Upload
others
View
80
Download
0
Embed Size (px)
Citation preview
HUNTON & WILLIAMS/ o 3
BRUSSELS, BELOIOM 2OOO PENNSTtVANIA AVEKtTE, N. W. RICHMOND. VIRGINIAWARSAW, POLAND FAIRFAX. VIRGIN.AHONG KONG WASHINGTON, D. C. 2OOO6 - 1812 NORFOLK. VIRGINIANEW YORK, NEW YORK RALEIGH, NORTH CAROLINA
ATLANTA. GEORGIA TELEPHONE (3O2) 955-I5OO KN
JEFFREY N. MATTW FACSIMILE (2O2) 778-saoi DMCTDIAL: (202)955-1552DAN J. JORDANGE* DIRECT DUL: (804)788-8609
September 11, 1995
Mr. Cesar LeeRemedial Project Manager (3HW21)SE PA Remedial SectionEnvironmental Protection AgencyRegion ffl
841 Chestnut BuildingPhiladelphia, Pennsylvania 19107
Metal Bank Cottman Avenue SiteSecond Request for Extension of Comment Period on
Proposed Plan and Notification of Dispute Resolution Claim
Dear Cesar:
On behalf of the Cottman Avenue PRP Group, we make a second request fora 30-day extension to the comment period on EPA's Proposed Plan for the CottmanAvenue Site. The extension is essential to enable the Group, EPA and otherinterested parties to evaluate the very significant findings yielded by the test pitsampling activities recently conducted at the site. The preliminary results of thesampling are enclosed along with this letter.
Also on behalf of the Group, we invoke the dispute resolution provision ofthe Administrative Order by Consent (AOC), Section XIV, as a result of EPA'srefusal to meet with PRP Group representatives to discuss data recently collected inaccordance with the AOC. The EPA has yet to provide the Group with final ||comments on the RI/FS Reports. The RI/FS process therefore is not complete, ilEPA's failure to meet represents a very serious concern in light of the new datawhich appear to contradict several key assumptions underlying the proposed remedyannounced by EPA in July of 1995. The Administrative Order forJhe_RIZFSobligates the Agencyjoeyaluate the significance of all site data. The dispute thatthe Group raises, however, could be resolved fairly and expeditiously if EPA willgrant a 30 day extension of the comment period and schedule a brief meeting duringthat scheduled period to evaluate the significance of the new data.
AR304575
HUNTON & WILLIAMS
Mr. Cesar LeeSeptember 11, 1995Page 2
I. Extension of Comment Period
There are several reasons why an extension of the comment period untilOctober 18, 1995 is necessary for EPA to consider all available information on theSite and for the Group to have a meaningful opportunity to comment on EPA'sProposed Plan. The most important reason for extending the comment period is theneed to incorporate into the remedy selection process the additional information thatthe Group is collecting for EPA's consideration. That information consists of (1)test pit data further defining the distribution of PCBs across the Site and (2)treatability testing data to determine if stabilization/solidification is a viable treatmentalternative for the Site. These data will provide EPA with information that isessential for the agency to make a final decision about the Site remedy. The resultsof the test pit work are enclosed and include data tables, a contour map of the areascontaining 25 ppm or greater of PCBs, and a calculation of the volume of soilcontaining that level of PCBs. This information demonstrates that EPA hassubstantially underestimated the volume of soil that would need to be excavated toachieve a cleanup goal of 25 ppm.
In addition to the need for EPA to consider this information, an extension isnecessary for the Group to comment meaningfully on the Plan. Section 117(a)(2)of CERCLA requires that EPA provide the public, including PRPs, a "reasonableopportunity for submission of written and oral comments" on the Plan. Thisopportunity must also be "meaningful" under the circumstances in which the Planis issued. United States v. Seymour Recycling Corp.. 679 F. Supp. 859, 864 (S.D.Ind. 1987). We described for you in our letter dated August 7, 1995, the reasonswhy, to be reasonable and meaningful for the Group, the opportunity to commentrequires a longer extension than EPA has provided.
