Upload
phamxuyen
View
222
Download
0
Embed Size (px)
Citation preview
FAQs Page 2 of 18
Version Control
S.No Version No Date of Release Remarks
1. Ver1.0 27th Jun 2017
First Release of FAQs based on queries reported by users either
on helpdesk portal or through telephonic conversation. Finance
has been excluded
FAQs Page 3 of 18
Table of Contents
1. Access Management ................................................................................................................................................ 4
2. Proposal Management.............................................................................................................................................. 5
2.1. Project Application ........................................................................................................................................... 5
2.2. Initial Screening ................................................................................................................................................ 7
2.3. Qualitative Appraisal ........................................................................................................................................ 8
2.4. PAC-EC ............................................................................................................................................................ 9
3. Project Management .............................................................................................................................................. 11
4. Training Centre Management ................................................................................................................................ 12
5. Training Management ............................................................................................................................................ 13
6. Placement Management & Tracking ..................................................................................................................... 15
7. Project Monitoring ................................................................................................................................................. 17
FAQs Page 4 of 18
1. ACCESS MANAGEMENT
SN Question Possible Solution
1. Who will create the users in the MRIGS?
Only the admin users for MoRD, SSM and CTSA/ TSA are
created by the database administrator. All other users are either
automatically generated or are created by the respective
administrator of MoRD, SSM and CTSA/ TSA.
2. How many users can be created in the
MRIGS?
The MRIGS allows creation of indefinite number of users
under each stakeholder. There is no restriction on number of
users.
3. Can all users under a stakeholder access all
the processes?
The MRIGS is role based. Unless a required role is assigned to
a user, he/ she cannot access the process group/ procedure.
4. How do I create users in MRIGS?
First create the profile of the user using “Stakeholder” under
“Access Management”. Assign role using “User
Management” and submit the form. The default password will
be “p326@MORD”
5. How do I change my MRIGS password?
After logging into the MRIGS, click on your name on the top
right corner of the screen, you will find the option to change
the password. When you log-in for the first time, the MRIGS
will ask you to change the password.
6. Can my password be the same as previous
password?
You cannot use the last 4 passwords while changing the
password.
7. How to retrieve the password, in case I
forget it?
Go to ruralskills.in and Click on the tab “login”
Do not use the user id and password, and click on the link
“forgot password”
Enter Login id, a link on the email id associated with the user
id will sent to retrieve the password.
8. How do I (admin) block users, if they leave
the organization?
Go to user management: Click on right symbol against the user
from the list of the users - Change the status from “active” to
“inactive” in the first half of the screen
9. How can Admin reset password?
Go to user management under access management after login
through admin credentials, select the user and submit. The
password will be reset to default password.
10. How to unlock users?
At times, the user id gets locked due to wrong usage of
password multiple times (5 times) in a single day. In that case,
admin can unlock the user by using the unlock function under
access management.
11. What is difference between “Unlock
users”, Reset Password” and “Forgot
Password”?
“Unlock Users” simply unlocks the user and does not change
the password and is acted by the administrator.
“Reset Password” changes the password to default password.
May be used when the user has forgotten the password by the
administrator
“Forgot Password” is to retrieve the password by the users (not
by the administrator)
FAQs Page 5 of 18
2. PROPOSAL MANAGEMENT
2.1. PROJECT APPLICATION
SN Question Possible Solution
1. Which log-in id should a PIA use to file a
Project Application?
To file a proposal, the PIA has to use the PIA admin login
(PRN login). This is the only function allowed through admin
user id as a lot many PIAs are novice and giving the process in
user id would have created chaos and huge number of queries.
2. How does a PIA file a Project Application?
To file a project application, submission of “Organization
Profile” is pre-requisite. The organization profile is common
to all project application. Project specific parameters are
recorded through Project Proposal function under proposal
management process group.
3. Can a PIA change his organization profile?
Yes. A PIA can change his organization profile any time he
desires. Each time the PIA makes changes in the organization
profile, a new version of the organization profile is created.
4. Does changes in the organization profile
affect the already submitted proposal?
No. Any change in organization profile does not have
retrospective effect. The last submitted version on the date of
submission of a project application is freezed with the project
application and cannot be edited or changed.
5.
While accessing the Project Proposal
Module, the message is popping that NITI
Aayog registration is required.
