23
2473-36 Joint ICTP-IAEA School on Nuclear Energy Management P. Warren 15 July - 3 August, 2013 IAEA, Vienna, Austria Financing Structures for a Nuclear Power Plant Project

Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

2473-36

Joint ICTP-IAEA School on Nuclear Energy Management

P. Warren

15 July - 3 August, 2013

IAEA, Vienna, Austria

Financing Structures for a Nuclear Power Plant Project

Page 2: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA International Atomic Energy Agency

Financing Structures for a Nuclear

Power Plant Project

ICTP/IAEA Nuclear Energy Management School 2013

Paul Warren

Planning & Economic Studies Section

Page 3: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Plan of presentation

Presentation outline:

1. Key dimensions of financing structures

2. Risk premia

3. Risk allocation and financing cost

4. Takeaways

2

Page 4: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Financing structure

3

Owner/

Operator

Commercial

banks

Shareholders Host

government

Electricity

Utility

Fuel supplier

EPC

contractor

Export credit

agencies

Multilateral

agencies

Shareholder

agreement Fuel

supply

agreement

EPC

contract

PPA

Loan

agreement

Loan

guarantee

Political

risk

insurance

Political

risk

insurance

Page 5: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

How can financing structures differ?

• How can financing structures differ between

projects?

• Structures can differ along five key

dimensions:

1. Debt versus equity

2. Ownership

3. Contracting

4. PPAs

5. Recourse

4

Page 6: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

1. Debt versus equity

5

Owner/

Operator

Commercial

banks

Shareholders Host

government

Electricity

Utility

Fuel supplier

EPC

contractor

Export credit

agencies

Multilateral

agencies

Shareholder

agreement Fuel

supply

agreement

EPC

contract

PPA

Loan

agreement

Loan

guarantee

Political

risk

insurance

Political

risk

insurance

Page 7: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

2. Ownership: a more traditional model

6

Power

Purchase

Agreement

Private

Shareholders

Utility

Owner/

Operator

Fuel supplier

EPC

contractor EPC

contract

Taxpayers

Fuel supply

contract

NSSS

supplier

Equipment

contract

?

Ratepayers

Loan

agreement Bank

Page 8: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

2. Ownership: a more recent model

7

Power

Purchase

Agreement

Utility

Developer Fuel supplier Fuel supply

contract

Ratepayers

Loan

agreement Bank

Host

Government

Shareholder

agreement

Sovereign

Guarantee

EPC

contractor

NSSS

supplier

Page 9: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

3. Contracting

8

Commercial

banks

Shareholders Host

government

Electricity

Utility

Fuel supplier

EPC

contractor

Export credit

agencies

Multilateral

agencies

Owner/

Operator

Shareholder

agreement Fuel

supply

agreement

EPC

contract

PPA

Loan

agreement

Loan

guarantee

Political

risk

insurance

Political

risk

insurance

Page 10: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

3. Contracting: contract language and risk

“The contractor undertakes to construct a

power plant with a (net) capacity of 900MWe

for the sum of 4 billion USD.

The contractor will pay for replacement

power for each day in excess of 10 in any

year in which unplanned outages exceed 10

days.

The contractor will also pay for replacement

power for every day on which the plant is not

synchronized to the grid after January 1,

2018, except for delays caused by

unreasonable regulatory performance.”

Schedule

delays

Design

performance

not achieved

Regulatory

delay

Design

capacity not

achieved

Construction

cost overrun

9

Owner/Operator

EPC contractor

Page 11: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

4. Power Purchase Agreements (PPAs)

10

Commercial

banks

Shareholders Host

government

Electricity

Utility

Fuel supplier

EPC

contractor

Export credit

agencies

Multilateral

agencies

Owner/

Operator

Shareholder

agreement Fuel

supply

agreement

EPC

contract

PPA

Loan

agreement

Loan

guarantee

Political

risk

insurance

Political

risk

insurance

Page 12: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

5. Recourse

11

Commercial

banks

Shareholders Host

government

Electricity

Utility

Fuel supplier

EPC

contractor

Export credit

agencies

Multilateral

agencies

Owner/

Operator

Shareholder

agreement Fuel

supply

agreement

EPC

contract

PPA

Loan

agreement

Loan

guarantee

Political

risk

insurance

Political

risk

insurance

Page 13: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Shifting risk away risk premia