The first reason is that the alternative proposed in EPA's Plan is not one ofthe twelve alternatives identified and evaluated in the Feasibility Study Report. TheGroup needs a minimum of 10 weeks to evaluate and prepare comments on analternative that was not evaluated during the many months when other alternativeswere under consideration. A second reason for extending the comment period is thata coordinated set of comments on the plan from the PRP Group will require at least90 days to prepare. Third, the Group requires additional time to collect, evaluateand provide to EPA the test pit and treatability testing information that will help theagency select the best remedy for the Site. These_data provide significant newinformationjbr the RI/FS Reports and, consequently, the administrative record onwhich EPA is making remedial decisions. EPA has never provided the Group withfinal comments on the RI/FS Reports, thereby making the RI/FS process as set out
AR30l*576
HTJNTON &. WILLIAMS
Mr. Cesar LeeSeptember 11, 1995Page 3
in the NCP and in the AOC (see Section Vm.F) incomplete. Evaluation andincorporation of the new data into the RI/FS is necessary before the RI/FS processwill be complete.
In order to consider this information fully as it develops the Record ofDecision, EPA should extend the comment period on the Proposed Plan an additional30 days. The PRP Group and EPA share an interest in ensuring that the remedyselected is the best possible remedy for the Site. Given the several years that thePRP Group has worked to investigate site conditions, and the millions of dollarsinvolved in that effort, it clearly is not unreasonable for EPA to grant an additional30 days to submit comments.
II. Dispute Resolution under AOC
Section XTV of the AOC authorizes the PRP Group to invoke disputeresolution in the event that the Group objects to any "EPA action or omission takenpursuant to this Consent Order." In this case, for the reasons discussed above, theGroup objects to EPA's failure to extend the comment period an additional 30 daysand to EPA's refusal, reported to Pete Swinick of EARTH TECH on September 7,to meet with Group representatives to discuss the test pit data. The Group thereforeinvokes Section XIV of the AOC, which requires EPA to respond to this letterwithin 14 days of the day on which you receive it. In the meantime, we request thatEPA meet with representatives of the PRP Group to discuss the reasons for invokingdispute resolution in this case.
If the comment period is extended an additional 30 days and if EPA agreesto a meeting within that time frame, the Group will withdraw its dispute.
If you have any questions or would like to discuss this request, please do nothesitate to call one of us.
Jeffrey N. MartinDan J. Jordanger
Group CounselEnclosures
AR30l*577
HUNTON & WILLIAMSMr. Cesar LeeSeptember 11, 1995Page 4
cc: Mr. Patrick Anderson (3HW21)Elizabeth Lukens, Esq. (3RC23)Cottman Avenue PRP GroupSteering CommitteeTechnical Committee
Mr. Peter P. SwinickJoseph P. Vitale, P.E.
AR3Q14578
MEMORANDUM9103/prap/field
Date: September 11, 1995
From: Peter Swinick & Joseph Vitale (EARTH TECH)
Subject: Test pit Program Summary
Enclosed with this memorandum are the following items:
• Analytical results from the testpit program;
• Contour maps showing the extent of contamination in subsurface soils in excess of 25 PPM ofPCBs and 10,000 PPM TPH:
• Volume calculations based this new testpit data as well as data collected during the RI; and
• - Revised cost estimates to implement Containment, Ex situ Stabilization, and Off-site disposaloptions based on the volume estimate.
In August 1995, EARTH TECH began the testpit sampling program to gather information in support ofour efforts to comment on EPA's proposed plan. The specific purpose of this program was to collectsamples in support of the S/S treatability studies and to characterize subsurface soils to determine thevolume of soils in excess of 25 PPM PCBs and 10,000 PPM TPH. The remainder of this memorandumpresents an overview of field activities, the estimated volume of soils in excess of proposed cleanup levels,and the estimated cost to implement Containment, Ex -situ stabilization, and Off-site disposal optionsconsidering the new volume estimate.