The PIA should go to NGO Darpan portal and register with the
NITI Aayog. The registration details are required to be updated
in MRIGS through “NITI Aayog Registration” function
available under “Tools” process group.
6. Can a PIA make any changes in the
submitted Project Application?
No. Once a Project Application has been submitted by the PIA,
no changes are possible in the project application which
includes the last submitted version of the organization profile.
If a PIA is of the opinion that it has missed some information
in the organization profile or wrongly mentioned some data or
wrongly uploaded some document in the last submitted
version of the organization profile, it can always change the
data/ document which will create a new version of the
organization profile. The new version of the organization
profile will not impact previous project applications submitted
by it.
7. Are all parameters in the Organization
Profile mandatory?
No Parameters is mandatory in Organization profile unless the
user PIA declares the parameters as “Yes”.
8. If a PIA does not fill all parameters in
organization profile, what will be impact?
IF a PIA does not fill all parameters, as applicable, it may
impact the category and technical score and the parameter will
not be available for initial screening which may lead to
rejection of the project application during initial screening.
9. Who determines the project category? The project category is determined by the MRIGS based on
predefined logic.
FAQs Page 6 of 18
SN Question Possible Solution
10. What is the project category in case of a
project proposal submitted as consortium?
In case of consortium, the highest project category among the
participating PIAs is considered as the project category for the
project proposal.
11. If a Champion Employer is in consortium
and is not the applicant PIA, what will be
the project category?
If Champion Employer is not the applicant PIA and project
category of the champion employer is higher than the applicant
partner, the project category of the applicant partner will be
considered as project category. The project can be considered
as a project by a champion employer only when the champion
employer is an applicant partner.
12. How the project cost in a project
application determined?
The cost of a project in a project application is validated by
Project Cost Component with the fund eligibility. Welfare
Cost component is over and above the project eligibility.
13. When is a project considered as submitted?
In case a project application is being applied as “single”, it is
considered as submitted once the applicant PIA submits the
project application. In case of consortium, the application is
considered as submitted when the consortium partner approves
the project application. The date of submission will be the date
of approval by the consortium member.
14. Which Financial years are considered for
the project application?
The MRIGS does not allow application filing if financials of
2015-16 is not uploaded and declared “audited”.
15. Which financial years are considered for
calculating average turnover in MRIGS?
For non-NSDC partner applicants, FY 2015-16, 2014-15 and
2013-14 are mandatory and for NSDC partner applicant, FY
2015-16 is mandatory till June 30th, 2017.
16. Can a PIA submit an application with
technical score less than 10?
No. at the time of submission of the project application,
technical score is validated.
17. Can a PIA change the QA documents
submitted with the project application?
No. The PIA can provide additional document through
document upload section. Base documents (submitted with the
project application) will remain as submitted.
18. What is the maximum size of the document
that can be uploaded?
30 MB and for Financials and Curriculum and course content,
it has been increased to 60 MB.
FAQs Page 7 of 18
2.2. INITIAL SCREENING
SN Question Possible Solution
1. How many users are required for
completion of initial screening?
At least 2 operations users are required to complete the two-
staged Initial Screening procedure.
2.
We are not able to see all project
application in the initial screening module?
Project applications for Additional target and Industrial
internship will not be available for initial screening in the log-
in of SSM.
3.
When an initial screening of a project
application is considered as completed?
The procedure is considered as completed when the L2
(recommendation of the initial screening) has been submitted
by the L2 user.
4.
Can the same user perform on both the
modules – initial screening and
recommendation of initial screening?
No. The user who has performed initial screening will not get
the edit rights in recommendation of initial screening function.
5.
Is there any restriction on L1 and L2 users
for initial screening?
No. There is no restriction on specification of L1 and L2 users.
The only restriction is that the same user id cannot be used for
performing on both the modules.
6.
If L1 in initial screening has wrongly
process the project application, how to
correct it?
L2 (recommendation of initial screening) has the rights of
“send back to L1”
7.
If L2 in initial screening has wrongly
process the project application, how to
correct it?
After decision of L2, the initial screening stage is considered
as completed and mail of the decision is sent to the respective
PIA. There is no option to revert the decision of L2 in the
MRIGS. It can be done only after extraordinary approval of
MoRD.
8.
