56
1 | Page SUMMER TRAINING REPORT 2011 (23 rd MAY-15 th JULY) INDIAN OIL CORPORATION LIMITED PANIPAT REFINERY ATMOSPHERIC AND VACCUM DISTILLATION UNIT SUBMITTED BY RAVI VERMA (08112028) DEPARTMENT OF CHEMICAL ENGINNERING Dr. B.R. AMBEDKAR NATIONAL INSTITUTE OF TECHNOLOGY JALANDHAR

IOCL Report 2011

Embed Size (px)

Citation preview

Page 1: IOCL Report 2011

1 | P a g e

SUMMER TRAINING REPORT 2011

(23rd MAY-15th JULY)

INDIAN OIL CORPORATION LIMITED

PANIPAT REFINERY

ATMOSPHERIC AND VACCUM DISTILLATION UNIT

SUBMITTED BY

RAVI VERMA (08112028)

DEPARTMENT OF CHEMICAL ENGINNERING

Dr. B.R. AMBEDKAR NATIONAL INSTITUTE OF TECHNOLOGY

JALANDHAR

Page 2: IOCL Report 2011

2 | P a g e

ACKNOWLEDGEMENT

My sincere thanks to Mr.Y.B.Joshi and Mr. Ravi Sharma for allowing me to

do training under their guidance. I am grateful for their cooperation.

I express my sincere gratitude to Mr. K.S.Shukla and Mr. Subhajit Sarkar for

providing invaluable support and guidance.

My acknowledgement especially to Mr.Vikas kashyap (Process Engineer) who

helped me to understand the practical aspects of my project and in giving the

useful data necessary for the project.

The various guidelines and information given to me by Mr. BARDAN LAMA,

Mr. PRATEEK and Mr. GAGAN were of extreme help during project.

I would like to appreciate the time taken out by them for clarifying my doubts

and helping me at various steps.

RAVI VERMA

08112028 ------------------------------

DEPARTMENT OF CHEMICAL ENGINNERING

NATIONAL INTITUTE OF TECHNOLOGY

JALANDHAR

(2008 – 2012)

Page 3: IOCL Report 2011

3 | P a g e

CONTENTS

SECTION -1 IOCL

1. An Introduction To INDIAN OIL CORPORATION

2. IOCL PANIPAT

SECTION -2 ATMOSPHERIC AND VACCUM DISTILLATION

UNIT

1. INTRODUCTION

2. PRODUCTS OF UNIT

3. CRUDE AND PRODUCT SPECIFICATION

4. LIST OF EQUIPMENTS

5. PROCESS DESCRIPTION

6. CRUDE DISTILLATION UNIT

7. NAPTHA STABILIZER SECTION

8. NAPTHA SPLITTER SECTION

9. MTO SPLITTER SECTION

10. VACCUM DISTILLATION UNIT

11. LPG AMINE & CAUSTIC WASH SECTION

12. FUEL GAS TRAETMENT SECTION

13. CHEMICALS REQUIRED

14. UTILITIES REQUIRED

SECTION -3 PROJECTS

1. INTRODUCTION

2. FLOW DIAGRAM

3. CALCULATION

4. RESULT

SECTION -4 REFRENCES AND BIBLOGRAPHY

Page 4: IOCL Report 2011

4 | P a g e

SECTION 1:

IOCL

Page 5: IOCL Report 2011

5 | P a g e

INDIAN OIL CORPORATION

Indian Oil Corporation Ltd. is India’s largest commercial enterprise, with a

sales turnover of Rs.2,85,337 crore and a net profit of Rs.2,950 crore for

the year 2008 – 09. Indian Oil is also the highest ranked Indian company

in the prestigious Fortune Global 500 listing ( 116 to position in 2008).

Indian Oil Company Ltd. established as an Oil marketing entity on 30th

June 1959, and was renamed Indian Oil Corporation Ltd. on 1st September

1964 following the merger of the refining entity ,Indian Refineries Ltd.

Since then, the Indian Oil people with their dedication and determination

have nurtured the integrated downstream petroleum company into India’s

No. 1 company and the country’s largest commercial enterprise . It is the

ceaseless efforts of several generations of the Indian oil family that has

today placed the corporation firmly among the world’s largest corporate ,

with the distinction of being 18th largest petroleum company in the

world .

Set up with a clear mandate for achieving self-sufficiency in petroleum

refining ,pipelines transportation and marketing operations for a nascent

nation set on the path of economic growth and prosperity , Indian Oil is

proud to account for nearly half of India’s petroleum consumption today .

Indian Oil and its subsidies account for 49% petroleum products market

share , 40.4 % refining capacity and 69 % downstream

Sector pipelines capacity in India. The Indian Oil Group of companies owns

and operates 10 of India’s 20 refineries with a combined refining

capacity of 60.2 MMPTA. i.e. 1.2 barrels per day. The Corporation’s cross –

country network of crude oil and product pipelines ,spanning about 9,300

km and the largest in the country, meets the vital energy needs of the

consumers in an efficient, economical and environmental – friendly manner.

Page 6: IOCL Report 2011

6 | P a g e

To achieve the next level of growth, Indian Oil is currently forging

ahead on a well laid – out road map through vertical integration -

upstream into oil Exploration & Production and downstream into

petrochemicals and diversification into natural gas marketing, besides

globalization of its downstream operations .

As the leading public sector enterprise of India, Indian Oil has

successfully combined its corporate social responsibility agenda with its

business offerings, meeting the energy needs of millions of people

everyday across the length and breadth of the country , traversing a

diversity of cultures , difficult terrains and harsh climatic conditions . The

corporation takes pride in its continuous investments in innovative

technologies and solutions for sustainable energy flow and economic

viable and environment- friendly products & services for the benefit of its

consumers.

IOCL PANIPAT

Panipat Refinery is the 7th refinery of Indian Oil commissioned in 1998.

Referred to, as country’s technically advanced refinery is situated in the village

Baholi in Panipat District of Haryana. Built at the cost of Rs.3, 868 crore, it has

an installed capacity of 15 MMTPA now. Backed by global, state-of-the-art

technologies from IFP-France, Haldor Topsoe-Denmark, UNOCAL/UOP-USA,

Stone & Webster-USA, and Delta-Hudson-Canada. The refinery is designed for

processing both indigenous and imported crudes. It receives crude oil through

the chaksu-Kamal branch pipeline of the Salaya-Mathura pipeline Vadinar

Gujarat coast to Panipat through a 1339 km long pipeline.

The various products of the refinery are:

01. Liquefied Petroleum Gas

02. Naphtha

03. Motor Spirit

04. Aviation Turbine Fuel

05. Mineral Turpentine Oil

06. Superior Kerosene

07. High Speed Diesel

08. Heavy Petroleum Stock

09. Bitumen

10. Sulphur

Page 7: IOCL Report 2011

7 | P a g e

Around 66% of these products are transported through environment-friendly

pipelines, while both rail and road account for 17% each.

Panipat Refinery meets demands of petroleum products not only of Haryana but

also the entire Northwest Region including Punjab, J&K, Himachal,

Chandigarh, Western U.P. and part of Rajasthan and Delhi.

Indian Oil Corporation Limited (IOCL) at Panipat consists of various units.

