16
GCOM-W1 Status Keizo Nakagawa 1 , Norimasa Ito 1 , Marehito Kasahara 1 , and Keiji Imaoka 2 1 GCOM Project Team 2 Earth Observation Research Center (EORC) Japan Aerospace Exploration Agency (JAXA) June 29, 2011 NCDC, Asheville 1

GCOM-W1 Status

  • Upload
    wilma

  • View
    47

  • Download
    0

Embed Size (px)

DESCRIPTION

GCOM-W1 Status. Keizo Nakagawa 1 , Norimasa Ito 1 , Marehito Kasahara 1 , and Keiji Imaoka 2 1 GCOM Project Team 2 Earth Observation Research Center (EORC) Japan Aerospace Exploration Agency (JAXA) June 29, 2011 NCDC, Asheville. 1. GCOM 1 st Generation Satellites. GCOM-W1. GCOM-C1. 2. - PowerPoint PPT Presentation

Citation preview

Page 1: GCOM-W1 Status

GCOM-W1 Status

Keizo Nakagawa1, Norimasa Ito1, Marehito Kasahara1, and Keiji Imaoka2

1 GCOM Project Team2 Earth Observation Research Center (EORC)

Japan Aerospace Exploration Agency (JAXA)

June 29, 2011

NCDC, Asheville

1

Page 2: GCOM-W1 Status

SGLI IRS (SRU)

SGLI VNR(SRU)

SGLI IRS (ELU)

SGLI VNR(ELU)

GCOM 1st Generation Satellites

2

GCOM-W1 GCOM-C1

Orbit Sun synchronous sub-recurrent orbit

Recurrence cycle 16 days 34 days

Altitude 700 km 798 km

Inclination 98.2 deg 98.6 deg

Local sun time of descending node 1:30 10:30

mass <1,991kg < 2,100kg

power > 3,880W > 4,000W

Mission instrumentAdvanced microwave scanning radiometer 2

(AMSR2)

Second-generation global imager(SGLI)

Design life 5 years

AMSR2 Sensor Unit

AMSR2 Control Unit

GCOM-W1

GCOM-C1

Page 3: GCOM-W1 Status

Deployable main reflector system with 2.0m diameter (1.6m for AMSR-E).

Frequency channel set is identical to that of AMSR-E except 7.3GHz channel for RFI mitigation.

Two-point external calibration with improved HTS (hot-load).

Deep space calibration maneuver to check consistency between main reflector and CSM.

Add a redundant momentum wheel to increase reliability.

GCOM-W1/AMSR2 characteristics

Scan and rate Conical scan at 40 rpm

Antenna Offset parabola with 2.0m dia.

Swath width 1450km

Incidence angle Nominal 55 degrees

Digitization 12bits

Dynamic range 2.7-340K

Polarization Vertical and horizontal

AMSR2 Channel Set

Center Freq.[GHz]

Band width [MHz]

Pol.Beam width [deg](Ground res. [km])

Sampling interval

[km]

6.925/7.3

350

VandH

1.8 (35 x 62)

1010.65 100 1.2 (24 x 42)

18.7 200 0.65 (14 x 22)

23.8 400 0.75 (15 x 26)

36.5 1000 0.35 (7 x 12)

89.0 3000 0.15 (3 x 5) 5

AMSR-EAMSR2

Overview of AMSR2

3

Page 4: GCOM-W1 Status

GCOM-W1 Progress

The system PFT started in August 2010. The electrical performance test, EMC test and Mechanical environmental test were over in February, 2011.

The earthquake occurred on March 11th, 2011 when preparation of thermal vacuum test was performed. Some parts of the walls in the test facility were broken down and the satellite was covered with the dust.

It took one month that another test facility (anechoic chamber) restored. GCOM-W1 moved to this facility and made cleaning and test. At the week of June 13th, the satellite came back to the same configuration as before the earthquake.

The end-to-end test including satellite and ground system was performed from June 22nd to 24th.