The “Submit” button does not appear at the
bottom of the screen in initial screening.
You have not verified the application fee submitted by the
applicant. Select decision on Payment decision and click on
“proceed”.
9.
Some documents are not visible as
required under notification 20/2017
The documents are not visible because the applicant has
chosen not to upload the document. If the applicant does not
declare a parameter as “yes”, documents are not demanded in
organization profile.
10. In some cases, financial certificate is
appearing but not the ITR.
The PIA has declared “No” against ITR. It also means that the
PIA has not filed ITR.
11.
If an appraisal response is “Yes” against
any of the special conditions in initial
screening, do I need to verify each
document with remarks?
No.
12. Is remarks mandatory for document
verification?
Yes. Whether the document is acceptable or not acceptable.
13. Can I submit the Initial screening form
without final remarks?
No
14.
Why 2 dates are being captured in initial
screening?
“Initial screening done on” is a user input and is expected to
be actual date of screening whereas “Initial Screening result
entered on” is system date, the date on which the form is being
submitted and cannot be changed by the user.
FAQs Page 8 of 18
SN Question Possible Solution
15.
What decision criteria are available for
Initial Screening?
For champion employers – Recommended for PAC-EC or Not
recommended for PAC-EC and for non-champion employers -
Recommended for QA or Not recommended for QA. L2 gets
an addition decision parameter – Send back to L1.
16. Is L2 required to follow the
recommendations of L1?
No. L2 can independently decide on the project application.
The decision of L2 is final irrespective of the decision of L1.
17.
What Additional roles does L2 play in
initial screening, if any?
Deciding on QA appraisal fee wherever required (non-
champion employers) and If other states’ QA has been
considered, no QA Fee will be required to be specified.
18. Can I see the proposal details of the project
application?
Yes. Link given in the top half of the form.
19. Can I see the list of other project
applications filed by the PIA?
Yes. Link given in the top half of the form.
20.
What happens if the project application is
not-recommended at Initial Screening
Stage?
The project application will appear in PAC-EC agenda as “For
information”
2.3. QUALITATIVE APPRAISAL
SN Question Possible Solution
1. How do we define the QA fee? Through “Project Appraisal Fee” module under Proposal
Management Process group.
2. When can we proceed with the QA? After submission of “Document Upload” form by the PIA.
3. What if the QA fee prescribed by the State
is 0?
Still the PIA has to submit through document upload as he/ she
has the privilege of providing additional document.
4. What if the PIA does not submit the
document upload form?
The privilege of the PIA will lapse and you can proceed with
the QA based on the base document.
5. How much time does a PIA get to submit
document upload form? 15 days excluding the date of completion of initial screening?
6. Can we accept the QA of other states for
our state?
Yes. The right is to be exercised during initial screening only.
If Initial screening has been completed without exercising the
option, you cannot consider the QA of other states.
7. What happens if the QA of other state has
been considered?
The project application is sent to PAC-EC agenda and QA
process is by-passed.
8. Can an applicant submit fee other than
prescribed?
The MRIGS does not validate the fee entered by the PIA. The
fee displayed is only for information to the PIA.
9. How do we calculate normalized score?
The scores are automatically displayed on selection of
appraisal parameter. Click on “Calculate Normalized Score”
and the normalized score as per notification 20/2017 is
calculated.
10. Can we print the Score Sheet of QA? Yes. Click on “View and download Score Card”.
11. Can the errors of L1 be corrected in QA? Yes. L2 has the discretion of sending back to L1.
FAQs Page 9 of 18
12. Which document are required to be
uploaded in QA by appraiser?
The distinction has been provided for Appraisal report, Score
Card and Relevant Document. Relevant document gives
option to describe the name of the document and multiple
document can be uploaded.
2.4. PAC-EC
SN Question Possible Solution
1. How to create PAC-EC Agenda? Go to “PAC-EC Agenda” module under proposal
management, click on “create PAC/EC agenda”.
2. Which project applications will appear in
PAC/EC Agenda?
Project Application which have been recommended in Initial
Screening (Champion Employers) and Qualitative Appraisal
(non-Champion Employers) and whose PIA Feedback has
been submitted by CTSA will appear in first half of the screen
for selection.
All not-recommended project applications will be displayed
for information of PAC/EC and will mandatorily form part of
the agenda?
