If you can't read please download the document
View
212
Download
0
Embed Size (px)
ENVIRONMENTAL IMPACT STATEMENT OBERON EARTHMOVING PTY LIMITED
Executive Summary Middle Creek Quarries
Report No.930/01
ES-1
R. W. CORKERY & CO. PTY. LIMITED
Executive Summary
INTRODUCTION
This Environmental Impact Statement (EIS)
has been prepared by RW Corkery & Co.
Pty Limited on behalf of Oberon
Earthmoving Pty Limited (the Applicant)
to support a development application for the
continued operation and extension of
Middle Creek Quarries (the Quarry).
The existing Quarry has been operated
since 2014 under development consent
DA 10.2010.66.1, which limits disturbance
to less than 2ha and production to less than
30 000m3. Figure A identifies the regional
setting of the Quarry, approximately 3.5km
west of Oberon on Lot 2 DP 1112479
(50 Sewells Creek Road), referred to herein
as the Project Site.
The proposed extension of the Quarry
would include progressively increasing the
extraction area to approximately 15ha (see
Figure B) and providing for transport of up
to 250 000tpa of product.
By virtue of total disturbance exceeding 2ha
and production exceeding 30 000m3, the
proposed development is considered
designated under the provisions of
Schedule 3(1) of the Environmental
Planning and Assessment Regulation 2000
(EP&A Reg). As Designated Development
for the purpose of extractive industry, the
Proposal is also classified as Regional
Development under Part 4 of the State
Environmental Planning Policy - State and
Regional Development 2011 by effect of
Schedule 4A(8) of the Environmental
Planning and Assessment Act 1979 (EP&A
Act). As Regional Development, the
development application will be determined
by the Joint Regional Planning Panel
Western Region.
Figure A Locality Plan and Local
Setting
A4/colour
Dated 02/05/16 Inserted 17/05/16
This EIS describes the proposed
modifications to the currently approved
operations (the Proposal), describes the
environment within and surrounding the
Quarry, presents the environmental
safeguards the Applicant would incorporate
into the design and operation of the Quarry
and assesses the impacts (if any) that the
safeguarded activities would have on the
local environment.
The EIS also evaluates the Proposal in
terms of Ecologically Sustainable
Development, justifies the Proposal in
terms of biophysical, economic and social
considerations and examines the
consequences of not proceeding with the
Proposal.
OBERON EARTHMOVING PTY LIMITED ENVIRONMENTAL IMPACT STATEMENT
Middle Creek Quarries Executive Summary
Report No.930/01
ES-2
R. W. CORKERY & CO. PTY. LIMITED
Figure B Project Site Layout
A4/colour
Dated 04/05/16 / Inserted 17/05/16
ENVIRONMENTAL IMPACT STATEMENT OBERON EARTHMOVING PTY LIMITED
Executive Summary Middle Creek Quarries
Report No.930/01
ES-3
R. W. CORKERY & CO. PTY. LIMITED
THE PROPOSAL
The Proposal incorporates the following
key components, identified as relevant on
Figure B.
An increase in the extraction area to
approximately 15ha, further segregated
into three separate cells.
Cell 1: an area of approximately
5.9ha (including the current
extraction area) extending from the
existing quarry.
Cell 2: an area of approximately
4.4ha incorporating the most
elevated and northerly section of the
ridge.
Cell 3: linking Cells 1 and 2 and
incorporating an area of
approximately 4.7ha along the top of
the ridge.
An increase in the rate of extraction and
production up to a maximum of
150 000tpa with an expected average of
80 000tpa.
Campaign crushing and screening of the
extracted rock (to suit customer
requirements).
Importation of:
raw mulch (up to 25 000tpa);
ENM (up to 50 000tpa); and
treated drilling mud generated by
hydro-excavation methods (up to
60 000tpa).
for stockpiling and sale, composting
blending with extracted gravel, or
application to the completed extraction
area as part of rehabilitation of the
Quarry.
