaid Nse Project
11/32
Table 1: Method Statement for poultry building
construction
Operation Qty Method Predetermine Contemporary Labour out
put rate
No of
Labour
No of
days
A Provision of aggregates 92m3 TipperLorry
- E, F, G 4.6m3/day 20 men 10 days
B Site clearance 400.95m2 Manual - C 100m2/day 4 men 2 days
C Setting out of works 340.2m2 Manual B D 2 men 1 day
D Excavation of foundation 48.35m3 Manual C E, F, G 4.05m3/day 11 men 2 days
E Moulding and curing of
blks
3559blks Manual A, D H 350blk/day 6 men 10 days
F Blinding of foundation
trench
10.48m3 Manual A, D I 0.5m3/day 6 men 1 day
G Provision of Cement and
water
10 Tons/
15000ltrs
Lorry/
Tanker
A, D K 1.67Tons/day 1 men 6 days
H Dummy activity - Manual E I - - 0 day
I Blockwork - setting
foundation to DPC level 1029blks Manual H, F I
85blk/day 12 men 2 days
J Laterite earthworks
filling, leveling andcompaction 88.25m3 Manual I K 3.0m3/day 30 men 3 days
K Over site concrete 37.18m3 Manual J, G M, L 1.49m3/day 25 men 1 days
L Roofing materials
delivery Do Lorry K N Sum 2 men 4 days
M Blks work setting DPC to
window seat to roof level 2326blks Manual K O, P, Q 75blks/day 32 men 6 days N Frames & Doors
preparation
8 Nos
Manual L O, P, Q 2 Nos/day 8 men 4 days
O Roof trusses formation Do Manual M, N R 4 men/day 16 men 4 days
P Plumbing works Do Manual M, N U, V, W 2 men/day 10 men 5 days
Q Excavation of foundation
trench for water tanks 0.65m3 Manual M, N S 4.05m3/day 1 men 1 day
R Roof sheeting Do Manual O II, V, W 4 men/day 4 men 1 day
S Construction of water
tank base
1.69m3 Manual Q T 0.5m3/day 4 men 1 day
T Block work- water tank 224blks
2.0m3 Manual S U, V, W
85blks/day
5 men 3 days
U Rendering internal &
eternal wall 216m
2
Manual R, P, T Z, Y 18m
2
/day 12 men 3 daysV Fixing of door frames 8 Nos Manual R, P, T X Sum 2 men 1 day
W Provision of wire netting 240m2 Lorry R, P, T Z, Y Sum 1 men 2 days
X Dummy activity - - V Z, Y - - 0 day
Y Framework for Netting Lump Manual U, X, W ZB 3 men/day 12 men 4 days
Z Floor screeding 10.36m3 Manual U, X, W ZA 0.83m3/day 11 men 2 days
ZA Casting of Floor B 14.48m3 Manual Z ZA 0.5m3/day 21 men 2 days
ZB Netting 237m3 Manual Y ZC 3 men/day 10 men 3 days
11
8/8/2019 Junaid Nse Project
12/32
ZC Fixing of Doors 8 door Manual ZB ZD 2 Nos/day 4 men 2 days
ZD Clearing of site Do Manual ZC, ZA ZE 1 men/day 1 men 1 day
ZE Handling over - ZD - 1 men/day 1 men 1 day
12
8/8/2019 Junaid Nse Project
13/32
Table 2: Programme Probability Distribution forConstruction of Poultry Building project at GracibFarm Site
Activitie
s
(a) (m) (b) (t)
A 10 12 15 12 0.83B 2 3 5 3 0.50C 1 1 2 1 0.17D 2 3 5 3 0.50E 10 14 20 14 1.67F 1 2 3 2 0.33G 6 10 15 10 1.50H 0 0 0 0 0I 2 3 5 3 0.50
J 3 5 8 5 0.83K 5 7 10 7 0.83L 4 5 7 5 0.50M 6 8 10 8 0.67N 4 5 8 5 0.67O 4 5 6 5 0.38P 5 8 14 10 1.50Q 1 2 3 2 0.33R 1 2 3 2 0.33S 1 2 3 2 0.33T 3 4 6 4 0.33
U 3 5 8 5 0.83V 1 2 3 2 0.33W 2 3 4 3 0.33X 0 0 0 0 0.00Y 4 6 7 6 0.50Z 2 3 5 3 0.50
ZA 2 3 5 3 0.50ZB 3 4 5 4 0.33ZC 2 3 4 3 0.33ZD 1 2 2 2 0.17
ZE 1 2 2 2 0.17
The major problem encountered on this project is that there
was no hydraulic engineering design for the land drain. I sought
the permission from Engr. Essien to allow me design a suitable13
8/8/2019 Junaid Nse Project
14/32
trapezoidal open channel for the lined drain, which he did, and
make little correction on the design in conjunction with council
Engineer before the final execution was carried out without stress
before the asphalt resurfacing.
