Jodhpur Discom. Presentation before Sh. Sudhansh Pant I.A.S. Chairman Discoms & Managing Director,J.V.V.N.L.,Jaipur. 30.08.2011. WARM WELCOME. Sh. Sudhansh Pant I.A.S. Chairman Discoms & Managing Director,J.V.V.N.L.,Jaipur. Jodhpur Discom. DISCOM PROFILE. - PowerPoint PPT Presentation

Text of Jodhpur Discom

  • Jodhpur Discom Presentation beforeSh. Sudhansh Pant I.A.S.Chairman Discoms & Managing Director,J.V.V.N.L.,Jaipur.30.08.2011

  • WARM WELCOMESh. Sudhansh Pant I.A.S.

    Chairman Discoms & Managing Director,J.V.V.N.L.,Jaipur.

  • *Jodhpur Discom

    Zone wise

    JODHPUR DISCOM PROFILE

    S.No.DISTRICT COVEREDJODHPUR ZONEBIKANER ZONEJODHPUR DISCOM

    (1)AREA (SQ. km)117801647061.82 Lacs182507

    POPULATION AS PER CENSUS 20011186801882255872.01 Cr.20093605

    POPULATION DENSITY(PER SQ. KM)100.75127.12227.87110.0977222791

    TEHSIL COVERED39317070

    NO OF PANCHAYAT SAMITI44287272

    NO OF GRAM PANCHAYATS1604107126752675

    URBAN TOWNS25315656

    NO OF VILLAGES (As per census 2001)575867741253212532

    VILLAGE ELECTRIFIED UP TO 31.03.2011 (Including 206 Nos. UIV)521164571166811668

    VILLAGE ELECTRIFIED IN 2011-12 (Upto JULY ,11)0000

    % ELECTRIFICATION90.5095.3293.1193.1056495372

    (2)POWER NETWORK

    NO OF 400KV GSS3255

    NO OF 220KV GSS1792626

    NO OF 132KV GSS6847115115

    NO OF 33KV GSS (as on JULY. 2011)88651013961396

    LENGTH OF 33KV LINE (KM) (as on JULY., 11)1166167261838718387

    LENGTH OF 11KV LINE (KM) (as on JUNE 11)7395743367117324117324

    NO. OF 11/04.KV S/S (as on JUNE, 11)14634068046214386214386

    LENGTH OF LT LINE (KM) (as on JULY., 11)47096179446504065040

    NOS. SINGLE PHASE TRANSFORMERS ( JUNE,11)20941130423398333983

    A B CABLE IN KMS ( Upto JUNE, 11)20475140623453734537

    % T & D LOSSES FOR 11-12 (UPTO JULY,11)18.4821.8719.8220.89

    (3)Business Dimensions

    Revenue Sub-Divisions7451125125

    Total Active Consumers AS ON 30.06.20111393836102983224236682423668

    (a) Domestic108053286679319473251947325

    (b) Agriculture (Flat)3545465724202642026

    (c ) Agriculture (Metered)1270745033817741217741281475

    (D) Total Agriculture16252856910219438219438

    (e) PHED5707402197289728

    Annual Revenue (2010-11) (Rs. In Crores)1960.931143.183104.113104.1101

    Monthly Average Revenue (Rs. In Crores)163.4195.27258.68258.6758416667

    (4)FEEDER RENOVATION PROGRAM

    Total Rural Feeders Covered232610813407340722019

    218210683250325035278

    Villages getting 24 HRs. Supply489159571084810848

    14413157157

    Total 3 Phase Trans. To be installed as on 31.03.1062540237918633186331

    Total 3 Phase Trans. installed up to JULY.116129423759850538505325275

    BALANCE 3 Phase Trans. To be installed12463212781278012842

    (5)RGGVY15847

    Scheme costRGGVY31774.1111167.0642941.1742941.178372

    AREP603.53904.541508.071508.07119633

    No. of Unelectrifies/ Deelectrified villages coveredRGGVY9985271525152529931

    AREP60157217217

    No of villages electrifiedRGGVY53147010011001

    AREP55157212212

    (6)BPL Connections covered in Scheme (RGGVY)208974169695378669378669

    Nos.of BPL connections released (upto JULY.11)119183139053258236258236

    (7)AGRICULTURE

    Agriculture Connections IN 2010-11DN ISSUED4171329674677471

    DN DEPOSITED (Including Dep. As on 31.03.10)1468779672265422657

    CONN. RELEASED1290073082020820210

    BALANCE ( Deleting the Cancelled Appl.)157656521412142

    Agriculture Connections IN 2011-12DN ISSUED JULY,111403192662329723298

    DN DEPOSITED (Including Dep. As on 31.03.11) UPTO JULY,11796151411310213103

    CONN. RELEASED UP TO JYLY,111262119424562458

    BALANCE ( Deleting the Cancelled Appl.)656939471051610516

    No of SC AG released During 2011-12 up to JULY,1158477013541354

    (8)Mukhymantri sabke liye Vidyut Yojana

    Total Nos. of Groups Applied (UP TO JULY,11)1294035281646816468

    Total DN Issued to Groups (UPTO JULY,11)7784182996139613

    Total DN Deposited (UPTO JULY 11)5790152273127312

    Groups Electrified Upto 31.3.20115283139166746674

    Groups Electrified in 2011-12 (UPTO JULY, 11)30195396396

    TOTAL GROUP ELECTRIFIED5584148670707070

    No. of Cluster Sanctioned/Domestic Applications Covered366466832832

    2874372866026602

    No. of Cluster Connections Released/Domestic Connections Released2000200200

    1165011651165

    BALANCE GROUPS TO BE ELECRIFIED AGAINST DN DEPOSITED Deleting cancelled appl.)207122329329