Overview of Field Activities
EARTH TECH installed 14 testpits to collect samples in support of the S/S treatability studies and tocharacterize subsurface soils in excess of the proposed cleanup levels. To install the testpits, we mobilizedtwice in the month of August. Under the first field effort beginning in the week of August 7, we collectedsoils samples from 3 testpits (TP-T-1, TP-T-2, and TP-T-3) to be used support of the S/S treatabilitystudies. This field effort began on August 7 and ended on August 11. Samples were sent to STCRemediation, Wastech, Fluid Tech, and EARTH TECH for treatability testing.
After much discussion with EPA and NOAA on the details of the testpit sampling program, EARTHTECH began the second field effort beginning in the week of August 21. Over the course of 6 days.
«logo»
AR30i*579
EARTH TECH installed 11 testpits and collected three samples per testpit. Samples were collected fromthe 2 to 5 foot interval, the 5 to 10 foot interval, and the 10 to 15 foot interval. Each sample was analyzedfor total PCBs, TPH, and lead. Locations of these testpits are shown on Figure 1. The results of theseanalyses are presented in Table 2.
Soil Volume Estimates
To determine the volume of soil above the water table, we multiplied the depth of each soil interval by thearea determined by the contours presented in Attachment A. The contours developed enclose areas bydepth interval in excess of the proposed cleanup levels. The contours used in the analysis were based on RIsoil boring data and the recent testpit data which are presented in Tables 1 and 2. Based on this approach,the soil volume above the water table is approximately 32,000 cubic yards.
Revised Cost Estimates
We revised the cost estimates for the Containment, ex-situ Stabilization, and Off-site disposal optionsbased on the above volume determination and recent inquiries on the unit price of off-site disposal of PCBcontaminated wastes. The details of the cost estimate is presented in Attachment B.
AR30l*580
E A R T H
1" = 180f0 90 180 360
SCALE IN FEET
Figure 1Test Pit Location
AR30l*58l
Summary Table 1RI Sampling Results Cottman Ave/Metal Bank
Location
BlB2B3B4B5B6B768B9BIOBllB12B13B14B15B16B17BISB19B20B21B22B23SB-101SB-102SB-103SB-104SB- 105SB- 106SB-107SB- 108
TPHConcentrations in
0'-5'267030102150NT*285014786142905690NT148266922124008571085011500NTNT*NT*5655104004860NTNTNTNTNTNTNTNT
mg/kgDepth Interval
5' - 10' 10' - 15'NT1340359NT*211355148064547804590232<41.35108631280013190174006480NT*NT*1402158006213500NTNTNTNTNTNTNT
36007543120NT*56203143595631044703880106<4268906570108001436416010000NT*NT*6429977013600NT21008703100NT2800NTNT
PCBConcentrations in
0'-5'1.70.9490.2410.2*5.13<0.351.0684.22<0.902NT1
3.16NT3.2<9.3BDL26NT3.6*BDL*25
<0.177NTNTNTNTNTNTNTNT
mg/kgDepth Interval
5' - 10' 10' - 15'NT1.126<1.82.48*0.7030.3264.65<0.9070.39429
0.247<0.170.6<0.895
3.85420.976.3*13.7*6.56.67.85.3NTNTNTNT1.81.8<3.4
28<3.79<1.9NT*4.81<0.214BDL<0.96.6511.7<0.89<0.170.7818.2<6.30.43
7.54NT*0.37*8.70.344.7NT24.60.757.312151.1<1.8
Notes: 1. NT = Not Taken/Not Tested2. BDL = Below detection limit (detection limit was not provided in the RI)3. Shaded values are out of the specified depth interval.4. * = No backup data was provided in the Remedial Investigation5. The highest detection limit for all the PCB alochlors was used for the PCB
sampling results indicated as less than (<) a specific value.