12

Commercial

banks

Shareholders Host government

Electricity Utility

Fuel supplier

EPC contractor

Export credit

agencies

Multilateral

agencies

Owner/

Operator

Shareholder

agreement

Fuel supply

agreement

EPC

contract

PPA

Loan

agreement

Loan

guarantee

Political risk

insurance

Political risk

insurance

• As you put together your project as an Owner/Operator you can

offload risk – but there’ll be a cost of doing so: a risk premium

Page 14: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Risk premium example

• Consider the development of a 15-year agreement

between an NPP owner/operator (e.g. a utility) and

a nuclear fuel supplier

• Price of U3O8 (as well as the prices of SWU, zirconium

etc.) is subject to escalation risk

• If the NPP owner were to insist on a price for fuel which

was fixed throughout the contact, fuel supplier would

demand a risk premium

• Risk premium would be reflected in the fuel price

13

Page 15: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Risk premium example

• Suppose the U3O8 price for the duration of the

contract was projected to average $100/kg

• Consistent with fuel price of p* per fuel assembly

• If the fuel supplier took the risk it would insist on a price

of p' where p' > p*

• p ' - p* is the risk premium

14

Page 16: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Intuitions on risk premia

• Premium paid by OO to shift risk to the other side

of a contract (‘counterparty’) will depend on:

1. Size of the risk • Volatility

• Monetary value

2. Counterparty’s financial capacity relative to the

size of the risk • A small party, with limited financial capacity might be willing to

bear a large volatile risk, but….

• …it will demand a large risk premium for doing so

3. Counterparty’s risk appetite

4. Couinterparty’s ability to control the risk

15

NB!

Page 17: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Contracting net income

16

Owner/

Operator

Electricity

Utility

Fuel supplier

EPC

contractor

Fuel

supply

agreement

EPC

contract

PPA

Commercial

banks

Shareholders

Shareholder

agreement

Loan

agreement

Net income

Page 18: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Risk allocation and financing cost

• Potential financers will be concerned about the risk

(“default risk”) that the owner of the project will be

unable to pay dividends, or to repay some part (or

any) of the principal or interest on the loan

• Default risk associated with volatility of net income

• Default risk associated with a project will be a

concern for equity investors and lenders

• This makes it a concern for the project owner as

well: the higher the default risk that financers

perceive in a project, the more they will charge

to finance!

17

Page 19: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

All risk is financial risk!

18

Owner/

Operator

Electricity

Utility

Fuel supplier

EPC

contractor

Fuel

supply

agreement

EPC

contract

PPA

Commercial

banks

Shareholders

Shareholder

agreement

Loan

agreement

Volatility of net

income =

financial risk

Page 20: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Interest During Construction (IDC)

19

• Given the size of the capital

investments needed, and

length of time over which

construction can stretch

financing crucial!

• With an interest rate of 10%

p.a. and a seven year

construction period, a total OC

of $5750M gives rise to IDC of

$2780M

• Reducing the interest rate by 1%

reduces IDC by $326M

• Reducing the construction period

by one year – even by adding all

Y7 spending to Y1 – reduces IDC

by $390M

0

200

400

600

800

1000

1200

1400

1600

1800

2000

1 2 3 4 5 6 7

$M

Construction period

Page 21: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Takeaways

1. The way an NPP project is structured financially

is all about allocating risk

2. As you put together your project as you can

offload risk – but there’ll be a cost of doing so: a

risk premium

3. For financing purposes, all risk should be

regarded as financial risk

20

Page 22: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA

Financing TECDOC CMs

• Document is currently being prepared

• Authors (5) are investment banking professionals

• Extensive financing experience in energy and nuclear ‘space’

• Framework, contents and topics set out by IAEA

• Document will constitute a “textbook” (a comprehensive set

supporting material) for future Expert Missions on financing

• Two Consultancy Meetings (CMs) will be held in

Vienna in November

• Purpose is to get feedback from potential users (i.e. Member

States)

• Contact: [email protected]

21

Page 23: Financing Structures for a Nuclear Power Plant Projectindico.ictp.it/event/a12196/session/94/contribution/64/material/0/0.pdf · 2473-36 Joint ICTP-IAEA School on Nuclear Energy Management

IAEA 22

Thank you!

…atoms for peace