3. Some project applications are not available
in PAC/EC Agenda?
The reason may be that the QA, or PIA feedback or Initial
Screening (for Champion Employers) has not been submitted
in the MRIGS by L2.
4. Some project applications are not available
in PAC/EC Decision L1?
The reason may be that the QA Decision date, or PIA feedback
date or Initial Screening Date (for Champion Employers) is
later than the proposed date of PAC/EC.
5. Will the “FYI” project application will
appear in next agenda?
No. once a project application has been considered in one
agenda, it will not be available in subsequent agenda except
one condition – Deferred.
6. We forgot to include some of the project
applications in the Agenda created.
Create a new agenda with the same date of first agenda and
select the project applications and submit. The new agenda
will be termed as supplementary agenda and will appear in
PAC/EC decision along with the primary agenda.
7.
PAC/EC has decided on changing the
project proposals of the applicant PIAs,
either reduction in target/ increase in
target/ districts proposed for training/
trades proposed by the applicant etc. How
do we modify in the system?
In PAC/EC Decision L1 and approved by L2, select option
“Approved with changes”, the proposal will be opened in edit
mode in PIA login and the PIA can modify as per the
instructions recorded in PAC/EC Decision L1. After
submission by the PIA, the proposal has to be approved again
using L1 and L2 of PAC/EC decision.
8. The applicant did not align the project
proposal when approved with changes? Resend the proposal with “Approved with changes”.
9. We have submitted each proposal in L1 but
no project application appears in L2.
Probably you have not submitted the L1 form. After taking
decision on each project application, the PAC/EC form is also
required to be submitted.
10.
A proposal was supposed to be approved
with changes but was wrongly “approved”
by L1.
L2 can send back the proposal back to L1 for amendment of
decision.
FAQs Page 10 of 18
SN Question Possible Solution
11.
L2 also wrongly approved the proposal
with wrong decision, how to correct the
situation?
L1 and L2 can send back the proposal to PAC/EC Decision L1
through Sanction Order recording module.
12. A proposal was wrongly approved in
Sanction Order Recording, including L2.
The defined process of database reversal approval is to be
adopted.
13.
Can secondary agenda be generated after
PAC/EC Decision L1/L2 has been taken
for any date of proposed PAC/EC Agenda?
No. the agenda is considered as completed.
14.
Can we generate an agenda for a different
date but record the same date of actual
PAC/ EC in PAC/ EC Decision L1
module?
No
15. How can we download the Agenda? Click on download on the dashboard and the PDF of the
agenda is displayed which can be downloaded.
16.
How can we download the comprehensive
summary of the appraisal of a project
proposal?
Open the agenda, click on the download against any of the
proposal, the comprehensive summary of initial screening, QA
and PIA feedback with brief summary of the proposal is
displayed for presenting before PAC. The same can be saved.
17. What should be done after recording
sanction order? PPWS is to be filled by the PIA for the sanctioned project.
18. When can a PIA fill the PPWS? Once the sanction order has been recorded, PPWS can be filled
by the PIA under Project Management.
19. What are other steps after PPWS to be
completed by SSM?
Go to project management process group and record the
procedures in sequence – MoU -> Fund Release -> PCO under
Project Management and the project commencement date will
be set for the project. Without PPWS, MoU cannot be
submitted.
20. What is required under MoU?
Under MoU, scanned copies of all the documents required to
sign MoU – Sanction order signed by PIA, MoU, Standard
Terms & Conditions, any Special Terms and Conditions, any
revision of sanction order, any revision of MoU, bank details
and document etc.
FAQs Page 11 of 18
3. PROJECT MANAGEMENT
SN Question Possible Solution
1. Is PPWS required to be approved by SSM? Yes. After approval, the PPWS is freezed.
2. When can a PIA submit PER? After the project has been sanctioned.
3. Is PER required to be approved by SSM? Yes.
4. Can PER be sent for modification? Yes.
5. Why is meant by Sanctioned Project Set-up
and Proposal Conversion?
These two are exceptional modules for taking onboard the
projects which were a) received offline and sanctioned offline
(sanctioned project set-up) or b) proposals were received online
and sanctioned offline without following the online appraisal
process.
6. Can we use these modules to sanction
projects?
