MCE Deepwater Development 2016 PAU, FRANCE • 5-7 APRIL 2016 Goliat FPSO Marine Installation – Execution Highlights and Learnings Øyvind Lundby DOF Subsea

Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

  • Upload
    voliem

  • View
    221

  • Download
    4

Embed Size (px)

Citation preview

Page 1: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

PAU, FRANCE • 5-7 APRIL 2016

Goliat FPSO Marine Installation –

Execution Highlights and Learnings

Øyvind Lundby

DOF Subsea

Page 2: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

Hammerfest Site

Page 3: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

Field Lay-Out

DOF Subsea 3

- 14 Anchors in 4 + 4 +6 clusters- Unsymmetrical line/cluster configurations – Chain, Fibre, Buoyancy elements- Existing Infrastructure

Page 4: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

Main Achievements

DOF Subsea 4

- Offshore Towing: Start 07.05 @ 04:50, at target: 08.05 @ 01:30- Safe Mooring: Start 08.05 @ 01:30, 6 lines on: 10.05 @ 18:35 - All lines connected: Start 08.05 @ 01:30 all lines on: 16.05 @ 09:59- Tensioning: Start 12.06 @ 09:08 competed: 14.06 @ 22:10

Page 5: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

Philosophies and Basis

DOF Subsea 5

- DNV RP H101 – Risk Management in Marine- and Subsea Operations

- Minimize Manual Handling- Proven and robust methods and design- ALARP Principle- Clear “Safe Hold Conditions”- Avoid parallel operational activity

- “One Team Approach”- Target ownership, relations and commitment;

- Client- Contractors- SubContractors- Third Parties

- All involved early

- HSE Focus- Continuously focused from day one- Always on the agenda- Allocated resources

Page 6: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

Testing and Training

DOF Subsea 6

- Testing, training and verifications- Visit and Inspect equipment and sites- Verify and test properties and functionality- Training and familiarisations

Page 7: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

DSNO Marine Installation Scope

WP 00

• 2012

• Fabrication Start; 14 Suction Anchors

WP01

• 2013

• Transport and Handling of all Anchors, chain and shackles

• Anchor and Bottom Chain Pre-Inst.

WP02

• 2014

• Transport and Handling of fibre reels and buoyancy elements

• Fibre, Buoyancy Element, Top Chain Pre. Inst. (Korea)

In Shore -2015

• Spring 2015

• FPSO Receipt and tow in

• Tug Assisted Mooring

Offshore -2015

• Spring/Summer 2015

• FPSO Tow Out and Installation

• FPSO Mooring - Tensioning

Page 8: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

WP01• Summer / Autumn 2012

• Anchor Fabrication (Finland)

Page 9: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

WP01• Spring 2013

• Anchor and Bottom Chain Pre-Inst.

Page 10: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

WP02

• Summer 2014

• Fiber, Buoyancy Element, Top Chain Pre. Inst.

Page 11: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

WP – In Shore

• Spring 2015 – FPSO Receipt

• Inshore Tug Assisted Mooring

• Offshore Towing and Installation

- Pre – Installation of Inshore Mooring in Hammerfest

- Preparations of FPSO on Vanguard- FPSO Tow In- Install and Maintain FPSO in Inshore

Mooring- Release and Tow Out of FPSO

Page 12: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

WP – In Shore

• Preparations on DW Vanguard

Page 13: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

WP – Off Shore

• FPSO Installation in Offshore Moorings

- Two Installation Vessels- Four Vessels for station keeping- 3 Teams each shift for operating winches

Page 14: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

Success Criteria

DOF Subsea 14

- One Team Approach

- Attention to details

- Testing, Training and inspection/involvement

- Robust Design and Contingency philosophy

- Robust manning

Page 15: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

Client Relations - Experiences

DOF Subsea 15

- Excellent through four WP’s and three Offshore Campaigns - Genuine “One Team Approach”- Excellent relationship characterised by;

- Mutual trust and support- Honest and without any hidden agenda- Open communication- Benefitted both Eni and DSNO

Page 16: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

SubContracting - References

DOF Subsea 16

Sub-Contractors nominated and selected based on;- Recognized and proven records- Compatible HSEQ policies and system- Committed and proactive and involved- Commercially competitive- Continuity and key personnel flagged as important

SubContracting - Experiences- “One Team Approach” conveyed towards Contractor- Schedule, progress and marked monitored- Involved early (enough) for;

- DSNO to familiarise with Contractor- introduction, familiarisation and testing

- All Sub-Contractors performed well (exceptionally), all in a proactive and positive manner.

- No HSEQ issues- All flexible (under challenging conditions)

Page 17: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

MCE Deepwater Development 2016

Happy times!

Page 18: Goliat FPSO Marine Installation Execution Highlights …mcedd.com/wp-content/uploads/02_Oyvind Lundby - Dof Subsea.pdf · Goliat FPSO Marine Installation – Execution Highlights

Thank you!