Among them major once are:

1. Atmospheric and Vacuum Distillation Unit(AVU)

2. Continuous Catalytic Reformer Unit(CCRU)

3. Visbreaking Unit(VBU)

4. Hydrogen Generation Unit(HGU)

5. Resid Fluidized Catalytic Cracking Unit(RFCCU)

6. Once Through Hydrocracker Unit(HCU)

7. Diesel Hydro Desulphurisation Unit(DHDS)

8. Amine Regeneration Unit(ARU)

9. Sour Water Stripper Unit(SWSU)

10. Bitumen Blowing Unit(BBU)

11. Recovery Unit(SRU)

Page 8: IOCL Report 2011

8 | P a g e

Atmospheric and Vacuum Distillation Unit(AVU)

SH Steam

Crude Filter Desalter

Furnace

Atmospheric

Column

Unstablised Gasoline

Inter Naphtha

Heavy Naphtha

Kerosene/ATF

Light Gas Oil

Heavy Gas

Oil

SH Steam

Atmospheric Residue

Non-Condensable

Vacuum Residue

Heavy Vacuum

Gas Oil

Light Diesel Oil

Light Vacuum

Gas OilVacuum

Column

AVU is designed to process 6.0 MMTPA Bombay High and Arab Mix crudes in

blocked out operation. AVU, a fully integrated unit, consists of the following

sections. Crude Distillation Unit, Vacuum Treating Units for Fuel Gas, LPG and

Page 9: IOCL Report 2011

9 | P a g e

Naphtha. The Unit was mechanically completed in February 1998 and trial

operation of the various sections started in phases starting from May 1998. The

Unit was commissioned on 2nd

October 1998

Continuous Catalytic Reformer Unit(CCRU)

LPG

Reformate

H2 Rich Gas

Fuel Gas

LPG

Absorber

StabliserRecontacting

Drum

Hydrotreater Recycle

Gas Compressor

Hydrotreater

Naphtha

Feed

Seperator Stripper

Reforming

Reactors

Seperator

Purge to

ATU

Recycle Gas

Compressor

H2 Rich Gas

Compressor

Hydrotreated

Naphtha

Storage

M/s. IFP, FRANCE licenses the CCRU. This unit is designed to process 0.5 MMTPA

of SR Naphtha from Arab mix and/or Bombay High crude. This unit consists of

Naphtha Hydro Treating, Catalytic Reforming and Catalyst Circulation and

Page 10: IOCL Report 2011

10 | P a g e

Regeneration Sections. Catalytic Reforming is a major conversion process that

transforms low octane Naphtha feed stock to high octane reformate (RON : 98)

for use as a gasoline blending component to make lead free petrol (MS). A rich

hydrogen gas (about 90% purity) and LPG are obtained as valuable by- products. The

reformer can also be run for production of reformate rich in benzene, toluene, and

xylenes (BTX).

Visbreaking Unit(VBU)

SHS

Soaker

AR

Quench

Fractionator

Unstablised

Gasoline

VB Gas Oil

Visbreaking Unit (VBU) is designed to process 0.4 MMTPA Arab mix vacuum

residue. This unit is a soaker Visbreaker, which reduces the viscosity of feed at

lower temperature. The unit was mechanically completed in March 1998 and

the trial operation started in July, 98. The unit was commissioned on 29th

Page 11: IOCL Report 2011

11 | P a g e

October 1998.The visbreaker is designed to process 400000 MTPA of Arab mix

vacuum residue from a crude mix of 50:50 Arab heavy and Arab light crudes.

The unit consists of a two pass heater and separation system. The products from

the unit are fuel oil, gasohol, and naphtha and fuel gas.

Products

VB Gas 8200 MTPA

VB Naphtha 13600 MTPA

VB Gasohol 44800 MTPA

VB Tar (350 C) 333400 MTPA

Hydrogen Generation Unit

Recycle H2

Light NaphthaHydro-

Desulphurisat ion

Sulphur

Absorber 1 & 2

Pre-ReformerTubular ReformerMT-Shift

Converter

Pressure Shift

Adsorber

Product H2

Off Gases

The Panipat Refinery Hydrogen Unit is designed to produce 38,000 MTPA of

high purity (99.99%) hydrogen gas Hydrogen is produced in the unit by Steam

Page 12: IOCL Report 2011

12 | P a g e

Reforming of Naphtha based on the technology from M/S Haldor Topsoe A/S,

Denmark.

The process for hydrogen generation involves the following four major

steps.

Sulphur removal from Naphtha.

Steam reforming of Naphtha

Medium and low temperature shift conversions.

Hydrogen purification in a PSA unit.

Residue Fluidised Catalytic Cracking Unit

HP

Receiver

Na

ph

tha

Sp

litte

r

LCN

HCN

De

bu

ten

ise

r

Compressor

HCO

Flue Gas

to Stack

Main

Column

Air

Blowe

r

Reactor

RG-2

RG-1

DCO

O/H

Receiver

LCO

LPG

Str

ipp

er

Pri

ma

ry

Ab

so

rbe

r

Sp

on

ge

Ab

so

rbe

r

Off

Gas

Rich

Oil

Feed

Slurry +

HCO

Page 13: IOCL Report 2011

13 | P a g e

The demand of the petroleum products in the world is shifting more towards

light distillates because of increasing demand of LPG and Gasolene as a result

of the steady growth in private transportation system and shift towards the

cooking gas in the developing countries. The declining market for fuel oil

coupled with anticipated changes in the future crude quality and the shift in

product demand in favour of light distillate placed and additional emphasis on

upgrading the bottom of the barrel i.e. the heavier residues into more and more

light distillates

Diesel Hydrodesulphurisation Unit

Hydrogen

Make up gas

Compressor

Section

Hydrogen

Reactor

Heater

System

Reactor

Section

Recycle gas

Compressor

Section

Feed

System

Stripper

Section

Naphtha

Stabilizer

Section

HP Amine

Absorber

Section

LP Amine

Absorber

Section Rich Amine

to ARU

Naphtha to

Storage

Gas Oil to

Storage

Separation

Section

Feed

Preheating

System

Page 14: IOCL Report 2011

14 | P a g e

The DHDS unit is set up to reduce sulfur content in the diesel and produce

diesel with 0.25% Sulphur.

The unit treats the following gas-oils fractions.

1. S.R.Gas oil

2. Vacuum Diesel

3. Vis-Breaker Gas Oil

4. Total Cycle Oil

DHDS unit has been designed to reduce the sulphur content in High Speed

Diesel to less than 0.05% wt. The process technology for this unit was built

within the record time on LUM SUM TURN key (LSTK) basis by M/s.

L&T. The capacity of the unit is 0.7 MMTPA. The unit was mechanically

completed in March’99 and commissioned on the 12th

July.

Amine Regeneration Unit(ARU)

ARU is designed to process Hydrogen Sulfide rich amine from amine

Absorption units and recover amine after releasing the acid gas to the Sulphur

Recovery Unit. This unit was mechanically completed in February’99 and was

commissioned on 6th

March’99.

Sour Water Stripper Unit(SWSU)

The unit consists of 2 Sour Water Stripping Units, one for the sour water from

the Hydrocracker unit and the other for the sour water from the remaining units.

This unit was mechanically completed in December’98 and was commissioned

on 15th

February’99.

Page 15: IOCL Report 2011

15 | P a g e

Bitumen Blowing Unit (BBU)

Bitumen Blowing Unit (BBU) has been designed to produce 3 grades of

Bitumen, viz.: 80-100, 60-70 and 30-49 from vacuum residue of high Sulfur

Crudes. The capacity of the unit is 0.5 MMTPA. This unit was mechanically

completed in March 1998; trial run of the unit was taken in July 1998 and was

commissioned on 12th December 1998.

Sulfur Recovery Unit (SRU)

SRU is designed to process Hydrogen Sulfide rich acid gas recover elemental

sulfur. The unit was designed by M/s. EIL for a capacity of 84tonnes per day

96% recovery efficiency, which has further been revamped to 115 tonnes per

day and 99% recovery efficiency based on the process technology of M/s. Delta

Hudson, Canada. This unit was mechanically completed in March’99 and was

commissioned on 30th March’99.

Other Facilities:

Off sites

The off sites facilities at Panipat Refinery are spread over an area of 115 acres.

There are 77 Storage tanks having storage capacity of 400,000KL Crude Oil

and 830,000KL of Petroleum products. There are 7 nos. of pump stations, a

blending station and connecting pipelines. There are 7 nos. of LPG Horton

Spheres each of 1500KL capacity. The off sites operation is controlled from the

centralized DCS control room of OM&S. The special feature of offsite

operation is that Tank Truck loading (TTL) and Tank Wagon Loading (TWL)

facilities are provided at the Marketing Terminal, which is adjacent to the

refinery. Offsite operation of the Refinery started with the receiving of the first

batch of crude oil in Refinery Storage Tanks on 30th

November’97.

Page 16: IOCL Report 2011

16 | P a g e

Thermal Power Station & Utilities

The Power and Steam requirement of the refinery is met from the Captive

Power Plant designed and constructed by BHEL in consultation with NTPC.

