Houston ISD/High School for Law Enforcement and Criminal Justice renovation budget

Embed Size (px)

Citation preview

  • 8/8/2019 Houston ISD/High School for Law Enforcement and Criminal Justice renovation budget

    1/5

    11/4/2010 TEA 034 Page 1 of 5 P

    Capital Improvement Program High School for Law Enforcement andProposed Budget2007 Facilities Capital Program

    Original

    Budget

    Admin

    Adjustment

    B

    Trustee Allot

    C

    P1 HVAC

    D

    Athletics Sci E

    Project Data for New and Renovation

    Existing Building(s) Sq. Ft. 87,582 Proposed Classroom Capacity -

    New Sq. Ft. 0 Current Classroom Capacity 645

    Demolition Sq. Ft. 0 New Seats Gained (645)

    Proposed Total Sq. Ft. 87,582 Proposed Core Capacity -

    # of T-Buildings (2007) 15 Current Site Acres 11

    Student Enrollment (2007) 674 Proposed Site Acres -

    New Construction and Renovation Cost

    Total Estimated New Construction Cost - - - - -

    Total Estimated Renovation Cost 899,179 138 - - -

    Total Estimated New Construction and Renovation Cost 899,179 138 - - -

    Other Program Costs for New and Renovation Proposed Actual

    T-Building Costs - - - - -

    Contingency (Various% of Construction Costs) 44,959 7.97% 71,652 - - - -

    Design Fees (Various% of Construction Costs) 80,926 5.58% 50,157 - - - -

    Management Fee (Various% of Construction Costs) 35,967 8.03% 72,215 - - - -

    Soft Costs, Testing, Surveys, Printing, etc. (Various% of Constr. Costs) 0 14.86% 133,638 - - - -

    Project Reserves 64,525 - - - -

    Total Estimated Other Program Costs for New and Renovation 392,187 - - - -

    Furnishings/Equipment for New and Renovation Proposed Actual

    Furnishings and Equipment (Various% of Constr. Cost) 89,918 0.00% - - - - -

    Replacement Media Center Books & Materials - - - - -

    Media Center Books & Materials for Increased Capacity - - - - -

    Technology Equipment ($600,000 + $5.00 per sq ft) - - - - -

    Technology Cabling 21,496 - - - -

    Other Equipment - - - - -

    Science Equipment and Furnishings Upgrades 149,500 - - - -

    Total Estimated Furnishings and Equipment for New and Renovation 170,996 - - - -

    Land Purchase for New and Renovation

    Additional Site Area 0 acres x $1 per acre = - - - - -

    Total Estimated Land Purchase for New and Renovation - - - - -

    Grand Total of New Construction and Renovation Cost 1,462,362 138 - - -

    Inflation (Const. & Equip.) 49 months @ $0 per month -

    Anticipated Bid Date October-11

    Budget Adjustments

    Summary for New Construction and Renovation

  • 8/8/2019 Houston ISD/High School for Law Enforcement and Criminal Justice renovation budget

    2/5

    11/4/2010 TEA 034 Page 2 of 5 P

    Capital Improvement Program High School for Law Enforcement andProposed Budget2007 Facilities Capital ProgramEstimate Date September-07

    Grand Total with Inflation 1,462,362 138 - - -

  • 8/8/2019 Houston ISD/High School for Law Enforcement and Criminal Justice renovation budget

    3/5

    11/4/2010 TEA 034 Page 3 of 5 P

    Capital Improvement Program High School for Law Enforcement andProposed Budget2007 Facilities Capital Program

    Original

    Budget

    Admin

    Adjustment

    B

    Trustee Allot

    C

    P1 HVAC

    D

    Athletics Sci E

    New Construction Costs

    Building Construction 0 s.f. x $0 per s.f. = -

    Site Development 0 acres x $0 per acre = -

    Site Utilities -

    Demolition Costs -

    Other Costs (Specify) -Total Estimated New Construction Cost - - - - -

    Other Program Costs New Construction Proposed Actual

    T-Building Costs -

    Contingency (5% of Construction Costs) 0 0.00% -

    Design Fees (6.5% of Construction Costs) 0 0.00% -

    Management Fee (3.5% of Construction Costs) 0 0.00% -

    Soft Costs, Testing, Surveys, Printing, etc. (10% of Construction Costs) 0 0.00% -

    Project Reserves -

    Total Estimated New Construction, Soft Costs & Fees - - - - -

    Furnishings/Equipment for New construction Proposed Actual

    Furnishings and Equipment (10% of Construction Cost 0 0.00% -

    Replacement Media Center Books & Materials -

    Media Center Books & Materials for Increased Capacity -

    Technology Equipment ($600,000 + $5.00 per sq ft) -Technology Cabling -

    Other Equipment -

    Science Equipment and Furnishings Upgrades -

    Total Estimate New Construction Furnishings and Equipment - - - - -

    Land Purchase For New Construction

    Additional Site Area 0 acres x $0 per acre = -

    Total Estimated Land Purchase for New Construction - - - - -

    Total Estimate New Construction Costs(Current $) - - - - -

    New Construction

  • 8/8/2019 Houston ISD/High School for Law Enforcement and Criminal Justice renovation budget

    4/5

    11/4/2010 TEA 034 Page 4 of 5 P

    Capital Improvement Program High School for Law Enforcement andProposed Budget2007 Facilities Capital Program

    Original

    Budget

    Admin

    Adjustment

    B

    Trustee Allot

    C

    P1 HVAC

    D

    Athletics Sci E

    Construction Costs for Renovations to Existing Facility

    Site -

    Roofing -

    Structural -

    Exterior 39,789

    Interior 46,044Mechanical 241,191

    Electrical -

    Plumbing 67,921

    Fire/Life Safety 8,649

    Technology Infrastructure 218,392

    Conveyances 15,331

    Specialties -

    Other Needs -

    Science Infrastructure 262,000

    Rounding Adjustments (138) 138

    Total Estimated Renovation Cost 899,179 138 - - -

    Other Program Costs Renovations to Existing Facility Proposed Actual

    T-Building Costs -

    Contingency (5% of Construction Costs) 44,959 7.97% 71,652Design Fees (9% of Construction Costs) 80,926 5.58% 50,157

    Management Fee (4% of Construction Costs) 35,967 8.03% 72,215

    Soft Costs, Testing, Surveys, Printing, etc. (10% of Construction Costs) 133,638

    Project Reserves 64,525

    Total Estimated Renovation, Soft Costs & Fees 392,187 - - - -

    Furnishings/Equipment for Renovations to Existing Facility Proposed Actual

    Furnishings and Equipment (10% of Construction Cost 89,918 0.00% -

    Replacement Media Center Books & Materials -

    Media Center Books & Materials for Increased Capacity -

    Technology Equipment ($600,000 + $5.00 per sq ft) -

    Technology Cabling 21,496

    Other Equipment -

    Science Equipment and Furnishings Upgrades 149,500

    Total Estimated Renovation Furnishings and Equipment 170,996 - - - -

    Land Purchase for Renovations to Existing Facility

    Additional Site Area 0 acres x $0 per acre = -

    Total Estimated Land Purchase for Renovation Construction - - - - -

    Renovations to Existing Facility

  • 8/8/2019 Houston ISD/High School for Law Enforcement and Criminal Justice renovation budget

    5/511/4/2010 TEA 034 Page 5 of 5 P

    Capital Improvement Program High School for Law Enforcement andProposed Budget2007 Facilities Capital Program

    Total Estimate Renovation Costs (Current $) 1,462,362 138 - - -