41
Installation & Commissioning Report Mukalla Iron & Steel Plant 1 © Wärtsilä 23 January 2011 Place: Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power Plants Mukalla, Yemen. Engine Model : Wärtsilä18V32. Engine Serial Number: PAAE150665, PAAE150666, PAAE150667, PAAE150668, PAAE150669, PAAE150670, PAAE167202, PAAE202656’PAAE202657 & PAAE202658.

Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

  • Upload
    others

  • View
    61

  • Download
    4

Embed Size (px)

Citation preview

Page 1: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Installation & Commissioning Report

Mukalla Iron & Steel Plant

1 © Wärtsilä 23 January 2011

Place: Hadramout Investment Power Company (HIPC).Al-Harshiyat Power Station75 MW Power PlantsMukalla,Yemen.

Engine Model : Wärtsilä18V32.Engine Serial Number: PAAE150665, PAAE150666, PAAE1 50667, PAAE150668, PAAE150669,

PAAE150670, PAAE167202, PAAE202656’PAAE202657 & PAA E202658.

Page 2: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Contents

■ General Information

■ Shipment

■ Technical

■ Installation

● Civil

● Mechanical

2 © Wärtsilä 23 January 2011

● Electrical

■ Pre-commissioning

■ Commissioning

Page 3: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

General Information

Owner :Hadramout Investment Power Company (HIPC).Al-Harshiyat Power Station75 MW Power PlantsMukalla,Yemen.

Suppliers : Wärtsilä Finland Oy.Tarhaajantie 2, Fin-65101 Vaasa,Finland.

Engine Model : 10XWärtsilä18V32Engine Serial Number: PAAE150665, PAAE150666, PAAE150667, PAAE150668, PAAE150669,

PAAE150670, PAAE167202, PAAE202656, PAAE202657 & PAAE202658.

3 © Wärtsilä 23 January 2011

PAAE150670, PAAE167202, PAAE202656, PAAE202657 & PAAE202658.Alternator Type : AMG 1120 MR08 DSEAlternator Serial No. : 4602059, 4602060, 4602061, 4602062, 4602063,

4602064, 4605928, 4609026, 4609027 & 4609028.

General Information about Mukalla sites:• Site Location: Al-Harshiyat Power station, Mukalla, Yemen.• Type of Power Plant: Light Fuel Oil (LFO) and Heavy Fuel Oil (HFO) Power Plant.• Capacity of Plant: 75 MW Power Plants.• Owner of the Plant: Hadramout Investment Power Company Ltd (HIPC).• Site Altitude above Main sea level: 220m • Grid Connection: 33/11 kV.• Grid Frequency: 50 Hz.• Rural country side, Sand stone, Hill, Rock and Mount area (Dusty area).

Page 4: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

First Shipment:

• Ship arrived at Mukalla sea port on 28.10.09

• Unloading started on 29.10.09

• Unloading completed on 30.10.09.

Second Shipment (Indian Portion):

• Ship arrived at Mukalla sea port on 29.11.2009

• Material arrived at site on 13.12.2009.

Main Shipment:

• Ship arrived at Mukalla sea port on 28.12.2009

Shipment Shipment

4 © Wärtsilä 23 January 2011

• Unloading started on 29.12.2009.

• Unloading completed on 01.01.2010.

Third Shipment (Extended part):

• Vessel arrived at Mukalla sea port on 23.05.2010.

• Material arrived at site on 25.05.2010.

Page 5: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

DG unloaded from vessel to Tailor

Shipment

5 © Wärtsilä 23 January 2011

DG unloaded from vessel to Tailor

Page 6: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Shipment

DG unloaded from Tailor to Foundation

6 © Wärtsilä 23 January 2011

Container unloaded from vessel to Tailor

Page 7: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Technical

• Mechanical Basic Design received on 08.11.2009.• Electrical basic design received on 08.11.2009.• Mechanical detailed design received on 10.02.2010• Electrical detailed design received on 10.02.2010.

Installation

Civil

7 © Wärtsilä 23 January 2011

• Civil is not Wartsila scope but before placing the DG sets and others equipment to ensure that the foundation leveling, center line and 0-line are marked as per Wartsila drawing.

• Checked all DG sets foundation leveling, center line and 0-line, checked Engine auxiliary module foundation, Compact booster unit foundation.

• Checked Exhaust gas Boiler, Exhaust gas silencer, Auxiliary boiler container, Charge air filter , Cooling water radiator , Station transformer and Black start container foundation.

• Fuel treatment house (Feeder unit, HFO Separator & Oily water treatment unit foundation), Day tanks foundation, Fire water tank, Treated water tank, and Water treatment unit container foundation checked.

• HFO & LFO Storage tank, Unloading station and transfer pump units foundation checked.

.