EARTH TECHProject No. 9103 page I 9103/prap/tablestfPH-PCBJCLS
AR30U582
Summary Table 2August 1995 Test Pit Program
Sampling ResultsCottman Avenue/Metal Bank
Sample Laboratory TPH Total PCBs Total LeadIdentification Sample No. (mg/kg) (mg/kg) (mg/kg)
TP-1-5' 113997 1400 <2 1160TP-1-10' 113998 7000 22 323TP-1-121 113999 24000 10 671TP-4-5' 113994 52000 36 541TP-4-10* 113995 12000 45 2600TP-4-11.5' 113996 28000 50 1900TP-7-5' 114112 910 <2 429TP-7-10' 114113 19100 <2 1800TP-7-13' 104114 4200 <2 210TP-8-5' 114109 180 <2 75TP-8-101 114110 27 <2 330TP-8-15' 114111 1210 2 1780TP-9-5' 114105 3040 35 22700TP-9-101 114104 630 <2 10600TP-9-13' 114101 380 <2 356TP-11-51 114106 1630 <2 900TP-11-101 114107 6500 <2 1300TP-11-13' 114108 8200 <2 1200TP-12-5' 114216 1730 4.4 590TP-12-101 114217 2190 7.7 415TP-14-51 114212 2000 <2 82TP-14-7.51 114213 9000 <2 96TP-16-51 114218 2200 <2 264TP 16-8.5' 114219 9200 <2 2150TP-18-5' 114100 1020 <2 407TP-18-10' 114102 1520 <2 1000TP-18-121 114103 930 <2 1720TP-21-5' 114214 80 <2 38TP-21-7.51 114215 160 <2 750TP-T-1-5' 124470 28900 108 572TP-T-1-101 124469 13300 10.5 359TP-T-1-151 124465 52800 41 485TP-T-2-5' 124467 66100 230 673TP-T-2-10' 124466 51200 150 384TP-T-2-121 124464 16000 77 346TP-T-3-5' 124468 6420 0.77 574TP-T-3-10' 124463 6170 <1 1460TP-T-3-15' 124471 2240 0.87 243
EAR TH TECHProject No. 9103 page 1 9103/hsw/prap/tables/nt
AR3CH583
Attachment A
«k>go»
B_i? iB-t.^ ', *"'<»
BIO4
MW6 B-aO pwio
...BIOS
TP-J+*-"LEGEND \l 1 i£ J_ __ _ TOTAL PCBS CONCENTRATION
PARTS PER UHJUON (PPM)
+ B~U BORMC LOCATION (AUC./SEPT. 1«91)
08'04 BORMC LOCATION (MAY. 1993)
TP-1TESTPIT LOCATION (AUGUST, 1995)
0 50 100 200TESTPIT LOCATION (AUGUST, 1995) ^ —1 00
SCALE IN FEETFigure 1
TPH Concentration 2-5 FeetMetal Bank/Cottman Avenue
flR30l»585
\ FP-10
- B-21/1KW5
___ TOTAL PC8S CONCENTRATIONPARTS PER MUION (PPM)
BORWO LOCATION (AUG./SEPT. 1M1)
08'04 BORWC LOCATWH (MAY. 1993)
FP-J=100
0 50 100TCS1PIT LOCATION (AUCUST, 1995)
SCALE IN FEETFigure 2
TPH Concentration 5-10 FeetMetal Bank/Cottman Avenue
BOWN6 LOCATION (AUG./SEPT. 1S91)
BORINC LOCATION (MAY, 1993)
TP-J
Figure 3TPH Concentration 10-15 Feet
^^ Metal Bnnk/Cottman Avenue» R T H £) T I C I I —————————————————————————————————————————————————————————————————————
^ AR30l*587
B-1SA-2 TP-?