    TOTAL DL CONNECTIONS RELEASED (UP TO JULY, 2011)3918097404892048920

    (9)APDRP DETAILS000

    TOTAL SCHEMES (NOS.)0077

    COST OF SANCTIONED SCHEMES (RS. IN CRORE)00359.29359.29

    EXPENDITURE INCURRED (RS. IN CRORE)00311.74311.74

    barmer cir

    BARMER CIRCLE PROFILE

    S.NO.DISTRICT COVEREDBARMERJAISALMER

    (1)AREA (SQ. km)2838738401

    POPULATION AS PER CENSUS 20011964835508247

    POPULATION DENSITY(PER SQ. KM)6913

    TEHSIL COVERED83

    NO OF PANCHAYAT SAMITI83

    NO OF GRAM PANCHAYATS402128

    URBAN TOWNS22

    NO OF VILLAGES (As per census 2001)1941637

    VILLAGE ELECTRIFIED UP TO 31.03.2010 (Including 206 Nos. UIV)1281562

    VILLAGE ELECTRIFIED IN 2010-11 (Upto DEC,10)1950

    % ELECTRIFICATION76.04%88.23%

    (2)POWER NETWORK

    NO OF 400KV GSS10

    NO OF 220KV GSS31

    NO OF 132KV GSS113

    NO OF 33KV GSS (as on DEC. 2010)15544

    LENGTH OF 33KV LINE (KM) (as on DEC., 10)26341653

    LENGTH OF 11KV LINE (KM) (as on DEC,10)156326875

    NO. OF 11/04.KV S/S (as on DEC.,10)265375604

    LENGTH OF LT LINE (KM) (DEC,. 10)61511088

    NOS. SINGLE PHASE TRANSFORMERS ( DEC,10)2939305

    A B CABLE IN KMS ( Upto DEC., 10)4317520

    % T & D LOSSES FOR 10-11 UPTO NOV.,1013.28

    (3)Business Dimensions

    Revenue Sub-Divisions14

    Total Active Consumers AS ON SEPTEMBER 1016099548107

    (a) Domestic11589838021

    (b) Agriculture (Flat)2875329

    (c ) Agriculture (Metered)230133358

    (D) Total Agriculture256103687

    (e) PHED1349351

    Annual Revenue (2009-10) (Rs. In Crores)286.42

    Monthly Average Revenue (Rs. In Crores)23.87

    (4)FEEDER RENOVATION PROGRAM

    Total Rural Feeders Covered478127

    377127

    Villages getting 24 HRs. Supply1264502

    1010

    Total 3 Phase Trans. To be installed as on 31.03.10145631785

    Total 3 Phase Trans. installed up to DEC.10126191785

    BALANCE 3 Phase Trans. To be installed19440

    (5)RGGVY

    Scheme costRGGVY20995.861338.78

    AREP603.53

    No. of Unelectrifies/ Deelectrified villages coveredRGGVY66898

    AREP60

    No of villages electrifiedRGGVY20798

    AREP55

    (6)BPL Connections covered in Scheme (RGGVY)6012410368

    Nos.of BPL connections released (upto JAN.11)72056770

    (7)AGRICULTURE

    Agriculture Connections IN 2009-10DN ISSUED45062174

    DN DEPOSITED (Including Dep. As on 31.03.09)47241497

    CONN. RELEASED3198757

    BALANCE ( Deleting the Cancelled Appl.)1514740

    Agriculture Connections IN 2010-11DN DEPOSITED Up to DEC.20101268659

    TOTAL TO BE RELEASED (incl. BALANCE of FY 2009-10 )27821399

    25831261

    BALANCE ( Deleting the Cancelled Appl.)188138