Capacity of the power plant is:

Steam Turbine Generator – 3 x 25 MW.

Gas Turbine Generator – 30 MW.

Steam boiler – 3 x 160 T/hr.

Heat Recovery Steam Generator: 125 T/hr.

The first boiler was commissioned in May’97 and first TG was commissioned

in August’97.

Nitrogen Plant

Nitrogen is produce in a cryogenic separation plant by air distillation after

liquefying the same. M/s. BHPV constructed the plant on a turnkey basis. The

capacity of the plant is 800 NM3/hr. The plant was commissioned on

December’97.

Miscellaneous

One raw water reservoir of capacity 200,000KL

Raw water treatment plant of capacity 2100KL/hr.

Four chains of DM Water treatment plant

Compressed air system with 4 nos. of compressors and 3 nos. air drier.

Cooling tower with 5 cells for TPS and 8 cells for process units

Page 17: IOCL Report 2011

17 | P a g e

SECTION 2

ATMOSPHERIC AND VACCUM

DISTILLATION UNIT

Page 18: IOCL Report 2011

18 | P a g e

INTRODUCTION

Atmospheric, Vacuum and Naphtha Splitter unit of Panipat Refinery is designed

to process 100% Bombay High Crude and 100% Arab Mix Crude (consisting of

light and heavy crude in 50:50 proportion by weight) in blocked out operation

without loss of throughput @ 7.5 MMTPA. Unit is located in an area of 24800

square meters & was commissioned with 6.0 MMTPA in May 1998 and

revamped to 7.5 MMTPA in October 2010. In actual practice various low

sulphur crude and high sulphur crude are being processed since commissioning

of the plant.

AVU is called a mother unit as it provides feed to other secondary units like

hydrogen unit, CRU, HCU, FCC, Bitumen unit and VBU.

In addition to crude processing, AVU also maintains Fuel Gas amine wash

system and LPG vaporiser to maintain refinery fuel gas header pressure.

SECTIONS IN THE UNIT :

a) Crude Desalting section.

b) Preflash section.

c) Atmospheric Distillation section.

d) Stabiliser section.

e) Naphtha splitters for HGU, CCRU and PX feed

f) Naphtha Caustic wash section.

g) MTO splitter section.

h) Vacuum Distillation section.

i) LPG Amine & caustic wash section.

j) Centralised Sour Fuel gas Amine treatment section.

k) LPG vaporiser section.

CAPACITIES :

1) Crude Distillation Unit 7.50 MMTPA

2) Vacuum Distillation Unit. 4.125 MMTPA

3) Naphtha stabiliser. 1.525 MMTPA

4) Pre-topping column. 1.375 MMTPA

Page 19: IOCL Report 2011

19 | P a g e

5) MTO splitter. 0.03 MMTPA

0.03 MMTPA production from ATF/KERO stream of Arab Mix with

4000 Hrs. operation.

6) Naphtha caustic wash

C5-90ºC cut. 0.48 MMTPA

90-120º C cut. 0.6MMTPA

S.N

O SHORT

NAME

LONG NAME CUT RANGE º

C USAGE

1. GAS

Fuel gas C1-C2 Internal fuel

2. LPG Liquefied Petroleum

Gas

C3-C4 Domestic/Auto

fuel

3. NAPH Naphtha C5-120 MS Component

4. HN Heavy Naphtha 120-150 HSD

Component

5. KERO Kerosene 140-270 Domestic fuel

6. ATF Aviation Turbine Fuel 140-240 Aeroplanes

7. LGO Light Gas Oil 240/270-320 HSD/

DHDS/DHDT

feed

8. HGO Heavy Gas Oil 320-370 HSD/

DHDS/DHDT

feed

Page 20: IOCL Report 2011

20 | P a g e

2. PRODUCTS OF THE UNIT

3 . CRUDE AND PRODUCT SPECIFICATION

SPECIFICATION OF CRUDE :

1) Gravity 30-40 º C API

2) Viscosity 3-24 Cst @ 36 º C

3) Pour point (-) 30 – (+) 30 º C

4) RVP 0.34-0.67 Kg/cm2 (max.)

5) Salt content 165 ppm (max.)

6) BS & W 2.0% vol. (max.)

7) Total Sulphur 0.17-2.35 % Wt.

8) Wax Content 10.68-2.8% wt.

SPECIFICATION OF PRODUCT :

9. VD Vacuum Diesel 370 HSD/

DHDS/DHDT

feed

10. LVGO Light Vacuum gas Oil 370-425 Feed to

HCU/FCCU

11. HVGO Heavy Vacuum Gas

Oil

425-550 Feed to

HCU/FCCU

12. V.SLOP Vacuum Slop 550-560 IFO Component/

feed to RFCCU

13. VR Vacuum Residue 560+ Bitumen/ VBU

feed/ DCU feed /

RFFCU feed

14. C5-90º C cut NAPTHA C5-90 HGU

feed/ISOM Feed

Page 21: IOCL Report 2011

21 | P a g e

1) LPG Confirm to IS-4576 to general and

following specifications in

particular.

a) Vapour pressure @ 65º C not to

exceed 16.87 Kg/cm2 (a)

b) Weathering 95% vol. Minimum

at 2º C and 760 mm HG

pressure.

c) Not more than 1% of C5

components.

2) STABILISED NAPHTHA RVP not to exceed 0.7 Kg/Cm2 (a)

3) HN Flash : >15 C

Distillation : 120-140 º C

4) KERO Confirm to IS : 1459-

1974

FBP : 300º C (max.)

Flash : 38º c (min)

5) ATF Flash : 38º C (min)

Freezing : (-) 50º C (min)

Silver strip : Nil

Corrosion.

Density @ : 0.775 to 0.84

6) MTO Confirm to BIS-1440 in general and to

the

Page 22: IOCL Report 2011

22 | P a g e

Following specifications in particular.

ASTM D-86 IBP : 145º C

FBP : 200º C

Flash : 38º C

7) LGO Flash : 35º C (min)

Pour : As per instruction.

8) HGO Flash : 35º C (min.)

Pour : As per instruction

Recovery : 90% @360 º C

9) RCO Flash : 150º C

Density : As reported

Recovery : 10% at 370º C

10) Vac. Diesel Flash : >125º C

Pour : (+6) to (+) 18º

Recovery : 90% @360 º

C

11) LVGO CCR :

0.50wt.%max.

12) HVGO Pour : (+) 27 to (+)

42º C

Page 23: IOCL Report 2011

23 | P a g e

4. LIST OF EQUIPMENTS:

A. COLUMNS:

1. Crude Distillation column

2. Heavy Naphtha stripper

3. KERO/ATF Stripper

4. LGO stripper

5. HGO stripper

6. Naphtha stabilizer

7. Naphtha splitter

8. MTO Splitter

9. Vacuum Distillation column

10. LPG Amine Absorber

11. Fuel Gas Amine Absorber

A. VESSELS

B. PUMPS

C. FURNACES (Crude furnace, Naphtha Splitter Furnace and Vacuum

furnace)

D. EJECTORS

E. AIR FIN COOLERS

F. AIR FIN COOLER FANS

G. EXCHANGERS

H. REBOILERS

I. DESALTERS (Crude Desalter 1st stage, 2

nd stage and 3

rd stage)

5. PROCESS DESCRIPTION

Crude oil from crude charge pumps is charged to preheat exchanger trains in

two parallel streams.

Page 24: IOCL Report 2011

24 | P a g e

1st PREHEAT TRAIN

The first crude stream passes through Crude v/s vacuum diesel CR and

picks up heat from Vacuum Diesel CR coming at 142-166º c. Vacuum

Diesel CR is cooled to 91-99º C, whereas crude is getting heated upto 56-

61º C.

Crude outlet from above enters Crude v/s Hy. Naphtha CR exchanger.

Crude gets heated upto 87-103º C whereas Hy. Naphtha CR gets cooled

from 122-147º C to 94-108º C.

After that, Crude enters Crude v/s VR exchanger. Crude gets heated upto

113º C whereas VR gets cooled from 237-242º C to 178-128º C.

The second crude steam passes through Crude v/s Kero/ATF where it is

picking up heat from Kero/ATF coming at 124-125º c & getting cooled to

95-98º C whereas crude is getting heated upto 55-58º C.