_ _ _ TOTAL PC8S CONONTRATIONPARTS PER MUJON (PPM)
B~13 BOXMG LOCATION (AUG./SEPT. 1981)
BORWO LOCATION (UAY. I99J)
T?7-/TESTPIT LOCATION (AUGUST. 199$)
SCALE IN FEETFigure 4
PCB Concentrations 2-5 Feet^ Metal Bank/Cottman Avenue
E A R T H fel I f C H ——————————————————————————————————————————————————————————————————————
. . AR30U588
V- ivr10 1 *a-9 «r *7/lJ*• w • Ar - -•- -\w *B-1S/P-2 77>-^ B-M |
t/y*7 rp-js iJF-4* /Bm f**™ *r *.HHK T M' -
«-« .4>81M -x
APPffOX/MATT LOW*a*i*r !««:-—= — «-" "'" B- J
FP-12
LE2ENG_ _ _ TOTAL PCBS CONCENTRATION
PARTS PER MUION (PPM)
+ ~'3 BOXMC LOCATION (AUC./SEPT. 1991)
^ BORING LOCATION (MAY. 1993)
TESTPIT LOCATION (AUGUST. 1995) 1=1 00'0 SO 100 200
_______________________SCALE IN FEETFigure 5
PCB Concentration 5-10 FeetMetal Bank/Cottman Avenue
t A R T H HI T i e n —————————-————•—-————————————————————————
B-15/P-2 TP-7
7P-JJ B-21/MW15
_ _ _ TOTAL PC8S CONCENTRATIONPARTS PER MILLION (PPM)
BORW« LOCATION (AUG./SEPT. 1891)
B104BORMC LOCATION (MAY. 1993)
TP-J 1=100*50 100
TCSTPIT LOCATION (AUCUST. I99S)
SCALE IN FEETFigure 6
PCB Concentration 10-15 FeetMetal Bank/Cottman Avenue
AR30U590
Attachment B
Revised Cost Estimates
E A R T H S I T E C H
AR30l*59l
Containment with a Permeable Cap
The total volume of on-site material to be excavated for this alternative is 30,600 cubic yards.30,000 cubic yards will be excavated during the UST removal.600 cubic yards will be excavated from the courtyard.
Assumptions
1. The courtyard soils will be disposed of as a TOSCA waste.Rationale: Samples are over SO ppm Total PCBs
Sample ID ConcentrationTB1S 52 ppmTB2S 140 ppmTB2S(dup) 110 ppmCY-136 70 ppm
2 Concrete slab will be disposed of as a TOSCA waste.3 Conversion factor 1.5 tons/cy for soil and debris.4 The water table is at 15.0 ft below the surface.5 All the spoils generated during the removal of the UST will be screened to separate out
the debris6 All sediments placed on site will be used as backfill.
Total volume of sediments = 8900 cy+2850 cy = 11,750 cy? The on-site soil contains 20% debris/80% soil.8 The debris will be transported in trucks/trailers with a 20 cy capacity.
Transportation and Disposal Cost = $215+$1425/20=S286/cy9 Geognd Unit Cost = $2.00/square yard.10 The volume of soil to be disposed of off site = 0.8*30,000 cy + 30 cy =
=24000 + 30The addditional 30 cy of material is the USTs concrete slab.
9103/hsw/prap/containl.docAR30l*592
Coat Summary for Remedial Alternative : Containment(Addreaaing •oil above the water tablet
lle»N«.
3A3BJCIDIE3F3O
3H
31
3J3K
CMBftMWlM
Short Term MonMormg (ojuanoly - 2 yen)Lot* Ttn« Monitormt (•nmally yn 3 -30)DeedRaBncuomACCOM RMricuomW«nun»5iin»Public Educauen fnftaiExowuon md Dapoed of Courtyvd SoilExcmuonTnraporation end DuptMl of SoilBackfillConpicuonOradmfondSeeainf.