No. These are exceptional modules and the authority of approval
lies with MoRD. These modules are mutually exclusive to each
other and the online appraisal process.
7. How to sanction projects sanctioned before
March 31st, 2016?
It is two stage procedure. Once recommended by L1 through
“Sanctioned Alignment Recommendations” and approval by L2
through “Sanctioned Alignment Approvals”.
8. Can the sanction alignment proposed by
PIAs be modified?
Using the L1 and L2, the projects aligned to CNN can be sent for
modification with instructions. The projects can be modified by
the concerned PIA only.
9. Is there any time limit for the PIA to resubmit
the projects sent for modification? Yes. 15 days.
10. What if the PIA does not align within the
stipulated time frame?
Resend the project for modification using the procedure
explained above.
11. When can a PIA start batches?
Before starting batches, the pre-requisites are – DD approval of
the training center, Curriculum design followed by Training Plan
creation (activity planner) and registration and selection of
candidates.
12. Can curriculum designed for one project be
used for another project?
Yes. Provided the training duration of each component of the
course (group of trades) is exactly the same.
13. Is PIA required to design training plan for
each project separately?
No. The training plan designed for one project can be imported
for another project provided the training duration of each
component of the course (group of trades) is exactly the same.
14. Can an executive of the PIA be assigned
multiple projects?
Yes. Using Project Assignment, PIA has to indicate the
assignment of executive to different projects.
15. How does a PIA indicate internal placement
target provided in the SOP?
“Internal Placement Target” under “Project Management”
process group.
16. What is GP saturation?
As defined in DDU-GKY policy, a PIA is required to suggest the
village panchayats where it intends mobilize candidates in a
block/ district. The GP saturation is also subject to approval SSM.
17. Can a project be closed? A project can be closed using “Project Closure” Module.
18. What is the impact of Project Closure? No operation can be performed related to the project.
FAQs Page 12 of 18
4. TRAINING CENTRE MANAGEMENT
SN Question Possible Solution
1. What is Centre Allocation?
Center Allocation means a training centre infrastructure,
residential facility infrastructure and human resources are
clubbed together by operations and are proposed by PIA Ops
to Q Team for Due-Diligence.
2.
Why there are separate modules and not
one module for Centre creation for a
project?
The modules have been segregated to create unique identities
of each component (TC Infrastructure, Residential facility and
Human Resources) so that the changes in each component of
centre can be considered when a centre is operational. For
example, a trainer may be transferred from one centre to
another centre which is independent of approval of the training
centre, additional trainers may be assigned to the training
centre. The training infrastructure may be used for another
project (multiple allocation of a training centre/ residential
facility).
3. What is “Edit Allocation”?
This function is available with SSM to send an approved centre
for modification which may be requested by a PIA for changes
in Trades or amendments in training centre infrastructure or
residential facility(s).
4. What is meant by Active/ inactive centres
in the MRIGS?
The status of the centre may be changed to Active/ Inactive is
simply to indicate that there is no training going on in the
centre assisting the SSMs to schedule inspection. The change
in status does not affect any operation related to the Training
Centre. This is only informative and has no practical impact on
data processing.
5. How is it different from Closed Centre?
If a centre is marked closed, no operation can be performed
related to the training centre like inspection, placement, desk
verification or physical placement, financial transaction
related to the centre etc. A centre closed means closed forever
and all the resources are freed to be allocated to any other
project or the same project.
6. Can a PIA update the status of failure of
equipment through MRIGS? Yes. Through TC-Daily Facility Update.
7. Can training continue after closure of
residential facility?
Yes. Residential facility may be closed using “Residential
Facility Close” function and all enrollment will be non-
residential as there will be no residential facility attached to the
centre.
FAQs Page 13 of 18
5. TRAINING MANAGEMENT
SN Question Possible Solution
1. When can a PIA start registration of
candidates (recording mobilization)? After allocation of training centre to a project by OPS Team.
2. Is complete data is required during
mobilization?
No. The registration will be in draft mode. Mandatory fields and
documents will be required for submission of registration form.
3. What is meant by “Selection of Candidates”?
“Selection of Candidates” is internal check procedure in which
only those candidates appear whose registration form has been
submitted.
4.
Can a candidate registered through one
centre be transferred to another centre if the
candidate wishes to enroll in program being
run by the other centre?
