GLOBAL SOLAR EPC
SUMMIT 2012
16th & 17th May,
Eros Hilton, New Delhi
Organized By
www.renewablemarketsindia.com
7/28/2019 Epc Summit
2/41
Criterion for Selection ofEPC Partner
Presented by - B N Bhardwaj
May 16 , 2012
Electrotherm Immodo Renewables Ltd.
Global Solar EPC summit India
2012
7/28/2019 Epc Summit
3/41
Solar projects
1. Licensee / PPA regime :-
Projects allotted by NVVN
Projects allotted by States
2. Renewable Energy Certificate (REC) mechanism3. Renewable Purchase Obligations (RPO)
4. Allocation of projects linked with setting up of solar
manufacturing facilities
5. Roof top projects arising out of policies by MNRE andvarious states
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
4/41
What is there in Store National solar Mission ----- to achieve 20000 MW by
2020
Gujarat Planning to add 5000 MW of solar PV Plants
Rajasthan Developing a global hub of solar power andhas a target of 10000-12000 MW in the long term
Karnataka 80 MW
Madhya Pradesh bidding process already over. States
like Rajasthan, Maharashtra, Tamil Nadu and Andhra
Pradesh are in various stages of bidding process.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
5/41
Contd..
World wide 2012 may see a capacity addition of 20-30GW around the world.
Main capacity addition will be contributed by China and
India, followed by the southeast Asia, Latin America,the Middle East and North Africa in the next five years.
MNRE and many states are now in the process of
forming Roof top policy.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
6/41
NodalAgencies
Developer
Discoms
State
Govt.
NVVN /
MNRE
Financial
Institutions
Local
Admn
Custom Excise
Electrotherm Immodo Renewables Ltd.
Stake Holders
7/28/2019 Epc Summit
7/41
EPC for Solar PV - Definition
Under an EPC contract, the EPC Provider willEngineer/Design the installation, Procure the necessary
materials and Construct the PV Installation. The EPC
Provider bears the projects risk not only in terms of
timing but also in terms of budget
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
8/41
EPC Roles
Electrotherm Immodo Renewables Ltd.
Investor
EPCIntegrator
DevelopingLegal &
Financial
advice
Engineering Procurement ConstructionO & M
Full
Services
7/28/2019 Epc Summit
9/41
EPC - Definition
An Investor/Owner chooses an EPC Provider for severalcritical reasons, that is:
EPC approach ensures quality and minimizes risks,
EPC gives the Investorone point contact, facilitating
its monitoring and coordination
Owner is not affected by the market componentsfluctuations, since the Investment amount is known at
the start of the project.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
10/41
Reasons for EPC contract
Reduced stress for owner
Single point of contact for owner simplifies execution
and communications.
Ready availability of post-commissioning services
Ensures quality construction and reduces practical issues
faced in other ways
Owner is protected against changing prices for materials,
labor, etc.
Cost is known at the start of the project
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
11/41
Points to consider
Scope and the specifications of the plant
Quality
Project duration
Cost
The cost (the price to be paid to the EPCC) is negotiated
and finalized and paid in mutually agreed installments.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
12/41
Why EPC is important
The project installation in Solar PV Power project is a crucial
step as it involves perfect planning, technical expertise and
right execution strategy
Selecting right EPC provider holds key to successful and
sustainable business revenue for developer
Project requires right PMC skills to keep watch on milestonesand EPC work quality during project installation.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
13/41
Role of EPC in solar
An EPC Contractor executes a Solar Power Plant projecton turnkey basis, which includes plant design &
engineering, procurement and construction at site.
The EPC Contractor is responsible for delivering thesolar plant within agreed cost, time and with desired
quality
The EPC Contractor guarantees plant performance, thusenabling the project developer to avail finance from their
banking partners.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
14/41
Criterion for EPC partner
EPC company shall be backed up with:- Vast experience
World wide presence
Experience of working under different conditions
Execution of project in given time frame . Revenue is
directly linked to time taken by EPC contractor.
In house manufacturing and technical capabilities
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
15/41
Contd..