After this, crude enters crude v/s Kero/ATF CR exchanger. Crude gets

heated upto 107-115º C, whereas Kero/ATF CR gets cooled from 154-

171º C to 115 º C.

After that, crude enters crude v/s Kero/ATF exchanger. Crude gets heated

upto 132-135º C, whereas Kero/ATF CR gets cooled from 163-174º C to

124-125 º C.

Crude oil from both streams is combined to average the temperature @ 136-

141º c and enters crude desalters 03-LD-001 & 03-LD-002 in series.

Provision has been kept to inject wash water and demulsifier.

ELECTRIC DESALTING

The desalter is an electrostatic coalescer used for purification of crude from

sludge, salts and corrosion inducing salts. Sludge and salts like NaCl

generally gets deposited on the tubes of exchangers and thus reduce preheat

temperature. Salt if not removed will cause corrosion in distillation column.

Salts may vary widely in the ratio of metal ions and brine concentration

though 75% Na, 15% Mg and 10% Ca are common averages. Chloride is the

source of the indices of corrosion potential of the crude. MgCl2 is the most

specific producer of HCI with Ca and Na in descending order. In desalting,

the electric field is a powerful tool for overcoming the resistance of

stabilising films. The collision and coalescence of drops is accomplished by

Page 25: IOCL Report 2011

25 | P a g e

an induced dipole attraction between them. That is the electrical charges

inherent in each droplet are separated so that positive charges move to one

end of the droplet and negative charges move to the other end.

As droplets then approach each other, the force between them becomes very

great. The stabilizing films are squeezed between drops and coalescence is

rapid. In a 5% emulsion, drops average about two diameters apart;

coalescence proceeds almost instantaneously. The distance between drops

then increases as drops fall due to gravity. For a 1% emulsion, drops are four

diameters apart and coalescence slows. When the emulsion content is 0.1%,

drops are eight diameters apart on the average. The forces of dipole

attraction, diminished by a factor of 250, are insignificant at this distance and

the final emulsion content shall depend on this to about 0.1%.

Crude from second desalter, bypassing crude pump (03-P—003 A/B/C)

discharge, is divided into parallel heat exchanger trains

2ND

PREHEAT TRAIN

The first desalted Crude stream passes through Crude v/s HGO where

it is picking up heat from HGO coming at 185-194º C and getting cooled

to 140-144º C whereas crude is getting heated up to 140-142º C.

After this, crude enters Crude v/s LVGO exchanger. Crude gets heated up

to 166-174º C whereas LVGO gets cooled from 265-268º C to 147-152º

C.

Subsequently, crude enters Crude v/s HGO exchanger. Crude gets heated

up to 185-194 º C.

The second desalted crude stream passes through 03-E-021 (Crude v/s

Kero/ATF) where it is picking up heat from Kero/ATF coming at 195-

205º c and getting cooled to 163-174º C whereas crude is getting heated

upto 146-153º C.

Further, crude enters Crude v/s LGO CR where it is picking up heat from

LGO CR coming at 185-190º C and getting cooled to 170-180º C

whereas crude is getting heated upto 155-162º C.

Page 26: IOCL Report 2011

26 | P a g e

After that, crude enters Crude v/s HVGO where it is picking up heat from

HVGO coming at 248-291º C and getting cooled to 204-211º C whereas

crude is getting heated up to 173-176º C.

Crude oil from both streams is combined to average the temperature @ 179-

180º C and enters pre-flash drum where 3-4% wt. of light ends are removed.

Crude after flashing in the preflash drum is pumped by through 3rd

preheat train,

after being further divided into two parallels preheat circuits.

3rd

PREHEAT TRAIN

The first crude stream passes through Crude v/s LGO CR where it is

picking up heat from LGO-CR coming at 241-249º C and getting

cooled to 185-190º C whereas crude is getting heated upto 210-213º

C.

Crude then enters Crude v/s HVGO CR exchanger. Crude gets heated

up to 218-228º C whereas HVGO CR gets cooled from 259-271º C to

239-258º C.

After that, crude enters Crude v/s HGO CR exchanger. Crude gets

heated up to 223-249º C whereas HGO CR gets cooled from 302-311º

C to 275-303º C.

Subsequently, crude enters Crude v/s HVGO CR exchanger. Crude

gets heated up to 241-277º C whereas HVGO CR gets cooled from

238-298º C to 239-271º C.

Further, crude enters Crude v/s HVGO exchanger. Crude gets heated

up to 251-283º C whereas HVGO gets cooled from 298-306º C to

201-248º C.

After that, crude enters Crude v/s HGO exchanger. Crude gets heated

up to 259-289º C whereas HGO gets cooled from 323-325º C to 291-

260º C.

The second crude stream passes through Crude v/s LGO where it is

picking up heat from LGO coming at 226-258º C and getting cooled to

179-197º C whereas crude is getting heated up to 184-198º C.

After that, crude enters Crude v/s LVGO CR exchanger. Crude gets

heated up to 218-236º C whereas LVGO CR gets cooled from 258-

265º C to 204-214º C.

Further, crude enters Crude v/s VR exchanger. Crude gets heated up to

248-265º C whereas VR gets cooled from 350/350º C to 237-242º C.

Page 27: IOCL Report 2011

27 | P a g e

After this, crude enters Crude v/s vacuum slop exchanger. Crude gets

heated up to 258-288º C whereas vac slop gets cooled from 353/370º

C to 298-353º C.

Crude is combined to average the temperature @ 259-289º C .This

temperature is called preheat temperature or coil inlet temperature (CIT).

FIRED HEATERS :

The preheated crude is further heated and partially vaporized in Atmospheric

Heater having eight passes. (Four sections with 6 inches sch. 40 tubes).

The atmospheric heater is a box-type vertical furnace with up firing burners,

8 Nos. of burners in each section are provided on the floor with FG and FO

firing facilities. A total 32 nos. of burners have been provided in CDU

heater. Out of 32 burners, 28 nos. of burners have both FO and FG firing

facility and 4 burners, called LP burners have facility to fire off- gas from

VDU column and FG (called support burners).

This heater is having two distinct heating sections i.e.

A) Radiant Section: It houses the burners and forms the combustion

chamber or fire box. Tubes are arranged in a vertical arrangement

along the walls of each cell with tube arrangement itself forming the

cell.

B) Covection Sections: It receives heat from hot flue gases leaving the

radiant section. Tubes are arranged in horizontal bank and positioned

above radiant section.

Page 28: IOCL Report 2011

28 | P a g e

6. CRUDE DISTILLATION SECTION

The column is provided with 56 trays of which 10 are baffle trays in the

stripping section. In addition 6 nos. of chimney trays are also provided in the

column. Feed to the column is on tray # 10. The vaporized portion of the feed

along with the light ends from the Pre-topping Vessel are fractionated on trays

above the flash zone to yield liquid side draw products, pump arounds

(circulating refluxes) and overhead vapor stream.

Heated and partly vaporized crude feed coming from fired heater enters the

flash zone of the column at tray no. 10 at 360-370 º C (LS crude)/370-380º C

(HS crude). Hydrocarbon vapors flash in this zone and get liberated. Non

flashed liquid moves down which is largely bottom product, called RCO.

Certain degree of over flashing of crude is desirable for proper stabilisation of

RCO and fractionation of gas oil components. Over flash is achieved by setting

up COT at slightly higher value than actually required. This over flashed

material mostly condenses on 11th

tray. The condensed liquid withdrawn from

11th tray is put back on 10

th tray into the column. Over flash liquid travels down

form tray 11 to tray 10. It strips out heavier vapour components coming up from

RCO stock collected at column bottom and which otherwise could move and

cause coloration of gas oil stream. Flow of over flash liquid could be increased

by either increasing COT and condensing more material on 11th

tray or by

reducing HGO draw off and dropping more HGO components on 11th

tray.

However, this will result is less gas oil yield and higher energy consumption

without any advantage. Too large flow of over flash liquid may result in drop in

bottom temperature and lighter bottom product, RCO.

