Upload
wilma
View
47
Download
0
Tags:
Embed Size (px)
DESCRIPTION
GCOM-W1 Status. Keizo Nakagawa 1 , Norimasa Ito 1 , Marehito Kasahara 1 , and Keiji Imaoka 2 1 GCOM Project Team 2 Earth Observation Research Center (EORC) Japan Aerospace Exploration Agency (JAXA) June 29, 2011 NCDC, Asheville. 1. GCOM 1 st Generation Satellites. GCOM-W1. GCOM-C1. 2. - PowerPoint PPT Presentation
Citation preview
GCOM-W1 Status
Keizo Nakagawa1, Norimasa Ito1, Marehito Kasahara1, and Keiji Imaoka2
1 GCOM Project Team2 Earth Observation Research Center (EORC)
Japan Aerospace Exploration Agency (JAXA)
June 29, 2011
NCDC, Asheville
1
SGLI IRS (SRU)
SGLI VNR(SRU)
SGLI IRS (ELU)
SGLI VNR(ELU)
GCOM 1st Generation Satellites
2
GCOM-W1 GCOM-C1
Orbit Sun synchronous sub-recurrent orbit
Recurrence cycle 16 days 34 days
Altitude 700 km 798 km
Inclination 98.2 deg 98.6 deg
Local sun time of descending node 1:30 10:30
mass <1,991kg < 2,100kg
power > 3,880W > 4,000W
Mission instrumentAdvanced microwave scanning radiometer 2
(AMSR2)
Second-generation global imager(SGLI)
Design life 5 years
AMSR2 Sensor Unit
AMSR2 Control Unit
GCOM-W1
GCOM-C1
Deployable main reflector system with 2.0m diameter (1.6m for AMSR-E).
Frequency channel set is identical to that of AMSR-E except 7.3GHz channel for RFI mitigation.
Two-point external calibration with improved HTS (hot-load).
Deep space calibration maneuver to check consistency between main reflector and CSM.
Add a redundant momentum wheel to increase reliability.
GCOM-W1/AMSR2 characteristics
Scan and rate Conical scan at 40 rpm
Antenna Offset parabola with 2.0m dia.
Swath width 1450km
Incidence angle Nominal 55 degrees
Digitization 12bits
Dynamic range 2.7-340K
Polarization Vertical and horizontal
AMSR2 Channel Set
Center Freq.[GHz]
Band width [MHz]
Pol.Beam width [deg](Ground res. [km])
Sampling interval
[km]
6.925/7.3
350
VandH
1.8 (35 x 62)
1010.65 100 1.2 (24 x 42)
18.7 200 0.65 (14 x 22)
23.8 400 0.75 (15 x 26)
36.5 1000 0.35 (7 x 12)
89.0 3000 0.15 (3 x 5) 5
AMSR-EAMSR2
Overview of AMSR2
3
GCOM-W1 Progress
The system PFT started in August 2010. The electrical performance test, EMC test and Mechanical environmental test were over in February, 2011.
The earthquake occurred on March 11th, 2011 when preparation of thermal vacuum test was performed. Some parts of the walls in the test facility were broken down and the satellite was covered with the dust.
It took one month that another test facility (anechoic chamber) restored. GCOM-W1 moved to this facility and made cleaning and test. At the week of June 13th, the satellite came back to the same configuration as before the earthquake.
The end-to-end test including satellite and ground system was performed from June 22nd to 24th.
4
June 13June 13thth
Present GCOM-W1 Feature
5
Future Works and Ground Segment
GCOM-W1 Works until Launch- From July the preparation of thermal vacuum test (TVT) will start and
the TVT will be performed for almost one month in August.- After TVT additional acoustic test will be performed to confirm the
workmanship of the satellite re-assembling work. Then the final electrical performance test will be performed maybe until mid. October.
- The pre-shipment review is planned in late October. - The launch date will be determined at the end of August.
Ground Segment- GCOM-W1 ground system is completed except L2,L3 processing
software.- The end to end test with the satellite was finished in June.- The L2,L3 processing software will be completed in July.- The training and rehearsal will start 4 months prior to the launch.
6
4 5 6 8 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3
System integration
Electrical performance test(incl. EMC, Ground compatibility test)
Mechanical environmental test
Cleaning & Test
End to end test including groundsystem
Thermal vacuum test
Additional accoustic testElectrical performance test
Pre- shimment rewiew
Ready for shipment
Launch site campaign
J FY 2010 J FY2011
Earthquake on March 11th
GCOM-W1 Schedule
7
Current Status and Results
8
- 80
- 70
- 60
- 50
- 40
- 30
- 20
- 10
0
- 9 - 8 - 7 - 6 - 5 - 4 - 3 - 2 - 1 0 1 2 3 4 5 6 7 8 9
Rel
ativ
e ga
in [d
B]
Angle [degree]
Co- Pol. X- Pol.
AMSR2 PFM antenna pattern measurement (6.925 GHz)
Current Status and Results
9
GCOM-W1 PFM EMC test
Current Status and Results
10
AMSR2 antenna deployment test
Current Status and Results
11
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
H V H V H V H V H V H V H V H V
6.9G 6.9G 7.3G 7.3G 10G 10G 18G 18G 23G 23G 36G 36G 89GA 89GA 89GB 89GB
[Kel
vin]
NEDT@room temperature specification
AMSR2 PFM NEDT measured at room temperature
GCOM-W1 in A-Train
12
Inertia-lockStarts
Inertia-lockEnds
Simultaneous view of deep space by MREF and CSM
Consistency check
Deep space measurement as spatially uniform target
Scan bias identification
MREFView
CSMView
MREFView
CSMView
Deep Space Calibration Maneuver
13
Overview of SGLI
14
SGLI
VNR IRS
Visible and Near Infrared Radiometer(Non-polarization and Polarization)
Infrared Scanning Radiometer(Shortwave Infrared and Thermal Infrared)
Spectral Channels
Non-polarization: 11CH 380-865nmPolarization(0, 60, 120deg): 2CH 670,
865nm
SWI: 4CH 1.05-2.21μmTIR: 2CH 10.8, 12.0μm
Spatial resolution
250m, 1000m 250m-1000m
Scan type Push-broom electric scan Wisk-broom mechanical scan
Swath width 1,150km 1,400km
SGLI IRS (SRU)
SGLI VNR(SRU)
SGLI IRS (ELU) SGLI
VNR(ELU)
IRS(SRU)
VNR(SRU)
GCOM-C1 Progress
Critical design of SGLI is progressing by reflecting the results of EM test.
Mechanical test model (MTM) of GCOM-C1 was struck by the earthquake in Tsukuba but didn’t suffer from any damage. Mechanical tests are now progressing in the safe test building
Thermal test model (TTM) of GCOM-C1 will be tested in a vacuum chamber after finishing MTM test.
Critical design of GCOM-C1 satellite is progressing toward the critical design review (CDR).
15
GCOM-C1 Progress
16
GCOM-C1 MTM