Page 8: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Power House concreting

Foundation

8 © Wärtsilä 23 January 2011

DG –sets Foundation

Page 9: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Foundation

Stack Foundation

9 © Wärtsilä 23 January 2011

Tank Foundation

Page 10: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Mechanical

• DG-sets placed on foundation and checked spring location, centre line and 0-line• Engine auxiliary module alignment along with Engine and fixed on foundation with anchor bolts • Compact booster unit alignment with Engine auxiliary module and inter connect the flanges.• Exhaust gas module Installed respect to the DG sets.

DG-sets Installation

10 © Wartsila 23 January 2011

Compact Booster Unit

Engine Auxiliary Module

DG sets

Page 11: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Compact Booster UnitEngine Auxiliary ModuleDG sets

DG-sets, EAM, CBU & EGM Installation

11 © Wärtsilä 23 January 2011

DG sets on Foundation

Page 12: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

DG-sets, EAM, CBU & EGM Installation

EGM Placed on Foundation

12 © Wärtsilä 23 January 2011

Fuel system:

● HFO and LFO unloading pump unit are placed on foundation.

● HFO and LFO Feeder unit has been placed on foundation.

● LFO transfer pump unit has been placed on foundation.

● HFO and LFO Piping (Inside Power house and outside Power house) fabrication, welding, pressure test, pickling and flushing checked with customer representative.

● HFO and LFO Storage tank Fabrication, welding and pressure test checked with customer representative.

● HFO day tank, buffer tank and LFO day tank fabrication, welding and pressure test checked with customer representative.

Page 13: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Fuel oil system

HFO & LFO transfer pump unit HFO & LFO Feeder Unit

HFO & LFO Storage tank, & Unloading pump units

13 © Wärtsilä 23 January 2011

HFO & LFO transfer pump unit HFO & LFO Feeder Unit

Page 14: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Mechanical Installation

Cooling water system:• Maintenance water tank placed on foundation.• Radiators has been placed on foundation (with legs) including railings.• Cooling water piping (Inside & outside power house) fabrication and welding checked.• Cooling water piping pressure test and flushing checked.

Cooling water Radiator Cooling water Piping

14 © Wärtsilä 23 January 201114 © Wärtsilä 23 January 2011

Page 15: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Mechanical

Compressed air system:

• Starting air Compressor unit and Starting air vessel has been placed on foundation.• Instrument air compressor unit and control air bottle has been placed on foundation.• Starting air and Control air piping fabrication, welding and pressure test checked.

15 © Wärtsilä 23 January 2011

Page 16: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Lubricating oil system:• Lubricating oil unloading pump unit has been placed on foundation.• Lubricating oil transfer pump unit (Stationary) have been placed on foundation.• LO piping (Inside and outside power house) fabrication , welding, pickling & flushing checked.• LO storage tank (Fresh & Used) and service tank fabrication, welding, and pressure test checked.

Mechanical

LO Unloading pump unitLO Transfer pump unit

16 © Wärtsilä 23 January 2011

Page 17: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Mechanical

Compressed air system:• Starting air Compressor unit and Starting air vessel has been placed on foundation.• Instrument air compressor unit and control air bottle has been placed on foundation.• Starting air and Control air piping fabrication, welding and pressure test checked.

Starting & Instrument Air compressor unit Starting Air Vessel

17 © Wärtsilä 23 January 2011

Instrument air system Commissioning: Checked all suction/delivery valve in the compressor, air vessel & Dryer. Checked oil level in compressor, power supply in the local panel, checked vessel & dryer drainage solenoid valve functionality, start compressor and fill-up the vessel and checked any leakage. Supply the air in the main distributions line and checked any leakage.

Page 18: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Heat recovery system:• All exhaust gas boiler has been placed on foundation.• Auxiliary boiler container are placed in foundation with feed water tank.• Steam header has been placed on foundation and piping works completed.• Boiler washing water pump and tank has been placed on foundation & piping completed.• Steam and Condensate piping fabrication, welding, pressure test and insulation completed.

Mechanical

18 © Wärtsilä 23 January 2011

Exhaust gas Boiler (EGB)

Page 19: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Oily water system:Oily water treatment unit has been placed on foundation.Oily water transfer pump unit and feed pump unit has been placed on foundation.Oily water piping fabrication, welding and pressure test completed.Oily water buffer tank fabrication, welding sand blasting, pressure test & painting completed.Sludge loading pump has been placed on foundation and piping works completed.Sludge tank fabrication, welding, sand blasting, pressure test & painting completed.

Mechanical

Oily water treatment unit

19 © Wärtsilä 23 January 2011

Oily water transfer pump

Page 20: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Instrument air system Commissioning: Checked all suction/delivery valve in the compressor, air vessel & Dryer. Checked oil level in compressor, power supply in the local panel, checked vessel & dryer drainage solenoid valve functionality, start compressor and fill-up the vessel and checked any leakage. Supply the air in the main distributions line and checked any leakage.