The optimum over flash flow is about 4-5 % on crude throughput. MP steam

having some degree of superheat is introduced in the column below tray 1, at

approximately 3.5 Kg/Cm2 (g) and 290º C for stripping of RCO. Steam

stripping helps to remove lighter constituents from the bottom product RCO by

reducing their partial pressure and helping them vaporize without requiring

additional heat. Hydrocarbon vapours liberated by flashing move up along with

steam in the column for further mass transfer at trays in upper section.

Page 29: IOCL Report 2011

29 | P a g e

Steam flow to column is regulated based on outgoing RCO quantity to Vacuum

Heater. To reduce pressure drops at column entry nozzle and achieve

homogenous distribution, steam is introduced through two nozzles.

Reduced crude oil product is collected at bottom of the column. Column bottom

level control can be done either by manipulating RCO flow to vacuum heater or

by manipulating VR+Quench rundown flow (in case of only CDU run when

VDU is not operating).

OVERHEAD SECTION :

The overhead vapors are totally condensed in Crude Overhead Air Condensers.

This condensed overhead product is separated as Hydrocarbon and water in a

Reflux Drum. Water is drawn out under inter-phase level control and sent to

sour water stripper or to ETP by a pump. Unstabilised naphtha containing Fuel

Gas, LPG and Naphtha is partially refluxed and partially pumped to the

Stabilizer.

HEAVY NAPHTHA SECTION:

Heavy Naphtha is withdrawn as side product from tray # 44 to the Side Stripper.

Light ends in Hy. Naphtha is stripped in the Hy. Naphtha Reboiler using LGO

as the hot medium. Stripped vapors from the side stripper are routed to tray # 46

of the Atmospheric Column. The bottom product is cooled in Hy Naphtha

/BFW Exchangers followed by a trim cooler and sent to storage.

KERO SECTION:

Kero is withdrawn as side product from tray # 31 to the Kero side stripper .

Light ends in Kero are stripped in the Kero Reboiler using HVGO CR as the hot

medium. Stripped vapors from the side stripper are routed to tray # 33 of the

Atmospheric Column. The bottom product is routed to MP Steam Generator

followed by LMP Steam Generator and Crude Preheat exchanger (to reduce

Page 30: IOCL Report 2011

30 | P a g e

vapour pressure & hence increase available NPSH) before being pumped. The

discharge of routed to crude preheats exchangers and finally cooled before

being routed under flow control to storage.

LIGHT GAS OIL SECTION :

LGO is withdrawn as side product from tray # 22 to the LGO side Stripper.

Light ends in LGO are stripped using MP steam. Stripped vapors from the side

stripper are routed to tray # 24 of the Atmospheric Column. The bottom product

is pumped by 03-P-12 A/B under flow control through Hy. Naphtha Reboiler,

Crude preheat exchangers and finally cooled in tempered water exchanger, air

coolers and trim cooler before being routed to storage.

Facility has been provided to supply hot LGO to DHDS.

HEAVY GAS OIL SECTION:

HGO is withdrawn from tray # 15 to the HGO side stripper 03. Light ends in

HGO are stripped using MP steam. Stripped vapors from the side stripper are

routed to tray # 18 of the Atmospheric Column. The bottom product is routed to

preheat exchangers, tempered water exchanger and coolers before being finally

routed to storage on Flow Control to DHDS/DHDT feed tanks through blending

station at OM&S.

Facility has been provided to supply hot HGO to DHDS.

REDUCED CRUDE OIL :

Stripped RCO drawn from the bottom is pumped to the Vacuum heater of

vacuum Distillation Unit on Level control. Single pump will operate during

turndown operation for both AM/BH operations. Starts up lines connect RCO to

VR pump discharge line. Provision to route RCO to VR, and to route RCO

through HVGO PDT & CR circuit and finally through VR product cooler is also

provided to cater to short period of operation of CDU without VDU operation.

Page 31: IOCL Report 2011

31 | P a g e

CIRCULATING REFLUXES

In order to maximize heat recovery and balance tower loadings, heat is removed

by way of circulating reflux (or pump around) from each of the sections. These

pump around are withdrawn and pumped through preheat train for maximum

heat recovery, thus cooling these streams. Duty controllers are provided for

removing the requisite duty. HGO CR is used to reboil the Stabilizer Bottom.

LGO CR is used for generating LP Steam. For turndown operations single

pump will operate for HN/Kero/LGO/HGO CR pumps.

7. NAPHTHA STABLIZER SECTION

Unstabilised Naphtha from Crude Column overhead is pumped to the Naphtha

Stabilizer after preheating with stabilizer bottoms in the Feed/Bottom

exchanger. A bypass has been provided to maintain NSU feed temperature in

the range of 85-90 º C and stabiliser feed temperature about 125- 128 º C. This

column has 40 trays with feed entering on the 21st tray. Necessary heat to reboil

is provided by HGO-CR to the Horizontal Thermosyphon Reboiler on Flow

control (opposite acting). Temperature on tray # 3 regulates HGO CR flow

through the reboiler.

A. LPG:

Stabiliser overhead vapors are condensed in the overhead condenser and then

flow into the reflux drum. The stabilizer works either on partial condensation

mode or total condensation mode. During full condensation is under control

action and under control operation. Any water present with the overheads and

separated in the Reflux drum and part of Hydrocarbons is refluxed. The balance

(LPG) is pumped to Caustic & Amine treating Unit for treatment on LIC/FIC

control by pumps provided with double mechanical seal with methanol as seal

fluid releasing to flare on pressurization.

Page 32: IOCL Report 2011

32 | P a g e

Fuel Gas generated during BH/AM operation is routed to Amine Treatment

Unit (located within CDU/VDU unit) to remove H2S before being routed to the

Fuel gas KO Drum and then to the plant Fuel Gas Distribution Header.

B. STABILIZED NAPHTHA:

Naphtha from stabiliser bottom after exchanging heat with feed Naphtha is

routed to the Naphtha Splitter Unit. In case naphtha splitter is shutdown, the

stabilized naphtha is cooled and sent to rundown through CRU naphtha caustic

wash system.

Provision is also made to divert unsterilized Naphtha to slop header during start

up.

8. NAPHTHA SPLITTER SECTION

In the Naphtha Splitter, stabilized Naphtha is split to C5-65/90º C and 115/165

ºC cuts as overhead and bottom product respectively. This column has four

packing beds with single feed entering above the 2nd

bed.

A) NAPHTHA SPLITTER OVERHEAD PRODUCT :

The overhead vapour is condensed in Air cooler and the condensed product

flows to the reflux drum from where a part is refluxed back to the column. This

overhead product is further cooled to 40º C before being routed to storage via

Caustic Wash. Min. flow bypass has been provided for pumps for turndown

operations. Provision of partial or total C5-90 Naphtha diversion has given to

caustic and water wash (as no need of caustic/water wash of bottom stream).

This is done due to high production of C5-90 Naphtha and inadequate capacity

of the vessel.

Page 33: IOCL Report 2011

33 | P a g e

B) NAPHTHA SPLITTER BOTTOM PRODUCT :

The bottom product is cooled in two air coolers, to 40 º C before being routed to

storage via a separate caustic wash. Two control valves were provided in

parallel to cater to the wide variations in flow between the various operations.

C) NAPHTHA SPLITTER REBOILER (FURNACE) :

The heat for reboiling is provided by a fired heater 03-F-002. The heater can be

fired with FO/FG or combination fuel. Vacuum heater and Naphtha Splitter

fired reboiler share a common Air preheating system. Firing is controlled by

temperature on the 3rd

tray. For better control Coil Outlet Temperature, the

principles of pass balancing is used. This is a vertical cylindrical Heater having

six flows passes. The radiant section is provided with 6” Sch. 40 tubes having

two 8” Sch. 40 tubes as last and second last tubes at the outlet of each pass

while the pass while the connection section is provided with 6” Sch. 40 tubes.

The radiant section tubes are disposed in a vertical arrangement along the walls

of the combustion chamber.

The heater is provided with 12 forced drafts, low NOx combination fuel fired

burners (fuel oil & Refinery fuel gas). These burners are arranged in a circle and

are fired vertically upward from the floor.

The convection section of Naphtha Splitter Reboiler has 8 Nos. of soot blowers,

which are controlled by automatic sequential control panel provided at grade

level.