Rcmowl ml DupoMl of USTROKMlofSW)Examion (UST BM only)Roaonl/DiipoMlofMnkconunaRcpheancM Soil (BwfcTill in UST ttm only)CoapKaonSiamdanmi link niteaCollMion/Dnpoal of damns ""dHmdlins/Scranmc of Exemicd MMcfalTmpacuiion Bid Dupoal of Soil (UST only)Tnraponwon md Di KMl of DcbmMnccllmeaui
< u«ntlQr
600900600600600
3030000100001125011250
4
250030000360006030
Conuinmcni Sy*um (Sheet Pile Wall md UwhMe Collection)Sheet Pile WillTrcncninsBackfillCompccuonIvUnhola;HDPECoHecoonPipeMobiliauon/DanobiliauonNAPL Collection nd D«po«lNAPL Smnger lyitemDnimOrunheuoiConerate conuinneM vaDupoal of NAPLEkctncmi
MucdlineoiaExcmu Sediment md Reuon MudfltUenrableC*?•nd A Graml BorrowGndu*CoracvcuanQeogndXMfH/ToptOll
Dradinf md SeedingKiofMnnns Well*l»(i«eelUn«MAnrnul Mmnumnct
S6000390067006700
I1100
1
6666
2751
3420034200342004S4001610016100
5
Untt
cylorn«yeyey
cy«jr»l*yeyhrpl«ylamey
ifeyeyeyafb
mac*•(«li
eyeyey•yeyey•
UnMCMl
HS25SSIOS3*5
SI50SI»1«SIOS3
S375SI6S5
S255J2«S
S15SI5SIOS3
S2.400S40
$60,000
S9.000S25S200
Sl.OOOSl<
S10.000
SI2stS3S2S1IS5
SIJOO
EnmeiM
S4.SOOJ229.500S6.000$1.100$3.000
$4.500$240,000$160,000SII2400$54.730SI OO$40,000$150,000
S9.ISO.OOO$1.726,100$1.000.000
$140.000$JIJOO$67.000$20.100$19.100S72.000S60.000
$54.000$150
$1.200$6.000
$10.000$500.000
$410.400$273.600$102.600$96.100S2S9.SOO$10.500$6,000
SI 26,000
CmftMCuH
$10,000$27,900Sl.OOO$35.000$245.100
SI 2.739.350
$1.701.150
S3.96I.OOO$1.316.000
O«MCMt
$1.000
$37.650$125
$1.200
$4.400$1.200
OAMTMBte
$301.900$75.600
$2 00
S4.000
$45 75
KOOO
Subtoul Altondm C-4 $20,II3>»EnguwcnntQIOH SZ01 1.000
$3.017.000
Tout S25.I4I.500
Total Pioent Wonh(n-30. i-O.StV) $27.954.000
EAKTHTECH
Cost Summary for Ramadial AKamativa : Ex Shu Stabilization with Containment(Addraaaing aoil abowa tha watar labial
IteaiNa.
12AI2B12C12D12E12F120
12H
12
rjrj*
IM
^AffWMHtmt
Short Tom Maniumi (quvtely - 2 y«n)La« Tern Manitanng (mmMlly yn 3 -30)Deed RancuoraAccm RatnanniW««i»Sir»Public Eduauon PnfiM<Exemuon md DupoMl of Cowtymd SoilExcmuonTnrapoiuuan mi Dupo«l of SoilBKldill (counyvd toil only)Coap*cuonGradii««idScedii«
Ro»ovmlindDupo«lofUSTRcmonlofSbbExamuon (UST **• only)Ranonl/DiipOHl ofunk eontcnuCompactionSutmclaning Unk wrfacttCollecuon/DupoMl of clennf MClH«ndlti«/Screcning of Exoraled MmaulTtmsponuion ind Dapoul of Defens (UST va only)Miiccllineoia
OuanHir
600900600600600
30300001000011750
42SOO300006030
Canuinmeni System (Sheet Pik Will nd LochMe Collecuon)Sheet Pile WillTrenchingBackfillCompKtionMmnolaHDPE Colleaion PipeMobihaiion/DemobiliationNAPL Collecuon md Dupo«lNAPL S«vw er lyuemDnjmDn*n haienConcrrtc roniainmem maDicpoul of N'APLElrcwaJ
MiacelianeouiLu»»u Sedmeni ind Reuort MudflmL» S«i SiabmaiionMotoiianonSeupDecon /DemobEjuxmion (PCB rat only)HaidJini Screenint of Excavated MauralSottdifiauaivSubiliBtion ProeatHandJmf of Subilind KUunalTfanaponauon ind Diipoul of Debnt (PCS veai onlyRefuMory ComplianceMjaotllmaoui
PemaaMcCapSand ± Ctvral BonwrOndtniCompactionOaoandLoam/TopamlGrading and SeeduM]Moniionng Welb
iscellancouiAnnual Maintenance
56000390067006700
tino
i66662S1
1S90190
1470030900IK
342003420034200414001610016100
5
Unit
eykmeyey«y
eyey9*Vtoadeyey
>reyeyeyeairb
c>eaeac*f«l*
1eyeyeyeyey