I joined Fatnuroye Nigeria Limited in 1994 as Site Engineer
under the supervision of Engr. Sogbetun and Engr. Odedoyin.
During this period, I executed various Civil Engineering projects
at private, governmental and institutional level. These includes:
(i) Construction of housing Unit at Abesan 5
(ii) Grading of rural roads in Odeda Local Government
(iii) Underground water development (Borehole) in Aigbede
(iv) Rehabilitation of building project in Abeokuta south local
government
(v) Construction of prototype office building at Federal College of
Education Abeokuta
(vi) Construction of College Clinic Phase 1& II at F.C.E. Abeokuta.
(vii) Rehabilitation of Main Hall F.C.E. Abeokuta
(viii)Construction of 1500 seating capacity lecture theatre phase 1 at
F.C.E. Abeokuta
In November 2006, I joined Oasis/Cardinal Nigeria Limited
as a Site Engineer for the renovation of schools in Owu/Gbagura
Community. A World Bank assisted project under the supervision
14
8/8/2019 Junaid Nse Project
15/32
of Ogun State Community Based Urban Development Project. The
Consulting Engineer is Osot Associate Limited under the
leadership of Engr. R.A. Kumolu.
The renovation works includes:
(i) Holy Trinity Primary School
(ii) Abeokuta North L.G. Pry Sch I, Oke Ago-Owu
(iii) Abeokuta North L.G. Pry Sch. II, Oke Ago-Owu
I later joined Batson Nig. Ltd in August 2007 for
rehabilitation of Gbongan-Iwo-OYSB road in Osun State for major
rehabilitation as company Project Manager. This project was
under the supervision of federal ministry of transportation
engineers, and was supervised by Engr. Z.O. Iseyemi, Federal
Ministry of Transportation field office, osogbo.
In January 2008, I joined Adkon Nigeria Limited as Project
Engineer. On assumption of office I was transferred to supervise
the renovation works at Zenon House, Victoria- island, Lagos.
2.0 DETAILS OF PROFESSIONAL TRAINING ANDEXPERIENCE
On assumption of office at Fatnuroye Nigeria Limited as a
Site Engineer, I was introduced to Engr. Odedoyin and Engr.
15
8/8/2019 Junaid Nse Project
16/32
Sogbetun, they are both registered engineer and has been with
the company for several years on part-time basis. I was the only
engineer on full pay roll list; meanwhile I was faced with multiple
challenges. But I had little or no fear because of my exposure
during my service year with Ritman Nigeria Limited where I
worked independently without much supervision from my boss -
Engr. Emmauel Essien.
2.1 CONSTRUCTION OF HOUSING UNIT AT ABESAN 5
The housing unit at Abesan 5 was my first assignment. I
used few days in the office for project planning. The following
document was released to me for proper planning of the job.
(i) Price Bill of Quantities
(ii) Architectural drawing
(iii) Structural drawing
Other parts of the contract document like payment schedule
for the preparation of interim payment certificate, as well as
expected time of completion of the project were also released, to
enable me prepare my programme of work.
16
8/8/2019 Junaid Nse Project
17/32
I produced a comprehensive programme of work for the
project within the projected cash flow projection and method
statement for each activity. This was later followed by sourcing
for various equipments that are to be hired for the execution of
the project. At the same time, certain items and materials were
listed for sub-contractors for execution. At the end of these
planning we moved to site immediately and started with
preliminary items like.
(i) Site clearance and construction of site office
(ii) Provision for adequate supply of water and electricity.
(iii) Movement of equipment and matetrials to the site.
The major problem encountered was that the structure was designed
on strip foundation,but the site fall within the swampy and water-
logged area of the estate that calls for raft foundation design or wide
strip foundation.. The attention of the resident engineer and other
consultants were called to address the situation,raft foundation was
finally approved which I carried out the design under Engr. Sogbetun
The bill of addendum was forwarded for the new raft foundation
design.
