42
Transformer Monitoring System TEC System Inocencio Solteiro, PPTR/AT 05.06.2013

Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

Transformer Monitoring System TEC System

Inocencio Solteiro, PPTR/AT 05.06.2013

Page 2: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB

2011 | Slide 2

Voltage, Current,

Gases and Bushing,

etc,

On load Tap Changer,

Oil and Ambient Temperature,

Communication

system

Overview Online Transformer Monitoring

“ABB” monitoring system

(converts raw data into useful

informations)

Page 3: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB

2011 | Slide 3

Overview Online Transformer Monitoring

Control Room

Page 4: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

Short Introduction of the TEC System

Fiber optic

cable

TCP/IP Ethernet

network cable

USB Serial

adapter

Converter box

TC 190

TEC

Laptop during

installation

Remote computer

RS232

Serial cable

Cables to/from

the transformer

Optional

TEC Server,

Modem, etc

© ABB 02/03/2012 | Slide 4

Page 5: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

Frequent Questions by End User

Why Transformer monitoring ?

What are the cost benefits ?

When should I install ?

What is the Minimum Size of Transformer to install ?

What are the sensors that I should install ?

What are the functions that I should install ?

Configuration / Communication in the network ?

How many days take to install in the old Transformer ?

Page 6: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 6

Benefits of the Monitoring System

Early identification of a fault evolution.

Avoid costly unplanned outages.

Avoid catastrophic failures.

Extended life time of the Transformer

Reduces maintenance costs of the Transformer

Reduced risk of the transformer failure and grid blackout

Increase the operational availability of the Transformer

Reduces maintenance costs of the On load Tap changers

Reduces costs of insurance policy with the insurance company

Continually assess the operational status of the transformer.

Enhanced overload capability through intelligent cooling control

Assist in maintenance planning.

Store properly a lot of data

Page 7: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

Economic Benefits - CIGRE

Page 8: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

Place of Development & Manufacturing

© ABB Group June 5, 2013 | Slide 8

TEC Ludvika Factory - Sweden

Over 100 year of Transformer Experience.

100% Developed and Manufactured by ABB.

04 year of Development

02 year on Laboratory

02 year on Site

Fingerprint Concept.

On-line Monitoring Data in real time.

Friendly device for User

Page 9: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 9

TEC Smart (since 2011)

TEC (since 2003)

TEC – Transformer Electronic Control

Page 10: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

TEC – Transformer Electronic Control

Page 11: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 11

Source: PPTR/AT

Global Reference List 2003 - 2012

SAM

252 TEC

SAS

74 TEC

NAS

161 TEC

NAM

84 TEC

NEU

112 TEC CEU

39 TEC

IMA

43 TEC

MED

204 TEC

Page 12: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

TEC Reference List - Chile

Page 13: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 13

TEC

Installation Version in the Transformer Tank

Basic Integrate

TEC Smart

Basic

Integrate

Page 14: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

New Transformers

Old Transformers

Non-ABB Transformers

TEC Cabinet Installation

Page 15: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

It is based on a microprocessor.

Modular and expandable system.

Do not need the PC for storage of data.

Communication of data over fiber optics.

Easy to install and mount.

Based on approved technology.

Bus communication with sensors.

Reduced cabling on transformer

Electronic components – Military grade

Protocol board: IEC 61850 IEC 60870 DNP 3 Others

TEC Smart

TEC

© ABB Group June 5, 2013 | Slide 15

TEC – Transformer Electronic Control

Page 16: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group June 5, 2013 | Slide 16

Certificate Tests

Page 17: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

No special

computer is

needed

Dual

language

support

© ABB Group June 5, 2013 | Slide 17

User Friendly Interface

Page 18: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

Display Interface

Important information available at the transformer in real-time

• Press to see

next value

• Press and hold

(> 3 sec) to see

active events

ALARM

WARNING

NORMAL

Page 19: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 19

RI2 losses high voltage winding kW 89.5 32.2

RI2 losses low voltage winding kW 131.0 47.2

RI2 losses tertiary winding kW N/A N/A

Eddy losses in high voltage winding kW 8.3 3.0

Eddy losses in low voltage winding kW 9.55 3.4

Eddy losses in tertiary winding kW N/A N/A

Calculated values for type test AF AN (When applicable)

Top oil temperature rise °C 56.5 58

Average oil temperature rise °C 41.5 49

No load loss at test kW 124 124

Load losses at test - 764 275

Tap-changer position - -2X2.5%(2) -2X2.5%(2)

Current high voltage winding A 510.5 306.3

Current low voltage winding A 1600 960

Current tertiary voltage winding A N/A N/A

Hot-spot temperature high volt. wind. °C 74.3 67.5

Hot-spot temperature low volt. wind. °C 75.3 67.5

Hot-spot temperature tertiary volt. wind. °C N/A N/A

Temperature gradient high volt. wind. °C 17.8 (3) 9.5(3)

Temperature gradient low volt. wind. °C 18.8(3) 9.5(3)