In house ready availability of construction equipments
like:-
Diesel Generator,
Porta cabins,
Portable diesel lights,
Hydra, crane, Fork lift etc.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
16/41
Criterion for EPC Partner -
Operation & Maintenance
Should have experience of managing solar assets and
assure performance globally.
Provide additional value at market prices analyzingproduction daily with optimization software.
Control system accessible to an investor/banker daily by
cell phones or through password protected on-line accessfor each specific project for stakeholders to see
operations in anywhere in the world .
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
17/41
How EPC achieves its objective
Realistic planning and scheduling
Efficient and economic design of plant
Source material & equipment globally from proven
manufacturers
Manage logistics of delivering material & equipment to
site.
Expediting delivery to ensure project is completed on
schedule
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
18/41
Cost optimization that includes using designs based on
local standards, reducing manufacturing cost, forming
strategic alliances, maximizing local content, and
standardizing the power block design.
Clear and clean installation of panel, inverter and cable
is important task from O & M perspective once EPC
completes his job.
Electrotherm Immodo Renewables Ltd.
Contd..
7/28/2019 Epc Summit
19/41
Key Selection
Modules
Stability of module manufacturer
Size
Modules of only tier 1 manufacturers Best available efficiencies,
Positive tolerances,
Proven reliability and
25 years performance warranty
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
20/41
Key Selection
Modules
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
21/41
Contd..Inverters
Only from internationally reputed manufactures
Best efficiency,
Thermal tolerance,
Minimum auxiliary power consumption and Proven performance under Indian conditions.
For large size projects larger capacity like 800 KW
with IP65 (outdoor) installation.
Inverters, transformers and AC side equipments shall
be economically sized without sacrificing energy
generation or plant / equipment long term reliability.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
22/41
Contd..Inverters
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
23/41
Contd..Transformers
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
24/41
Contd..
Module Mounting Structure Module mounting structures (MMS) are designed to
meet site conditions
Maximum wind velocity; Ease in prefabrication,
Ease in Transportation & Installation (totally bolted
construction)
Hot dip galvanized carried out under strict qualitycontrol.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
25/41
Contd..
Module Mounting Structure
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
26/41
Contd..Cabling
Adequately sized DC & AC cables to ensureminimum losses, long term reliability
Cables are to be buried at suitable depth underground
with inspection chambers suitable at suitable
distances.
PE warning tapes are installed in entire cable trench
to protect the cable.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
27/41
Contd..Cabling
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
28/41
Contd..Washing of modules
A well designed piped (non corrosive PVC) wash watersystem:-
Eliminates the dependence of local water tankers
Dust raised by them while moving in the plant area.
Ensures minimum water consumption
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
29/41
Contd..Tilt
Key factors affecting:- Land
Budget
Incremental cost
Type :-
Fixed Tilt
Seasonal Tilt
Single Axis tracking
Double Axis tracking
Seasonal Tilt is most preferred these days because of Incremental land required is very marginal
Can be operated through semi skilled labor.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
30/41
Overall Plant Design
To make best and effective use of land available.
Fully accessible in case of hazards,
Security & O & M aspects
Computes and predicts energy generation data usinglatest tools and solar.
Meteo data bases like PVSyst 5.31,
METEONORM 6.1 etc.
Shadow analysis is conducted for the proposedconstruction.
Very effective Lightning Arrestor (L A) for Solar Field.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
31/41
Monitoring/optimization/control system integrated witha 1st class security system with on-site surveillance when
alarms are tripped.
24*7 manned control center which manages distributedskilled O&M workforce.
Electrotherm Immodo Renewables Ltd.
Contd..
7/28/2019 Epc Summit
32/41
Overall Plant Design Finer Points Provision of Ring Main Units (RMU) for switching,
transformer protection and redundancy
Provision of UPS with sufficient back up supply toinverters ensuring quality of power as well as continuity.
Data Monitoring System (DMS) is critical and shouldhave features like remote accessibility.
Weather Monitoring Station (WMS) with data logger
and parameters like temperature measurement ofambient and module frame, anemometer, rain gauge,relative humidity etc.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
33/41
Overall Plant Design Finer Points
Electrotherm Immodo Renewables Ltd.