A combined air preheater system containing one cast Air preheater and one

Glass Air preheater along with two forced draft fans and one induced draft fan

is provided for both Vacuum Heater and Splitter Reboiler.

The turndown factors are as follows: -

For AM, C5-90º C overhead product with max. Reflux, 75/55/65% on

FO/FG/Comb Fuel is possible with vacuum Heater also in operation. With NSU

heater operating in isolation no turndown is possible.

Page 34: IOCL Report 2011

34 | P a g e

For BH, C5-90º C overhead product, 50% turndown is achievable with or

without Vacuum Heater in operation.

D) NAPHTHA CAUSTIC WASH SYSTEM :

The Naphtha Splitter overhead Product & the Bottom product are Caustic

washed to remove H2S, phenols and mercaptans in two separate wash facilities.

Caustic wash consists of mixer settler unit with 12-15% caustic followed by

mixer settler unit of water wash with Service water to remove Caustic traces.

The Naphtha cuts flow separately from the Splitter to the Caustic wash vessels

through mixing valves where it is mixed with 25 vol. % of 12-15 wt %

circulating Caustic on flow control. The thorough mixing given in the mixing

valve transfers the H2S, part of phenols (from stripped sour water through the

desalter), and part of mercaptans from Naphtha cuts to the caustic. The mixture

is given adequate residence time in the vessels for the Hydrocarbon and Caustic

phases to separate. The Hydrocarbon phase leaves at the top of the vessel and

the Caustic phase from the bottom. As the circulation goes on, the strength of

the Caustic goes down and when Caustic is 75% spent the entire Caustic is

drained out.. Shorter batch times may be required with heavier feed mercaptans.

The Hydrocarbon phase is then sent for water wash in vessels to remove

entrained Caustic, water is circulated by pumps for the overhead and bottom

products, and the hydrocarbon is thoroughly mixed with water in the mixing

valve upstream of the wash water vessel. Here again 25-vol. % of service water

is circulated on flow control. The washed Naphtha cuts are routed to storage.

Presently both naphtha splitter streams go to rundown without caustic and water

circulation.

Page 35: IOCL Report 2011

35 | P a g e

9. MTO SPLITTER SECTION

Part of Kero/ATF, upstream of the Product Rundown Control Valve is pumped

to the MTO Splitter after exchanging heat with MTO bottom product (Hy.

Kero). The balance heat required is provided by HVGO CR in the Horizontal

Thermosyphon Reboiler on flow control (opposite acting). Temperature on the

3rd

tray regulates HVGO CR flow through the Reboiler.

The column is designed with 26 trays with feed entering on the 10th tray.

Provision to route the feed to the 8th tray is also provided.

A.MTO SPLITTER OVERHEAD:

The overheads are condensed in tempered water Exchanger and routed to the

Reflux Drum from where a part of the condensed products is refluxed and the

rest pumped to Kero/ATF rundown line after cooling.

B.MTO PRODUCT:

This product is drawn from a total draw tray below tray # 19. A part is refluxed

and the balance cooled, before being rundown to storage. During BH operation

this stream is blended with Kero/ATF rundown line.

C.HEAVY KERO (MTO SPLITTER BOTTOM):

The bottom product is pumped by and finally cooled and routed to storage on

flow control. During AM operation this product is blended with Kero/ATF in

the rundown line.

One provision is made to route Light Kero, MTO and Heavy Kero together to

route to ATF R/D at MEROX ATF R/D.

Page 36: IOCL Report 2011

36 | P a g e

10. VACUUM DISTILLATION UNIT

VACUUM FURNACE:

Hot RCO from the atmospheric column bottom at 355/365º C is mixed with

slop recycle from Vacuum Column, heated and partially vaporized in the 8-pass

Vacuum Furnace and introduced to the flash zone of the Vacuum Column. The

flash zone pressure is 57MM. Velocity Steam (MP) is injected into individual

passes and regulated manually. 3-injection points have been provided on each

pass. This is to maintain required velocities in the heater passes and to prevent

coking at high coil outlet temperatures. The heater can be Fuel Gas, Fuel Oil or

Combination fuel fired.

This is a twin cell cabin heater provided with eight flow passes. The radiant

sections of 5: sch. 40 tubes having 8” Sch. 40 tubes as last tubes and 6” Sch. 40

as second last tube at the outlet of each pass while the convection section is

provided with 5” Sch. 40 tubes. The radiant section tubes are arranged

horizontally along the side walls and arch of each cell of combustion chamber.

The common convection section has horizontal bank of tubes positioned above

the combustion chamber.

The heater consists of 24 forced draft, low NOx combination fuel fired burners

(both fuel oil and refinery fuel gas). Each cell is provided with 12 burners fired

vertically upshot from furnace floor along the centreline of the cell. Convection

section is provided with 16 nos. of soot blowers, which are controlled by

automatic sequential control panel from grade level.

A combined air preheating system has been envisaged for Vacuum heater and

Naphtha Splitter Reboiler Furnace for maximum energy recovery. Turndown

restrictions of furnace are governed by burner and FD fan limitations.

Turndown facilities are as follows: -

Page 37: IOCL Report 2011

37 | P a g e

50% turndown for operation of AM with or without Naphtha Splitter

Reboiler operating.

For BH operation the turndown possible are 80/60/70% for FO/FG/Comb

Fuel with NSU heater also in operation and max. Slop recycle. For Vacuum

Heater operation without NSU heater 60% is possible with max. slop recycle

VACUUM COLUMN:

The vaporised portion entering the flash zone of the column along with stripped

light ends from the column bottoms, rise up in the Vacuum column and is

fractionated into four side stream products in 5 packed sections. The

Hydrocarbon vapours are condensed in the HVGO, LVGO, and Vac. Diesel

sections by circulating refluxes to yield the side draw products. One utility

provision is made at VDU column to evacuate Oxygen by Nitrogen during start-

up of the unit to save the unit start-up time.

The column has been provided for achieving low-pressure drop. Random

packing’s have been provided inside the column with combination bed in the

slop (wash) section. Demister pads have been provided above the wash zone to

prevent asphaltenes carry over and at the top, to minimise carryover of

hydrocarbons to the ejector section.

The stripping section is provided with 10 baffle trays.

The following features have been incorporated to ensure quality of

Hydrocracker Unit feed stock: -

Provision of de-entrainment baffles in the bottom section.

Maintaining reasonable vapour velocities in the flash zone (corresponding to

vapour capacity factor of 0.2-0.3).

Providing adequate vapour of stages in the wash zone.

Providing adequate vapour of stages in the wash zone.

Page 38: IOCL Report 2011

38 | P a g e

Ensuring adequate liquid flows in the wash section.

Providing suitable metallurgy to ensure that iron pick up on account of

corrosion is less than 1PPM.

VACUUM DIESEL:

Vac. Diesel is drawn from the top most packed section along with Circulating

Reflux (CR) and internal Reflux (IR) from Chimney tray below the Bed # 1 .IR

is returned to the LVGO section (bed#2) through spray nozzle distribution. The

CR is returned to the top of the Vac. Diesel packing (Bed#1) after exchanging

heat with crude to maintain overhead temperature of 60-65º C. Higher overhead

temperature would lead to high Hydrocarbon carry over to ejector.

Vac Diesel product exchanges heat with a tempered water exchanger and water

cooler before going to storage on flow control. Slop oil from hot well is also

joining to the vacuum diesel at rundown. Facility has also been provided to

route hot vac. diesel to DHDS feed.

LIGHT VACUUM GAS OIL:

This section comprises of two beds # 2, and # 3, for fractionation and heat

transfer respectively. LVGO is drawn along with CR and IR from Chimney tray

# 2. It is combined with HVGO CR & routed to the HVGO packing bed # 4

through spray nozzle distributor. CR is returned to the top of the bed # 3 after

exchanging heat with Crude.

HEAVY VACUUM GAS OIL:

HVGO is drawn from the Chimney tray # 3 below bed # 4 along with CR and

IR. The IR is returned to the wash zone (Bed#5) through spray distribution

nozzles, on flow control to maintain the required irrigation rate of 0.7-0.3

gpm/ft2 on the wash bed. The CR is used to reboil MTO and kero stripper and

crude preheat train exchangers, before being returned to the top of HVGO

Page 39: IOCL Report 2011

39 | P a g e

section on flow control.HVGO product goes through crude preheat exchangers

and TW exchanger before being routed to storage.