Temperature gradient tertiary volt. wind. °C N/A N/A

Mass parameters

Cu-Mass of high voltage winding kg

Cu-Mass of low voltage winding kg

Cu-Mass of tertiary winding kg

Free oil kg

Oil in insulation kg

Core steel mass kg

Other steel mass (tank, yoke plate, etc.) kg

Paper mass kg

Type test values AF AN (When applicable)

Ambient temperature °C

Top oil temperature rise °C

438

3337 kg/limb

N/A

99915

4000

67000

4461 kg/limb

89049

Design Data – Fingerprint Concept

Page 20: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 20

Temperatures, Gases, OLTC Curves and Event List

Page 21: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 21

Shows overload capacity

Based on Transformer data, ambient temperature and loading conditions

Overload Capacity

Page 22: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 22

No traditional hot-spot thermometer needed

Hot-spot temperature calculation

• HV winding

• LV winding

• Terciary winding

Hot-spot Temperature Calculation – IEC & IEEE

y

roh KHg

IEC-354 o = Top oil temperature

Hgr = Hot-spot to top-oil gradient

K = Load factor (load current/rated current)

y = Winding exponent

Page 23: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB 3/18/2010 | Slide 23

Intelligent Cooling Control

Signal from

CT

TEC Cabinet

T Top Oil

T Bottom Oil Thermometer pocket

Hot-spot

temp

ON CABINET

ALARM

WARNING

NORMAL

Display

Algorithms

Group

1

Group 3

Up to 6 Cooler Groups can be controlled

Group 2 Group 4

Group 5

Group 6

Enhancements from traditional cooling

• Control up to 6 cooler groups

• Starts on top oil, hot-spot and forecast

• Remote start of coolers possible

• All cooler groups equally used

• Logic to exercise motors each week

• Time in service shown in station interface

• Time delay between cooler group start

• Reduced noise level

• More stable temperature, reduced breathing

Traditional top oil thermometer used as

back-up start of coolers and for emergency trip

Page 24: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB 3/18/2010 | Slide 24

Cooling from

Radiators or

Coolers Losses

T Top Oil

T Bottom Oil

T Air

Cooling

from the

Tank

TEC keeps track of the transformer temperatures and compares

them with a theoretical model to indicate changes, in the cooling

conditions or heat generation, that could place restrictions on the

overloading capacity.

Transformer Temperature Balance

Page 25: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB 3/18/2010 | Slide 25

Transformer tank

UZ tank

TAir

PFault+PRI2 POLTC (Heat from

the OLTC) Ptr (Heat from

the transformer)

Ttr TOLTC

Keep track of the tap-changer temperature and compare it with a

model to indicate over temperatures in the tap-changer

Tap Changer Temperature Balance

Page 26: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 26

Processor board - TC 122

Temperature and

Moisture sensors

Cabinet Condition

Page 27: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 27

Minimal Functions

Page 28: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 28

Minimal Scope of Supply

Top oil temperature

• Hot-spot temperature

• Load

• Ageing

• Temperature balance

• Cooling control

Current transducers

• Hot-spot temperature

• Load

• Ageing

• Cooling control

• Contact wear

• Temperature balance

Bottom oil temperature

• Temperature balance

Ambient temperature

• Sun

• Shadow

Gases and Moisture package

• Gases detection / Trends

• Moisture detection

• Ageing acceleration due to moisture

• Data displayed and stored in TEC

Intelligent Cooling Control package

• Controls up to 6 cooler groups

• Star and stop based on top oil, hot-spot

• Weekly exercise of cooler groups

• Back-up in case malfunction

Overload package

• Overload capacity

• Hot-spot forecast Gas sensor

Relay box

• Generates up to 8 digital signal from dry contact for different alarms or warnings from TEC

• Can relay box

Page 29: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 29

© ABB Group June 5, 2013 | Slide 29

TEC system

TCP/IP

Fiber optic

Gas sensor

Connection with Customer´s Network

Minimum scope of supply

Page 30: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 30

© ABB Group June 5, 2013 | Slide 30

TMU 100 Bushing monitoring

Capacitance

Tan delta

DGA device

Individual 8 gases

Moisture TEC system

Thermal

Currents

Coolers

OLTC

TCP/IP

Fiber optic

Connection with Customer´s Network

Page 31: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 31

© ABB Group June 5, 2013 | Slide 31

Connection with Customer´s Network

Page 32: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB 22/07/2009 | Slide 32

TEC Cabinet installation - overview

1) Mount TEC on transformer.

2) Connect sensors and power supply according to drawings and connection tables.

3) Start system.

Note: The display indicates present status and events.

Page 33: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 33

TEC Web page

TEC

http://www.abb.com/product/db0003db004283/6242000fec997581c1257b1000211293.aspx

Page 34: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

TEC – Transformer Installation

Page 35: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 35

Installation of TEC Basic Version

Page 36: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 36

Installation in the Old Transformer

Page 37: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 37

Installation of TEC Integrate Version

Page 38: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 38

Installation in the Old Transformer

Page 39: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 39

Installation of TEC Smart Basic Version

Page 40: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 40

Installation of TEC Smart Basic Version

Page 41: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer

© ABB Group • | Slide 41

Control Room of Substation

Page 42: Inocencio Solteiro, PPTR/AT 05.06.2013 Transformer