eyeyey«yeyeyt*
(taMCaat
SIS2S5S10S3SS
ItSOstSI6S3
S375$16SS
$216
SISSISSIOS3
$2.400$40
$60.000
$9.000S2S$200
$1.000$16
$10.000
Jl 37.500st$5
$120$5
$2S6
$12St$3$2Sit$5
$1.200
EzWMiM
$4.100$229.500$6.000$1.100$3.000
S4JOO$240,000$160.000$35.250$1400$40.000$130.000
$1.726.100$353.600
$140.000SSt.500$67.000$20,100$19.200$72.000$60,000
$54.000$150
$1.200$6.000
$10.000$500.000
$137.500$7.120$4.450
$1964.000$154.500$51.4tO1250.000
$1.000.000
$410.400$273.600$101600$96.100$219.100$*UOO$6.000
$126.000
Capital Cart
$10.000$27.900$1.000$35.000$245.100
$2,710.950
$1.701.150
S3.96I.OOO$4.569.050
Sl.3t6.000
O AM C«<
$1.000
$37.650$125
$1.200
$400$1.200
$4,000
OAMTatab
$301.900$75.600
S2JOO
$4.000
S4U7J
SO
$4.000
Subtotal Altemain* C-7 SI4.6S4.ISOEnnnecm«310K $1.465.000Conunamey«ISH $2.191000
Tool $11417.150
Total Pinem Won*(»-30.rO.S*) S2I.059.000
EMTHTECH
AR30I*595
Ex Situ Stabilization with Containment
The total volume of on-site material to be excavated for this alternative is 31,490 cubic yards.30,000 cubic yards will be excavated during the UST removal.600 cubic yards will be excavated from the courtyard.890 cubic yards will be excavated from areas centered around B-l and B-21.
Assumptions
1. The courtyard soils will be disposed of as a TSCA waste.Rationale: Samples are over 50 ppm Total PCBs
Sample ID ConcentrationTB1S 52 ppmTB2S 140 ppmTB2S(dup) 110 ppmCY-136 70 ppm
2 Concrete slab will be disposed of as a TSCA waste.3. Conversion factor 1.5 tons/cy for soil and debris.4 The water table is at 15.0 ft below the surface.5 All the spoils generated during the removal of the UST will be screened to separate out
the debris.6 All sediments placed on site will be used as backfill.
Total volume of sediments = 8900 cy+2850 cy = 11,750 cy7 The on-site soil contains 20% debris/80% soil.8 The debris will be transported in trucks/trailers with a 20 cy capacity.
Transportation and Disposal Cost = $215+$1425/20=$286/cy9 Geogrid Unit Cost = $2.00/square yard.10 Stabilized soil will expand 20%.11 The volume of material to be stabilized - 0.8*(30,000 cy + 890 cy) = 24,700 cy12. The volume of stabilized material to be handling (after stabilization) = 1.25*24700cy13 The volume of debris to be disposed of consists of the following:
30 cy from the USPs concrete slab;20% of 30,000 cy (UST area) - 6000 cy20% of 890 cy (PCB areas) = 178 cy
9103/hsw/prap/exsitul.doc
Off-Site Disposal with Containment
The total volume of on-site material to be excavated for this alternative is 31,490 cubic yards.30,000 cubic yards will be excavated during the UST removal.600 cubic yards will be excavated from the courtyard.890 cubic yards will be excavated from areas centered around B-l and B-21.
Assumptions
1. The courtyard soils will be disposed of as a TSCA waste.Rationale: Samples are over SO ppm Total PCBs
Sample ID ConcentrationTB1S 52 ppmTB2S 140 ppmTB2S(dup) 110 ppmCY-136 70 ppm
2. Concrete slab will be disposed of as a TSCA waste.3 Conversion factor 1.5 tons/cy for soil and debris.4. The water table is at 15.0 ft below the surface.5. All the spoils generated during the removal of the UST will be screened to separate out
the debris.6 All sediments placed on site will be used as backfill.