We swung into action after the final approval of the addendum
and begin with setting out of works. The project planning agenda
17
8/8/2019 Junaid Nse Project
18/32
makes the execution easier and interesting I prepared progress
report and photograph against every monthly site meeting for
various level of stages of work.
2.2 REHABILITATION OF RURAL ROADS IN ODEDA LOCALGOVERNMENT
The grading of roads project was the second assignment to
be handled. These roads connect various communities and
villages in Ilugun, Olodo and Alagba ward in Odeda Local
Government. The contract was awarded in October and was
expected to complete within 45 days. The major assignment was
patching of potholes and clearing of road verges. Meanwhile, we
set out having prepared programme of work and immediately
moved to the site for execution. The major problem encountered
was that most of these roads has been abandoned for years.
Therefore I make provision for the earth drains on both sides and
culvert drains where necessary. But before this was carried out, I
had earlier informed the Council Engineer about the development
and importance of this to protect the flexible pavement. This
enables me to prepare variation on extra job and was approved
by the Council Chairman. The project was completed within the
working time frame of programme of work.
18
8/8/2019 Junaid Nse Project
19/32
2.3 UNDERGROUND WATER DEVELOPMENT (BOREHOLE)IN AIGBEDE VILLAGE
The huge success recorded on the rehabilitation of roads
fetch the company underground water development in Aigbede.
It was awarded via a job order from local government council
chairman.
The geophysical study was carried out within Aigbede
village by council geophysicst consultant. The result revealed
that the aquifer is 124.7m below NGL and sedimentary layer
takes about 35m while bedrock take about 90m depth. The result
enables me to look for a powerful drilling rig for the execution of
this job.
The drilling and casing operation however went
successfully. The major problem encountered was during the
geophysical operation. The geophysical studies took us longer
time before we could get a better location for high yield of the
aquifer.
Other problem encountered was that of distribution by
gravitational method to minimize cost on supply. This was tackled
by construction central elevated storage on nearby hill to ensure
even distribution by gravity to all nooks and corners of the
village.
19
8/8/2019 Junaid Nse Project
20/32
2.4 REHABILITATION OF BUILDING PROJECT IN ABEOKUTASOUTH LOCAL GOVERNMENT COUNCIL
The project was designed for staff accommodation and was
later abandoned for years. As a result, various cracks have
developed within the structure, roof leakages due to lack of
maintenance. All the cracks were corrected with wire-mesh
concrete, and the building was re-roof with aluminum long span.
The major problem encountered was at the early planning
stage when I discovered that certain items were omitted while
some are under quoted in the bill of quantities. These include
reinforced concrete works on the sun breakers and the external
works on septic tank. I prepared the bill of addendum in respect
to these items and forwarded to council engineer for approval.
20
8/8/2019 Junaid Nse Project
21/32
2.5 CONSTRUCTION OF COLLEGE CLINIC PHASE I & II ATF.C.E ABEOKUTA
The project was awarded to Fatnuroye Nigeria Limited by
selective tendering having being convinced on the competence of
the company on previous projects handled, such as the prototype
office building and the minor renovation of the Main Hall in the
previous year.
I submitted my programme of work after working on the bill
of quantities and the working drawings - architectural and
structural drawings. The stakeholder on this project includes the
work and services department of the college, the consultant
architect- Ren consult (Arc Remi Ayegbajeje) and consultant
engineer- Tropaed Group (Engr. Sogbetun). Engr. Abiodun and
myself represent the contractor at the site meeting. Engr Abiodun
is a registered Engineer and works on part-time basis with the
company. The project is the first major capital project awarded to
us by the college. I prepared progress report on site activities
monthly for Engr Abiodun against every site meeting. I coordinate
and manage all the site activities and ensure the job is executed
to specification standard within working timeframe.
21
8/8/2019 Junaid Nse Project
22/32
2.6 REPORT OF PROFESSIONAL EXPERIENCE ONCONSTRUCTION OF 1500 SEATING CAPACITY LECTURETHEATRE PHASE 1 AT FEDERAL COLLEGE OFEDUCATION OSILELE ABOKUTA
2.6.1 Introduction
In the year 2003, Federal College of Education Osiele
Abeokuta increased her regular student intake by 50% while the
Sandwich Programme Students intake was double. As a result,
there is need to get a bigger space lecture theatre for students.