Auxiliary system Commissioning

Instrument Air compressor units

20 © Wärtsilä 23 January 2011

Page 21: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Auxiliary system Commissioning

Water supply system commissioning:Raw Filling in raw water tank, Control air line blow throwing, Suction & delivery valve checking in raw water booster unit. Multi layer & water softener tank checked, Nacl filling in Nacl Solution tank, Nalco PC- 191 filling in chemical dosing tank. Power supply in the panel board. Checking motor rotation in raw water Booster, treated water booster, RO pump & chemical dosing pump. Start the system and checked as per manufacturer instruction (Pump suction /delivery pressure, air pressure etc). Flow meter and level switch adjusted and successfully commissioning the water treatment system & producing treated water, test the water and found pH value is satisfactory. System run continuously and producing treated water as per boiler & DG sets requirement .

Water Treatment unit

21 © Wärtsilä 23 January 2011

Page 22: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Auxiliary system Commissioning

Fuel (LFO) oil system: LFO unloading pump and transfer pump suction and delivery valve checked and kept open position, power supply on in the local panel board, checked motor/pump rotation after that pump started and unloading LFO from tank lorry to LFO storage tank (Flow meter reading checked with customer representative) and same procedure LFO transfer from Storage tank to LFO day tank.

LFO feeder unit : LFO day tank to Feeder unit and feeder unit to auxiliary boiler day tank and power pouse all valve checked and kept open position. Control air checked, power supply to feeder unit local panel board, checking Motor/pump rotation after that LFO Feeder started and shifting LFO day tank to Auxiliary boiler day tank and also checked all LFO pipe line any leakage.

Fuel (HFO) oil system: HFO unloading pump and transfer pump suction and delivery valve checked and kept open position, power supply on in the local panel board, checked motor/pump rotation after that pump started and unloading HFO from tank lorry to HFO storage tank (Flow meter reading checked with customer representative) and same procedure HFO transfer from Storage tank to HFO buffer tank. Fuel oil 3-way valve checking and found actuator solenoid valve defective and replaced solenoid valve from extension part. Pre-heating the HFO buffer tank.

22 © Wärtsilä 23 January 201122 © Wärtsilä 23 January 2011

extension part. Pre-heating the HFO buffer tank.

Separator Commissioning: Checked HFO buffer tank to separator all suction/delivery valve and kept open position, checked instrument air, steam and condensate line and treated water line etc.all HFO separator started and completed commissioning (Separator commission by Westfalia commissioning engineer) .

HFO feeder unit:HFO day tank to Feeder unit and power house all valve checked and kept open position. Control air checked, power supply to feeder unit local board, checking Motor/pump rotation, Auto and manual filter checked, Viscometer function checked after that HFO Feeder started and checked main HFO pipe up to CBU.

Page 23: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Auxiliary system Commissioning

HFO & LFO Feeder unit

23 © Wärtsilä 23 January 201123 © Wärtsilä 23 January 201123 © Wärtsilä 23 January 2011

HFO Separators units

Page 24: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Cooling water system:Filling treated water with cooling additives in Maintenance water tank . checked maintenance water transfer pump rotation, mixing water with additives, maintenance water tank to system suction & delivery valve kept open position, after that cooling water filling in the system and checked leakage, water filling radiator also. Radiator fan functionality checking. Expansion vessel checked.

Auxiliary system Commissioning

Cooling water Radiator

24 © Wärtsilä 23 January 201124 © Wärtsilä 23 January 2011

Page 25: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Compressed air system:Checked all pipe line up to start air vessel & engine auxiliary modules, checked all suction & delivery valves in compressor & air vessel, oil filling in compressor as per manufacture instruction. Power supply in local panel board, compressor rotation checked. Start compressor fill-up the vessel and checked any leakage in compressor to vessel. Supply the air in the main distributions line and checked any leakage.

Starting compressor unit Starting Air Vessel

Auxiliary system Commissioning

25 © Wärtsilä 23 January 2011

Page 26: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Charge air & Exhaust gas system:Charge air duct and charge air silencer inspect, Charge air filter (dry pack) cleaned, oil filling in charge air filter.Exhaust gas ducting & silencer inspect, water lock inspect.

Auxiliary system Commissioning

26 © Wärtsilä 23 January 2011

Page 27: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Mechanical Auxiliary system

Auxiliary Boiler Container

Black start container

Exhaust gas Boiler

27 © Wärtsilä 23 January 2011

Steam HeaderOily water treatment unit

Page 28: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Electrical

Wartsila Scope for Electrical system:

1. LV system: Complete2. MV system: Complete3. DC system: Complete4. Control and monitoring system: Complete

HV system was in scope of Customer. And it was supplied by M/S MN Dashtur, India, Ltd.