RMU
DMS
WMS-PYRANOMETER
7/28/2019 Epc Summit
34/41
Electrotherm Immodo Renewables Ltd.
Sr. No. PERFORMANCE RATIO (PR)
1 PV Syst Estimation 74.4%
2 EIRL Guarantee for FAT 73%
3 Actual Average PR achieved during
FAT
76.66%
4 Max. PR achieved during FAT 80.82%
5 PR Result 5% gain overguaranteed PR value
Note: FAT stands for Facility
Acceptance Test. It was conducted
for 30 days (720 hours continuously)
15 MW Solar PV Plant, Solar
Park, Charanka
7/28/2019 Epc Summit
35/41
Electrotherm Immodo Renewables Ltd.
Sr. No. ENERGY GENERATION
1 PV Syst Estimation 24.1 million
units/annum
2 EIRL Guarantee for Generation in 1st Year 23.25 million
units/annum3 Target Energy Generation Target for April
2012 based on Ratio of Radiation for April
and Total Annual Radiation
2.30 million units
4 Actual Energy Generation in April 2012 2.46 million units
5 Energy Generation Result 5 % above
guaranteed
generation
15 MW Solar PV Plant, Solar Park,
Charanka
P f C i S l PV
7/28/2019 Epc Summit
36/41
Electrotherm Immodo Renewables Ltd.
Performance Comparison at Solar PV
Gujarat Solar Park, Charanka
Source: SLDC, Gujarat
STATION
April 2012-
Generation (Export-
Thousand Units)
(Reference:SLDC)
Thousand Units/MWp
in April 2012
Performance
(Rank)
Palace (15 MWp) 2467 164.47 1
Developer 2 (20 MWp) 3281 164.05 2
Developer 3 (6 MWp) 966 161.00 3Developer 4 (10 MWp) 1577 157.70 4
Developer 5 (25 MWp) 3899 155.96 5
Developer 6 (25 MWp) 3863 154.52 6
Developer 7 (25 MWp) 3848 153.92 7
Developer 8 (5 MWp) 735 147.00 8
Developer 9 (10 MWp) 1437 143.70 9Developer 10 (25 MWp) 3583 143.32 10
Developer 11 (5 MWp) 694 138.80 11
Developer 12 (5 MWp) 668 133.60 12
Developer 13 (15 MWp) 1267 84.47 13
Developer 14 (15 MWp) 856 57.07 14
7/28/2019 Epc Summit
37/41
Electrotherm Immodo Renewables Ltd.
Performance Comparison at Solar PV
Gujarat Solar Park, Charanka
Source: SLDC, Gujarat
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
160.00
180.00
Gross Energy Export-April 2012(Thousand Units/MWp)
Palace (15 MWp)
Developer 2 (20 MWp)
Developer 3 (6 MWp)
Developer 4 (10 MWp)Developer 5 (25 MWp)
Developer 6 (25 MWp)
Developer 7 (25 MWp)
Developer 8 (5 MWp)
Developer 9 (10 MWp)
Developer 10 (25 MWp)
Developer 11 (5 MWp)Developer 12 (5 MWp)
Developer 13 (15 MWp)
Developer 14 (15 MWp)
7/28/2019 Epc Summit
38/41
Guaranteed and Enhanced plant performance. ProvenGuarantee.
One-point contact
Upfront knowledge of project cost and payment terms
Insulation from variation of prices
Electrotherm Immodo Renewables Ltd.
Fruits of Good EPC
7/28/2019 Epc Summit
39/41
Insulation from variation of prices
LD clauses - timely completion
Effective O&M service as they are the ones whoconstructed the plant in the first place.
Other Value added services.
Electrotherm Immodo Renewables Ltd.
Contd..
7/28/2019 Epc Summit
40/41
So choose your EPC partner carefully
COST SHOULD NOT BE ONLY
FACTOR.
Electrotherm Immodo Renewables Ltd.
7/28/2019 Epc Summit
41/41
THANK YOU