This led the institution to call for design of 1500 seating capacity
lecture theatre within the Main campus.
Our success story on construction of college clinic phase 1
& 2 made us to aspire for bigger challenging projects. However
this led us to go for the open and competitive tendering on
construction of the 1500 seating capacity lecture theatre phase
1.
The job was awarded to us after the final ratification of the
tendering board and governing council of the college.
2.6.2 Preliminary Planning
The project planning started as usual with the working
drawings which includes architectural drawings and structural
drawing; the priced bill of quantities to enable draw a
22
8/8/2019 Junaid Nse Project
23/32
comprehensive programme of work at the same time give high
priority to cash flow projection and other relevant issue in site
management.
2.6.3 The Architectural Design
Both the architectural and structural works of this beautiful
project was perfectly carried out by experienced professionals on
assumption that a suitable site that conform to the design slope
would be found within the main campus by the works and
services department of the institution for the project. Therefore
the preliminary survey of the site to locate the project was not
carried out before the design. In the design, the architect avoids
creation of upper floor and basement slab to minimize cost so
that this project could pass through a ministerial approval.
2.6.4 Problems
The site chosen did not conform to assumed slope used for
the design, therefore the first major assignment on site, was to
carry out the preliminary survey to enable us to determine
Oversite concrete floor level. At the same time, give a clear
picture of the task ahead on substructure works, cost implication
and appropriate engineering solution that would be
23
8/8/2019 Junaid Nse Project
24/32
required to combat various problems at a minimal cost
without compromising quality and standard.
It was observed from the earthworks calculation that the
required filling necessary exceeded cutting more than 100%.
These however necessitate for proper planning to avoid
additional cost on the following activities.
(i) Laterite earth filling
(ii) Substructure block wall
(iii) Reinforcement
(iv) Reinforced in-situ concrete
(v) Sawn formwork
(vi) In-fill weak concrete
(vii) External rendering of substructure block walls
(viii) Painting and decoration of external substructure block
walls
24
8/8/2019 Junaid Nse Project
25/32
Table 3: Spot heights Survey of Phase A
Location Back sight Fore sight H.I Reduced
Level2.968 2.68 Assumed R.I
A 2.968 0.000B 1.5895 +1.373C 2.450 +0.518D 1.715 +1.253E 2.203 +0.765F 1.029 +1.939G 1.928 +1.040H 1.162 +1.806J 1.469 +1.499K 0.728 +2.240L 0.782 +2.186
M 0.558 +2.410N 0.350 +2.618O 1.535 +1.433P 2.210 +0.758Q 3.148 -0.180R 0.550 +2.418S 0.861 +2.107T 1.559 +1.409U 3.595 -0.627V 3.215 -0.247W 3.242 -0.274X 3.612 -0.356Z 2.113 +0.855
T22 1.415 +1.553A22 3.364 -0.396
Table 4: Spot heights Survey of Phase B
Station Back sight Fore sight H.I Reduced
LevelM 2.412 14.822 14.822 12.410
(Assumed R.L.)M2 2.235 12.587M3 1.832 12.990M4 1.842 13.142N2 2.000 12.822N3 1.364 13.45825
8/8/2019 Junaid Nse Project
26/32
N4 0.912 13.910N5 0.564 14.258L2 2.268 12.554L3 2.251 12.571L4 2.256 12.598L5 2.201 12.621
2.6.5 Prospect
After due consultation at the site meeting with all the
stakeholders on the project, I took the following steps towards
the successful completion of the job.
(1) Reducing the seat risers from 150mm to 100mm scaled the
vertical height difference of the sub-structure down. This brought
down the cost on substructure works within level + 300 and level
+ 6600 by 30%.
(2) After the setting out of works has been carried out, I excavated
for the column bases and ignore preliminaries
excavation for foundation walls. This enables me to use a
pail loader to bring enough laterite earth filling into the
foundation rather than resulting into expensive manual
labour filling. After the exercise, I did my excavation and
raise the foundation wall. This task also saved me more
than 75% of the real cost of earth fillings.
(3) Also since basement slab was deliberately avoided for
financial reason I was forced to make laterite earth filling to
2.8m above the natural ground level in some areas.