    No of SC AG released During 2010-11 up to JAN.11446141

    (8)Mukhymantri sabke liye Vidyut Yojana

    Total Nos. of Groups Applied5407502

    Total DN Issued to Groups1776214

    Total DN Deposited1588154

    Groups Electrified Upto 31.3.1047345

    Groups Electrified in 2010-11 (UPTO DEC. 10)2106

    TOTAL GROUP ELECTRIFIED68351

    No. of Cluster Sanctioned/Domestic Applications Covered1260

    8050

    No. of Cluster Connections Released/Domestic Connections Released230

    1890

    BALANCE GROUPS TO BE ELECRIFIED AGAINST DN DEPOSITED Deleting cancelled appl.)905103

    TOTAL DL CONNECTIONS RELEASED4529332

    (9)APDRP DETAILS

    TOTAL SCHEMES (NOS.)

    COST OF SANCTIONED SCHEMES (RS. IN CRORE)

    EXPENDITURE INCURRED (RS. IN CRORE)

    JALORE

    JALORE CIRCLE

    S.NO.DISTRICT COVEREDJALORE

    (1)AREA (SQ. km)10640

    POPULATION AS PER CENSUS 20011448940

    POPULATION DENSITY(PER SQ. KM)136

    TEHSIL COVERED7

    NO OF PANCHAYAT SAMITI8

    NO OF GRAM PANCHAYATS268

    URBAN TOWNS3

    NO OF VILLAGES (As per census 2001)706

    VILLAGE ELECTRIFIED UP TO 31.03.2010 (Including 206 Nos. UIV)706

    VILLAGE ELECTRIFIED IN 2010-11 (Upto DEC,10)0

    % ELECTRIFICATION100.00%

    (2)POWER NETWORK

    NO OF 400KV GSS0

    NO OF 220KV GSS2

    NO OF 132KV GSS14

    NO OF 33KV GSS (as on DEC. 2010)157

    LENGTH OF 33KV LINE (KM) (as on DEC., 10)1623

    LENGTH OF 11KV LINE (KM) (as on DEC,10)14947

    NO. OF 11/04.KV S/S (as on DEC.,10)38998

    LENGTH OF LT LINE (KM) (DEC,. 10)10047

    NOS. SINGLE PHASE TRANSFORMERS ( DEC,10)4282

    A B CABLE IN KMS ( Upto DEC., 10)3388

    % T & D LOSSES FOR 10-11 UPTO NOV.,101.82

    (3)Business Dimensions

    Revenue Sub-Divisions12

    Total Active Consumers AS ON SEPTEMBER 10196237

    (a) Domestic135919

    (b) Agriculture (Flat)18376

    (c ) Agriculture (Metered)27063

    (D) Total Agriculture45439

    (e) PHED800

    Annual Revenue (2009-10) (Rs. In Crores)203.84

    Monthly Average Revenue (Rs. In Crores)16.99

    (4)FEEDER RENOVATION PROGRAM

    Total Rural Feeders Covered480

    463

    Villages getting 24 HRs. Supply697

    17

    Total 3 Phase Trans. To be installed as on 31.03.1019078

    Total 3 Phase Trans. installed up to DEC.1018841

    BALANCE 3 Phase Trans. To be installed237

    (5)RGGVY

    Scheme costRGGVY2367.41

    AREP

    No. of Unelectrifies/ Deelectrified villages coveredRGGVY30

    AREP

    No of villages electrifiedRGGVY30

    AREP

    (6)BPL Connections covered in Scheme (RGGVY)54217

    Nos.of BPL connections released (upto JAN.11)33719

    (7)AGRICULTURE

    Agriculture Connections