The combined production of gravel, fill,
soil, mulch and other specialty products
would not exceed 250 000tpa.
Installation of various erosion and
sediment control features to prevent
uncontrolled and contaminated discharge
from the Project Site.
Progressive rehabilitation of the
extraction area and other disturbance to
create a final landform amenable to
future agricultural, or other agreed, land
use.
The extraction operations would be
undertaken in a similar manner to existing
operations with erosion and sediment
controls first established followed by
vegetation clearing and soil removal (where
practical) to expose the underlying rock.
Any non-gravel overburden would be
removed and stockpiled either for sale as
select fill or replacement within the final
landform followed by extraction of the
gravel. Initially, the rock would be won by
ripping (using a bulldozer), however, where
the rock becomes too hard to win by
ripping, the Applicant would use
conventional drill and blast methods to
fracture the rock before ripping and
extraction.
As the rock becomes harder at depth, and
dependent on customer size requirements,
crushing and screening of the gravel would
be required. This rock would be loaded to a
mobile crushing unit, initially located
within the Crushing, Screening and
Resource Recovery Area, to reduce the size
and either separate into specific sizes or
produce a graded products. Rock which is
not loaded directly to the crushing unit
would be placed in stockpiles for future
crushing. Depending on the specifications
required by customers, additional screening
and/or blending with stockpiled overburden,
imported soils or other products could be
undertaken.
OBERON EARTHMOVING PTY LIMITED ENVIRONMENTAL IMPACT STATEMENT
Middle Creek Quarries Executive Summary
Report No.930/01
ES-4
R. W. CORKERY & CO. PTY. LIMITED
Waste materials to be accepted on to the
Project Site would be classified as follows.
Organic (Woody) Waste (Raw Mulch).
Excavated Natural Material (ENM).
Treated Drilling Mud.
Each would only be accepted in accordance
with the relevant Resource Recovery Order
issued under Part 9 of Protection of the
Environment Operations (Waste)
Regulation 2014 (POEO (Waste) Reg) and
either:
stockpiled for future sale (without
modification) within 12 months of
acceptance;
applied to land in accordance with the
relevant Resource Recovery Exemption
issued under Part 9 of the POEO
(Waste) Reg;
screened and blended to produce a
specialty gravel, fill or soil products; or
composted.
Screening / Blending
From stockpiles, selected ENM and treated
drilling muds would be screened to either
remove large rocks and organic material, or
produce a specific size fraction. The
screened material would be stockpiled for
sale or further blending with the Quarry
gravel to generate a specific gravel/fill
product.
Composting
From stockpiles, raw mulch would be
chipped, shredded, mulched and screened to
generate the specific size and consistency
required for each product. Material
designated for the production of compost
would be placed in wind rows for
pasteurisation (reduction in pathogens and
plant propagules) and maturation (to
biological stability) of the compost.
The proposed composting process would be
aerobic, to reduce the potential for odours,
and segregated from other Project Site
runoff, to prevent pollution of land or water
off the Project Site.
Quarry products would be despatched from
the Project Site via Sewells Creek and
Abercrombie Roads, towards Oberon and
beyond. The transportation of quarry
products would be undertaken
predominantly using truck and dog trailers
(50m3/32t), although larger vehicles (up to
B-double arrangement) or smaller vehicles,
such as rigid trucks, could be used.
The Applicant would generally restrict
extraction and processing operations to
between 6:30am and 6:30pm, Monday
Friday and 8:00am to 6:00pm on Saturday.
Haulage operations are proposed to be
undertaken 24 hours per day (to
accommodate deliveries of waste materials
from facilities which operate 24 hours per
day).
The Applicant would adopt a progressive
approach to the rehabilitation of disturbed
areas to ensure that, where practicable, as
extraction is completed, a stable landform is
finalised and vegetated. The final landform,
whilst not a replication of the pre-quarry
landform, would remain sympathetic to the
local visual aesthetic of cleared grazing