Installation and erection with commissioning support was covered by M/S HIDELECO

Evaluation

Delivery and Material Handling:

� Delivery Time from Wärtsilä Satisfactory

� HV system including Transformer delivery was delayed customer scope

28 © Wärtsilä 23 January 2011

� HV system including Transformer delivery was delayed customer scope

� Custom Clearance – Moderate It was in customer scope.

� Transport to Site- Quite Satisfactory

� Storage/ Store Keeping Quite Satisfactory

� Material Handling in siteQuite Satisfactory and in safe way

Erection

� Contractor used proper tools

� Contractor followed wartsila’s guide line and safety instruction

� Wartsila Supervisory support was well behind to the contractor

� Erection failure was minor- in MV panel some analog meters and selector switch were damaged

Page 29: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Electrical - continued

� Contractor’s skill and competency were well satisfactory� Co-ordination among electrical, mechanical and civil was Moderate

Erection Difficulties and suggestion:

Cable Ladder Layout- In some places, cable ladder routing was so difficult due to less space. Specially in the Auxiliary Module area.

MV panel Doors we found couple of MV cubicle doors are misaligned. And lock was not properly operable. Specially the breaker doors. Rectified at site.

Less space in Switchgear It was a compact switchgear room including LV, MV and MV (33KV). The space was not sufficient. For better cooling, air flow path and safely operation, a more specious room would be better.

Frequency Converter of Feeder Unit

29 © Wärtsilä 23 January 2011

Three frequency converters for Fuel feeder unit were located in Fuel treatment unit. Due to

* heavy high temperature * humidity * Possibility of more dirt in fuel treatment roomIt would be better to put those frequency converter in a separate cubicle with force ventilation facility. That cubicle would be placed along with BFA902 (LV panel at Fuel treatment house).

Engine hall ventilation unit (Generator side)Frequency converters were inside the ventilation unit.and there was no maintenance plat form/ ladder around the ventilation unit. It was difficult to work with the Frequency converters.

FC could be relocated in the engine hall just bellow the louver of ventilation unit/ near by the Neutral cubicle.

BJA panelSensor/actuator end connections were open, at site they were connected. It should be connected from factory. We have reported this issue in a separate report during installation.

Page 30: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Electrical - continued

Pre-Commissioning

� Pre-commissioning was performed according to the co-ordination plan with mechanical system requirement and completion

� We got sufficient man power with satisfactory skill from contractor. Contractor was quite helpful and knowledgeable.

� The over all pre-commissioning was :

- Well coordinated and planned- Less error found for connection- quick rectification support whenever modification advised or required

Pre-commissioning Difficulties and Suggestion

LV Power This was quite enough cited issue ever for this project. Delay of 33KV System initiated the difficulty. We had to use our black start unit for pre-commissioning support though customer arranged small

30 © Wärtsilä 23 January 2011

We had to use our black start unit for pre-commissioning support though customer arranged small generators. But it was very risky when multiple generators are connected to the LV system and frequent change over required.

Page 31: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Electrical- Continued

Pre-Commissioning Sequence-

31 © Wärtsilä 23 January 2011

Page 32: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power
Page 33: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Electrical - continued

� Engine governed by UNIC-C1. the followings are to note for UNIC-C1:

a. The hardware configuration was not exact the supplied installation drawings. The Speed control signal from AVR during Sync was connected to different port

b. The Base software for UNIC-C1 had very fast PID parameters c. The Speed sensors ( Flywheel) needed to adjust

� AVR synchronization

Very stable synchronization obtained

� Soft-start

Very stable soft start performed

33 © Wärtsilä 23 January 2011

Page 34: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Electrical- Continued

Some pictures

34 © Wärtsilä 23 January 2011

Page 35: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Electrical- Continued

35 © Wärtsilä 23 January 2011

Page 36: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Electrical- Continued

Overall Evaluation

Wartsila Scope:

Erection Contractor:

36 © Wärtsilä 23 January 2011

Customer’s Scope

Page 37: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Engine hall with DG-sets

37 © Wärtsilä 23 January 201137 © Wärtsilä 23 January 2011

Page 38: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Power House

38 © Wärtsilä 23 January 2011

Page 39: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Power House

39 © Wärtsilä 23 January 2011

Page 40: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Control Room

40 © Wärtsilä 23 January 2011

Page 41: Installation & Commissioning Report · Pre-commissioning Commissioning. General Information Owner :Hadramout Investment Power Company (HIPC). Al-Harshiyat Power Station 75 MW Power

Electrical Switchgear

41 © Wärtsilä 23 January 2011