VACUUM SLOP:

This section is a combination bed with demister pad provided above the wash

zone to prevent asphaltenes carry over. Slop distillate is withdrawn from

chimney tray # 4 below bed # 5 along with slop recycle. Slop recycle is routed

to Vacuum Heater. The slop product and quench is routed through crude preheat

exchanger and MP stream generator and tempered water exchanger. A part of

this stream is routed to the slop quench vessel and remaining portion is routed to

final storage. Two controls valves in parallel provided to eater to wide

variations in flow between AM/BH operations. Provision to run down slop

product to FCCU feed tanks or blend with HVGO or VR in run down lines is

also provided. One provision is made to route Vac slop partly or fully to FCC

feed surge drum directly.

VACUUM RESIDUE:

The liquid portion of the feed drops into the bottom section of the tower and is

withdrawn as Vacuum Residue. MP Steam is used for stripping. In view of

steam requirement for BH operation being very low, separate control valves are

provided in parallel for AM and BH operations. The tower bottom temperature

is kept at 350º C to reduce possible cracking during holdup in the tower by

quenching with cooled VR. Quenching is achieved by returning a quench

stream to the tower at a temp of 250º C after heat exchanges with crude in

preheat train on TIC/FIC cascade. Two parallel Control Valves are provided for

proper controllability during BH and AM operation due to wide variations in

flow.

Vacuum Residue is withdrawn and sent for heat exchange with incoming crude

in the crude preheats train. Split range Control Valve TIC-1106 is bypassed

during AM operation. During BH operation it ensures rundown temperature of

Page 40: IOCL Report 2011

40 | P a g e

120º C. VR is used to generate LP Steam, before being cooled in TW

exchangers and finally sent to storage.

One stream after is routed to Vacuum Column as VR quench whose flow is

cascaded with bottom temperature.

VACUUM COLUMN OVERHEAD SYSTEM:

Vacuum is maintained by a 3-stage ejector system with surface condensers.

The Vacuum column overhead vapours are routed to the 1st stage ejectors. The

outlet from the 1st stage goes directly to the 1

st stage inter condenser.

Uncondensed vapours from 1st stage inter condenser are routed to 2

nd stage

ejector. The outlet from the 2nd

stage ejector is routed to the 2nd

stage inter

condenser from where the uncondensed vapours are sent to the 3rd

stage ejector

system. The discharge of the 3rd

stage goes to the after condenser.

The condensed portion from the condensers are routed to the hot well from

where the non condensable are sent to the Crude furnace low pressure burners

or vented to the atmosphere. Condensate from the hot well is pumped to the

sour water stripper unit or to WWTP. Any oil which is carried over along with

the steam condensate is pumped to the Vacuum diesel run down line, after

removing any traces of water in the coalesce. Provision has also been provided

to route the hot well slop oil to DHDS feed tank.

11. LPG AMINE & CAUSTIC WASH SECTION

LPG AMINE SECTION:

Straight run LPG is fed to the 1st tray of 19-C-001.Lean amine ex LPG Merox

(strength @15-25% wt.) is fed through 19-FIC -1101 at the 10th tray. Both the

streams follow counter current operation.

Page 41: IOCL Report 2011

41 | P a g e

Maximum RSH content in LPG to be considered for LPG Caustic wash is 1000

Mole PPM

From the bottom of, Rich Amine goes to Amine Regeneration Unit. LPG goes

out ex top to Caustic wash section. Carried over Amine is drained. Pressure &

Temp. in the column is maintained @ 16.0 Kg/cm2 (g), and 40º C respectively.

LPG CAUSTIC WASH SECTION:

It is carried out in two-stage batch operation. Fresh Caustic (Strength=15% wt)

enters the 2nd

stage drum where as the LPG enters the 1st stage drum. Spent

Caustic is sent to spent Caustic drum. Caustic inventory is replenished by 15%

wt. fresh Caustic. Caustic from second stage drum is pumped to 1st stage drum.

Treated LPG which contains less than 5 PPM (wt) RSH (mercaptans) is passed

through a sand filter to remove entrained caustic.

Under Back Press C/V 19-PV-2101 @ 13.5 Kg/Cm2 (g), LPG is sent to storage

in Horton Spheres.

12. FUEL GAS TREATMENT SECTION:

The unit is having absorber column, which is designed to absorb H2S/CO2 from

sour gases of Crude Distillation unit, Visbreaker unit, Hydrocracker unit and

Catalytic Reformer unit.

PRE FILTRATION:

Off gases from CDU/VBU/OHCU/FCCU/CRU are routed to Sour Gas Filter

Separator under flow measurement. Liquid particles in fuel gases are separated

in Sour Fuel Gas Filter Separator and drained to CBD/Flare periodically

depending upon the liquid level in it. Provision is there to automatically shut

down the draining in case of very low liquid level in filter separator.

Page 42: IOCL Report 2011

42 | P a g e

If the pressure drop in Filter Separator exceeds 0.20 Kg/Cm2 the equipment is

by passed and cartridges in filter separator are changed before taking it again on

line.

A.ABSORPTION:

From the sour gas filter separator the gases are routed to the bottom of the Fuel

Gas Amine absorber 19-C-002. The Fuel Gas Amine absorber is provided with

valve trays and a demister pad above the top tray.

The absorber operates at a top pressure of 4.0 Kg/Cm2 (g) and temperature of

45º C. Lean Amine from ARU is introduced on the top tray under flow control.

Hydrogen sulphide and CO2 from the sour gas gets absorbed into DEA and

because of the chemical reaction the temperature of DEA solution rises to 57º

C. The rich DEA containing H2S/CO2 is pumped to ARU for the regeneration

and reused in Absorber. Differential pressure indicators measure their pressure

drop across trays.

B.POST FILTRATION:

From the top of the Absorber, the sweetened Fuel Gas under Absorber pressure

control is passed to Sweet Fuel Gas Filter separator where any Amine which is

entrained in the gas is trapped and sweet Fuel Gas is routed to Fuel Gas system.

Liquid collected in sweet Fuel Gas Filter separator is periodically drained to

Amine Sump. The operation of sweet Fuel Gas Filter separator is similar to sour

fuel gas filter separator.

Start up Fuel Gas demand of the unit is supplied by LPG vaporiser, which is a

vertical drum with submerged-in Reboiler heated by LP Steam.

13. CHEMICALS REQUIRED

1) AMMONIA

To neutralize the HCL (Hydrochloric Acid) formed due to the decomposition

of mainly calcium and magnesium chloride present in the crude oil at the initial

condensation point of water i.e. at crude & vacuum over head system

2) NEUTRALIZING AMINE

Page 43: IOCL Report 2011

43 | P a g e

3) CORROSION INHIBITOR

Corrosion inhibitors are amine compounds which forms a thin protective layer

in the column over head line to protect the line from corrosion by acidic

compounds present in the column overhead vapours..

4) FILMING AMINE

5) DEMULSIFIER

Demulsifier is used for breaking stable crude water emulsions to ensure proper

desalting and minimum carryover of oil along with brine

6) CAUSTIC SOLUTION (pre- & post desalter)

Caustic (NaOH) is dosed in pre- desalter crude to neutralise free Napthenic

acid present in crude. It is dosed in post- desalter crude to neutralise the acids

formed due to hydrolysis of calcium and magnesium salts in desalter.

7) TSP (Tri-Sodium Phosphate)

It is used to increase the pH from Acidic to Neutral and to protect the steam

generating exchangers/ vessel from corrosion. In CDU/VDU it is used in steam

generating vessel (03-V-23/24/E-54).

Handling of hazardous Chemicals:-

Hazardous chemicals used in AVU are Caustic , Ammonia ,Corrosion

Inhibitor & Demulsifier .These are to be handled carefully since unsafe

operation can lead to personal injury. Always use face shield, safety goggles,

safety gloves & rubber boots during preparation of these chemicals. Avoid

contact with eyes, skin & clothing. Avoid breathing vapors or mist. Never use

cutting torch on or near the container, since vapors may travel away from the

container & explosion may result.