Total volume of sediments = 8900 cy+2850 cy = 11,750 cy7 The on-site soil contains 20% debris/80% soil.8 The debris will be transported in trucks/trailers with a 20 cy capacity
Transportation and Disposal Cost = $215+$1425/20=$286/cy9. Geogrid Unit Cost = $2.00/square yard.
9103/hsw/prap/offsitel.docAR30U596
Coat Summary for Remedial Alternative : Off She Diapoaal with Containment(Addreaaing eoil above the water table!
IttaCto.
I2A12B12CI2DI2EI2F12O
12H
121
\VI2K
12M
12K
f» aaaialaientfwVlaWVwnn
Short Tcm Monitorint (quanoly • 2 ywi)Long T«n» MonMonns (mwlly yn 3 -30)DMdReancucmACCM RMhcuomWarangSienB
Excmuon and DupoaU of Courtytri SoilExcrauonTmporlauon *nd Dupoul of SoilBecfcfillCompletionOradmfind Seeding
Renwwl md DupoMl ofUSTRewmlofSlabExcmuon (UST am only)Rnwotl/Dupoal ofttnk oonunuReplacement Soil (Backfill for UST «•)CoBjptcuonSinew Inning tank taitcaColUcuoi/Dupoaal of ckara«j atariI !•• ill'n B^Ti •• IHI II • iiffnl ai^ • 1 1 In 1 1 ' 1
Trmpocuuon A DopoMl of Soil (UST only)TiwpocttUon * DnpoMJ ofDebn* (UST only)MiKdlmeoui
Ovanttcr
600900«00400600
3030000100001125030000
4
25003000C3600060)0
Conuinmcm Synon (Sheet Pile Will ind LeKhtte Collecuon)Sheet Pile W«llTrtnehinfB«kfillConpKtionVUnhol«i IHOPE Collecuon PipeMotxliation/DemobihaiionNAPL Collection «nd DuposilNAPL Semnaer lyneniDnmE>nnihe«enConcrete conuintncnt mDupoMlofNAPLEkonctl
MoeellBMOutExava* Sediment *nd Reuore MudfliuOfT-Sile Duponl (TSDF)E«muon<PCB tnm only)tfandlmf/Screeninf of SoilTnraporuuon md Dupoul of SoilTnrapcnuon md Dupcad oTDebmPOTMOin(OrdltfXMl
Reptaocwm of Soil (PCB *e> only)Bedkfill (PCS •«. only)GradmsConptouon
PenneMc Cap
56000390067006700
11100
1
6666
2751
1901901061171
190190190
Umtt
eylamey«yey
«yeyerieyeyVadeytoneey
«feyeyeye*If•
eaa«e>«*ii
eyeyIoney
eyeyey
UnttCwt
SIS255(10S315
$150S*SICSIOS3
$375SI6$5
S255S2*6
SI5SI5SIOS3
S2.400S40
S60.000
S9.000S25S200
11.000S16
SI 0.000
st$5
S255szw
SIOSIS3
Estimlm
S4.tOOS229.500$6.000$1.100$3.000
M.500$340.000$ieaooo$11X500$90.000SIJOOS4aooo$150.000
$9.110,000$1.726.100$1.000,000
SMO.OOO$51.500$67.000S2Q.IOO$I9JOO$72,000$60.000
$54.000$150
$1 00$6.000
$10.000$500.000
$7.120$4.450
S272J40$50.953$250.000
swoo$7.120$1670
C««IMC«4
$10,000$27JOO$1.000$35.000$245.100
SI2.774.600
$1.701.150
S3.96I.OOOS5S4.S63
SIS.690
SI4M.OOO
OAMCMl
$1.000
$37.650$125
$1.200
$4.400SIJOO
OAMTettki
$301 00$75.600
$2JOO
$4.000
S45J7S
$4.000
Subtottl AMemetm C-12 S20.752J03Ennncamg^Km $2.075.000Comweency 915*4 $3.113.000
Toul S25.940J03
ToMlPnMMWonh(n-30.H).5H) SJS.7S3.000
EMTHTECH
AR30I>597