17
Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 1 Effects of the Compressed Schedule INSTALLATION OF LSS (Experimental insertions)

INSTALLATION OF LSS (Experimental insertions)

  • Upload
    arien

  • View
    29

  • Download
    0

Embed Size (px)

DESCRIPTION

INSTALLATION OF LSS (Experimental insertions). OUTLINE. Critical case: sector 7-8 LSS before installation of the beam line components Provisional installation sequence of LSS8R (8-1) Experimental insertions specificities Summary. LSS8L. CRITICAL CASE: SECTOR 7-8. - PowerPoint PPT Presentation

Citation preview

Page 1: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 1

Effects of the Compressed Schedule

INSTALLATION OF LSS(Experimental insertions)

Page 2: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 2

Effects of the Compressed Schedule

OUTLINE

• Critical case: sector 7-8• LSS before installation of the beam line

components• Provisional installation sequence of LSS8R (8-1)• Experimental insertions specificities• Summary

Page 3: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 3

Effects of the Compressed Schedule

CRITICAL CASE: SECTOR 7-8

LSS8L

• Installation by CERN of the QRL in sector 7-8 gives the opportunity to:– Start with QRL sub-sector A and B (~600m left of point 8

(LSS8L)) in March 2005 and then, install magnets in parallel with the remaining of the QRL

– Start QRL cold testing in June 2005– Start installing magnets (LSS8L) in parallel with the

remaining of the QRL in August 2005– LSS8L cool down & power tests from October 2005 to

March 2006– Gather maximum experience on the field in 2005 with a

view to propose an optimized and reliable scenario for the other sectors

Page 4: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 4

Effects of the Compressed Schedule

CRITICAL CASE: SECTOR 7-8 (cont.)

• The following main diverse material have to be available for installation in Summer 2005:– Components:

• Support jacks (supplied by CAT-India) – Motorised jacks for Inner Triplets: CAT-India jacks modified

• Resistive magnets: MBXW and MBXWS• Inner Triplet (Q1-Q2-Q3)• DFBXG• D1-D2• Collimator, TCL• Q4, Q5• DFBMA/C

Page 5: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 5

Effects of the Compressed Schedule

CRITICAL CASE: SECTOR 7-8 (cont.)

– Installation tooling such as:• Spreader beams for all magnets• Transportation system for DFBX

– Vacuum equipment:• Cold-warm transitions (VAX, VAB,…)• Vacuum chambers• Supports• Beam position monitors (BPTX, BPMWB, BPMSW, BPMSX…)• Instrumentation

– Others

Page 6: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 6

Effects of the Compressed Schedule

No-coactivity during cool-down!

Powering test possible co-activity with

vacuum (bake-out and NEG activation)

No-coactivity during power

converters short circuit tests!

Page 7: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 7

Effects of the Compressed Schedule

LSS BEFORE INSTALLATION OF THE BEAM LINE COMPONENTS

• General requirements:– General services installed– Tunnel floor prepared for support jacks installation– QRL installed– DC cabling installed– Control and signal cabling installed– HLS (Hydrostatic Level System) and WPS (Wire Positioning

System) preinstalled (where applicable)

• And…where required:– Installation of transfer rails for Q1-Q2 installation (RB14,

RB16, RB26, R542, R561, RB86)– Installation of shielding plugs (RPX24, RB26, RB84, RB86)

Page 8: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 8

Effects of the Compressed Schedule

PROVISIONAL INSTALLATION SEQUENCE OF LSS8R (8-1)

LSS8R

• Starting point:– QRL installation finished by June 2005– QRL commissioning in August and September 2005

• Installation sequence of LSS8R:– Shielding in RB86– Support jacks– Beam line elements installation:

• Resistive magnet (MBXWS)• Inner Triplet and D1• DFBXH• D2, Q4, Q5• TCDD, TDI, MKI, MSI

Page 9: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 9

Effects of the Compressed Schedule

Oct-Dec 2005

Page 10: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 10

Effects of the Compressed Schedule

PROVISIONAL INSTALLATION SEQUENCE OF LSS8R (8-1) (cont.)

• Alignment (Q1 Q5)• Magnets interconnection and closure (DFBX included)• DFBMA/C: transport and installation• Vacuum:

– Install and connect components (Q1 Q5)– Install and connect standalone sectors (D2/Q4, Q5)– Install and connect components (warm sectors)– Reception, bake-out and NEG activation (warm sectors)

• Power cables connections, signal cables, cooling and control components

• Installation of survey equipment: HLS and WPS

Page 11: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 11

Effects of the Compressed Schedule

Nov 2005-Nov 2006

Page 12: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 12

Effects of the Compressed Schedule

EXPERIMENTAL INSERTIONS SPECIFICITIES: IR8

• RB84: Starting point: steel shielding installed– Standard installation of Inner Triplet

LSS transport vehicle and transfer tables

F. DELSAUX 27/04/2004

RB 84 Shielding

F. DELSAUX 27/04/2004

RB86 Shielding

QRL

MBXWS

RB 86 (28 April 2004)

• RB86: Starting point: main part of shielding installed– Q1 installation: transfer with rails and motorised

bogies

Page 13: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 13

Effects of the Compressed Schedule

EXPERIMENTAL INSERTIONS SPECIFICITIES: IR1

• Installation of steel-welded structure for continuing the rails and personnel access inside the ATLAS forward shielding tube TX1ST.

• Installation of 2xQ1: transfer with rails and motorised bogies

HLS and WPS preinstalled

UX 15

Holes for Q1 motorised Jacks

RB14 Shielding

Page 14: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 14

Effects of the Compressed Schedule

EXPERIMENTAL INSERTIONS SPECIFICITIES: IR2

RPX24

• RB24: Starting point: RPX24 supporting structure and shielding installed

PX24: used to lower down special magnets!

Page 15: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 15

Effects of the Compressed Schedule

EXPERIMENTAL INSERTIONS SPECIFICITIES: IR2

• RB26:

Starting point: main part of shielding installed

• Installation of Q1 and Q2: transfer with rails and motorised bogies

Page 16: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 16

Effects of the Compressed Schedule

EXPERIMENTAL INSERTIONS SPECIFICITIES: IR5

HLS and WPS preinstalled

UPS galleries for alignment purposes

Point 5: Q1 located in UXC55 and R542/R561

CMS Shielding opening approx.

4x2x2(m)

• Installation of 2xQ1 and 2xQ2: transfer with rails and motorised bogies

Page 17: INSTALLATION OF LSS (Experimental insertions)

Chamonix XIV January 2005 S.Bartolomé - EDMS:547511 17

Effects of the Compressed Schedule

SUMMARY

• Installation dates:– LSS8L August 2005– LSS8R October 2005– LSS1L October 2005– LSS5L December 2005– LSS5R April 2006– LSS2L July 2006– LSS1R August 2006– LSS2R September 2006

• Each LSS is a particular case due to the specific configuration of the area and safety constraints such as: restriction on co-activities, on transports, on access during pressure tests, cold down and electrical tests.

• A Schedule Change Request (SCR) will be required for each LSS.