If in case of physical contact with these chemicals, wash the affected portion

with water immediately, remove the person to fresh air & seek medical advice.

Threshold Limit Value for Ammonia & Corrosion Inhibitor is 25 ppm & that of

caustic is 2.5 mg/m3.

Page 44: IOCL Report 2011

44 | P a g e

Filled Ammonia cylinders should always be stored in vertical position & empty

cylinders in horizontal position in separate area. At any point of time more than

5 filled cylinders should not be kept at the site.

14. UTILITIES REQUIRED :

LP Steam Pressure: 3.5 kg/cm2

MP Steam Pressure: 14 kg/cm2

Instrument air : 6.0 kg/cm2

Cooling Water: 4.0 kg/cm2

FG Pressure : 3.0 kg/cm2

FO Pressure: 9.0 kg/cm2

Page 45: IOCL Report 2011

45 | P a g e

SECTION 3

PROJECT

Page 46: IOCL Report 2011

46 | P a g e

INTRODUCTION

A fired heater is a direct-fired heat exchanger that uses the hot gases of

combustion to raise the temperature of a feed flowing through coils of tubes

aligned throughout the heater. Depending on the use, these are also called

furnaces or process heaters. Some heaters simply deliver the feed at a

predetermined temperature to the next stage of the reaction process; others

perform reactions on the feed while it travels through the tubes.

Fired heaters are used throughout hydrocarbon and chemical processing

industries such as refineries, gas plants, petrochemicals, chemicals and

synthetics, olefins, ammonia and fertilizer plants. Most of the unit operations

require one or more fired heaters as start-up heater, fired Reboiler, cracking

furnace, process heater, process heater vaporizer, crude oil heater or reformer

furnace.

Sankey diagram of reheating furnace

Page 47: IOCL Report 2011

47 | P a g e

There are majorly four sections in furnace:

Radiant Section: The radiant tubes, either horizontal or vertical, are located

along the walls in the radiant section of the heater and receive radiant heat

directly from the burners or target wall. The radiant zone with its refractory

lining is the costliest part of the heater and most of the heat is gained there. This

is also called the firebox.

Page 48: IOCL Report 2011

48 | P a g e

Convection Section: The feed charge enters the coil inlet in the convection

section where it is preheated before transferring to the radiant tubes. The

convection section removes heat from the flue gas to preheat the contents of the

tubes and significantly reduces the temperature of the flue gas exiting the stack.

Too much heat picked up in the convection section is a sign of too much draft.

Tube temperature is taken in both convection and radiant sections.

Stack and Breeching: The transition from the convection section to the stack is

called the breeching. By the time the flue gas exits the stack, most of the heat

should be recovered and the temperature is much less. From a measurement

point of view, this location places fewer demands on the analyzer but is much

less desirable for the ability to control the process. Measurement of stack

emissions for compliance purposes is normally made here.

Shield Section: Just below the convection section is the shield (or shocktube)

section, containing rows of tubing which shield the convection tubes from the

direct radiant heat. Several important measurements are normally made just

below the shield section. The bridge wall or break wall temperature is the

temperature of the flue gas after the radiant heat is removed by the radiant tubes

and before it hits the convection section.

CALCALUTION:

DATA REQUIRED FOR FURNACE EFFICIENCY

BASED ON RAD.LOSS OF 1.0

LHV OF FG 11200.00

LHV OF FUEL OIL 9998.00

AMBIENT TEMP 14.00

HGU-I PSA OFF GAS 1291.00

HGU-II PSA OFF GAS 1156.00

NAPTHA 10531.00

C/H WT FO 7.00

C/H WT FG 4.00

HUMIDITY OF AIR KG/KG 0.022

Page 49: IOCL Report 2011

49 | P a g e

For CDU furnace, THE DESIGN EFFICIENCY IS 91%.

Practical CDU furnace efficiency is calculated by following method:-

Fuel gas(FG) used = 35 MT/D

Fuel oil(FO) used = 112 MT/D

Heat released by fuel gas =

= 11200 x 35 / 24 x 1000

= 16.33 MMKCAL/HR

Heat released by fuel oil =

= 9998 x 112 / 24 x 1000

= 46.65 MMKCAL/HR

TOTAL HEAT RELEASED =Heat released by fuel gas + Heat

released by fuel oil

= 62.98 MMKCAL/HR

O2 content in STACK = 4.0

CO2 content in STACK = 10.64

STACK TEMPERATURE = 188 ° C

Atomizing steam= 1.86 T/HR

Atomizing steam = 1.86 x 24 = 44.64 T/HR

Page 50: IOCL Report 2011

50 | P a g e

Theoretical air for fuel oil =

= (7 + 3) x 1000/ (7 +1) x 12 x 0.21

= 496 KGMOLES

Theoretical air for fuel gas =

= (4+ 3) x 1000/ (4 +1) x 12 x 0.21

= 556 KGMOLES

Total theoretical air required

=

= 112 x 496 + 35 x 556

= 75012 KGMOLES

Total CO2 =

= ((7) x 112 / (7) +1) + (4) x 35 / (4) +1)) x 1000/12

= 10500 KGMOLES

Page 51: IOCL Report 2011

51 | P a g e

Total H2O =

= (112 / 7 +1) + 35 / 4 +1) x 1000/4

= 5250 KGMOLES

Total theoretical N2 =

= 75012x0.79

= 59259.48 KGMOLES

Flue gas O2 =

= 4 x (10500 + 5250 + 59259.8)/ (100-4/0.21)

= 3706.35 KGMOLES

Actual air required =

= 75012 + 3706.35/0.21

= 92661.28 KGMOLES

Air average mol. Wt = 29

Total air (normal condition) = 92661.28 x 22.4/ 24

= 86483.87 NM3/HR

Total air (given condition) at 35 ° C = 86483 x (273+35)/273

= 97571.54 M3/HR

Page 52: IOCL Report 2011

52 | P a g e

% EXCESS AIR = TOTAL AIR - TOTAL THEO. AIR REQUIRED x 100

TOTAL THEO. AIR REQUIRED

= (92661.28 – 75012) x 100 / 75012

= 23.53 %

H2O moles due to humidity =

= 0.022 x 92661.28 x29 /18

= 3284.32 KGMOLES

Total flue gas =

= 10500+5250+59259.48+3706.25/0.21+44.64 x 1000/18

= 98423.085 KGMOLES

Flue gas average mol. Wt =

------------------------------------------------------------------------------------------------

(Total Flue gas)

= 29

Page 53: IOCL Report 2011

53 | P a g e

Total flue gas (normal condition) = total flue gas x 22.4 / 24

= 91861.5 NM3/HR

Total flue gas (given condition) at 188 ° C = 91861.5 x (273+188)/273

= 155121.43 M3/HR

Flue gas heat loss = m *Cp * ΔT

Where m= total flue gas

=

= 98423.085 x 29/1000 + 1000 x 0.245 x (188-14) x 10^-6

= 5.069 MMKCAL/HR

% HEAT LOSS TO FLUE GAS =

= 5.069/62.98 x100

= 8.048%

Setting loss =

= 62.98 x 1 / 100

= .63 MMKCAL/HR

% Setting heat loss = 4%

Page 54: IOCL Report 2011

54 | P a g e

Actual furnace efficiency = 100 - % setting loss – % heat loss flue gas

= 100 – 8.048 - 4

= 87.95 %

RESULT:

For CDU furnace, THE DESIGN EFFICIENCY IS 91%.

ACTUAL EFFICIENCY IS 87.95 %

Page 55: IOCL Report 2011

55 | P a g e

SECTION 4

REFRENCES AND BIBLOGRAPHY

Page 56: IOCL Report 2011

56 | P a g e

REFERNCES:

1. www.google.com

2. www.wikipedia.com

3. www.iocl.co.in

4. Training AVU manual

5. Perry’s handbook of Chemical Engineering

6. www.cleanboiler.org

7. Industrial Furnace, Volume 1 and Volume 2, John Wiley &

Sons – Trinks

8. Improving furnace efficiency, Energy Management Journal