Yes. If a candidate is not enrolled or has been dropped out can be
transferred to another centre using “Candidate Search and
Transfer Request”. A candidate may be retained by a training
centre for a period of 90 days from the date of registration. If
transfer request is not approved by the transferor PIA, the
candidate is automatically transferred after 48 hours (2 days).
5. I am not able to see the trades (trade codes)
sanctioned under the project?
It may be possibly due to non-approval of the sanction alignment
proposed by you. Any new trade will be available for selection
only after approval of sanction alignment by concerned SSM.
6.
I am not able to find training plans for the
trades selected during batch creation though
I have prepared the training plan?
Check the trade code for which you have prepared the training
plan (especially before CNN alignment) and the trade code that
you requested for due-diligence. Important fact is “Trade Code”
and not the trade name.
7.
The batch size being displayed is less than
the batch size approved by CTSA during
due-diligence.
The batch size is calculated as prescribed in SOP (10 sqft for
individual training type or 15 sqft for combined training type) and
the batch size will be lowest of the room capacity. E.g., if the
capacity of theory room is 35 but for the practical room it is 32
and IT room it is 30 (no split batch is proposed), the batch size
will be 30 trainees.
8. What is “batch split”?
Batch split is basically splitting of a batch into two groups for
conducting training in IT/ Practical lab for better utilization of TC
capacity. This does not give any separate batch code for the split.
9. When a batch split is determined? Batch Split has to be indicated during creation of a batch with
defined number of trainees in each split.
10. Is it mandatory to assign trainers to a batch? Yes. For domain as well as non-domain trainers. The trainers are
verified during inspection for their training quality.
11. Can we change the batch start date? Yes. The change in batch start date is allowed before the start date
of a batch.
12. Can I delete a batch? Yes. Provided there is no enrollment made into the batch.
13. Can we enroll before start date of a batch? Yes.
14. After start date of a batch, how long can I
replace the enrolled candidates?
Till batch freeze date (10 days from the batch start date. Batch
start date is inclusive).
15. Can I reset the start date of a batch?
Yes. A PIA can only propose for batch reset. The batch reset is
effective only after approval from SSM/ TSA/ CTSA. A complete
trail is maintained.
FAQs Page 14 of 18
SN Question Possible Solution
16. What is Candidate De-registration and
Manual drop-out?
Candidate de-registration can be done within batch freeze period
for replacement of trainees and manual drop-out can be done after
batch freeze period. Both functions are mutually exclusive.
17.
I am not able to enroll a candidate in a batch
and the message displayed is there is no
vacant seat.
The batch size is determined at the time of batch creation and
enrollment in a batch is not possible beyond the freezed batch
size.
18.
I am enrolling candidates in residential
facility and it is showing there is no
residential facility available.
You may have selected both the genders for enrollment whereas
the residential facility is either for male or female candidates.
Select one gender at a time to enroll in a batch and allot the
residential facility.
19.
I am enrolling a candidate in a residential
facility but it shows no vacant seat is
available.
You may have already allotted trainees the residential facility in
previous batches and since the previous batches are not closed,
residential facility is not free for fresh allotment. Close previous
batches to free space in the residential facility.
20. Can I close a residential facility while a
residential training is in progress? No.
21.
If there is need to close a residential facility
while a residential training is in progress,
how do I do it?
Only after transfer of the batches in progress or termination of
batches in progress, which will free the residential facility for
closure.
22. Can I close a training centre while training is
progress?
No. only termination is possible which will terminate all batches
in progress.
23. Who can terminate a training centre or a
batch?
Training centre or a batch in progress can be terminated only with
the approval of SSM. PIA Ops can only propose.
24. Can I close a batch in future date? No. Batch can be closed as on date or a past date but not prior to
batch start date.
25. How do I update daily training deliveries? Using “Training Progress Update” function under Training
Management Process Group.
26. How can I record the internal assessments
conducted while training is in progress?
Using “Internal Assessment” function under Training
Management Process Group.
27. Can OJT be recorded in the MRIGS?
Yes. OJT Plan can be submitted through “OJT Plan Submission”,
Actual placement in OJT through “OJT Placement” and
Certificates through “OJT Certification" function under Training
Management Process Group.
28. How can we record external assessment
results and certification?