26
8/8/2019 Junaid Nse Project
27/32
Meanwhile, I looked for the way to minimize cost and
consider various options.
I consider double wall to be too expensive and structurally
unfit to resist the strong lateral earth pressure. Also, the
excessive height of the double wall that will start from foundation
and terminate at the German floor.
The second option considered was to replace the external
sub-structural block work with retaining wall.
The third option was to construct a LATERAL GROUND
BEAMS within the external sub-structural block work and
spanning over external columns. The lateral ground beam was
introduced at 1 metre apart to break the effect of
laterite earth filling pressure on the external wall as shown in the
diagram.
27
Lateral Beam 2
Lateral Beam 1
N.G.L
1 m
1 m
8/8/2019 Junaid Nse Project
28/32
Figure6 : Arrangement of lateral beam at the substructure
level
2.6.6 Design Analysis
Total horizontal pressure Ph = Area of s
Area of s = bxh
= Ph.h
= . .h.ka.h
= kah
2
where ka =
sin1
sin1
+
is angle of repose depend soil condition
= Density of the earthworks
h = height in metre
28
Pa
x
h
2/
3h
1/
3h
Pa= .h.ka
8/8/2019 Junaid Nse Project
29/32
Moment
Taking moment M due to Ph about base
M = Ph.h/3 = kah2. h/3 = 1/6 kah
3
M & h3 since and ka are constant
When h=0, M=0
At the base h=H M=Max
= 18KN/m3
When h = 2.8m
Ka = 0.33 (take angle of repose between soil to be 300)
M =6
2Kah
=
6)8.2(3 3.0/1 823
mxxmK N
= 21.73KN.m
29
8/8/2019 Junaid Nse Project
30/32
Reinforcements
Mu = 0.156 fcu bd2
= 0.156 x 20 x 225 x 2002
= 28KN/m2
Since M < Mu
Design for As only
K =2bdfcu
M=
2
6
20022520
1073.21
xx
x= 0.12
la = 0.5 +9.0
25.0 K = 0.5+
9.0
12.025.0
= 0.5+ 144.0 = 0.88
la = 0.88
As =dl aF
M
y
9 5.0=
20088.041095.0
1073.216
xxx
x
= 317mm2
Provide 2Y16 (402mm2) BOTTOM
Links Y10@ 225 C/C
Hanger bar 2Y12 (226mm2)
30
. ...
225mm
2Y122Y16
Y10@225 C/C
300mm
8/8/2019 Junaid Nse Project
31/32
2.7 REPORT OF PROFESSIONAL EXPERIENCE ON RECONSTRUCTION
OF ALG SCHOOL 1 & 2 OKE AGO-OWU
On assumption of office as a Site Engineer with
OASIS/CARDINAL Nig Ltd, I was hurriedly moved to Oke Ago-Owu
site to liase with the resident Consultant Engineers on the project
at the same time to pay attention to engineering matters on site.
2.7.1 Reconstruction of ALG School 1
The demolition exercise has been carried out before my
arrival and I quickly supervise the setting out of works to put the
job on the right course. The major problem encountered was on
substructure because of the topography of the site that
culminated into excessive height of the foundation wall and
oversite concrete floor level. But this was solved with introduction
of lateral ground beam on the sub-structure of the load-bearing
wall to prevent any possible shear failure, at the same time
enhance better structural stability.
The lintel level of the load-bearing and none load- bearing
wall was made of reinforced concrete all through to prevent
future vertical cracks that may occur.
31
8/8/2019 Junaid Nse Project
32/32
2.7.2 Reconstruction of ALG School 2
The project was initially billed for renovation when the
preliminary studies was carried out in 2002. The structural
defects on the building had reached alarming stage before the
project was awarded in 2006. The project consultant immediately
recommended total reconstruction to Ogun State Community
Based Urban Development Project, the recommendation was
approved and existing structure was demolished while the major
reconstruction was carried out.
The structural design of the reconstruction works was to be
carried out by the Supervising Project Consultant (Osot Associate)
under the leadership of Engr. R.A. Kumolu. But I sought the
permission of my humble mentor, distinguished registered and
highly respected Engineer (Engr. R.A. Kumolu) to allow me carry
out the design under his supervision. My request was granted, as-
built architectural drawing was produced and the design was
carried out as stated in volume 2 of this report.
32