4

Page 5: GCOM-W1 Status

June 13June 13thth

Present GCOM-W1 Feature

5

Page 6: GCOM-W1 Status

Future Works and Ground Segment

GCOM-W1 Works until Launch- From July the preparation of thermal vacuum test (TVT) will start and

the TVT will be performed for almost one month in August.- After TVT additional acoustic test will be performed to confirm the

workmanship of the satellite re-assembling work. Then the final electrical performance test will be performed maybe until mid. October.

- The pre-shipment review is planned in late October. - The launch date will be determined at the end of August.

Ground Segment- GCOM-W1 ground system is completed except L2,L3 processing

software.- The end to end test with the satellite was finished in June.- The L2,L3 processing software will be completed in July.- The training and rehearsal will start 4 months prior to the launch.

6

Page 7: GCOM-W1 Status

4 5 6 8 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3

System integration

Electrical performance test(incl. EMC, Ground compatibility test)

Mechanical environmental test

Cleaning & Test

End to end test including groundsystem

Thermal vacuum test

Additional accoustic testElectrical performance test

Pre- shimment rewiew

Ready for shipment

Launch site campaign

J FY 2010 J FY2011

Earthquake on March 11th

GCOM-W1 Schedule

7

Page 8: GCOM-W1 Status

Current Status and Results

8

- 80

- 70

- 60

- 50

- 40

- 30

- 20

- 10

0

- 9 - 8 - 7 - 6 - 5 - 4 - 3 - 2 - 1 0 1 2 3 4 5 6 7 8 9

Rel

ativ

e ga

in [d

B]

Angle [degree]

Co- Pol. X- Pol.

AMSR2 PFM antenna pattern measurement (6.925 GHz)

Page 9: GCOM-W1 Status

Current Status and Results

9

GCOM-W1 PFM EMC test

Page 10: GCOM-W1 Status

Current Status and Results

10

AMSR2 antenna deployment test

Page 11: GCOM-W1 Status

Current Status and Results

11

0

0.2

0.4

0.6

0.8

1

1.2

1.4

1.6

H V H V H V H V H V H V H V H V

6.9G 6.9G 7.3G 7.3G 10G 10G 18G 18G 23G 23G 36G 36G 89GA 89GA 89GB 89GB

[Kel

vin]

NEDT@room temperature specification

AMSR2 PFM NEDT measured at room temperature

Page 12: GCOM-W1 Status

GCOM-W1 in A-Train

12

Page 13: GCOM-W1 Status

Inertia-lockStarts

Inertia-lockEnds

Simultaneous view of deep space by MREF and CSM

Consistency check

Deep space measurement as spatially uniform target

Scan bias identification

MREFView

CSMView

MREFView

CSMView

Deep Space Calibration Maneuver

13

Page 14: GCOM-W1 Status

Overview of SGLI

14

SGLI

VNR IRS

Visible and Near Infrared Radiometer(Non-polarization and Polarization)

Infrared Scanning Radiometer(Shortwave Infrared and Thermal Infrared)

Spectral Channels

Non-polarization: 11CH 380-865nmPolarization(0, 60, 120deg): 2CH 670,

865nm

SWI: 4CH 1.05-2.21μmTIR: 2CH 10.8, 12.0μm

Spatial resolution

250m, 1000m 250m-1000m

Scan type Push-broom electric scan Wisk-broom mechanical scan

Swath width 1,150km 1,400km

SGLI IRS (SRU)

SGLI VNR(SRU)

SGLI IRS (ELU) SGLI

VNR(ELU)

IRS(SRU)

VNR(SRU)

Page 15: GCOM-W1 Status

GCOM-C1 Progress

Critical design of SGLI is progressing by reflecting the results of EM test.

Mechanical test model (MTM) of GCOM-C1 was struck by the earthquake in Tsukuba but didn’t suffer from any damage. Mechanical tests are now progressing in the safe test building

Thermal test model (TTM) of GCOM-C1 will be tested in a vacuum chamber after finishing MTM test.

Critical design of GCOM-C1 satellite is progressing toward the critical design review (CDR).

15

Page 16: GCOM-W1 Status

GCOM-C1 Progress

16

GCOM-C1 MTM