The participation of each trainee in External assessment is
recorded through “External Assessment” function. The results are
recorded through External Assessment Results and Certification”.
Each certificate number and copy is required to be uploaded by
the PIA.
29. How to record the assessment of
unsuccessful or ineligible trainees?
The certificate issued by the PIA to unsuccessful or ineligible
trainees is recorded through the same module and is determined
and segregated by the MRIGS.
FAQs Page 15 of 18
6. PLACEMENT MANAGEMENT & TRACKING
SN Question Possible Solution
1. I am not able to find the employer while
recording the appointment of a trainee?
The employer or the work location under the employer has not
been recorded in the MRIGS.
2. Do I need to create employer or the work
location for each candidate employment?
No. An employer or work location recorded by one PIA is
available for all other PIAs. Therefore, search for the employer
form the search option before creating a new record.
3.
Are Employer records/ Workplace
locations/ Employment Agency required
to be verified?
Yes. But currently the facility has been waived off due to lack
of resources at the end of approving authority.
4.
The candidate has been placed through a
placement agency which is providing the
salary slips. The organization where the
trainee works does not give any salary slip.
How to record the placement?
Such placements are called “outsourced placements”. Create
the placement agency under “Employment Agency” under
Placement Management. While appointing the candidate
(using the Appointment Module), select “on employment
agency payroll” and select the employment agency. The
employer (where the candidate will work) and the work place
is to be selected as done in case of direct employment.
5. What is monthly continuity?
Monthly continuity is to record the employment of the
candidate in each month. The function records not only data of
employment in the month but also the documentary evidence
of the employment for the month.
6.
I got only one document as evidence of
employment, can I still record the monthly
continuity?
Yes. But, you will not be able to verify the candidate as B1
(tracking).
7.
How do I update the second document
when it is received later or correct the data
of employment wrongly entered?
Under tracking, you are provided the facility to rectify the
records – “CTC Edit”.
8. The candidate has left the current job and
has joined another job.
Use “Separation” function to separate the candidate from the
existing job in the MRIGS and use the appointment function
to record new employment.
9. I am not able to submit the new
appointment after separation.
Check on the date of joining of the new job. It cannot be less
that the date of separation from previous job.
10. The candidate has been transferred to a
new work location by the employer.
User “Change in Work Location” to record the change in work
location within the same employer. IF the work location has
not been recorded earlier, record the work location details
under the employer using “Employer Work Location”.
11. If I do not change the work location, how
does it matter as the employer is the same?
During the physical verification of placement, the candidate
will not be available at the work location which has been
indicated in MRIGS hence may be considered as unemployed.
12. I am getting B2 option while tracking the
candidate?
The minimum CTC may be less than the prescribed norms or
both the documents as evidence of employment are not
uploaded in monthly continuity/ CTC edit.
13. For how many months, can I track a
candidate?
Two options are provided. First is within 12 months from the
batch closure month and the other is after 12 months from
FAQs Page 16 of 18
SN Question Possible Solution
closure of a batch. Thus, a candidate can be tracked till project
closure.
14. I am getting message that UAN is required
while submitting monthly continuity.
If the PF deduction is recorded in salary details, UAN of the
candidate will be mandatory except for the month of joining.
15.
I have entered wrong data in Appointment
of a candidate and also recorded the
monthly continuity.
Till the time the candidate has been tracked (Verified as B1/
B2), the record can be deleted in reverse order using
“Placement Management” under Tools. No approval is
required from the regulatory body as the data has not been
submitted as B1 or B2.
16. I wrongly tracked the candidate as B1/ B2.
How to correct the record?
By using Tracking Management under Tools, a PIA can make
request to the concerned SSM/ TSA for deletion of the
tracking. After approval from the concerned SSM/ TSA,
follow the Placement Management to correct the record for the
relevant month.
17. I get mandatory B1 even after 3 months of
tracking.
B1 Tracking for Three months out of four consecutive months
is required to consider the candidate as placed under DDU-
GKY. However, B1 Tracking is required if a candidate has
financial implications and the B1 tracking may be required for
first 6 months from the month of first joining of job by the
candidate and if the candidate is placed outside the state of
domicile, there is financial implication and B1 tracking will be
mandatory if monthly continuity has been recorded.
18. May I track a candidate as B2 after 6
months from the month of job joining?
Yes. Even if monthly continuity has been recorded in the 7th
month and onwards and the candidate fulfils the minimum
CTC criteria, B2 option can be exercised. B1 becomes
optional.
19.
What is the impact of B2 tracking after 6th
month even if candidate is eligible for B1
tracking?
You may lose on retention incentive that may accrue to you for
the candidate.
FAQs Page 17 of 18
7. PROJECT MONITORING
SN Question Possible Solution
1.
The Q Team of a PIA has wrongly reported
center due-diligence, what should I (SSM)
do?
You can send back the due-diligence for modification. PIA
Ops will resubmit the allocation for due-diligence by Q Team
and then it will come to SSM for approval.
2.
There is change of trade at an approved
centre, how do we incorporate such change
of trade?
Send back the centre allocation for modification using “Edit
Allocation” function for incorporating the changes in the
centre by PIA Ops, which will be checked by PIA Q Team
(due-diligence) and the centre will come for approval of SSM.
3.
When I go try do inspection using
inspection module, I do not find any record
for carrying out inspection.
Create Sample is pre-requisite to Inspection. If you have not
generated sample before accessing Inspection, the inspection
module will ask for create sample.
4. I created a sample but did not initiate
inspection. Can I use the sample next day?
A sample can be generated between 8:00 am till 8:00 pm and
has to be used on the same day. The sample will lapse if not
used on the same date and has to be generated a fresh next day.
5. I am not able to generate a new sample for
the same centre.
The previous inspection was initiated but not closed
(submitted). Two parallel samples cannot be generated. Only
one sample will be active at a time.
6. Can I discard a sample after initiating an
inspection?
No. as the candidate data is displayed once inspection is
initiated.
7. IF Q team did not complete inspection, can
SSM initiate inspection? Yes. Samples are specific to stakeholders.
8. How do I initiate surprise inspection?
There is no difference in regular or surprise inspection in the
MRIGS. You have to select the type of inspection and the
inspection will be marked as regular or surprise.
9. How do I raise advisories for discrepancies
found during inspection?
In each Tab of Inspection, add Advisory tab is given which
gives predefined heads and sub-heads for raising advisories.
You can put your specific remarks and if some predefined
head/ sub-head is not available, you can select others and raise
advisories.
10. How do I know the status of previous
advisories?
In inspection, previous advisory status with details are
displayed in each section of inspection form.
11. How to close advisories?
Once an advisory has been issued, it has to be complied by the
PIA Ops and closed by the respective stakeholder who raised
the advisory(s) using the Advisory closure module.
12. What is meant by closure of advisory? Closure of an advisory means a decision has been taken –
either accepted or rejected.
13. If I am not satisfied with the compliance of
the PIA Ops, what should I do?
If you are not satisfied with the compliance, you can demand
additional compliance from the PIA using the option in
Advisory closure module.
14. If I reject a compliance, what will happen? The rejected advisories are converted to default for which
default alerts can be issued.
15. What is Upload Legacy Inspection? This module has been provided to record inspections already
carried out in past so that inspection counts and advisories are
FAQs Page 18 of 18
SN Question Possible Solution
recorded. This function should not be used for current
inspections.
16. How do we carry out desk inspection?
Q Team/ TSA can do desk verification of placements based on
B1 submitted by the PIA Ops. It allows for two months B1 for
desk verification by each stakeholder.
17. How do I generate sample for desk
verification?
The MRIGS will generate samples as described in SOP for
each stakeholder.
18.
Can a PIA request for deletion of B1
verification submitted by it after
completion of desk verification?
No. all tracking and placement data is freezed for the month
after desk verification.
19. What changes in records proposed by a
PIA will require an approval of SSM?
The following change request will require approval of SSM:
1. Batch Reset Request
2. Batch management, consisting of
a. Enrollment Request
b. De-register Request
c. Drop-out Request
d. Reinstate Request
e. Change OJT (in Batch creation) Request
3. Tracking Management
a. B1/ B2 deletion
4. Change in Training centre parameters after approval
20. What changes in records by PIA will not
require an approval of SSM?
Manage Human resources – change in Human resources of the
PIA, batch deletion without any enrollment, Trainee
Information update, Trainee de-register within batch freeze
period, Manual drop-out after batch freeze period will not
require any approval from SSM.